S02 - Solicitation 36C26120R0028.pdf

PDF 923 KB Posted

Attached to
Y1LZ--Construct Additional Parking Lots Federal contract opportunity
Solicitation number
36C26120R0028
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 21

About this file

This is a solicitation for a design-build contract to construct additional parking lots at a Veterans Affairs medical center campus in Las Vegas, Nevada. The scope of work includes designing and constructing a total of approximately 500,000 square feet of additional asphalt parking across three areas on the campus, with a minimum of 420 parking spaces required in areas A1 and A2, 60 spaces in area B, and 400 spaces in area C. The contractor must provide lighting, signage, drainage, and other site improvements according to VA standards. The project value is between $2 million and $5 million. This is a two-phase solicitation that will select a design-build firm through a best value determination. The solicitation is a total small business set-aside for Service-Disabled Veteran-Owned Small Businesses. Proposals are due by April 27, 2020, with award planned for September 2020 and work expected to be complete within 195 days thereafter.

View the file

Other files for this federal contract opportunity

Other files attached to Y1LZ--Construct Additional Parking Lots, newest first.
File Type Posted
S27 - Notice of Award - 36C26120C0069_1.docx DOCX document
ATTACHMENT B_Version 2 - Past Performance Questionnaire.docx DOCX document
ATTACHMENT A_Version 2 - PHASE 1 FACTOR 2 - EXPERIENCE.xlsx XLSX spreadsheet
Amend 0002 - Vendor Questions and Government Response.docx DOCX document
Solicitation 36C26120R0028 - Amend 0002.pdf PDF
Amend 0001 - Off-Site Tributary Drainage.pdf PDF
Amend 0001 - Existing Site Storm Drain Infrastructure.pdf PDF
Amend 0001 - Instructions to Offerors.docx DOCX document
Amend 0001 - Combined Campus Utility CU-107 to CU-119.pdf PDF
Solicitation 36C26120R0028 - Amend 0001.pdf PDF
Amend 0001 - Site Vistit - Construct Additional Parking Lots.pptx PPTX presentation
Amend 0001 - Statement of Work.doc DOC document
Amend 0001 - Existing Site Drainage.pdf PDF
Amend 0001 - Existing Peak Run-off Rates at POA.pdf PDF
Amend 0001 - Vendor Questions and Government Response.docx DOCX document
Amend 0001 - Pre Proposal Site Visit - Prime Contractor List - Those Agreeing to Publication of Info.pdf PDF
ATTACHMENT E - Wage Determination - NV20200001.txt TXT text file
ATTACHMENT C - Offerors Key Personnel.docx DOCX document
01 32 16 16 Schedule - Design-Build Only.pdf PDF
Const Add Parking Lots Dwg 20200122.pdf PDF
Phase IV Geotechnical Report 050106.pdf PDF
01 42 19 Reference Standards.pdf PDF
ATTACHMENT F - Supplemental Pricing Breakdown.docx DOCX document
ATTACHMENT B - Past Performance Questionnaire.docx DOCX document
01 33 23 Shop Drawings Product Data and Samples.pdf PDF
01 35 26 SAFETY.pdf PDF
ATTACHMENT D - CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL.docx DOCX document
ATTACHMENT A - PHASE 1 FACTOR 2 - EXPERIENCE.xlsx XLSX spreadsheet
01 45 29 Testing Laboratory Services.pdf PDF
01 45 00 Quality Control 050120.pdf PDF
01 57 19 Temporary Environmental Controls.pdf PDF
010000 GENERAL REQUIREMENTS Rev 200117.pdf PDF
36C26120R0028-006.docx DOCX document
36C26120R0028-007.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C26120R0028

X

07-01-2020

593-20-2-5921-0013

593-19-308

00261

Department of Veterans Affairs Network Contracting Office 21 VA Southern Nevada Healthcare System 6900 N. Pecos Road, Building 6 North Las Vegas NV 89086

Department of Veterans Affairs Network Contracting Office 21 VA Southern Nevada Healthcare System 6900 N. Pecos Road, Building 6 North Las Vegas NV 89086

Maxwell Derck 702-791-9000 x 14939

Project Title: Construct Additional Parking Lots VA Southern Nevada Health Care System 6900 North Pecos Rd.

Las Vegas, NV 89086 Project #: 593-19-308

Contractor shall provide all supervision, labor, materials, services, tools, equipment, and transportation to design and construct a total of approximately 500,000 square feet of additional parking at the Las Vegas Southern Nevada Health Care System.

In accordance with VAAR 836.204 - Disclosure of the magnitude of construction projects, the magnitude of construction for Project 593-19-308 is between $2,000,000 and $5,000,000.

This project is being NAICS 236220 with a small business size standard of $39.5M.

Note #1 to OFFERORS: This contract will be awarded in accordance with FAR Part 15 - Tradeoff Process (FAR 15.101-1) and FAR Part 36 - Two-Phase Design-Build Selection Procedures (FAR 36.3)

Note #2 to OFFERORS: Bid Bonds, Payment Bonds, and Performance bonds shall be required under this solicitation and any resultant contract.

Note #3 to OFFERORS: This procurement is a 100% Total Service-Disabled Veteran-Owned Small Business Set-Aside.

Public Law 109-461 is final authority on SDVOSB Set Aside.

Note #4 to OFFERORS: In accordance with established public law, all Contractors are required to be registered and current in System for Award Management (SAM), the official web-site of the U.S. Government at www.sam.gov

Note #5 to OFFERORS: A pre-proposal conference and site visit shall be held on July 09, 2020 at 10AM PST at the VA Southern Nevada Health Care System, 6900 N. Pecos Rd., Admin Building 6 Meet in lobby outside of coffee shop.

Please note: COVID-19 screenings will take place upon entry, and face masks are required at all times while on campus.

Note #6 to OFFERORS: All Requests for Information (RFI's) shall be submitted to the Contract Specialist, maxwell.derck@va.gov in writing, by July 15, 2020 11AM PST

10 195 x x 52.211-10

X 10

0 1600

07-31-2020

X

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

00261

Network Contracting Office 21 Southern Nevada Healthcare System 6900 N. Pecos Road, Building 6 North Las Vegas NV 89086

Financial Services Center P.O. Box 149971

Austin TX 78714-9971

Table of Contents

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) . 1

A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION,

OR REPAIR)– BACK

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

INSTRUCTIONS TO OFFERORS

PART I. GENERAL

2.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB

1998)

2.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)

2.3 52.209-11 REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT

TAX LIABILITY OR A FELONY CONVICTION UNDER ANY FEDERAL LAW (FEB 2016)

2.4 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—

CERTIFICATION (JUN 2018)

2.5 52.216-1 TYPE OF CONTRACT (APR 1984)

2.6 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF

THE WORK (MAY 2014)

2.7 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION

MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014)

AND ALTERNATE II (JUN 2009)

2.8 52.233-2 SERVICE OF PROTEST (SEP 2006)

2.9 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) ...32

2.10 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)

2.11 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION

(OCT 2018)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)

3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS

AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (DEC 2019)

GENERAL CONDITIONS

4.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

4.2 SUPPLEMENTAL INSURANCE REQUIREMENTS

4.3 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION

SYSTEMS (JUN 2016)

4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984) ALTERNATE I (APR 1984)

4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION

(MAR 2020)

4.6 52.223-20 AEROSOLS (JUN 2016)

4.7 52.223-21 FOAMS (JUN 2016)

4.8 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)

4.9 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE

AGREEMENTS (OCT 2019)

4.10 52.236-4 PHYSICAL DATA (APR 1984)

4.11 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

4.12 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-

OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)

4.13 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND

COMPLIANCE (JUL 2018)

4.14 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019)

4.15 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)

4.16 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND

VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)

4.17 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION

CONTRACTS (INCLUDING NAS– CPM) (NOV 2018)

4.18 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV

2018)

4.19 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR

2019)

4.20 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)

4.21 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)

4.22 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT

ADMINISTRATION (APR 2019)

4.23 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP

2019)

4.24 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) 72

DESIGN BUILD INSTRUCTIONS

4.25 PARTNERING

4.26 GENDER

4.27 CONTRACTOR'S COST BREAKDOWN

4.28 SCHEDULE OF PAYMENTS FOR DESIGN SERVICES

4.29 OWNERSHIP OF ORIGINAL DOCUMENTS

4.30 RETENTION OF REVIEW DOCUMENTS

4.31 CONTRACT DRAWINGS AND SPECIFICATIONS GOVERNMENT FURNISHED

PLANNING INFORMATION

4.32 COORDINATION WITH MEDICAL CENTER

4.33 RESPONSIBILITY OF THE DESIGN-BUILD CONTRACTOR

4.34 DESIGN-BUILD SPECIFICATIONS

4.35 ADDITIONAL ATTACHMENTS

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO

BIDDERS/OFFERORS

DESIGN-BUILD STATEMENT OF WORK

Project 593-19-308

CONSTRUCT ADDITIONAL PARKING AREAS

Veterans Affairs Southern Nevada Healthcare System

1.0 PROJECT IDENTIFICATION:

1.1. Project Title: Construct Additional Parking Areas at the Las Vegas Veterans Affairs Medical Center (LVVAMC)

1.2. Project Location: Veterans Affairs Southern Nevada Healthcare System (VASNHS) 6900 N. Pecos Road, North Las Vegas, NV 89086

2.0 PROJECT DESCRIPTION:

The LVVAMC is procuring a Design-Build contractor for design and construction services for project no. 593-19-308, Construct Additional Parking Areas. The design and construction are to provide a total of approximately 500,000 SF of additional asphalt parking on the Northeast and Southeast areas of the Medical Center Campus.

3.0 PROJECT REQUIREMENTS:

3.1. AREA A1 and A2

1) Contractor shall construct a minimum of 420 total additional asphalt parking spaces (380 regular parking, 8 van accessible and 32 regular handicap parking stall). Please Note: Total parking requirements reflect what is expected to be delivered when both areas are combined. Parking stall allocation and total square footage for Areas A1 and A2 to be determined subsequent to coordinated design effort with ongoing designs for a new Primary Care Clinic and Women’s Care Clinic at the Las Vegas Southern Nevada Health Care System.

2) Asphalt minimum thickness shall be per Ninyo & Moore Geotechnical Report dated May 2006, Table 6, Traffic Type Areas, Automobile.

3) The entire parking area shall be asphalt paved with minimum of 4 ea. access and 2 ea. connecting A1 and A2 (typical of 30’ wide minimum).

4) Provide culverts with wing headwall at each access for the parking lot at existing drainage.

5) The contractor shall provide exterior self-contained (dusk to dawn) pole-mounted Solar LED lighting.

6) Provide 3’ high elevated concrete light pole bases.

7) Demolish any existing culverts, and other items associated with existing temporary parking lot.

8) Provide striping, directional signage and parking identification per VA Design Guide.

3.2. AREA B

1) The contractor shall construct a minimum of 60 ea. total additional asphalt parking spaces (4 handicap parking and 56 parking stall). Total square footage to be determined by design.

2) Asphalt minimum thickness shall be per Ninyo & Moore Geotechnical Report dated May 2006, Table 6, Traffic Type Areas, Automobile.

3) Protect existing electrical transformers in the area with 6 ea. concrete filled 4’ high X 10” dia. bollards.

4) The contractor shall provide exterior self-contained (dusk to dawn) pole-mounted Solar LED lighting.

5) Provide 3’ high elevated concrete light pole bases.

6) Provide striping, directional signage and parking identification per VA Design Guide.

3.3. AREA C

1) The contractor shall construct a minimum of 300,000 SF asphalt parking area.

2) Scarify native soil up to 4” deep, remove rocks 3” or larger and compact to 95 percent relative compaction.

3) Grade area to drain at southside stormwater management collection point.

4) Provide striping for maximum automobile parking stalls (minimum 400 parking stalls).

5) Provide stormwater management per VA Site Development Design Guide and local codes.

6) There will be no solar lighting and curbing in this area.

7) Adjust valve boxes and other utility access to new grade.

8) Protect above ground water valves with 4 ea. concrete filled 4’ high X 10” dia.

bollards.

Note: The contractor shall use the VA Numbered Standards for Construction (PG-18 series).

Note: The contractor shall provide light poles with elevated bases and affix self-contained solar powered light emitting diodes (LEDs) lights in identified areas. There shall be no electrical connections of these solar systems to other light poles. The solar powered lights must illuminate every day from dusk to dawn the next morning. The contractor shall use and follow the guidelines of the VA Construction Facilities Management Lighting Design Manual, section 3.2, for parking lot exterior lighting.

Note: The contractor shall provide the following information tasks described in the attachments to this SOW:

☒ Task A: Preliminary Plans and Investigative Services

– Due 15 Calendar days from design NTP

☒ Task B: Construction Technical Package

- 35% due 25 Calendar days from design NTP

- 100% due 55 days from design NTP

4.0 OTHER REQUIREMENTS:

1) The contractor shall provide all labor, materials, equipment, and supervision for the construction of the vehicle parking areas.

2) The contractor shall use VA Parking Design Manual and Demand Model dated April 2013.

3) The contractor shall obtain all required permits.

4) Grading and Stormwater Drainage Requirements:

a) Grades shall provide an efficient drainage pattern that directs runoff from the surface areas of the asphalt parking areas to existing adjacent stormwater drainage management, ditches and swales.

b) The drainage pattern shall include 4”-8” landscape rock to prevent erosion of the drainage channel.

5) The construction contractor shall use the General Contractor’s AE Designed final VA approved Additional Parking Areas Drawing and VA Specifications for grading and final slopes for parking areas A1, A2, B and C. Final slopes shall adhere to VA standards.

5.0 SITE VISITS AND EXISTING CONDITIONS:

1) The contractor shall reference the Medical Center Campus Parking Plan Drawing and Specifications, section 01.00.00, General Requirements, Section 1.1.

2) Discrepancies in Planning Information: The contractor shall immediately report to the Contractor Officer, in writing, any discrepancy between this contract and the

Additional Parking Areas Drawing and Specifications provided by the Government. The contractor shall make no adjustments to his/her work due to the discrepancy before the Contracting Officer has reviewed and approved any changes. The contractor’s failure to report any such discrepancy or wait for the Contracting Officer’s determination shall be at his/her risk and expense.

3) The contractor shall attend the Pre-Construction Meeting at LVVAMC in support of this effort. This meeting will occur no later than fourteen (14) calendar days after notice to proceed has been issued by the Contracting Officer. The meeting will be used to review the requirements of the Scope of Work (SOW) and discuss roles, responsibilities, expectations and deliverables. The contractor shall also identify to the Government any issues or concerns they have with the Additional Parking Areas Drawing and Specifications. The contractor shall communicate with the CO and COR via e-mail to establish the dates, times, and location of this meeting.

6.0 PERFORMANCE MONITORING: The VASNHS COR will monitor the SOW in the following manner:

1) All identifiable phases of work shall be coordinated with the COR at least ten

(10) working days before the scope is executed. This includes but is not limited to site work, site improvements, site structures, asphalt pavements, site accessories, landscape and irrigation, site grading, storm water drainage, site lighting, physical security, impacts to patient and staff parking, and any other identifiable scope of work items as identified.

7.0 SECURITY REQUIREMENTS:

1) All contractor’s and subcontractor’s personnel shall be subject to VA Directive 0735, Homeland Security Presidential Directive 12 (HSPD-12) Program, Federal laws, regulations, standards, and VA Handbooks similar to VA personnel regarding information and information system security.

2) Non-Personal Identity Verification (PIV) Card requests shall be submitted to VA COR (Contracting Officer Representative) by the contractor. Requesting submission is the contractor’s responsibility. Please ensure to properly fill out the documents identified below. The following documents will become a package for submission of PIV Card application:

a) VA Fingerprinting form

b) Declaration for Federal Employment (OF306), if there are any questions that were answered “yes” on item 9-13 on this form, fill out the appropriate addendum and include in the package.

c) Authorization for Release of Information (VA Form 0710)

e) Self-Certification of Continuous Service

f) Contractor Background Investigation Request

3) PIV Card process may take 30-45 days, depending on the contractor’s personnel background check, Special Agreement Check (SAC). SAC is an automated records check conducted by the Federal Bureau of Investigation in collaboration with the Office of Personnel Management (OPM).

4) PIV Card Applicant is subject to National Agency Check with written Inquiries (NACI) conducted by OPM. This investigation covers a period of 5 years and a review of current records in the OPM Security Investigation Index (SII), DOD Defense Central Investigations Index (DCII), FBI name check, and FBI fingerprint check as well as written inquiries from previous employers and references on the application for employment. It is used for Non- sensitive or Low Risk positions in VA.

5) Once all documents are completely and properly filled out, hand carry and submit to VA COR. Do not send completed forms through email due to Personal Identifiable Information.

6) VA COR will then provide all documents to Engineering Service’s VA PIV Sponsor/Manager to initiate the Non-PIV process.

7) PIV Sponsor/Manager will notify each applicant when to proceed for fingerprinting appointment.

8) Each applicant shall be fingerprinted at VA Southern Nevada Healthcare System’s PIV Office, located first floor in Building 6 (Administration Building), 6900 N. Pecos Road, N. Las Vegas, NV 89086. Each applicant shall sign in at the Security Desk.

9) VA COR or PIV Sponsor/Manager will provide status of each applicant’s PIV Card.

10) PIV Card is critical for the construction start date, as the contractor’s personnel without PIV Card may result with a restricted, limited, or no access to the job site. See attached blank forms/documents that is required for submission of PIV Card application for each of contractors/sub-contractors

8.0 GOVERNMENT FURNISHED EQUIPMENT (GFE):

1) No GFE will be provided by the VASNHS on this contract.

9.0 OTHER PERTINENT INFORMATIOIN OR SPECIAL CONSIDERATIONS:

1) The contractor is responsible to ensure all equipment that will be used on the project by the contractor at LVVAMC campus has been inspected and certified as safe for use. The contractor shall provide safety certification inspection sheets to the COR prior to using any equipment for the parking area construction (dump trucks, cement mixers, road graders, earth movers, front-end loaders, cranes, etc.) on LVVAMC properties at least five (5) working days prior to their planned use. Any construction equipment that has not passed a safety certification or whose safety certification has expired cannot be operated or used on LVVAMC

Page 10 of properties. The contractor’s personnel shall be licensed, certified, and trained as required to operate this equipment.

2) Identification of Potential Conflicts of Interest (COI). All bidders shall inform the VASNHCS of any COI that may exist where the nature of the work to be performed may, without some restriction on future activities, (1) result in an unfair competitive advantage to the contractor; or, (2) impair the contractor’s objectivity in performing the contract work.

3) Identification of Non-Disclosure Requirements. No sensitive or proprietary information is needed or supplied for this project.

4) Information Technology (IT) Certification & Accreditation (C&A). The Contractor shall not connect any contractor-owned IT devices (such as a lap top computer or remote connection from a Contractor system) to a VA internal trusted network.

Therefore, the C&A requirements do not apply, and a Security Accreditation Package is not required. If this situation changes, the Contractor shall immediately inform the COR in order to facilitate the preparation of the Security Accreditation package.

5) Inspection and Storage. The Contractor shall be responsible for the inspection and storage of all contractor equipment and materials that will be used in the execution of this contract. The contractor will be allowed to temporarily store equipment and materials needed for the construction of the parking areas at the Medical Center Campus. The contractor shall inform the COR by e-mail on any equipment or materials they would like to store inside the Campus at least fourteen (14) working days prior to storing them. The COR will inform the contractor by e- mail as to whether or not the contractor can store this material or equipment within five (5) working days after being notified by the contractor.

6) Inspection and Acceptance Criteria. Final inspections shall be conducted by the VASNHS COR to ensure all aspects of the contract have been met. The contractor will not receive final payment until all parking area construction activities have been completed and accepted by the VA.

10.0 RISK CONTROL:

1) The VASNHS is an active hospital and therefore will require consideration to those areas with patients and staff.

2) The contractor shall perform daily cleanup of the construction areas affected by the execution of this contract sufficient to the point there are no hazards or safety concerns with VA patients and staff.

3) The contractor shall ensure all construction materials and equipment have been secured from the VAMC patients and staff, theft, damage and weather and the work area cleaned and made safe at the end of each working day.

Page 11 of

4) The contractor shall erect and place a temporary 6-foot high chain-link fence around all area construction zones with required construction signage and lockable gate. The contractor shall remove all temporary fencing from these areas after completion and Government acceptance of the parking area.

11.0 PLACE OF PERFORMANCE:

1) The work will be accomplished at the LVVAMC located at 6900 North Pecos Road, North Las Vegas, NV 89086. The contractor shall perform the work in the outside areas of the Medical Center Building. See Government provided outline drawing for the location of the parking areas that will be constructed at the Medical Center Campus.

12.0 PROGRESS PAYMENTS:

1) The contractor shall submit progress payment invoices at the end of the billing month.

2) Before the invoice is submitted, the contractor shall consult with the COR or Project Engineer to determine the percentage of work completed.

3) Progress Payments will be based on actual work completed.

4) Progress invoices shall be submitted with a progress report detailing the work completed.

5) The contractor shall complete a Standard Form 1413, Weekly Payroll Reports and Daily Reports and shall include the SF 1413 with the Progress Payment Invoices to the Contracting Officer for review and acceptance.

6) Payment of high value materials or equipment shall be arranged with COR and approved by CO prior to Schedule of Values submittal.

7) The contractor shall ensure progress invoices include a certification statement that prompt payment is being made to suppliers and subcontractors, if applicable, as soon as provision of supplies or work has been satisfactorily completed.

8) The contractor shall ensure all correspondence and invoices reference the VA Contract Number and Obligation Number.

9) The Contractor shall be registered in, and submit all invoices to http://www.tungsten- network.com/us/en.

13.0 HOURS OF WORK, SUBMITTALS AND MEETINGS:

13.1. Duty Hours

1) Normal duty hours are 7:30 am – 4:00 pm, Monday thru Friday. All work performed shall be coordinated and scheduled thru the COR. Work may be accomplished during off duty hours and over weekends with CO/COR approval.

13.2. Notice To Proceed

Page 12 of

1) The contractor shall attend the Notice To Proceed (NTP) meeting with the CO and COR as scheduled. Telephone attendance is acceptable if a representative of the contractor is unavailable in the local area.

13.3. Submittals

1) The construction contractor shall submit the following to A/E Design Firm on Record, but not limited to the following:

a. Shop drawings, product data, product samples, and other submittals as referenced in the Additional Parking Spaces Specification paragraph 01 33 23, Shop Drawings, Product Data, and Samples for parking areas.

b. Request for Information (RFI).

c. Design changes, contract modifications.

2) All submittals, design changes, modifications, etc shall be reviewed and verified by A/E Design firm on Record per approved construction plans and specifications before submittal to VA Contracting Officer for approval.

3) Unless stated otherwise in this SOW, the VA review for all contractor deliverables shall be 10 working days.

4) The contractor shall coordinate all work with COR in accordance with the Additional Parking Spaces Specification paragraph 01 00 00, General Requirements.

5) The contractor shall submit by e-mail a 3 week look ahead and 1 previous week construction schedule to the COR by 8:00AM Pacific Time every Monday during the period of performance. This 4-week schedule will summarize the construction activities planned for the next 3 weeks and verify what was performed the previous week.

13.4. Construction Review Meetings and Comments

1) The contractor shall be required to attend Construction Review Meetings at the site or via telephone as required to coordinate the progress of the construction process, get approval/clarification of the submittals, etc.

2) The COR and the contractor will determine who should attend each meeting.

3) The contractor will provide Meeting Notes to all attendees no later than three

(3) working days after the meeting. The contractor shall provide a written response to each review comment. The COR will review the Meeting Notes. If necessary, the contractor will make corrections to the Meeting Notes and re-issue them. The meeting Notes will serve as the VA’s comments.

14.0 TESTING / PUNCH LIST / END-USER TRAINING / ACTIVATION:

Page 13 of

1) The contractor shall prepare punch lists if needed and schedule a pre-final walkthrough with the COR at least five (5) working days prior notice once substantial completion of each parking area is achieved. After the pre-final walkthrough, the VA will submit its own punch list if needed.

2) Once contractor has completed or resolved all punch list items, the contractor shall schedule a final walkthrough with the CO/COR of the area.

3) Required documentation:

a. Contractor’s punch list and confirmation of completion.

b. Confirmation of VA’s completed punch list.

c. As-built drawings for all parking areas constructed by the contractor.

d. All warranty information.

4) A copy of the final transmittals must be sent to the CO.

5) The contractor shall not submit final invoice for payment until all punch list items have been completed and final transmittals have been confirmed as received and accepted by the COR.

15.0 DELIVERY AND ACCESS TO CONSTRUCTION AREAS:

1) Materials delivered to the VASNHCS shall be in their original sealed packages or containers; labeled for identification with the manufactures’ name and brand.

2) The contractor shall insure delivered materials are protected from damage due to handling, weather, and construction operations before, during and after installation.

3) The contractor shall ensure patient and staff cannot enter any parking lot areas under construction. The requirements of paragraph 11.d above apply.

16.0 QUALITY ASSURANCE/QUALITY CONTROL:

1) To reduce errors and omissions, the contractor shall develop and execute a QA/QC plan that demonstrates their proposed design phase and construction phase have gone through a thorough review and coordination effort.

2) No later than 14 calendar days after receipt of Notice to Proceed (NTP), the contractor shall submit a QA/QC plan describing each task that will be taken during the construction phases of the parking areas and the name of the contractor team member responsible for QA/QC, for Contracting Officer (CO) approval. Each task shall be initialed and dated by the responsible contractor responsible team member.

Page 14 of

17.0 PERIOD OF PERFORMANCE:

1) The project requires the tasks to be completed within 195 calendar days after NTP has been issued. NOTE: Separate NTP will be issued for Design and Construction.

2) Required milestones below: NTP typically issued within 14 calendar days of contract award.

Design Notice to Proceed (NTP) Preliminary Design/Concept Review 35 Percent Design Submittal to VA 35 Percent Design Review Meeting – 10 calendar days

65 Percent Design Submittal 65 Percent Design Review Meeting – 10 calendar days 100 Percent Design Submittal

100 Percent Design Review Meeting -10 calendar days NTP Construction Phase

3) The government requires 10 calendar days to review the A/E’s submittal(s) inclusive of all requirements (tasks) specified in this scope of work.

18.0 PRICING:

1) The contractor shall provide a fee for the required services using the format applicable to the Request for Proposal document issued by the Government’s Contracting Officer.

19.0 APPLICABLE REFERENCES:

1) Construction of parking areas A, B, and C shall be in compliance with the requirements of the below applicable references and/or standards:

# VA Standard Title/Section

1 Master Construction Specifications Index (PG-18-1)

2 VHA PROGRAM GUIDE (PG-18-3 Design and Construction Procedures)

3 National CAD Standard Details (PG-18-4)

4 Equipment Guide (PG-18-5)

5 Equipment Inspection Manual (Program Guide 7610.2)

6 Equipment Reference Manual (PG-18-6)

7 VA Handbook H-18-8, Seismic Design Requirements

Page 15 of

8 Space and Facility Planning (PG-18-9) (Handbook 7610)

9 Design Manuals (PG-18-10)

10 Design Guides (PG-18-12)

11 Accessibility (PG-18-13)

12 Submission Instructions (PG-18-15)

13 Conceptual Design Submission Requirements (Submittal Guide PG-18-15)

14 Environmental Compliance Manual (PG-18-17)

15 Fire Protection Design Manual - Fourth Edition

16 Cost Estimating

17 Physical Security Design Manuals for VA Facilities - Mission Critical Facilities

18 VA Parking Lot Signage 12/2012

19 Sustainable Design and Energy Reduction Manual (Final Draft)

20 Natural Disasters Non-Structural Resistive Design (formerly CD-54)

21 International Building Code – Latest Edition

22 National Electric Code – Latest Edition

23 2010 Nevada Department of Transportation Standard Plans for Road and Bridge

Construction

24 2014 Nevada Department of Transportation Standard Specifications for Road and

Bridge Construction

25 VA CFM Lighting Design Manual, 2015

26 VA Site Development Design Manual, 2013

20.0 INNOVATION:

1) Requirements indicated are not intended to limit innovative service delivery of the contractor. The Government will consider variations from the Statement of Work (SOW), if the proposed change is within the schedule and budget limitations, meets the objectives for the project, and results in an improved outcome. The Government may approve all proposed changes to the SOW.

ATTACHMENT (check box, and include)

☒ TASK A: PRELIMINARY PLANS AND INVESTIGATIVE SERVICES

The contractor shall provide a concept design to asses needs and requirements for the construction of the additional parking areas. The concept design shall include a feasibility design to ensure area is suitable for the desired functions. The contractor shall provide a minimum of two (2) concept design recommendations to meet the government’s requirement.

Project Initiation: The Planning Team (consisting of representatives from the VASNHS and the contractor) shall attend the “Project Kickoff and Requirements Review” meeting to discuss the following objectives:

a) Review the requirements of the Scope of Work.

b) Define the project schedule and identify all meetings, deliverables, and milestones on the schedule.

c) Identify all the stakeholders and critical players required to be involved at the various stages of the project.

d) Begin data collection for utility survey and site analysis.

e) Develop a detailed work plan, project schedule, and outline of all project deliverables.

f) Visual and aesthetic conditions for the new parking areas to be constructed.

g) Signage and lighting requirements for the constructed parking areas.

Deliverables

The plans and investigative services package for submission includes the following components:

1. Preliminary Concept Designs. One hard copy Architectural size E, size C and electronic copy. The contractor shall use PDF and AutoCAD Version 2017 for the electronic copy.

2. Narrative of Design proposals.

ATTACHMENT (check box, and include)

☒ TASK B: PROJECT CONSTRUCTION TECHNICAL PACKAGE

The contractor shall provide construction technical package for the construction phase of the project to support contracted design and construction of additional parking lots area A1, A2, B and C for VA approval.

Deliverables

1. Detailed construction plans (DWG and PDF format)

2. Detail cost estimate with labor, materials and equipment costs as a minimum.

The contractor shall account for conditions that would impede conventional construction means and methods such as outside of normal work hours (if applicable) and coordination requirements with the VASNHS. Costs shall be adjusted as necessary for working in a fully operational hospital. Every effort shall be made to minimize the impact to patient services. Cost estimates should be provided to the COR as a MS Excel workbook.

3. Detailed construction schedule with cost of each task (MS Projects)

4. Basis of Design

5. Submittal Register (Primavera Submittal Exchange – access will be provided)

INSTRUCTIONS TO OFFERORS

PART I. GENERAL

This procurement will follow the Two-Phase Design-Build selection procedures in accordance with FAR 36.3. The Government will evaluate Phase-One proposals and select a maximum of five (5) most highly qualified offerors to submit Phase-Two proposals. Phase-Two will select the best value offeror using the trade-off source selection process.

In Phase-One, the Government intends to select a maximum of (5) most highly qualified offerors to submit proposals for Phase-Two without conducting discussions with any offeror; therefore, the initial Phase-One proposal shall conform to the solicitation requirements and shall contain the best offer. The Government intends to evaluate Phase-Two proposals utilizing the Best Value Trade Off procedures outlined in FAR Part 15 and award a contract without conducting discussions; therefore, the initial Phase-Two proposal shall conform to the solicitation requirements and shall contain the best offer from a non-price and price standpoint.

The Government intends to award without discussions the proposal offering the Best Value to the Government. Award will be made on a Best Value trade off basis where all evaluation factors other than cost or price, when combined, are approximately equal in importance with cost or price. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary.

INSTRUCTIONS FOR OBTAINING THE REQUEST FOR PROPOSAL

The RFP can be accessed at https://beta.sam.gov. Printed copies of the RFP will not be issued.

INSTRUCTIONS FOR SUBMITTING QUESTIONS REGARDING SOLICITATION

Questions regarding the solicitation shall be submitted in writing in WORD format via electronic mail to maxwell.derck@va.gov. Questions shall reference the drawing/detail and/or the specification section including paragraph number. Verbal queries will not be entertained.

Responses to the properly submitted questions will be provided in the form of an Amendment posted to the web site https://beta.sam.gov. It is the offeror’s responsibility to check the website periodically for any amendments to the solicitation. The Government may not respond to questions submitted less than 10 days before the proposal receipt due date.

COMPETITIVE RANGE

The Government reserves the right to conduct discussions during Phase-One and/or Phase- Two if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines discussions are necessary, the Contracting Officer may conduct discussions with offerors determined to be in the competitive range. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

ENFORCEABILITY OF PROPOSAL

The Government shall consider the “offeror” to be the legal entity identified in Block 14 of the SF1442 of the Phase-One proposal. The legal entity that submitted the Phase-One offer shall https://beta.sam.gov/ mailto:maxwell.derck@va.gov not be changed, assigned, or otherwise substituted prior to award under any circumstances.

The proposal must set forth full, accurate, and complete information as required by this solicitation. The Government will rely on such information in the award of a contract. By submission of the offer, the offeror agrees that all items proposed in response to the evaluation factors (including subcontractors with teaming agreements, project schedule, building design etc.) will be enforced for the duration of the contract. Any substitutions after contract award will be equal or better than as proposed and shall require Contracting Officer's approval prior to implementation.

PART II. EVALUATION FACTORS AND BASIS OF AWARD

Offeror packets will be evaluated based upon the following criteria:

a. Definitions:

Size is defined as any project over $1,000,000.00 Complexity is defined as a design build project that includes several specialty trades and some engineering.

Scope is defined as work or activities related, or closely related to that which is outlined in the Statement of Work such as but not limited to; construction of new asphalt paving, compaction, grading, seal coating, striping, electrical and solar.

Recency is defined as a project completed in the previous five (5) calendar years.

Relevancy is defined as for purposes of this evaluation, as new construction and/or repair, alteration and related demolition of existing infrastructure completed within the past five years of the proposal issue date of this RFP. Infrastructure is defined as: 1) construction of a healthcare facility; 2) construction for industrial buildings and warehouses; 3) nonresidential buildings, other than industrial buildings and warehouses; or 4) improvements such as utilities, landscaping, and roadways. “New Construction” is defined as construction that provides for new or expanded facilities or infrastructure. New construction does not include repair and/or modernization of an existing facility nor does it include replacement or upgrade to an existing infrastructure.

EVALUATION CRITERIA AND BASIS OF AWARD

In accordance with Federal Acquisition Regulation (FAR) 36.3, this acquisition is based upon two-phase design-build selection procedures. The term “technical factors” refers to any non-price factor other than past performance. Factors 1-4 will be evaluated in Phase-One and Factors 5-6 will be evaluated in Phase-Two. Factor 1 will be rated Acceptable or Unacceptable. If an Offeror is rated Unacceptable in Factor 1, then they will not be considered for Phase-Two. In making the best value award decision after Phase-Two, the Government will consider Factors 2-6 and price.

The relative importance of evaluation factors 2-6 is as follows: Technical factors (Factors 2, 4, 5, 6,) are of equal importance to each other, and when combined, are equal in importance to the past performance factor (Factor 3). When the proposal is evaluated as a whole, the technical factors and past performance factor combined (i.e., the non-price evaluation factors) are approximately equal to price.

The contract resulting from this solicitation will be awarded to that responsible offeror whose offer, conforming to the solicitation, is determined to be the most advantageous to the Government considering price and non-price evaluation factors. Award may be made to other than the lowest priced offeror or other than the highest non-price rated offeror. Business judgments and tradeoffs will be used to determine the proposal offering the best value to the Government. In determining the best value to the Government, the Government need not quantify the tradeoffs that led to the best value decision.

PHASE-ONE and PHASE-TWO SUBMISSION REQUIREMENTS

(a) All proposals shall be submitted in one part, a Technical Proposal. Your submittal must include a one-sided original to be emailed to the Contract Specialist maxwell.derck@va.gov. Emails cannot contain attachments that exceed 5MB.

(b) All pages containing text shall be consecutively numbered, type-written to fit paper size indicated in each factor. Submissions shall be made electronically in pdf format. Past performance information shall be submitted separately. All technical proposals shall be compatible with Microsoft Office 2010 Microsoft Word.

(c) The format used for the areas and factors above shall be strictly adhered to. All responses in the offeror’s package shall clearly indicate the applicable Evaluation Area, and Section, if applicable.

(d) It is the offeror’s responsibility to insure the completeness of the proposal. The evaluation panel for the Government may evaluate solely on the information provided in the initial proposal and will not assume that an offeror possesses any capability that is not specifically identified in the proposal.

(e) Only one technical proposal will be evaluated for each offeror. Alternate methods of accomplishing the work required by this solicitation will not be evaluated.

Please Note: Missing, incomplete, or ambiguous information could result in an offer deemed deficient. The Government may NOT make an Award to a Deficient Offer; In addition, there may not be an opportunity to remedy deficiency if Government deems to make award without discussions.”

NOTE: DO NOT SUBMIT THE SF1442 OR BID GUARANTEE DURING PHASE-ONE. A

COVER PAGE AND ACKNOWLEDGEMENT OF ANY ISSUED AMENDMENTS SHALL BE

USED INSTEAD. NO PRICING OR COST INFORMATION SHALL BE SUBMITTED DURING

PHASE-ONE OF THE SELECTION PROCESS.

NON-PRICE EVALUATION FACTORS

Phase-One:

Factor 1: Technical Approach Factor 2: Experience Factor 3: Past Performance Factor 4: Safety

Phase-Two:

Factor 5: Key Personnel Factor 6: Project Schedule

***PHASE-ONE REQUEST FOR PROPOSAL (RFP) EVALUATON CRITERIA***

Factor 1 – Technical Approach:

(a) Solicitation Submittal Requirements:

mailto:maxwell.derck@va.gov

The Offeror (as identified on the SF1442) shall provide a narrative describing the general technical approach for accomplishing the requirements of this contract based on the General Requirements outlined in the statement of work. This is high level and does not require referencing specifications. The narrative shall include the roles and responsibilities of the offeror and the partnering firm. If the offeror is made up of more than one legal entity (e.g. Joint- Venture, Limited Liability Company, Limited Partnership, etc.), the narrative shall describe the roles and responsibilities of each legal entity(s) comprising the offeror. Provide an organizational chart, clearly depicting the offeror (including each legal entity comprising the offeror), the partner firm, and the lines of authority of the various entities. The narrative and organizational chart shall be limited to four (4) single-sided pages, 8.5” x 11”, 1” margin left/right/top/bottom, and 10-point font or larger.

(b) Basis of Evaluation:

The offeror’s technical approach will be used as a means to assess the Offeror’s understanding of the General Requirements of the contract, the roles and responsibilities of the offeror and lead design firm to accomplish the requirements of the contract. This factor will be rated on an Acceptable or Unacceptable basis.

Factor 2 – Experience:

(a) Solicitation Submittal Requirements:

Provide information on relevant and recent experience on design-build contracts of comparable size, complexity and scope within the last five calendar years as described in the below requirements. The Offeror shall complete the attached Phase-One Factor 2 Spreadsheet (Attachment A) for each project submitted. The attached (Attachment A) is structured to allow for the entry of up to six (6) total projects as requested in items 1 thru 3 below. The use of (Attachment A) and all information therein is MANDATORY and SHALL be used to evaluate experience. The Government will evaluate only the information provided in (Attachment A) and all other information provided on other than (Attachment A) will not be considered. The Offeror may expand individual cells on the (Attachment A). (Attachment A) submittals that do not comply with these requirements WILL NOT be evaluated.

1. Submit a maximum of Two (2) example projects demonstrating the experience and capability of the lead Architect-Engineering Firm that will be designing the project.

Examples should demonstrate offerors experience as the Prime Contractor on recent, relevant projects that are similar in size, scope, and complexity to the RFP.

2. Submit a maximum of Two (2) example projects demonstrating the experience and capability of the lead Construction Contractor that will be performing the largest construction effort on the project. Examples should demonstrate offerors experience as the Prime Contractor on recent, relevant projects that are similar in size, scope, and complexity to the

RFP

3. Submit a maximum of Two (2) example design/build projects that the prime contractor and the partner firm have completed together. Examples should demonstrate offerors and partner firm’s coordination and teamwork leading to successful completion on relevant projects that are similar in size, scope, and complexity to the RFP.

(b) Basis of Evaluation:

The basis of evaluation will include the offeror’s demonstrated experience and depth of experience in performing recent, relevant construction and design projects as defined in the solicitation submittal requirements of similar size, scope and complexity. The assessment of the offeror’s relevant experience will be used as a means of evaluating the capability of the offeror to successfully meet the requirements of the RFP. Offeror’s projects will be rated individually and then combined to achieve an overall factor rating. Offeror’s demonstrating recent and relevant design-build experience; project completion within initial stated period of performance;

recent and relevant design/construction of surface parking; recent and relevant examples of offeror and partner firm demonstrating a successful contractor team arrangement; and, recent and relevant projects completed in the NCO 21 Geographic location may be rated more favorably.

Factor 3 – Past Performance:

(a) Solicitation Submittal Requirements:

If a completed Contractor Performance Assessment Report System (CPARS) evaluation is available, it shall be submitted with the proposal for each project included for Phase-One Factor 2 for Experience. If there is not a completed CPARS evaluation, then submit Past Performance Questionnaires (PPQ - Attachment B) for each project submitted for Phase-One Factor 2. PPQs will not be accepted from the designer on a design-build project or from a prime contractor for work performed by a subcontractor. PPQs shall be completed and signed by the contracting agent and/or their representative responsible for construction contract administration.

This is the start of the file's text. The full file is on GovTribe.