Clarifications.pdf

PDF 6 KB Posted

Attached to
Columbus Ohio O&M
Solicitation number
47PF0017R0117
Issued by

About this file

Clarifications and changes to Equipment List

View the file

Other files

File Type Posted
RFI_3_RAV_AM0005.pdf PDF
Amend_0005.pdf PDF
Amend_0004.pdf PDF
Amend_0003_question.pdf PDF
Amend_0003.pdf PDF
Clarifications_2.pdf PDF
Amend_0002.pdf PDF
Amend_0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Clarifications

For Past Performance Criteria:

1) The contract was for mechanical O&M services in a commercial or government owned facility

(minimum 200,000 sq ft) as a prime contractor.

2) The contract was for Operations & Mechanical Maintenance Services in multiple locations

There was a question if each building had to be 200,000 sf, or did they need to total that amount together.

The answer is that at least one building must be a minimum of 200,000 square feet.

Changes to Inventory for Kinneary US Courthouse

1. The roof square footage on the equipment inventory list should be 26,400 NOT 779

2. Please include storm water tank on equipment inventory list - Water Control Custom Applied Technology, Model #RWUV46, Serial #1040. 5500 gallon tank used to irrigate lawn

3. The number of fire extinguishers should be 26 NOT 50

CPARS information is only available to those with an account. Accounts are limited to contractors and government buyers.

The $2,000 shared liability applies to all orders, regardless of dollar value.