This document is a design supplement for the 42240025 RANGE ROAD REPAVING project at Fort Indiantown Gap in Pennsylvania. The work includes replacing two 42-inch culvert pipes with HDPE pipes, replacing a 72-inch culvert pipe, installing rip rap aprons, full-depth removal and repaving of approximately 140,000 square feet of asphalt, removal and replacement of a 95-square yard concrete tank pad, sealing cracks and applying a seal coat, milling and repaving of 155,000 square feet, and completing line painting. The project has a mandatory pre-bid conference on July 25, 2024, with bids due on August 12, 2024. The contract includes Small Diverse Business (SDB) and Veteran Business Enterprise (VBE) participation goals of 6.0% SDB and 3.0% VBE.
The project is estimated to cost between $2,000,001 and $3,000,000, with liquidated damages of $750 per day. Bids will only be accepted electronically through the PA Supplier Portal. The contract is a standard low-bid project, and the successful contractor will be responsible for all traffic control, erosion and sediment control, and other incidental costs to complete the work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 42240025 RANGE ROAD REPAVING (2024)_DWGS 05 MAY 2024.pdf | ||
| Wage Rates - REBID.pdf | ||
| Instructions to Bidders DMVA - 2024.docx | DOCX document | |
| Sign in sheet.pdf | ||
| Addendum #1 - 6100061607.docx | DOCX document | |
| 42240025 RFI questions RESPONSES rebid.docx | DOCX document | |
| General Conditions to the Construction Contract DMVA 2024 v6.docx | DOCX document | |
| 42240025_RANGE ROAD REPAVING (2024)_SPECS 05 MAY 2024.pdf | ||
| 42240025_RANGE ROAD REPAVING (2024)_C.1.1.REV1 23 MAY 2024.pdf | ||
| FTIG Map 2017.pdf | ||
| Notice to Bidders.docx | DOCX document | |
| Administrative Procedures 2023 DMVA.docx | DOCX document | |
| Bid docs to be returned with bid submission.1.pdf | ||
| Addendum #2 - 6100061607.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DMVA 42240025 RANGE ROAD REPAVING
FORT INDIANTOWN GAP
18 JULY 2024
DESIGN SUPPLEMENT No. 1
Design Drawings: DMVA Project No. 42240025, dated 05 April 2024
Design Specifications: Project Manual 42240025 dated 05 April 2024
Design Supplement No.1 dated 18 July 2024
Revised Sheet C.1.1 (revision 1) dated 23 May 2024
1. Reference Sheet G.1.2 - Traffic Control Note 2: Regarding Stream Crossings:
FTIG can accommodate full closure for the minimum amount of time to install the pipe crossing under the road. Five days advance notice of closure shall be provided. A proposed work schedule for each crossing shall be prepared and submitted showing number of days each closure will be in place. The contractor will also be responsible for all traffic control devices and control (material and personnel) in accordance with PennDOT standards.
2. Reference Project Manual – Section 012200: Section 3.1: Regarding Unit Prices:
The Bid Proposal form has been revised from Lump Sum (as referenced in Section 012200) to Unit Prices with Units and Quantities shown on the Bid Proposal form.
The unit prices shall include all incidental costs/items to complete the work including but not limited to mobilize/demobilize, traffic control, E&S control, backup and restoration, painting, saw cuts, sealing, and intersection work.
Where the Unit is LF (lineal foot) it is noted that that is for the full width of the road.
Bid Unit Costs:
Full Depth Repaving (Asphalt) Unit $/LF (4700 LF)
Mill and Overlay (Asphalt) $/LF (5450 LF)
Seal Coat (Asphalt) $/LF (270 LF)
Tank Crossing (Concrete) – includes pipe and gravel work $/EA (1 EA)
Stream Crossing $/EA (3 EA)
Additional Unit Costs:
Remove and Replace Soft or Unsuitable Subgrade $/CY
Remove and Replace Full Depth Patching Under Mill and Overlay $/SY
Rip Rap Place $/TON
3. Reference Sheet C.1.1: Regarding crosswalk painting:
At the request of end user in Building 19-119, a new crosswalk shall be painted across Range Road at approximate station 83+45 from gravel lot to the north to Sorenson Road to the south, as shown on Sheet C.1.1 Revision 1 dated 23 May 2024. A clip of the sheet is below:
Any further clarification or explanation required, please let me know.
Respectfully, DOROTHY A. STERNER, P.E.