36E77619R0028-0002004.doc

DOC document 75 KB Posted

Attached to
Renovate Radiology - Construct CT Force NRM Minneapolis VAMC Federal contract opportunity
Solicitation number
36E77619R0028
Issued by
Department of Veterans Affairs Headquarters

About this file

36E77619R0028 0002 ICRA.doc

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Radiology - Construct CT Force NRM Minneapolis VAMC, newest first.
File Type Posted
36E77619C0041-000.docx DOCX document
36E77619R0028-0004000.docx DOCX document
36E77619R0028-0003001.docx DOCX document
36E77619R0028-0003000.docx DOCX document
36E77619R0028-0002002.pdf PDF
36E77619R0028-0002000.docx DOCX document
36E77619R0028-0002003.pdf PDF
36E77619R0028-0002001.docx DOCX document
36E77619R0028-0002005.pdf PDF
36E77619R0028-0001000.docx DOCX document
36E77619R0028-0001001.pdf PDF
36E77619R0028-008.pdf PDF
36E77619R0028-002.pdf PDF
36E77619R0028-003.pdf PDF
36E77619R0028-004.pdf PDF
36E77619R0028-009.pdf PDF
36E77619R0028-011.docx DOCX document
36E77619R0028-005.pdf PDF
36E77619R0028-006.pdf PDF
36E77619R0028-001.docx DOCX document
36E77619R0028-010.pdf PDF
36E77619R0028-007.pdf PDF
36E77619R0028-000.docx DOCX document
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construction Infection Control Risk Assessment (ICRA) CLASS IV PROJECT: Type “D” / Group 4

Construction Location: SPS
Bldg.#/Section: 70 / Basement, Basement Interstitial, Sub-Basement
Project Start Date: TBD
Project Title/#: Sterile Processing Services (SPS) Reverse Osmosis (RO) Expansion
Est. Duration:
Engineering COR: D. Fleck
Initial:
Date:
Phone # 612-467-4702
Infection Preventionist: J. Harper
Initial:
Date:
Phone #: 612-467-6924

TYPE

A

Inspections and non-invasive activities. Includes, but not limited to, removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet, painting but not sanding wall covering, electrical trim work, minor plumbing, and activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection.
GROUP

Low Risk

· Mechanical Spaces: Areas not directly adjacent to patient care, including interstitial spaces.

· Engineering or EMS office/work areas

· Office Areas: Areas not attached to/adjoining patient care areas, not used for patient interviews, evaluations or examinations.

· Public corridors: Spaces not on or directly attached to patient units or treatment locations.

GROUP

Medium Risk

· Outpatient Areas:

· Primary Care or Specialty Care Clinic Areas

· Behavioral/Menth Health Areas

· Extended Care / Rehab Clinic Areas

· Community Based Out Patient Clinics (CBOC’s)

TYPE

B

Small scale, short duration activities which create minimal dust. Includes, but is not limited to, installation of telephone and computer cabling, access to chase spaces, cuffing of walls or ceiling where dust migration can be controlled. Floor covering removal (without sanding or grinding).
GROUP

High Risk

· In-Patient Units:

· Including, but not limited to: Emergency Dept.; Nursing Units (3E, 3F, 3K, 3L, 2L, 4J, SCI, 1K, 1DTR); Radiology/MRI/CT/Ultrasound; Nuclear Medicine; Cafeteria/Kitchen/Canteen; Laboratories; Radiation / Oncology; Dialysis

TYPE

C

Any work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies. Includes, but is not limited to, sanding of wall for painting or wallcovering, removal of floorcoverings, ceiling tiles and casework, new wall construction, minor ductwork or electrical work above ceilings, major cabling activities, and any activity which cannot be completed within a single work shift. Floor covering removal (with sanding or grinding).
GROUP

Highest Risk

· ICU/SICU

· OR/PACU/Endoscopy

· GI

· Sterile Processing Services (SPS)

· Pharmacy

· Cath lab

Risk Level “GROUP”
1
2
3
4

Construction Activity

“TYPE”

class

TYPE

D Major demolition and construction projects. Includes, but is not limited to, activities which require consecutive work shifts, require heavy demolition or removal of a complete ceiling system, flooring and new construction.

A
I
I
I
III
B
II
II
III
III / IV
C
II
III
III / IV
III / IV
D
III / IV
IV
IV
IV

1. Keep areas free of debris, trash

2. Execute work to minimize of dust migration (e.g. wet mopping, HEPA vacuum)

3. Immediately replace any ceiling tile displaced for visual inspection.

Involving minor demolition in maintenance or remodeling.
CLASS

I

1. Same as Class I PLUS:

2. Establish material and debris route using non-patient/visitor pathway

3. Water mist work surface to control dust while cutting or drilling.

4. Block off and seal air vents

5. Seal unused doors with duct tape.

6. Create barriers as defined by Infection Prevention

7. Contain construction waste before transport in tightly covered container; tape covering unless solid lid.

8. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.

9. Place sticky mat at all work area entrances and exits.

10. Remove or isolate HVAC system in construction area

CLASS

II

1. Same as Class I and II PLUS:

2. Isolate HVAC system in construction area to prevent duct system contamination

3. Complete critical barriers (i.e. sheetrock, plywood, plastic) at all construction entries and exits; monitor for seal and take immediate corrective action as needed

4. Maintain and monitor negative air pressure within construction site utilizing HEPA equipped air filtration units.

5. Remove or isolate HVAC systems in area where work is being performed.

6. Check and replace air filters as needed regularly

7. Do not remove barriers from work site until project is complete & EMS has thoroughly cleaned area; remove barriers carefully to minimize spreading dust. debris.

8. Vacuum work with HEPA filtered vacuum.

9. Wet mop area with cleaner/disinfectant.

10. Mitigate vibration and noise to lowest impact where possible.

11. Display ICRA at site

12. Seal holes, pipes, conduits and punctures.

CLASS

III

1. Same as Class I, II, and III PLUS: 4 Construct ante room; all personnel must enter through it to be vacuumed

2. Inspect adjacent areas for dust migration; take immediate corrective using HEPA vacuum before leaving or to don/doff PPE as needed 5. Wear shoe covers when entering work site; remove upon exiting site

3. Use HEPA vacuum in area prior to start of construction

CLASS

IV

This is a CLASS IV Project.

Additional Requirements:

This area has been determined to be a low-risk tuberculosis area – therefore contractor testing is not required.

Recommend powered air purifying respirator or equivalent for contractors working overhead in the sub-basement area.

Constructed anteroom and personal protective equipment (gown, head cover, eye protection, and shoe covers) are required for entry and must be removed upon exiting the SPS area at all times.

All contractors working in SPS will be required to attend a VA taught infection control donning/doffing class (less than 1 hour in length)

Permit requested by:
Date:
Permit authorized by:

MVAHCS Construction ICRA Revised 9/5/17