ROH00760_OH0046ZZ_Dwg03_H201.pdf

PDF 378 KB Posted

Attached to
Cooling Tower Replacement Federal contract opportunity
Solicitation number
47PF0019R0099
Issued by
General Services Administration Public Buildings Service Region 5

About this file

RFP 47PF0019R0099 Drawing 03

View the file

Other files for this federal contract opportunity

Other files attached to Cooling Tower Replacement, newest first.
File Type Posted
Pre-Bid_Walkthrough_Q&A_and_Attendance_Sheets.pdf PDF
RFP_47PF0019R0099.pdf PDF
(specs)_ROH00760_Cooling_Tower_100pct_Specifications_2019-04-17.pdf PDF
ROH00760_OH0046ZZ_Dwg01_G000.pdf PDF
ROH00760_OH0046ZZ_Dwg04_E101.pdf PDF
ROH00760_OH0046ZZ_Dwg02_A101.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CT1

CT2

8" EQUALIZER

VFD-CT1

VFD-CT2

(E)1-1/4"

10"CS

8"CS

(E)MAKEUP

10"CR

8"CR

3" OVERFLOW

2" DRAIN

WITH VALVE

BELOW

OVERFLOW

8" CS

2" DRAIN

WITH

VALVE

EXISTING

DRAIN

(R)CT

(R)CT

(R)8" CWS

(R)8"

EQUALIZER

PIPE

(E)1-1/4"

(R)10"CWS

(R)8"CWS

(E)MAKEUP

ASSEMBLY

(R)10"CWR 3

(R)8"CWR 1

EXISTING VENT PIPING

FROM BOILER ROOM

(R)3" OVERFLOW

(R)2" DRAIN

BELOW

OVERFLOW

(R)2" DRAIN

EXISTING

DRAIN

S E

N S

I T

I V

E

B

U T

N C

L A

S S

I F

I E

D

S

B U

P

R O

P E

R T

Y

O

F

T

H E

I T

D

S

A

T E

S

G

O V

E R

N M

E N

T

F

O R

F F

I C

I A

L

U

L Y

O

N

M

O V

E

T

H I

T

I C

E

P

R O

P E

R L

S

T R

C

U M

E N

W

H E

N

N

O

L O

N G

E

D E

D

General Services Administration

Public Buildings Service

Great Lakes Region

Design and Construction Division

John C. Kluczynski Federal Building

230 South Dearborn Street

Chicago , IL 60604

Columbus, OH, 43215

Kinneary U.S. Courthouse

100% Construction Documents

04-17-2019

ROH00760OH0046ZZ

COOLING TOWERS

GS-05P-17-SC-D-0010

47PF00-18-F-0076

A

M

Cooling Tower Replacement

ROH00760

KORDA

KORDA

85 Marconi Boulevard

MARK DATE DESCRIPTION

PROJECT NUMBER:

CHECKED BY:

DESIGNED BY:

1650 WATERMARK DRIVE

COLUMBUS, OHIO 43215

SUITE 200

DRAWN BY:

2017-0210

Eric Stephens

Dave Balch

Dan Edwartoski

H202

Floor Plan

Mechanical

1/4" = 1'-0"

0 1 2 4

Demolition

1/4" = 1'-0"

0 1 2 4

New Work

NEW EQUIPMENT DATA:

CT1 COOLING TOWER (COUNTER FLOW)

CAPACITY: 780 GPM AT 96.2°F EWT. 86°F LWT. 78°F WB.

CENTRIFUGAL FAN (FORCED DRAFT): 40 HP AT 480 VOLT 3 PHASE.

PONY MOTOR: 10 HP AT 480 VOLT 3 PHASE.

BASIN HEATER: 10KW, 480 VOLT 3 PHASE, PROTECTION TO -20°F.

PROVIDE STAINLESS STEEL WATER BASIN.

UNIT DIMENSIONS: LENGTH:17'-8". HEIGHT:11'-3". WIDTH:7'-10".

CT2 COOLING TOWER (COUNTER FLOW)

CAPACITY: 780 GPM AT 96.2°F EWT. 86°F LWT. 78°F WB.

CENTRIFUGAL FAN (FORCED DRAFT): 40 HP AT 480 VOLT 3 PHASE.

PONY MOTOR: 10 HP AT 480 VOLT 3 PHASE.

BASIN HEATER: 10KW, 480 VOLT 3 PHASE, PROTECTION TO -20°F.

PROVIDE STAINLESS STEEL WATER BASIN.

UNIT DIMENSIONS: LENGTH:17'-8". HEIGHT:11'-3". WIDTH:7'-10".

NEW WORK CODED NOTES:

1. PROVIDE NEW 8" EQUALIZER LINE BETWEEN CT1 AND CT2.

2. PROVIDE NEW SELF REGULATING HEAT TRACE (8 W/FT, 120V/1PH) ON

ALL CS PIPING AND ON CR PIPING.

3. INSULATE ALL CS AND CR PIPING BETWEEN COOLING TOWERS AND PIT

FLOOR. PROVIDE EMBOSSED ALUMINUM COVER.

4. PROVIDE VFD FOR 40 HP MOTOR. INSTALL IN BASEMENT BOILER ROOM.

COORDINATE VOLTAGE AND PHASE WITH NEW ELECTRICAL

DISCONNECTS AND SWITCHES.

5. NEW ISOLATION VALVE IN VERTICAL PORTION OF CR PIPE.

6. PROVIDE NEW HEAT TRACE CONTROLLERS IN THIS LOCATION.

CONNECT TO (2) EXISTING ELECTRICAL CIRCUITS. MAKE CONNECTION

TO BUILDING AUTOMATION SYSTEM TO PROVIDE ALARM IN THE EVENT

OF CABLE FAILURE.

7. PROVIDE NEW COOLING TOWER WATER LEVEL CONTROLLER IN THIS

LOCATION. MAKE CONNECTION TO NEW LEVEL INDICATOR IN TOWER

AND TO EXISTING MAKE UP WATER VALVE.

8. NEW ISOLATION VALVE IN HORIZONTAL PORTION OF CS PIPE.

DEMOLITION CODED NOTES:

1. REMOVE CS LINES AND CR LINES BACK TO POINT WHERE THEY

PENETRATE PIT FLOOR. LEAVE ENOUGH EXISTING PIPE EXPOSED FOR

CONNECTION TO REPLACEMENT PIPES.

2. REMOVE COOLING TOWER DRAIN AND OVERFLOW PIPES.

3. DISCONNECT MAKEUP WATER LINE FROM COOLING TOWER. EXISTING

MAKEUP VALVE ASSEMBLY TO REMAIN FOR REUSE. REMOVE WATER

LEVEL INDICATOR AND CONTROLS.

4. REMOVE ALL INSULATION FROM EXISTING CS AND CR PIPING

(APPROXIMATELY 120 LINEAR FEET). REMOVE HEAT TRACE.

5. REMOVE COOLING TOWERS.

6. REMOVE CR VALVE IN VERTICAL PORTION OF PIPE.

7. REMOVE TWO HEAT TRACE CONTACTORS AND ASSOCIATED CABLE.

8. REMOVE COOLING TOWER WATER LEVEL CONTROLLER.

NOTE: ALL SYMBOLS NOT NECESSARILY USED

HVAC SYMBOLS LIST

EXISTING TO REMAIN

EXISTING TO BE REMOVED

EXISTING TO BE ABANDONED

SPECIALTIES

GENERAL

MISCELLANEOUS

CONDENSER WATER SUPPLY

CONDENSER WATER RETURN

CS

CR

(E)

(R)

(AB)

SOLENOID VALVE

PRESSURE RELIEF VALVE

PRESSURE REDUCING VALVE

PLUG VALVE

GLOBE VALVE

ISOLATION VALVE - SEE PROJECT

EXPANSION VALVE

CHECK VALVE

BUTTERFLY VALVE

BALL VALVE

BALANCE/SHUT-OFF VALVE

3-WAY CONTROL VALVE

2-WAY CONTROL VALVE

VALVES

RISE

DROP

CAP

VALVE IN RISER/DROP

CONNECT TO EXISTING

OC

FOR COORDINATION OR REFERENCE

DENOTES ITEM PROVIDED BY

ANOTHER CONTRACTOR, SHOWN

SPECIFICATIONS FOR REQUIREMENTS

GATE VALVE

PIPING

GENERAL NOTES:

1. PRIOR TO BID, THE CONTRACTOR SHALL MAKE A SITE VISIT TO VERIFY

EXISTING CONDITIONS AND SCOPE OF DEMOLITION.

2. COORDINATE DEMOLITION OF HVAC EQUIPMENT WITH ELECTRICAL

CONTRACTOR AND TEMPERATURE CONTROLS CONTRACTOR.

3. PROJECT SHALL TAKE PLACE IN COOLING OFF SEASON.

CT1

NEW

HEAT TRACE

CT2

T

AI

SUMP

TEMP

T

AI

V

F

D

BI

AO

BO

V

F

D

BI

AO

BO

EQUALIZING LINE

SHUT-OFF VALVE

TYP. 2

TOWER FAN

T

AI

HEAT TRACE AND HEAT TRACE CONTROLS ARE NEW.

SYSTEM IS SELF REGULATING BASED ON INTEGRAL AMBIENT

AIR TEMP. SENSOR. CONTROLLERS SHALL PROVIDE AN

ALARM TO THE BAS IN THE EVENT OF HEAT TRACE FAILURE.

T

AI

TO MECH ROOM

TOWER FAN

IN MECH CORRIDOR IN MECH CORRIDOR

N.T.S.

BINARY INPUT TO DDC SYSTEM

ANALOG INPUT TO DDC SYSTEM

BINARY OUTPUT FROM DDC SYSTEM

ANALOG OUTPUT FROM DDC SYSTEM

BACNET INTERFACE FROM EQUIPMENT

BO

BI

AO

AI

BAC

TEMPERATURE CONTROL

T

AMBIENT TEMP SENSOR

AI

M

C

C

IN MECH ROOM

M

C

C

IN MECH ROOM

BOBO

AO

AutoCAD SHX Text A

AutoCAD SHX Text Cooling Tower Area Floor Plan

AutoCAD SHX Text B

AutoCAD SHX Text Cooling Tower Area Floor Plan

AutoCAD SHX Text S

AutoCAD SHX Text C

AutoCAD SHX Text Cooling Tower Temp. Control

Sheets and Views
ROH00760OH0046ZZH201-Plot Sheet

File details come from the government source that posted it.