This solicitation requests design-build construction services for waterproofing exterior foundation walls at the Addabbo Federal Office Building in Jamaica, New York. The selected contractor will waterproof walls on the north and south sides of the building, investigate issues like sidewalk settling, and complete ancillary work like replacing trench drains. The General Services Administration intends to award a firm-fixed price contract using a two-step formal competitive proposal procedure with negotiations. The performance period is 217 calendar days from the notice to proceed for substantial completion and 60 additional days for final completion. The liquidated damages rate for delays is $1,073.20 per day.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SSA- Site Safety Supp Req.pdf | ||
| Amendment 1.pdf | ||
| MSDSReviewRequestForm.doc | DOC document | |
| SF 1442.pdf | ||
| Attachment A - Past Performance Questionnaire.docx | DOCX document | |
| Wage Determination NY20180003.pdf | ||
| GC Reps&Certs sep19.docx | DOCX document | |
| SF24-16d- Bid Bond.pdf | ||
| GSA527-15c1c - Contractor Qualification.pdf | ||
| 47PC0420B0001 - Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sol. Reference No. 47PC0420B0001 GSA Contract No: TBD
Document: DB101-SB/AUGUST 2019 (The Agreement)
Design Build Contract for: Addabbo Waterproofing Project – North/South Sides
The Agreement
Table of Contents
I. Project Information A. Project Summary B. The Contract C. Period Of Performance D. Work Conditions/Site Requirements E. Authorized Representatives F. Contract Liquidated Damages Rate G. Buy American Exceptions H. Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments
II. Prices
A. Basis of Pricing B. Contract Price Form
III. Terms and Conditions
A. Commencement, Prosecutions and Completion of Work B. Contractor Responsibilities C. Submittals D. Finality of Contract Modifications E. Liquidated Damages F. Insurance Requirements G. Order of Precedence H. Administrative Matters I. Non-Compliance with Contract Requirements J. Safeguarding Sensitive Data and Information Technology Resources K. Options and Allowances L. Additional Terms and Conditions
i. GSAR 552.236-74, Evaluation of Options (Mar 2019)
iii. GSAR552.236-76, Basis of Award – Sealed Bidding Construction (Mar 2019)
iv. GSAR 552.236-77, Government’s Right to Exercise Options (Mar 2019)
IV. Contract Clauses A. Clauses Incorporated in Full Text
1. FAR 52.222-99 Establishing a Minimum Wage for Contractor (JUL 2014)
(DEVIATION)
2. FAR 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013)
3. FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (MAY 08)
4. GSAR 552.204-9 Personal Identity Verification Requirements (OCT 2012)
5. GSAR 552.211-10 Commencement, Prosecution and Completion of Work
(Mar 2019)
6. GSAR 552.211-12 Liquidated Damages-Construction (Mar 2019)
7. GSAR 552.211-13 Time Extensions (Mar 2019)
8. GSAR 552.211-70 Substantial Completion (Mar 2019)
9. GSAR 552.232-5 Payments Under Fixed-Price Construction Contracts (Mar 2019)
10. GSAR 552.236-6 Superintendence by the Contractor (Mar 2019)
11. GSAR 552.236-11 Use and Possession Prior to Completion (Mar 2019)
12. GSAR 552.236-15 Schedules for Construction Contracts (Mar 2019)
13. GSAR 552.236-21 Specifications and Drawings for Construction (Mar 2019)
14. GSAR 552.236-71 Contractor Responsibilities (Mar 2019)
15. GSAR 552.236-72 Submittals (Mar 2019)
16. GSAR 552.252-6 Authorized Deviations in Clauses (Deviation FAR 52.252-6)
(Sep 99)
17. FAR 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (AUG 2019)
18. GSAR 552.204-70, Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment. (DEVIATION I) (AUG 2019)
19. Buy American Requirements
20. Additional Clauses
i. GSAR 552.236-70 Authorities and Limitations (Mar 2019)
ii. GSAR 552.236-73 Subcontracts (Mar 2019)
21. iii. GSAR 552.243-71 Equitable Adjustments (Mar 2019)Special 8(a) Requirements
22. FAR 52.222-62, Paid Sick Leave under Executive Order 13706 (Jan 2017) B. 23. FAR 52.223-21, FOAMS (Jun 2016)Clauses Incorporated by Reference C. Subcontract Requirements
I. Project Information
I.A. Project Summary
The General Services Administration (GSA) intends to waterproof the exterior foundation walls on the north (Jamaica Ave) and south (Archer Ave) sides of the Addabbo Federal Office Building (FOB) and ancillary work described herein at the Joseph P. Addabbo Federal Office Building, 155-10 Jamaica Ave, Jamaica, New York 11432. The contractor awarded the contract shall meet the requirements of this using the design/build delivery method.
I.B. The Contract
The Contract consists of the SF1442, the Agreement, the Statement of Work, Specifications, Drawings, Exhibits, Amendments, Modifications, and other Attachments identified herein (collectively, the Contract Documents). The Contract contains the entire agreement of the Parties, and no prior written or oral agreement, express or implied, shall be admissible to contradict or modify any part of the Contract.
(2) The Contractor shall provide and pay for all labor, materials, equipment, tools, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution of the work described in and reasonably inferable from the Contract Documents (the Work), whether temporary or permanent. In consideration for, and upon condition of, the Contractor's completion of the Work, GSA shall pay the Contractor the price or prices established in Section II, subject to the terms and conditions set forth in this Contract.
I.C. Period of Performance
(1) Commencement. The Contractor shall commence performance of the Work within 10 days after the Contractor receives the Notice to Proceed (NTP).
(2) Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than 217 calendar days from issuance of Notice to Proceed (NTP).
(3) Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 60 calendar days of Substantial Completion.
I.D. Work Conditions/Site Requirements
1. The contractor shall provide their own facilities to execute this work. These facilities will be outside of the building. The contractor shall show their proposed facilities on the Logistics plan that is to be submitted for GSA and SSA review and approval. The contractor shall be responsible for the storage and safe keeping of their construction materials. The construction contractor is solely responsible for the security of this area.
2. During the contractor's working hours, parking shall not be permitted on site.
3. The contractor is to provide and maintain the required toilet facilities on site but outside of the building. Contractor personnel are not permitted to use the toilet facilities inside of the building.
4. Contractor shall have sole responsibility for the selection and supervision of the appropriate, safe, and lawful means and methods of construction and construction operations, and shall ensure that all construction personnel are fully cognizant of their responsibilities under the contract documents and any other applicable requirements.
5. Provide a full time, competent, New York City licensed superintendent at the site.
6. Contractor shall be responsible for and must submit a safety plan to the GOV for approval, construction means and methods and safety procedures. Work and all construction operations shall be performed with strict adherence to mandated safety procedures, and in strict conformance with governmental standards, and building department regulations.
7. Contractor to coordinate all trades and sequences of work. All penetrations and partial demolition required for construction installations to be coordinated by the GC with GSA/SSA.
Site Protection
1. Provide temporary bracing and make safe all work areas at the site, and adjacent property as conditions require.
2. Provide, maintain, and pay for temporary services necessary to perform the work. Where existing utilities/facilities are available for use they may be utilized subject to contractor being responsible for proper maintenance and care. The contractor is reliable for securing all construction materials and equipment, the GOV will not be held responsible for any equipment or materials while at the work site.
3. Perform drilling and cutting necessary for the work. After installation work is completed, patch any disturbed adjacent construction in a neat and satisfactory manner, in conformance with applicable provisions of the contract documents.
4. To the satisfaction of the owner and the architect, work damaged or disturbed during the course of work shall be properly repaired with similar materials. Holes and depressions for piping, hardware or other such items which are removed during the course of work shall be patched and filled smooth.
5. Items indicated to be salvaged shall be carefully removed, and protected until ready for removal from the site or for reinstallation, at which time these shall be carefully re-installed.
6. Demolished items shall be promptly removed, and the premises kept "broom clean".
7. Provide necessary protection such as drop cloths, etc., to protect owner's property remaining at the site during the course of work hereunder.
8. Properly disconnect, remove, and legally dispose of existing construction being abandoned or no longer used or needed in the work, unless otherwise noted.
9. Removal work shall be performed to neat lines, and so as to minimize damage to existing portions of the work which are to remain.
10. Provide four (4) new trench drains, two (2) at the loading dock and two (2) at the entrance to the garage.
11. Protect the Under Vehicle Inspection System (U.V.I.S.) from damage throughout construction.
12. Contractor will be required to provide connections to systems outside the main area of work to satisfy the contract documents. Care should be taken when removing existing materials to access connection points/ areas and any required demolition, patching, repair & finishing completed in kind to match existing conditions.
I.E. Authorized Representatives
(1) This Contract is between the United States of America, acting by and through the Administrator of General Services (GSA), and the Contractor (the Parties). References in this Contract to "the Owner" or "the Government" shall be understood to refer to GSA. The following individual is designated as the only authorized GSA representative under this Contract, unless other warranted contracting officers are designated in writing:
Authorized Representative Information:
Contracting Officer’s Information
Name: Rhonda A. Pretlow
Address: General Services Administration 225 Cadman Plaza East Rm N180 Brooklyn, NY 11201
Telephone: 718-510-1817
Email: rhonda.pretlow@gsa.gov
(2) For the applicable authorities and limitations see Section IV of this Agreement, GSAR 552.236-70.
I.F. Contract Liquidated Damages Rate
In accordance GSAR 552.211-12, Liquidated Damages – Construction, in Section IV of this Agreement, liquidated damages shall be calculated at the rate of $1,073.20 per calendar day.]
I.G. Buy American Exceptions
For the applicable Buy American clause and any exceptions, see Section IV of this Agreement.
I.H. Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments
The following documents are incorporated by reference into this Contract.
1) Statement of Work
2) Wage Determination NY20190003, Dated 10/25/2019
The following documents are Sensitive but Unclassified (SBU) and require sign-in to the portal for access:
3) 2015 0617 Addabbo Paver Bid Set Specifications.pdf
4) 2015 0617 Addabbo Waterproofing 100% CAD-BID.pdf
5) 2015-03-15 Survey Plan.pdf
6) 2015-12-23 Jamaica Social Security Center Layout Plan2.pdf
7) 2018 0206 – 001-ARCHER-SURFACE-PROFILE.pdf
8) 2018 0206 – 002-ARCHER-SURFACE-PROFILE.pdf
9) 2018 0206 – 003-ARCHER SURFACE-PROFILE-SLOPES.pdf
10) 2018 0206 – 004-ARCHER-SEC-BOOTH-SETL.pdf
11) 2019-0217 – 01-Binder1-26-DWG PKG-1.pdf
12) 2019 1011 – SSA BIM Parameters Worksheet (v1.6).xlsx
13) 2019 1011 – SSA BIM Project Execution Plan (v1.6).xlsx
14) 2019 1011 – SSA BIM Requirements Document (v1.6).pdf
15) ADBO_STRL_PLNS_DTLS.pdf
16) Addabbo Survey 2011 C-1-0.pdf
17) C-0-1.pdf
18) C-1-0.pdf
19) C-1-1.pdf
20) C-2-1.pdf
21) C-2-2.pdf
22) C-2-3.pdf
23) C-2-4.pdf
24) C-2-5.pdf
25) C-2-6.pdf
26) C-3-1.pdf
27) C-3-2.pdf
28) C-4-1.pdf
29) C-4-2.pdf
30) GSA’s ePM Requirements – Appendix B.docx
II. Prices
II.A. Basis of Pricing
(1) Contract Prices. All Contract prices set forth in this Section include all costs necessary to complete the work for which the price is established (e.g., Base Contract, Unit Price, Options) in accordance with the Contract Documents, including, but not limited to, the cost of work performed by subcontractors and consultants, indirect costs, fees, expenses, taxes, and profit.
(2) Knowledge of Conditions Affecting Price. FAR 52.236-3, Site Investigations and Conditions Affecting the Work, is incorporated by reference in this Contract. The Contractor shall be presumed to have established all prices with knowledge of general and local conditions that may affect the cost of Contract performance at the site where the Work is to be performed, to the extent that such information is reasonably obtainable.
(3) Unit Prices and Allowances. If any portion of the Work is to be performed on a unit price basis, the Unit Price shall include all costs of coordinating and incorporating the unit-priced portion of the Work into the Base Contract Work. The Contractor shall only be obligated to perform unit-priced work to the extent that an Allowance has been established. The Contractor shall be obligated to perform such work in excess of a unit quantity for which an Allowance is established only if directed by the Contracting Officer in writing. The Contractor shall be bound to the unit price or prices set forth herein in all equitable adjustments for changes including unit priced work, and no markups shall be applied to such unit prices.
(4) Options. If any portion of the Work is to be performed upon the timely exercise of an Option, the Option Price shall include all costs of coordinating and incorporating the Option-priced portion of the Work into the Base Contract Work. An adjustment to the Contract price for such additional work shall be computed solely on the basis of the Option price or prices set forth herein. Unless otherwise specified, all options may be exercised within 90 days of Contract award.
(5) Bid Rates. If this Contract includes Bid Rates to be used in determination of equitable adjustments (e.g., overhead, profit, daily rates for time-related costs), such rates shall be deemed to include all costs recoverable as components of an equitable adjustment consistent with the requirements, definitions, and exclusions applicable to equitable adjustments set forth in this Contract, and consistent with the Contractor's cost accounting practices. Unless otherwise specified, the bid rates shall be deemed to include only the Contractor's costs, and not the costs of any subcontractors.
II.B. Contract Price Form
Please refer to SF 1442 and attached GC Bid Sheets for the Contract Price Form and related information.
III. Terms and Conditions
III.A. Commencement, Prosecution, and Completion of Work
FAR 52.211-10, Commencement, Prosecution, and Completion of Work and GSAR 552.211-10, Commencement, Prosecution and Completion of Work is supplemented as follows:
The Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of the Work, as defined in GSAR 552.211-70 Substantial Completion (Mar 2019) and the time specified in Section I (Project Information), “Period of Performance” clause. If the Contract specifies different completion dates for different phases or portions of the Work, the Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of such phases or portions of the Work within the times specified.
III.B. Contractor Responsibilities
GSAR 552.236-71, Contractor Responsibilities is located in Section IV.A. of this Agreement and is supplemented as follows:
(1) The Contractor shall secure and pay for all necessary permits and governmental fees, licenses, and inspections that are customarily secured after award of the Contract and that are legally required at the time of award. The Contractor shall provide a copy of the permits required for execution of the work to the Contracting Officer prior to commencement of any related work.
III.C. Submittals
FAR 52.236-21, Specifications and Drawings for Construction, GSAR 552.236-73, Submittals located in Section IV.A. of the Agreement is supplemented as follows:
(1) The Contractor shall prepare and submit to the Contracting Officer shop drawings, samples, calculations, product information, mockups, GSA Form 184 (associated 184A and 184B as necessary), and other submittals (collectively, "submittals") demonstrating compliance with Contract requirements for all Work components as specified elsewhere in this Contract.
III.D. Finality of Contract Modifications As set forth elsewhere in this Contract, the Contractor is entitled to additional consideration under certain conditions, including the issuance of change orders. It is the Contractor's duty to include in proposals for equitable adjustment or other consideration all compensation to which it may be entitled, including cost and time. Unless otherwise explicitly stated in a modification to the Contract providing such consideration, adjustments to the Contract price or time agreed upon therein shall be deemed to provide all compensation to which the Contractor is entitled, and shall constitute final settlement of the Contractor's entitlement to compensation on account of the change or other condition giving rise to the modification.
III.E. Liquidated Damages
The Contractor acknowledges that time is of the essence for the performance of the Work, and that determining actual damages from delay would be extremely difficult and impractical. If the Contractor fails to achieve Substantial Completion of the Work in accordance with FAR 52.211- 12, Liquidated Damages and GSAR 552.211-12, Liquidated Damages and the time specified in this Contract, the Contractor shall be liable to the Government for liquidated damages at the rate specified in Section I (Project Information), paragraph entitled, “Liquidated Damages Rate,” for each calendar day following the required completion date that the Work is not Substantially Complete.
III.F. Insurance Requirements
(1) The Contractor shall obtain and maintain for the entire life of the Contract, in addition to any insurance required by law, the following minimum kinds and amounts of insurance required pursuant to FAR clause 52.228-5, Insurance – Work on a Government Installation, and GSAR 552.228-5, Government as Additional Insured.
(a) Workers' compensation insurance in the amount required by the jurisdiction in which the Contract is performed. The Contractor shall obtain Employers' liability coverage of at least $2,000,000. If occupational diseases are not covered by workers' compensation insurance, Employers' liability coverage shall include occupational diseases.
(b) Broad form comprehensive commercial general liability insurance in the amount of at least $5,000,000 per occurrence. Such insurance shall include, but not be limited to, contractual liability, bodily injury and property damage.
(c) Comprehensive automobile liability covering the operation of all automobiles used in connection with performing the Contract in the amount of at least $1,000,000 per person and $2,500,000 per occurrence for bodily injury and $1,000,000 per occurrence for property damage.
(2) The Contractor shall promptly provide to the Contracting Officer proof that it has obtained insurance required by the Contract in the form of certificates of insurance. The Contractor shall submit to the Contracting Officer all renewal certificates issued during the life of this Contract immediately upon issuance.
III.G. Order of Precedence
Different requirements within this Contract shall be deemed inconsistent only if compliance with both cannot be achieved. In case of inconsistency between Contract Documents, the following order of precedence shall apply:
(1) Section IV of the Agreement
(2) Sections I, II, and III of the Agreement
(3) The Statement of Work
(4) The Specifications
(5) The Drawings
III.H. Administrative Matters
(1) Project Meetings. The Contractor shall attend a preconstruction conference and shall participate in regularly scheduled Project meetings.
(2) Payments. FAR clause 52.232-5, Payments under Fixed-Price Construction Contracts, is supplemented by GSAR 552.232-5 Payments under Fixed-Price Construction Contracts located in Section IV.A. of this Agreement. In accordance with the relevant FAR and GSAR clauses, GSA requires the following data be included with each invoice:
(a) Invoices shall be submitted in an original and two (2) copies to the designated billing office specified in this Contract or in individual delivery/work orders.
(b) Invoices must include the Account Document Number (ADN) assigned at award.
(c) The Contractor shall submit the following information or documentation with each invoice:
(i) GSA Form 184A and/or 184B - Construction Progress Report (Construction Phases Only), including the updated Schedule of Values upon which the payment request is based;
(ii) GSA Form 2419 - Certification of Progress Payments Under Fixed-Price Construction Contract;
(iii) The payment terms that apply for the particular services rendered
(iv) Updated project schedule that complies with the Contract Documents
(v) Additional documentation:
NA
(3) Prompt Payment. In accordance with FAR clause 52.232-27, the period for payments is as follows:
(a) Progress Payments: 14 days
(b) Subsequent Subcontractor Payments: 7 days
(4) Payment Information. The General Services Administration (GSA) makes information on contract payments available electronically at Office of the Chief Financial Officer. The Contractor may register at the site and review its record of payments. This site provides information only on payments made by GSA, not by other agencies.
(5) Security Clearances. Contractor shall comply with the following requirements pertaining to security clearances.
(a) All personnel performing work under the Contract on the Project site must obtain an Enter on Duty (EOD) determination before they will be granted access to the site.
(b) To obtain an EOD determination, Contractor shall submit for all such personnel fingerprints on Form SF87 and a completed Contractor Information Worksheet (CIW). Detailed information is available at GSA Access Card . USAccess Credentialing Centers can be located at US Access Centers .
(c) In addition, all such personnel who will be on site 6 months or longer must apply for and receive clearance in accordance with Homeland Security Presidential Directive 12 (HSPD- 12). See Section IV, Contract Clauses, GSAR 552.204-9.
(6) Safeguarding and Dissemination of Sensitive But Unclassified (SBU) Building Information.
This clause applies to all recipients of SBU building information, including offerors, bidders, awardees, contractors, subcontractors, lessors, suppliers and manufacturers.
(a) Marking SBU. Contractor-generated documents that contain building information must be reviewed by GSA to identify any SBU content, before the original or any copies are disseminated to any other parties. If SBU content is identified, the Contracting Officer (CO) may direct the contractor, as specified elsewhere in this contract, to imprint or affix SBU document markings to the original documents and all copies, before any dissemination.
(b) Authorized recipients.
(i) Building information designated SBU must be protected with access strictly controlled and limited to those individuals having a legitimate business need to know such information.
Those with a need to know may include Federal, State and local government entities, and nongovernment entities engaged in the conduct of business on behalf of or with GSA.
Nongovernment entities may include architects, engineers, consultants, contractors, subcontractors, suppliers, utilities, and others submitting an offer or bid to GSA, or performing work under a GSA contract or subcontract. Recipient contractors must be registered as “active” in the System for Award Management (SAM) database at www.sam.gov and have a legitimate business need to know such information. If a subcontractor is not registered in the SAM and has a need to possess SBU building information, the subcontractor shall provide to the contractor its DUNS number or its tax ID number and a copy of its business license. The contractor shall keep this information related to the subcontractor for the duration of the contract and subcontract.
(ii) All GSA personnel and Contractors must be provided SBU building information when needed for the performance of official Federal, State, and local government functions, such as for code compliance reviews and for the issuance of building permits. Public safety entities such as fire and utility departments may require access to SBU building information on a need to know basis. This clause must not prevent or encumber the dissemination of SBU building information to public safety entities.
c. Dissemination of SBU building information:
(i) By electronic transmission. Electronic transmission of SBU information outside of the
GSA network must use session encryption (or alternatively, file encryption). Encryption must be via an approved NIST algorithm with a valid certification, such as Advanced Encryption Standard (AES) or Triple Data Encryption Standard (3DES), in accordance with Federal Information Processing Standards Publication (FIPS PUB) 140-2, Security Requirements for Cryptographic Modules per GSA policy.
(ii) By nonelectronic form or on portable electronic data storage devices. Portable electronic data storage devices include, but are not limited to CDs, DVDs, and USB drives.
Nonelectronic forms of SBU building information include paper documents, among other formats.
1) By mail. Contractors must utilize only methods of shipping that provide services for monitoring receipt such as track and confirm, proof of delivery, signature confirmation, or return receipt.
2) In person. Contractors must provide SBU building information only to authorized recipients with a need to know such information. Further information on authorized recipients is found in Section 2 of this clause.
d. Record keeping. Contractors must maintain a list of all entities to which SBU is disseminated, in accordance with sections 2 and 3 of this clause. This list must include at a minimum: (1) the name of the State, Federal, or local government entity, utility, or firm to which SBU has been disseminated; (2) the name of the individual at the entity or firm who is responsible for protecting the SBU building information, with access strictly controlled and limited to those individuals having a legitimate business need to know such information; (3) contact information for the named individual; and (4) a description of the SBU building information provided. Once “as built” drawings are submitted, the contractor must collect all lists maintained in accordance with this clause, including those maintained by any subcontractors and/or suppliers, and submit them to the CO. For Federal buildings, final payment may be withheld until the lists are received.
e. Safeguarding SBU documents. SBU building information (both electronic and paper formats) must be protected, with access strictly controlled and limited to those individuals having a legitimate business need to know such information. GSA contractors and subcontractors must not take SBU building information outside of GSA or their own facilities or network, except as necessary for the performance of that contract. Access to the information must be limited to those with a legitimate business need to know.
f. Destroying SBU building information. When no longer needed, SBU building information must be destroyed so that marked information is rendered unreadable and incapable of being restored, in accordance with guidelines provided for media sanitization within GSA CIO IT Security 06-32, Media Sanitization Guide and Appendix A of NIST Special Publication 800-88, Guidelines for Media Sanitization. Alternatively, SBU building information may be returned to the CO.
g. Notice of disposal. The contractor must notify the CO that all SBU building information has been returned or destroyed by the contractor and its subcontractors or suppliers in accordance with paragraphs 4 and 6 of this clause, with the exception of the contractor's record copy. This notice must be submitted to the CO at the completion of the contract to receive final payment. For leases, this notice must be submitted to the CO at the completion of the lease term. The contractor may return the SBU documents to the CO rather than destroying them.
h. Incidents. All improper disclosures of SBU building information must be immediately reported to the CO at rhonda.pretlow@gsa.gov. If the contract provides for progress payments, the CO m at rhonda.pretlow@gsa.gov. If the contract provides for progress payments, the CO may withhold approval of progress payments until the contractor provides a corrective action plan explaining how the contractor will prevent future improper disclosures of SBU building information. Progress payments may also be withheld for failure to comply with any provision in this clause until the contractor provides a corrective action plan explaining how the contractor will rectify any noncompliance and comply with the clause in the future.
i. Subcontracts. The contractor and subcontractors must insert the substance of this clause in all subcontracts.
III.I. Non-Compliance with Contract Requirements
In the event the Contractor, after receiving written notice from the Contracting Officer of non-compliance with any requirement of this Contract, fails to initiate promptly such action as may be appropriate to comply with the specified requirement within a reasonable period of time, the Contracting Officer shall have the right to order the Contractor to stop any or all work under the Contract until the Contractor has complied or has initiated such action as may be appropriate to comply within a reasonable period of time. The Contractor will not be entitled to any extension of Contract time or payment for any costs incurred as a result of being ordered to stop work for such cause.
III.J. Safeguarding Sensitive Data and Information Technology Resources
In accordance with FAR 39.105, this section is included in the contract. This section applies to all users of sensitive data and information technology (IT) resources, including awardees, contractors, subcontractors, lessors, suppliers and manufacturers. The following GSA policies must be followed.
These policies can be found at Directives Library.
1. CIO P 2100.1K GSA Information Technology (IT) Security Policy
2. CIO P 2100.2B GSA Wireless Local Area Network (LAN) Security
3. CIO 2100.3C Mandatory Information Technology (IT) Security Training Requirement for
Agency and Contractor Employees with Significant Security Responsibilities
4. CIO 2104.1A CIO CHGE 1 GSA Information Technology IT General Rules of Behavior
5. CIO 2105.1 C CHGE 1 GSA Section 508: Managing Electronic and Information
Technology for Individuals with Disabilities
6. CIO 2106.1 GSA Social Media Policy
7. CIO 2107.1 Implementation of the Online Resource Reservation Software
8. CIO 2160.4A Provisioning of Information Technology (IT) Devices
9. CIO 2162.1 Digital Signatures
10. CIO P 2165.2 GSA Telecommunications Policy
11. CIO P 2180.1 GSA Rules of Behavior for Handling Personally Identifiable Information
(Pll)
12. CIO 2182.2 Mandatory Use of Personal Identity Verification (PIV) Credentials
13. CIO P 1878.2A Conducting Privacy Impact Assessments (PIAs) in GSA
14. CIO IL-13-01 Mobile Devices and Applications
15. CIO 2102 Information Technology (IT) Integration Policy
16. HCO 9297.1 GSA Data Release Policy
17. HCO 9297.2B GSA Information Breach Notification Policy
18. ADM P 9732.1 D Suitability and Personnel Security
The contractor and subcontractors must insert the substance of this section in all subcontracts.
III.K. Options and Allowances
Option - South Side
1. Excavate, remove existing waterproofing, and install new waterproofing on the foundation wall on Archer Ave;
2. Working with the AE Team and Civil Engineer, investigate the settling of the sidewalk on the Archer Ave side of the building, and prescribe in the CD’s the work required to remedy the settling of the sidewalk;
3. Remove existing and provide new sidewalk on the Archer Ave side of the building. Investigate and provide adequate backfill to support the new sidewalk;
4. Remove existing steel surround at the columns as required in order to waterproof, waterproof, and replace the steel surround with new steel surround;
5. Investigate the concrete abutments on the south side, and prescribe in the CD’s the work required to repair and waterproof the concrete abutments;
6. Investigate trench drain at the Loading Dock, and provide in the CD’s for it’s replacement;
7. Investigate the settlement of the existing Security Guard Booth on the south side, and prescribe in the CD’s the work required in order to properly support and reset the Guard Booth.
8. Provide for the replacement of the trench drain at the Loading Dock area so that it is properly waterproofed as part of this project.
9. Investigate the structural steel at the sidewalk level by the Loading Dock that is scheduled to be replaced by this project. This steel is partially located in the Mechanical Equipment Room (MER) in the Lower Level of the building. This scope is shown on the Dewberry CD’s dated June 17, 2015.
III.L. Additional Terms and Conditions
(i) GSAR 552.236-74, Evaluation of Options (MAR 2019) The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(ii) GSAR 552.236-76, Basis of Award – Sealed Bidding Construction (MAR 2019) A bid may be rejected as nonresponsive if the bid is materially unbalanced as to bid prices. A bid is unbalanced when the bid is based on prices significantly less than cost for some work and significantly overstated for other work.
(iii) GSAR 552.236-77, Government’s Right to Exercise Options (MAR 2019)
(a) The Government may exercise any option in writing in accordance with the terms and conditions of the contract. Unless otherwise specified, options may be exercised within 217 calendar days from Notice to Proceed.
(b) If the Government exercises the option, the contract shall be considered to include this option clause.
IV. Contract Clauses
IV.A. Clauses Incorporated in Full Text
(1) FAR 52.222-99 Establishing a Minimum Wage for Contractor (JUL 2014) (DEVIATION) This clause implements Executive Order 13658, Establishing a Minimum Wage for Contractors, dated February 12, 2014, and OMB Policy Memorandum M-14-09, Implementation of the President's Executive Order Establishing a Minimum Wage for Contractors, dated June 12, 2014.
(a) Each service employee, laborer, or mechanic employed in the United States (the 50 states and the District of Columbia) in the performance of this contract by the prime Contractor or any subcontractor, regardless of any contractual relationship which may be alleged to exist between the Contractor and service employee, laborer, or mechanic, shall be paid not less than the applicable minimum wage under Executive Order 13658. The minimum wage required to be paid to each service employee, laborer, or mechanic performing work on this contract between January 1, 2015, and December 31, 2015, shall be $10.10 per hour.
(b) The Contractor shall adjust the minimum wage paid under this contract each time the Secretary of Labor's annual determination of the applicable minimum wage under section 2(a)(ii) of Executive Order 13658 results in a higher minimum wage. Adjustments to the Executive Order minimum wage under section 2(a)(ii) of Executive Order 13658 will be effective for all service employees, laborers, or mechanics subject to the Executive Order beginning January 1 of the following year. The Secretary of Labor will publish annual determinations in the Federal Register no later than 90 days before such new wage is to take effect. The Secretary will also publish the applicable minimum wage on www.wdol.gov (or any successor website). The applicable published minimum wage is incorporated by reference into this contract.
(c) The Contracting Officer will adjust the contract price or contract unit price under this clause only for the increase in labor costs resulting from the annual inflation increases in the Executive Order 13658 minimum wage beginning on January 1, 2016. The contracting Officer shall consider documentation as to the specific costs and workers impacted in determining the amount of the adjustment.
(d) The Contracting Officer will not adjust the contract price under this clause for any costs other than those identified in paragraph (c) of this clause, and will not provide price adjustments under this clause that result in duplicate price adjustments with the respective clause of this contract implementing the Service Contract Labor Standards statute (formerly known as the Service Contract Act) or the Wage Rate Requirements (Construction) statute (formerly known as the Davis Bacon Act).
(e) The Contractor shall include the substance of this clause, including this paragraph (e) in all subcontracts.
(2) FAR 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013)
(a) In the performance of this contract, the contractor shall make maximum use of biobased products that are United States Department of Agriculture (USDA)-designated items unless—
(1) The product cannot be acquired—
(i) Competitively within a time frame providing for compliance with the contract performance schedule;
(ii) Meeting contract performance requirements; or
(iii) At a reasonable price.
(2) The product is to be used in an application covered by a USDA categorical exemption (see 7 CFR 3201.3(e)). For example, all USDA-designated items are exempt from the preferred procurement requirement for the following:
(i) Spacecraft system and launch support equipment.
(ii) Military equipment, i.e., a product or system designed or procured for combat or combat-related missions.
(b) Information about this requirement and these products is available at BioPreferred.
(c) In the performance of this contract, the Contractor shall—
(1) Report to System Award Management, with a copy to the Contracting Officer, on the product types and dollar value of any USDA-designated biobased products purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30; and
(2) Submit this report no later than—
(i) October 31 of each year during contract performance; and
(ii) At the end of contract performance.
(3) FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated
Items (MAY 08)
(a) Definitions. As used in this clause—
“Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”
“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this Contract, shall—
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and
(2) Submit this estimate to the Contracting Officer.
(4) GSAR 552.204-9 Personal Identity Verification Requirements (OCT 2012)
(a) The contractor shall comply with GSA personal identity verification requirements, identified at HSP12, if contractor employees require access to GSA controlled facilities or information systems to perform contract requirements.
(b) The Contractor shall insert this clause in all subcontracts when the subcontractor is required to have access to a GSA-controlled facility or access to a GSA-controlled information system.
(5) GSAR 552.211-10 Commencement, Prosecution and Completion of Work (MAR 2019)
FAR 52.211-10, Commencement, Prosecution, and Completion of Work, is supplemented as follows:
(a) The Contractor shall not commence work until the Contracting Officer issues a notice to proceed.
(b) Notwithstanding paragraph (a) above, the Contractor must submit any required safety plans before commencing any construction work.
(c) The Contractor shall diligently prosecute the work so as to achieve substantial completion of the work within the time specified in the contract. If the contract specifies different completion dates for different phases or portions of the work, the Contractor shall diligently prosecute the work so as to achieve substantial completion of such phases or portions of the work within the times specified.
(6) GSAR 552.211-12 Liquidated Damages-Construction (MAR 2019)
FAR 52.211-12, Liquidated Damages-Construction, is supplemented as follows:
(a) If the Contractor fails to achieve substantial completion of the work within the time specified in the contract, the Contractor shall be liable to the Government for liquidated damages at the rate specified for each calendar day following the required completion date that the work is not substantially complete.
(b) If the contract requires different completion dates for different phases or portions of the work, the Contractor shall be liable for liquidated damages at the specified rate for each calendar day following the required completion date that the phase or portion of work is not substantially complete. If a single rate is specified, the specified rate shall be apportioned between the different phases or portions of the work.
(c) If the Government elects to accept any portion of the work not specifically designated as a phase or portion of work with its own required completion date, the liquidated damage rate shall be apportioned between accepted work and uncompleted work, and the Contractor's liability for liquidated damages shall be computed accordingly.
(7) GSAR 552.211-13 Time Extensions (MAR 2019)
FAR 52.211-13, Time Extensions, is supplemented as follows:
(a) If the Contractor requests an extension of the time for substantial completion, the
Contractor shall base its request on an analysis of time impact using the project schedule as its baseline, and shall propose as a new substantial completion date to account for the impact. The Contractor shall submit a written request to the Contracting Officer setting forth facts and analysis in sufficient detail to enable the Contracting Officer to evaluate the Contractor's entitlement to an extension of time.
(b) The Contractor shall only be entitled to an extension of time to the extent that:
(1) Substantial completion of the work is delayed by causes for which the Contractor is not responsible under this contract, and
(2) The actual or projected substantial completion date is later than the date required by this contract for substantial completion.
(c) The Contractor shall not be entitled to an extension of time if the Contractor has not updated the project schedule in accordance with the contract.
(d) The Government shall not be liable for any costs to mitigate time impacts incurred by the Contractor that occur less than 30 calendar days after the date the Contractor submits a request for extension of time in compliance with this clause.
(8) GSAR 552.211-70 Substantial Completion (MAR 2019)
(a) General.
(1) For the purposes of FAR 52.211-10, Commencement, Prosecution and Completion of Work, and FAR 52.211-12, Liquidated Damages-Construction, the work shall be deemed complete when it is “substantially complete.”
(2) There may be different completion dates required for different phases or portions of the work, as established in the contract. However, the work shall be deemed "substantially complete" if and only if the Contractor has completed the work and related contract obligations in accordance with the contract documents, such that the Government may enjoy the intended access, occupancy, possession, and use of the entire work without impairment due to incomplete or deficient work, and without interference from the Contractor's completion of remaining work or correction of deficiencies in completed work.
(3) In no event shall the work be deemed “substantially complete” if all fire and life safety systems are not tested and accepted by the authority having jurisdiction, where such acceptance is required under the contract.
(4) Unless otherwise specifically noted, or otherwise clear from context, all references in the contract to "acceptance" shall refer to issuance of a written determination of substantial completion by the Contracting Officer.
(b) Notice of Substantial Completion.
(1) With reasonable advance notice, the Contractor shall submit to the Contracting Officer a written proposal recommending a substantial completion date.
(2) If the Contracting Officer takes exception to the notice of substantial completion, the Contractor shall be entitled to a written notice of conditions precluding determination of substantial completion. The Contractor shall only be entitled to an extension of time to address such conditions if, and to the extent that, the Contracting Officer provides notice of such conditions more than 30 calendar days after receipt of the notice of substantial completion.
(c) Acceptance of Substantial Completion.
(1) The Contracting Officer shall conduct inspections and make a determination of substantial completion within a reasonable time.
(2) Substantial Completion shall be established by the Contracting Officer's issuance of a written determination specifying the date upon which the work is substantially complete.
(d) Contract Completion.
(1) The Contract is complete if and only if the Contractor has completed all work and related contract obligations, corrected all deficiencies and all punch list items, and complied with all conditions for final payment.
(2) The Contractor shall not be entitled to final payment or release of any retainage held by the Government until after contract completion. If the Contractor does not achieve contract completion within the time required by this contract, the Government shall be entitled, after providing notice to the Contractor, to complete any work remaining unfinished. The Contractor shall be liable to the Government for all costs incurred by the Government to complete such work.
(9) GSAR 552.232-5 Payments Under Fixed-Price Construction Contracts (Mar 2019)
FAR 52.232-5, Payments under Fixed-Price Construction Contracts, is supplemented as follows:
(a) Before submitting a request for payment, the Contractor shall, unless directed otherwise by the Contracting Officer, attend pre-invoice payment meetings, as scheduled, with the designated Government representative for the purpose of facilitating review and approval of payment requests. Payment meetings will be conducted and may be in person. The Contractor shall provide documentation to support the prospective payment request.
(b) The Contractor shall submit its invoices to the Contracting Officer, unless directed otherwise by the Contracting Officer. Separate payment requests shall be submitted for progress payments, payments of retainage, and partial or final payments.
(c) The Contractor shall use GSA Form 2419 Certification of Progress Payments Under Fixed-Price Construction Contracts to provide the certification required under FAR 52.232-5(c).
(d) The Contractor shall use GSA Form 1142 Release of Claims to provide the certification required under FAR 52.232-5(h).
(e) If an invoice does not meet the requirements of FAR 52.232-27 and GSAM 552.232- 27, the Contracting Officer may return the invoice to the Contractor without payment for correction. If the Contracting Officer disputes the requested payment amount, the Government may pay the portion of the requested payment that is undisputed.
(f) GSA will not be obligated to issue final payment unless the Contractor has furnished to the Contracting Officer a release of claims against the Government relating to the contract, and submitted all required product warranties, as-built drawings, operating manuals, and other items as specified in the contract. The Contractor may reserve from the release specific claims only if such claims are explicitly identified with stated claim amounts.
(10) GSAR 552.236-6 Superintendence by the Contractor (MAR 2019) The requirements, of the clause entitled “Superintendence by the Contractor” at FAR 52.236-6, are supplemented as follows:
(a) The Contractor shall employ sufficient management and contract administration resources, including personnel responsible for project management, field superintendence, change order administration, estimating, coordination, inspection, and quality control, to ensure the proper execution and timely completion of the contract.
The Contractor shall designate a principal of the firm or other senior management official to provide executive oversight and problem resolution resources to the project for the life of the contract.
(b) The Contractor shall employ, and require its subcontractors to employ, qualified personnel to perform the contract. The Government reserves the right to exclude, or remove from the site or building, any personnel for reasons of incompetence, carelessness, or insubordination, who violate rules and regulations concerning conduct on federal property, or whose continued employment on the site is otherwise deemed by the Government to be contrary to the public interest.
(c) The Contractor shall be responsible for coordinating all activities of subcontractors, including all of the following activities —
(1) Preparation of shop drawings produced by different subcontractors where their work interfaces or may potentially conflict or interfere; and
(2) Scheduling of work by subcontractors; and
(3) Installation of work by subcontractors; and
(4) Use of the project site for staging and logistics.
(d) Repeated failure or excessive delay to meet the superintendence requirements by the Contractor may be deemed a default for the purposes of the termination for default clause.
(11) GSAR 552.236-11 Use and Possession Prior to Completion (MAR 2019) Exercise by the Government of the right conferred by FAR 52.236-11 shall not relieve the Contractor of responsibility for completing…