About this file
This document provides details for a federal contract opportunity for construction manager as constructor services for capital security project renovations at the Theodore Levin United States Courthouse in Detroit, Michigan. The solicitation seeks proposals for design and construction phase services including accessibility improvements, security screening upgrades, and secure corridors. Offerors must be registered in SAM.gov and the procurement is set aside for small businesses. The technical evaluation criteria are experience providing similar services, past performance, management approach, and personnel qualifications. The submission due date will be specified in the solicitation to be available on SAM.gov on or after a 15-day notice period. The pre-proposal conference date and response instructions will also be in the solicitation. The contract award will be made based on best value considering technical factors as more important than price.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amdt 0006_47PF0022R0013.pdf | ||
| Amdt 0004_47PF0022R0013.pdf | ||
| Amdt 0005_47PF0022R0013.pdf | ||
| Amdt 0004_47PF0022R0013.pdf | ||
| Past Performance Reference Attachment A2.pdf | ||
| Reference Attachment B .pdf | ||
| Amdt 0004_47PF0022R0013.pdf | ||
| CMc Pre-proposal Sign-in sheet.pdf | ||
| 47PF0022R0013 Amdt 0003.pdf | ||
| 47PF0022R0013 Amdt 0003.pdf | ||
| 47PF0022R0013 Amdt 0002.pdf | ||
| Amdt 0001.pdf | ||
| Pre-Proposal Conference Attendence Form 030222pdf.pdf | ||
| GSA527-21.pdf | ||
| 47PF0022R0013 Levin CMc.pdf | ||
| CMc Reps and Certs 47PF0022R0013.pdf | ||
| SF24-16d.pdf | ||
| Pre-Proposal Conference Attendence Form.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Agenda
47PF0022R0013
Levin Capital Security Project (CSP) Theodore Levin U.S. Courthouse Courthouse
Government Team:
Contracting Officers: Oana Sandru, Oana.Sandru@gsa.gov Daniel Ramirez, Daniel.Ramirez@gsa.gov
Contract Specialist: Della Ljungkull, Della.Ljungkull@gsa.gov Steven Juniper, Steven.Juniper@gsa.gov
Project Manager: Seth LaRocque, seth.Larocque@gsa.gov Contracting Officer’s Representative: Bradley Taplick Supervisory Property Manager: Laura Marble Property Manager: Joseph Blake Architect/Engineer: G.H. Forbes & Associates Construction Manager as Agent (CMa): Procon Consultants
QUESTIONS:
All questions shall be submitted in email to the Contracting Officer and Contract Specialist identified above.
SAM
All contractors must be active in the System for Award Management (SAM), www.sam.gov, prior to submission of offers to be considered for award. BE ADVISED: If you are registering a new entity in SAM.gov or updating your entity, you must provide and mail an original, signed notarized letter available here:
(https://www.fsd.gov/gsafsd_sp?id=kb_article_view&sysparm_article=KB0016652) stating that you are the authorized Entity Administrator.
Read the FAQs available here:
(https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=899cc97a1bab7c105465eaccac 4bcbae) for more information on these requirements and / or contact the Federal Service Desk at www.fsd.gov for additional questions or assistance.
CONTRACTUAL ITEMS
Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.
No oral statement made by a Government representative during the pre proposal conference, nor any written record of such oral statements as may be made and subsequently furnished to the offeror, will be deemed to have the effect of adding to, modifying, or otherwise varying from the written provisions of the Solicitation (including, but not limited to specifications, drawings and mailto:Oana.Sandru@gsa.gov mailto:Della.ljungkull@gsa.gov mailto:Seth.Larocque@gsa.gov https://www.fsd.gov/gsafsd_sp?id=kb_article_view&sysparm_article=KB0016652 https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=899cc97a1bab7c105465eaccac4bcbae https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=899cc97a1bab7c105465eaccac4bcbae
Levin Capital Security Project (CSP) Theodore Levin U.S. Courthouse Courthouse written amendments to the solicitation). In the event the discussion or questions raised during the pre proposal conference indicate a need to modify the Solicitation, an amendment to the Solicitation will be issued in writing; any such amendment to the Solicitation must be acknowledged in the same manner and under the same conditions as all other written amendments to the Solicitation.
I.G Receipt of Offers
(1) In order to be considered for award, offers conforming to the requirements of the RFP must be received at the following office no later than 2:00 pm CST local time on the following date and at the following address.
Date: 03/21/2022
Electronic Submission: Oana.Sandru@gsa.gov, Della.Ljungkull@gsa.gov, Daniel.Ramirez@gsa.gov and Steven.Juniper@gsa.gov
(2) Offers sent by commercial package delivery and hand delivery shall be deemed received as of the date and time of delivery to the office designated for receipt of offers - NOT Applicable, all offers are to be sent electronically.
(3) Offers sent by United States Mail shall be deemed timely if delivered to the address of the government installation designated for receipt of offers on or before the date established for receipt of offers. - NOT Applicable, all offers are to be sent electronically.
II.A. Proposal Contents Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:
1. Price Proposal
2. Technical Proposal
3. Representations & Certifications
4. Attachment C-- Offeror Information
5. GSA Form 527 Contractor’s Qualification and Financial Information
6. SF24 Bid Bond
II.B. Proposal Format
Offerors who wish to submit an offer will be required to submit a complete proposal package to the Contracting Officers (Oana Sandru and Daniel Ramirez) with a carbon copy to the Contract Specialist (Della Ljungkull and Steven Juniper) by the closing date and time of this solicitation.
mailto:Oana.Sandru@gsa.gov mailto:Della.Ljungkull@gsa.gov mailto:Daniel.Ramirez@gsa.gov mailto:Steven.Juniper@gsa.gov
Levin Capital Security Project (CSP) Theodore Levin U.S. Courthouse Courthouse
The technical package should be organized to correspond with the evaluation criteria as listed herein. The submission should not exceed 30 double sided pages (not including forms). Pages that exceed the limit may not be considered.
II.D. Technical Proposal
Technical proposals will be evaluated on the four (4) factors listed below; all factors are weighted equally.
TECHNICAL EVALUATION CRITERIA
1. Experience in providing Design and Construction Phase Services on similar project
2. Management Approach (Design and Construction Phase Services)
3. Qualifications and Experience of Key Personnel
4. Past Performance in providing Design Phase Services and Construction Phase
Services on similar projects
Key Personnel Highlights
**Note 1: No substitution to key personnel shall be made without prior approval of the CO. In the event that personnel approved by the CO are unable to perform their duties due to death, illness, resignation from the Contractor's employment, the CO's request for removal, or similar reasons, the Contractor shall promptly submit to the CO, in writing, the name and qualifications of a proposed replacement with equal or superior qualifications. This replacement, if approved by the CO, shall be submitted to the Government within three calendar days from the time of removal and shall in no way delay the project schedule. Any approved substitutions shall be made at no increase in contract price and/or decrease in capabilities.
Technical Project Scope Summary:
Scope, General: The scope items listed below include modifications to existing architectural, structural, mechanical, electrical, plumbing, elevator, fire protection, and other systems.
Selective demolition will be required, as well as some existing materials which may contain asbestos, lead, or other hazardous materials which shall be properly mitigated as part of this project per GSA standard specifications. The GSA Historic Preservation Principles shall apply to all aspects of the project scope.
CMc Design Assist: Note that the CMc will be expected to partner with other members of the project team to finalize the design through the Design Development and Construction Document stages. The A/E has provided a “CMc Design Assist Log” which outlines some of the tasks that
Levin Capital Security Project (CSP) Theodore Levin U.S. Courthouse Courthouse can be expected to be performed by the CMc during these stages, such as testing, existing conditions verification, and mock-ups/samples that shall be provided. Other similar tasks may be necessary to help develop and finalize the scope of work prior to NTP for construction.
Base Scope:
1. Renovations at the building entrance from Lafayette Blvd.
a. New ramps to be built on the existing sidewalk
b. A new screening station will be built on the east (plan north) side of the existing interior stairs.
c. A new lift will be installed to assist visitors who cannot use the stairs from the lower portion of the first floor to the main level. This will include lowering of a portion of the existing floor slab and cutting a new opening from the existing entrance vestibule.
2. Renovations at the building entrance from Fort Street, within existing elevator lobby.
a. New partitions and security equipment will be installed within the existing elevator lobby.
3. New enclosed vehicle sally port in the Basement Loading Dock
a. A new CMU enclosure with roll-up doors shall be installed within the existing loading dock to provide a secure loading/unloading zone for prisoner delivery vehicles to access existing elevator #9.
4. Modifications to existing Elevator #9
a. The existing elevator shall be upgraded to meet current USMS Publication 64 requirements for the use as a secure prisoner elevator. This may include rebuilding the elevator cab, new controls, new motor, entrance doors, etc.
Additional Scope:
1. Alternate #1: Renovations at the building entrance from Fort Street, cutting through the
Detroit Room
a. Lower the existing floor slab in the corner of the existing “Detroit Room” for the purposes of building a new security screening station at the Fort Street entrance.
b. This alternate will be considered based on a cost/benefit analysis and may be awarded in lieu of the base scope noted at the Fort Street Entrance.
2. Option #1: Renovation of prisoner staging and secure corridors on the 2nd Floor.
a. New prisoner holding cells/staging areas are to be built adjacent to elevator #9 on the 2nd floor.
b. Modifications to existing corridors to be made in order to provide more secure passageways for prisoner movement to and from the courtrooms on the 2nd floor.
c. This option will be considered based on a cost/benefit analysis and may be awarded based on the availability of funding.
Levin Capital Security Project (CSP) Theodore Levin U.S. Courthouse Courthouse
Milestone Schedule: At this time, the project team estimates the following milestone schedule.
This is subject to change and will be revised and updated as the project progresses and the design is finalized.
1. CMc Award (Pre-construction services): May, 2022
2. Design Development Package Approved: June, 2022
3. 50% Construction Documents Approved: August, 2022
4. 75% Construction Documents Approved: September, 2022
5. Final Construction Documents Approved: December, 2022
6. Award GMP for Construction: March, 2023
7. NTP for Construction: May, 2023
8. Estimated Substantial Completion Date: November, 2024
9. Final Contract Closeout: March, 2025
Building Requirements Historic Preservation: The Courthouse is listed in the National Register of Historic Places, therefore, all work shall conform to strict requirements for repairing and maintaining historic buildings, comply with the Secretary of the Interior's Standards for Rehabilitation, and be approved by historic preservation staff. The building will remain open and fully operational during the entire period of performance of this project, so measures will need to be taken to limit disruption to building operations. Hazardous Materials, including asbestos and lead, are known to be present in the facility and are likely to be encountered as part of this project. The GSA Standard specifications for hazardous material mitigation practices shall be followed.
Security Requirements: Refer to the SOW regarding security requirements applicable to the building. All contract employees shall obtain proper security clearances in advance of doing any work on this project per GSA security requirements.
General Construction Logistics:
1. Occupied Facility: The facility shall remain fully occupied during the entire duration of this project. All disruptive/noisy work shall be scheduled and/or coordinated to limit disruption to building operations.
2. Parking: Onsite parking is NOT permitted at the Courthouse. Contractors shall be responsible for arranging for parking off site.
3. Building Site Limitations: There is limited area around the building site for contractors to set up construction trailers/lay down areas. The use or blocking of any roadways shall be coordinated with the GSA Property Manager and all affected municipalities.
4. Construction Office: There may be limited vacant areas within the existing building which could be made available for the use of the contractor to set up an on-site construction office. Logistics regarding the use of such areas shall be coordinated and approved by the GSA Property Manager.
Levin Capital Security Project (CSP) Theodore Levin U.S. Courthouse Courthouse
5. Loading Dock Access: The contractor shall coordinate the use of the existing loading dock for deliveries, dumpsters, etc. with the GSA Property Manager. Note that the loading dock is also used by building tenants, including loading/unloading zones for secured detainees. Those operations can impact delivery schedules for construction materials handling.
6. Use of existing elevators: If existing elevators are needed to transport workers and/or construction materials, those activities shall be coordinated and approved by the GSA Property Manager.
Site Walkthrough: A walkthrough will be conducted on-site for those in attendance. If additional site visits or walk-throughs are needed, please submit a request to the Contracting Officer/Contract Specialist. The GSA may or may not facilitate additional visits depending on personnel availability and timeline restrictions.