This solicitation is for design-build services to replace the public address and interactive television systems at the Central Iowa VA Health Care System campus in Des Moines, Iowa. The contractor will be responsible for installing a new fiber optic backbone network connecting all campus buildings, replacing the existing public address system with a new addressable paging system, and replacing the existing television system with a new interactive patient care and entertainment system integrated with the VA's electronic health record system. The contractor must complete site investigations, develop schematic and design development documents, and produce construction documents, specifications, and as-built drawings. The project has separate performance periods for installation of the new paging and interactive television systems of 365 and 504 days respectively following notice to proceed. Proposals are due by July 30, 2019 and the opportunity is set aside for Service-Disabled Veteran-Owned Small Businesses.

36C26319R0118 S02_Atch 8_TV_Paging Spec 018113 Sus Cons.docx

View the file

Other files

File Type Posted
36C26319R0118-016.pdf PDF
36C26319R0118-016.pdf PDF
36C26319R0118-0002000.docx DOCX document
36C26319R0118-0002000.docx DOCX document
36C26319R0118-0001001.pdf PDF
36C26319R0118-0001000.docx DOCX document
36C26319R0118-0001001.pdf PDF
36C26319R0118-0001000.docx DOCX document
36C26319R0118-004.pdf PDF
36C26319R0118-010.doc DOC document
36C26319R0118-012.pdf PDF
36C26319R0118-013.docx DOCX document
36C26319R0118-003.pdf PDF
36C26319R0118-009.pdf PDF
36C26319R0118-005.pdf PDF
36C26319R0118-007.docx DOCX document
36C26319R0118-002.pdf PDF
36C26319R0118-006.pdf PDF
36C26319R0118-011.pdf PDF
36C26319R0118-015.docx DOCX document
36C26319R0118-001.docx DOCX document
36C26319R0118-014.docx DOCX document
36C26319R0118-011.pdf PDF
36C26319R0118-010.doc DOC document
36C26319R0118-014.docx DOCX document
36C26319R0118-005.pdf PDF
36C26319R0118-008.pdf PDF
36C26319R0118-009.pdf PDF
36C26319R0118-004.pdf PDF
36C26319R0118-003.pdf PDF
36C26319R0118-001.docx DOCX document
36C26319R0118-006.pdf PDF
36C26319R0118-002.pdf PDF
36C26319R0118-007.docx DOCX document
36C26319R0118-012.pdf PDF
36C26319R0118-015.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

636A6-13-113 Interactive TV and Paging 6/4/19

SECTION 01 81 13

SUSTAINABLE CONSTRUCTION REQUIREMENTS

PART 1 - GENERAL

1.1 DESCRIPTION

This Section describes general requirements and procedures to comply with federal mandates and U.S. Department of Veterans Affairs (VA) policies for sustainable construction.

The Design Professional has selected materials and utilized integrated design processes that achieve the Government’s objectives. Contractor is responsible to maintain and support these objectives in developing means and methods for performing work and in proposing product substitutions or changes to specified processes. Obtain approval from Contracting Officer for all changes and substitutions to materials or processes. Proposed changes must meet, or exceed, materials or processes specified.

1.1 RELATED WORK

Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.

Section 01 74 19 CONSTRUCTION WASTE MANANGEMENT.

1.2 DEFINITIONS

Recycled Content: Recycled content of materials is defined according to Federal Trade Commission Guides for the Use of Environmental Marketing Claims (16 CFR Part 260). Recycled content value of a material assembly is determined by weight. Recycled fraction of assembly is multiplied by cost of assembly to determine recycled content value.

“Post-Consumer” material is defined as waste material generated by households or by commercial, industrial, and institutional facilities in their role as end users of the product, which can no longer be used for its intended purpose.

“Pre-Consumer” material is defined as material diverted from waste stream during the manufacturing process. Excluded is reutilization of materials such as rework, regrind, or scrap generated in a process and capable of being reclaimed within the same process that generated it.

Biobased Products: Biobased products are derived from plants and other renewable agricultural, marine, and forestry materials and provide an alternative to conventional petroleum derived products. Biobased products include diverse categories such as lubricants, cleaning products, inks, fertilizers, and bioplastics.

Low Pollutant-Emitting Materials: Materials and products which are minimally odorous, irritating, or harmful to comfort and well-being of installers and occupants.

Volatile Organic Compounds (VOC): Chemicals that are emitted as gases from certain solids or liquids. VOCs include a variety of chemicals, some of which may have short- and long-term adverse health effects.

1.3 reference standards Carpet and Rug Institute Green Label Plus program.

U.S. Department of Agriculture BioPreferred program (USDA BioPreferred).

U.S. Environmental Protection Agency Comprehensive Procurement Guidelines (CPG).

U.S. Environmental Protection Agency WaterSense Program (WaterSense).

U.S. Environmental Protection Agency ENERGY STAR Program (ENERGY STAR).

U. S. Department of Energy Federal Energy Management Program (FEMP).

Green Electronic Council EPEAT Program (EPEAT).

1.4 SUBMITTALS

All submittals to be provided by contractor to COR.

Sustainability Action Plan:

Submit documentation as required by this section; provide additional copies of typical submittals required under technical sections when sustainable construction requires copies of record submittals.

Within 30 days after Preconstruction Meeting provide a narrative plan for complying with requirements stipulated within this section.

Sustainability Action Plan must:

Make reference to sustainable construction submittals defined by this section.

Address all items listed under PERFORMANCE CRITERIA.

Indicate individual(s) responsible for implementing the plan.

Low Pollutant-Emitting Materials Tracking Spreadsheet: Within 30 days after Preconstruction Meeting provide a preliminary Low Pollutant-Emitting Materials Tracking Spreadsheet. The Low Pollutant-Emitting Materials Tracking Spreadsheet must be an electronic file and include all materials on Project in categories described under Low Pollutant-Emitting Materials in 01 81 13.

Construction Indoor Air Quality (IAQ) Management Plan:

Not more than 30 days after Preconstruction Meeting provide a Construction IAQ Management Plan as an electronic file including descriptions of the following:

Instruction procedures for meeting or exceeding minimum requirements of ANSI/SMACNA 008-2008, Chapter 3, including procedures for HVAC Protection, Source Control, Pathway Interruption, Housekeeping, and Scheduling.

Instruction procedures for protecting absorptive materials stored on-site or installed from moisture damage.

Schedule of submission of photographs of on-site construction IAQ management measures such as protection of ducts and on-site stored oil installed absorptive materials.

Instruction procedures if air handlers must be used during construction, including a description of filtration media to be used at each return air grille.

Instruction procedure for replacing all air-filtration media immediately prior to occupancy after completion of construction, including a description of filtration media to be used at each air handling or air supply unit.

Instruction procedures and schedule for implementing building flush-out.

Product Submittals:

Recycled Content: Submit product data from manufacturer indicating percentages by weight of post-consumer and pre-consumer recycled content for products having recycled content (excluding MEP systems equipment and components).

Biobased Content: Submit product data for products to be installed or used which are included in any of the USDA BioPreferred program’s product categories. Data to include percentage of biobased content and source of biobased material.

Low Pollutant-Emitting Materials: Submit product data confirming compliance with relevant requirements for all materials on Project in categories described under Low Pollutant-Emitting Materials in 01 81 13.

For applicable products and equipment, submit product documentation confirming ENERGY STAR label, FEMP certification, WaterSense, and/or EPEAT certification.

Sustainable Construction Progress Reports: Concurrent with each Application for Payment, submit a Sustainable Construction Progress Report to confirm adherence with Sustainability Action Plan.

Include narratives of revised strategies for bringing work progress into compliance with plan and product submittal data.

Include updated and current Low Pollutant-Emitting Materials Tracking Spreadsheet.

Include construction waste tracking, in tons or cubic yards, including waste description, whether diverted or landfilled, hauler, and percent diverted for comingled quantities; and excluding land-clearing debris and soil. Provide haul receipts and documentation of diverted percentages for comingled wastes.

Closeout Submittals: Within 14 days after Substantial Completion provide the following:

Final version of Low Pollutant-Emitting Materials Tracking Spreadsheet.

Manufacturer’s cut sheets and product data highlighting the Minimum Efficiency Reporting Value (MERV) for filtration media installed at return air grilles during construction if permanently installed air handling units are used during construction.

Manufacturer’s cut sheets and product data highlighting the Minimum Efficiency Reporting Value (MERV) for final filtration media in air handling units.

Minimum 18 construction photographs including six photographs taken on three different occasions during construction of ANSI/SMACNA 008-2008, Chapter 3 approaches employed, along with a brief description of each approach, documenting implementation of IAQ management measures, such as protection of ducts and on-site stored or installed absorptive materials.

Flush-out Documentation:

Product data for filtration media used during flush-out.

Product data for filtration media installed immediately prior to occupancy.

Signed statement describing building air flush-out procedures including dates when flush-out was begun and completed and statement that filtration media was replaced after flush-out.

1.5 QUALITY ASSURANCE

Preconstruction Meeting: After award of Contract and prior to commencement of Work, schedule and conduct meeting with COR/Resident Engineer and Architect to discuss the Project Sustainable Action Plan content as it applies to submittals, project delivery, required Construction Indoor Air Quality (IAQ) Management Plan, and other Sustainable Construction Requirements. The purpose of this meeting is to develop a mutual understanding of the Sustainable Construction Requirements and coordination of contractor’s management of these requirements with the Contracting Officer and the Construction Quality Manager.

Construction Job Conferences: Status of compliance with Sustainable Construction Requirements of these specifications will be an agenda item at regular job meetings conducted during the course of work at the site.

1.7APPLICABLE PUBLICATIONS
A.Publications listed below form a part of this specification to extent referenced. Publications are referenced in text by basic designation only. Comply with applicable provisions and recommendations of the following, except as otherwise shown or specified.
B.Green Seal Standard GS-11, Paints, 1st Edition, May 20, 1993.
C.ASHRAE Standard 52.2-2007.

PART 2 – PRODUCTS

2.1PERFORMANCE CRITERIA
A.Construction waste diversion from landfill disposal must comprise at least 50 percent of total construction waste, excluding land clearing debris and soil. Alternative daily cover (ADC) does not qualify as material diverted from disposal.
B.Low Pollutant-Emitting Materials:

Adhesives, sealants and sealant primers applied on site within the weatherproofing membrane must comply with VOC limits of SCAQMD Rule 1168:

Non-Flooring Adhesives and Sealants:

Drywall and Panel Adhesives: 50 g/L.

Multipurpose Construction Adhesives: 70 g/L.

Structural Glazing Adhesives: 100 g/L.

Metal-to-Metal Substrate Adhesives: 30 g/L.

Plastic Foam Substrate Adhesive: 50 g/L.

Porous Material (Except Wood) Substrate Adhesive: 50 g/L.

Wood Substrate Adhesive: 30 g/L.

Fiberglass Substrate Adhesive: 80 g/L.

Architectural Non-Porous Sealant Primer: 250 g/L.

Architectural Porous Sealant Primer: 775 g/L.

Other Sealant Primer: 750 g/L.

PVC Welding Adhesives: 510 g/L.

CPVC Welding Adhesives: 490 g/L.

ABS Welding Adhesives: 325 g/L.

Plastic Cement Welding Adhesives: 250 g/L.

Adhesive Primer for Plastic: 550 g/L.

Contact Adhesive: 80 g/L.

Special Purpose Contact Adhesive: 250 g/L.

Structural Wood Member Adhesive: 140 g/L.

Sheet Applied Rubber Lining Operations: 850 g/L.

Top and Trim Adhesive: 250 g/L.

Architectural Sealants: 250 g/L.

Other Sealants: 420 g/L.

Aerosol adhesives applied on site within the weatherproofing membrane must comply with the following Green Seal GS-36.

Aerosol Adhesive, General-Purpose Mist Spray: 65 percent VOCs by weight.

Aerosol Adhesive, General-Purpose Web Spray: 55 percent VOCs by weight.

Special-Purpose Aerosol Adhesive (All Types): 70 percent VOCs by weight.

Paints and coatings applied on site within the weatherproofing membrane must comply with the following criteria:

VOC content limits for paints and coatings established in Green Seal Standard GS-11.

VOC content limit for anti-corrosive and anti-rust paints applied to interior ferrous metal substrates of 250 g/L established in Green Seal GC-03.

Clear wood finishes, floor coatings, stains, primers, sealers, and shellacs applied to interior elements must not exceed VOC content limits established in SCAQMD Rule 1113.

Comply with the following VOC content limits:

Anti-Corrosive/Antirust Paints: 250 g/L.

Interior Flat Paint, Coating or Primer: 50 g/L.

Interior Non-Flat Paint, Coating or Primer: 150 g/L.

Sealers and Undercoaters: 200 g/L.

Concrete Curing Compounds: 350 g/L.

Recycled Content:

Any products being installed or used that are listed on EPA Comprehensive Procurement Guidelines designated product list must meet or exceed the EPA’s recycled content recommendations. The EPA Comprehensive Procurement Guidelines categories include:

Building insulation.

Consolidated and reprocessed latex paint.

Flowable fill.

Laminated paperboard.

Modular threshold ramps.

Nonpressure pipe.

Materials, products, and equipment being installed which fall into any of the following product categories must be Energy Star-labeled.

Applicable Energy Star product categories as of 09/14/2017 include:

Electronics and Information Technology:

Audio/Video Equipment.

Computers.

Data Center Storage.

Digital Media Player.

Enterprise Servers.

Imaging Equipment.

Monitors.

Professional Displays.

Set-Top and Cable Boxes.

Telephones.

Televisions.

Uninterruptible Power Supplies.

Voice over Internet Protocol (VoIP) Phones.

Other:

Decorative Light Strings.

Electric Vehicle Supply Equipment.

Laboratory-Grade Refrigerators and Freezers.

Light Bulbs.

Light Fixtures.

Electronic products and equipment being installed which fall into any of the following categories shall be EPEAT registered. Electronic products and equipment covered by EPEAT program as of 09/14/2017 include:

Computers.

Displays.

Imaging Equipment.

Televisions.

PART 3 - EXECUTION

3.1FIELD QUALITY CONTROL
A.Construction Indoor Air Quality Management:

0. During construction, meet or exceed recommended control measures of ANSI/SMACNA 008-2008, Chapter 3.

-----END----