This document contains an amendment to a solicitation and federal contract opportunity notice. The amendment extends the proposal due date to March 23, 2022 for request for proposal number 47PF0022R0013, which is seeking a construction manager as constructor for capital security project services at the Theodore Levin United States Courthouse in Detroit, Michigan. The project scope includes constructing an accessible public entrance, separating screened and unscreened individuals, adding interior queuing space, and installing a new security screening station. The contract will be set aside for small businesses with a NAICS code of 236220 and size standard of $36.5 million. Proposals will be evaluated based on experience providing similar design and construction stage services, past performance, management approach, and key personnel qualifications. Award may be made on initial proposals but discussions may be held if needed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amdt 0006_47PF0022R0013.pdf | ||
| Amdt 0004_47PF0022R0013.pdf | ||
| Amdt 0004_47PF0022R0013.pdf | ||
| Reference Attachment B .pdf | ||
| Amdt 0004_47PF0022R0013.pdf | ||
| Past Performance Reference Attachment A2.pdf | ||
| Levin CSP- CMc Preproposal agenda.pdf | ||
| CMc Pre-proposal Sign-in sheet.pdf | ||
| 47PF0022R0013 Amdt 0003.pdf | ||
| 47PF0022R0013 Amdt 0003.pdf | ||
| 47PF0022R0013 Amdt 0002.pdf | ||
| Pre-Proposal Conference Attendence Form 030222pdf.pdf | ||
| Amdt 0001.pdf | ||
| Pre-Proposal Conference Attendence Form.pdf | ||
| 47PF0022R0013 Levin CMc.pdf | ||
| CMc Reps and Certs 47PF0022R0013.pdf | ||
| SF24-16d.pdf | ||
| GSA527-21.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
Request for Proposal 47PF0022R0013 Amendment 0005
Construction Manager as Constructor (CMc) Levin Capital Security Project (CSP)
Theodore Levin U.S. Courthouse
The amendment to solicitation 0005 hereby extends the due date and provides additional clarifications:
A. The due date is hereby extended to Wednesday, March 23, 2022 at 8:00AM CST. The proposal shall be emailed to oana.sandru@gsa.gov, della.ljungkull@gsa.gov daniel.ramirez@gsa.gov and steven.juniper@gsa.gov.
B. This amendment hereby incorporates the following questions and the clarifications:
a. Question 1: Do you have a specific document for the items included in the overhead costs?
Answer: No, there is no specific document that GSA has for overhead cost items. Please submit the items which make up your overhead costs as indicated in the solicitation.
b. Question 2: If we are unable to have someone complete the Past Performance and Past Experience Reference Attachment B before the proposal due date, can we still submit?
Answer: Yes, you may still submit. Please ask your reference to email the questionnaire back to us by the due date and time (March 23, 2022 at 8AM CST). However, if that is not possible, as part of your submission please submit Attachment B with the section called “To be completed by Contractor” filled out in its entirety. Please make sure we have the phone number and email address of your reference. The GSA may reach out to your references, if needed.
c. Question 3: How many days should the proposal be valid for?
Answer: Your proposal shall be valid for 30 days from submission.
Standard Form 1442, section 13d shall have the following inserted: 60 days. The section will now read as follows: Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
d. Question 4: Is there a maximum number of projects we can submit for Factor 1?
Answer: There is a minimum number of projects which need to be submitted. Three similar projects must be submitted, therefore we recommend that you submit the top three most similar projects. Only the first three projects submitted will be considered.
mailto:oana.sandru@gsa.gov mailto:daniel.ramirez@gsa.gov mailto:steven.juniper@gsa.gov
Request for Proposal 47PF0022R0013 Amendment 0005
Construction Manager as Constructor (CMc) Levin Capital Security Project (CSP)
Theodore Levin U.S. Courthouse
C. On the Past Performance and Past Experience Reference Attachment B, question six (6) (which reads as follows: “Would you enter into a contract again with this offeror?”) will not be factored or considered into the total score. The total score shall be a maximum of 25 total points, made up of the five remaining questions.
D. This amendment shall be acknowledged and the first page of the SF30 returned along with any proposal package submitted in response to this RFP (this applies to any subsequent amendment issued for this solicitation).
E. All other terms and conditions not addressed herein remain unchanged and in full force and effect.
1.2
C:\PERFORM\FORMS\S30.FRP
Forms Management
C:PERFORMFORMSS30.FRP
Acrobat PDFWriter 2.01 for Windows D:19971010095222 D:19990614133004
C:PERFORMFORMSS30.FRP
Standard Form 30 - Amendment of Solicitation/Modification of Contract Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQUISITION NUMBER
5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6)
CODE
STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.
is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY
CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer) Previous edition unusable INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1) (2) (3) (4) (5) For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a) (b) (c) (d) (e) (f) Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data). When appropriate, indicate the impact of themodification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $ Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i) NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one ofthe following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g) (h) When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determinedto be due in settlement of the contract.
(1) (2) (3) (4) (5) (6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
| 9A. AMENDMENT OF SOLICITATION NUMBER: 0005 |
| 9A. AMENDMENT OF SOLICITATION NUMBER: 47PF0022R0013 |
| 7. CODE: |
| 12. ACCOUNTING AND APPROPRIATION DATA (If required): |
| 13A. THIS CHANGE ORDER IS ISSUED PURSUANT TO. Specify authority. THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.: |
| 13C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: |
| 13D. OTHER. Specify type of modification and authority.: |
| 15A. NAME AND TITLE OF SIGNER. Type or print.: |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER. Type or print.: |
| 14. DESCRIPTION OF AMENDMENT OR MODIFICATION (Organized by UCF section headings, including solicitation or contract subject matter where feasible.): Please see page 3 of Amendment to Solicitation 0005. |
| FACILITY CODE: |
| 6. ISSUED BY: R5 Design and Construction Project Programs Division |
230 South Dearborn Suite 2500 Chicago, IL 60604
| 8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code): |
| 7. ADMINISTERED BY (If other than Item 6): R5 Design and Construction Project Programs Division |
230 South Dearborn Suite 2500 Chicago, IL 60604
| 1. CONTRACT ID CODE: |
| 4. REQUISITION/PURCHASE REQUISITION NUMBER: |
| 10A. MODIFICATION OF CONTRACT/ORDER NUMBER: 02/11/2022 |
| 5. PROJECT NUMBER. If applicable.: |
| PAGE: 1 |
| PAGES: 4 |
| 3. EFFECTIVE DATE. Enter 2 digit month, 2 digit day and 4 digit year.: 2022-03-18 |
| 9B. DATED. SEE ITEM 11. Enter 2 digit month, 2 digit day and 4 digit year.: |
| 10B. DATED. SEE ITEM 13. Enter 2 digit month, 2 digit day and 4 digit year.: |
| 9A. AMENDMENT OF SOLICITATION NUMBER: 0 |
| 10A. MODIFICATION OF CONTRACT/ORDER NUMBER: 0 |
| 11. The above numbered solicitation is amended as set forth in Item 14. : 1 |
| 13A. THIS CHANGE ORDER IS ISSUED PURSUANT TO. Specify authority. THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.: 0 |
| 13B. THE ABOVE NUMBERED CONTRACT OR ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES. Such as changes in paying office, appropriation date, etc. SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103b.: 0 |
| 13C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: 0 |
| 13D. OTHER Specify type of modification and authority.: 0 |
| 13E. IMPORTANT: Contractor is not required to sign this document and return copies to the issuing office.: 0 |
| 13E. IMPORTANT: Contractor is required to sign this document and return copies to the issuing office.: 0 |
| 11. The hour and date specified for receipt of Offers is extended : 1 |
| 11. The hour and date specified for receipt of Offers is not extended : 0 |
| 15B. CONTRACTOR OR OFFEROR. Signature of person authorized to sign. Digital Signature.: |
| 16C. DATE SIGNED. Enter 2 digit month, 2 digit day and 4 digit year.: |
| number of copies: 1 |
| number of copies: |
| Enter the total (in dollars) the contract price increased. : |
File details come from the government source that posted it. Updated .