This document outlines a solicitation for upgrading an existing fire alarm system at the Oklahoma City VA Medical Center. The scope of work includes upgrading components and devices to bring the current system into compliance with NFPA 72 standards. The contractor will furnish all labor, materials, and equipment to upgrade detectors, speakers, notification devices, and control panels. Work also involves integrating existing building fire alarm systems and adding new devices.
The performance period is 300 calendar days from notice to proceed. The solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses. Offerors must be verified as eligible by the VA Center for Verification and Evaluation. The evaluation will consider past performance and price, with past performance significantly more important. The period of performance, place of performance, and standards for safety, environmental protection, badges, and building access are also outlined.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S05 - QNA Upgrade Existing Fire Alarm System) RD 2.pdf | ||
| S06 - 36C25922R0091 0003.docx | DOCX document | |
| Attachment 4 - 019100 General CX Requirements.pdf | ||
| Attachment 5 - 280800 CX of Elec Safety and Security System.pdf | ||
| S06 - 36C25922R0091 0002.docx | DOCX document | |
| S05 - QNAs (Upgrade Existing Fire Alarm System).pdf | ||
| S04 - Login Site Walk (Upgrade Existing Fire Alarm System).pdf | ||
| S06 - 36C25922R0091 0001.docx | DOCX document | |
| Attachment 2 - Design Narrative bound-OKC Fire Alarm 2.pdf | ||
| Attachment 1 - DWG.100_ Stamped OKCVA Upgrade Existing Fire Alarm.pdf | ||
| Attachment 3 - Specification Manual OKC Fire Alarm Phase 2.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25922R0091
X 11-03-2022
635-20-101 36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Jared.Detton@va.gov
Jared Detton 303-283-5307 The contractor shall furnish all labor, equipment, materials, and supervision to upgrade existing fire alarm system located at 921 NE 13th St., Oklahoma City, OK 73104: 635-20-101 (Upgrade Existing Fire Alarm System)).
Project magnitude: between $1,000,000 and $2,000,000 The NAICS code is 236220 - Small Business size standard is $39.5 M
In accordance with P.L. 109-461, this acquisition is 100% set aside for Service-Disabled Veteran Owned Small Businesses concerns. See VAAR 852.219-10, Notice of Total Service-Disabled Veteran Owned Small Business Set-Aside of this solicitation for information in regard to requirements in order to be considered. Offerors must be both VISIBLE and VERIFIED by the Department of Veterans Affairs Center for Verifications Evaluation (CVE) prior to proposal receipt.
Failure to be both VERIFIED by CVE and VISIBLE on VetBiz prior to contract award will result in the offerors proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the aforementioned required documents to obtain CVE verification of their SDVOSB status if they have not already done so.
In accordance with FAR 52.204-7, System for Award Management (SAM), Prospective contractors shall be registered in the SAM database prior to close of solicitation.
A site visit will be held on November 18th, 2022 at 9:00 AM MT / 10:00 AM Central Time (CT). Please meet at the North
Entrance of the Oklahoma City VA Medical Center.
All questions in relation to this solicitation must be submitted in writing via e-mail to Jared.Detton@va.gov and received no later than November 23rd, 2022 at 12:00 PM (NOON) Mountain Time (MT).
Instructions, Conditions, and Notices to Offerors. All submitted proposals must be received in email by the closing date and time. This solicitation closes December 2nd, 2022 at 2:00 P.M. MT.
Proposals shall be submitted via e-mail in accordance with Part I/Section B, to be considered for this project.
Proposals received in any other format will result in the offeror's proposal not receiving further consideration.
X X
52.211-10 X
2:00 PM
MT
12-02-2022 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111
Department of Veterans Affairs Financial Service Center PO Box 149971 Austin TX 78714-9971
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| A.3 PRICE/COST SCHEDULE | 5 |
| ITEM INFORMATION | 5 |
| A.4 STATEMENT OF WORK | 6 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 13 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 20 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 20 |
| 2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 20 |
| 2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 22 |
| 2.5 52.233-2 SERVICE OF PROTEST (SEP 2006) | 23 |
| 2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 23 |
| 2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 23 |
| 2.8 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 24 |
| 2.9 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 25 |
| REPRESENTATIONS AND CERTIFICATIONS | 25 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022) (JUL 2020) (DEVIATION) | 25 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 29 |
| 3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 32 |
| 3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 33 |
| GENERAL CONDITIONS | 35 |
| 4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021) | 35 |
| 4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 37 |
| 4.3 52.219-14 LIMITATIONS ON SUBCONTRACTING (SEP 2021) | 37 |
| 4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021) | 39 |
| 4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021) | 42 |
| 4.6 SUPPLEMENTAL INSURANCE REQUIREMENTS | 46 |
| 4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 46 |
| 4.8 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 49 |
| 4.9 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020) | 49 |
| 4.10 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 50 |
| 4.11 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 52 |
| 4.12 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION) | 52 |
| 4.13 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 54 |
| 4.14 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 54 |
| 4.15 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 55 |
| 4.16 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 56 |
| 4.17 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 57 |
| 4.18 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 57 |
| 4.19 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 57 |
| 4.20 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 59 |
| 4.21 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 60 |
| 4.22 WAGE DETERMINATION | 60 |
| 4.23 LIST OF ATTACHMENTS | 69 |
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
Base Pricing (See Statement of Work for Details)
Provide all work as described by attached plans, specifications, and Wage Determinations for Veterans Administration project VA Project 635-20-101 Upgrade Existing Fire Alarm System at the Oklahoma City VAMC as described in the attached scope of work. Price includes all costs for construction. Cost shall include but not be limited to direct and indirect costs including profit, overhead, general and administration, insurance, labor, bonds, taxes, necessary for 100% completion of the project as indicated in the attached SOW. The construction performance period is 300 calendar days from receipt of notice to proceed.
Contract Period: Base POP Begin:
POP End:
| GRAND TOTAL |
| __________________ |
A.4 STATEMENT OF WORK
Upgrade Existing Fire Alarm System Project No. 635-20-101
Objective:
The Government’s objective is to meet the fire alarm and suppression system requirements set forth by the National Fire Protection Association (NFPA) for Fire Protection Alarm Systems and Fire Suppression Systems, to ensure the safety of personnel and preservation of unit assets. Specifically, the Oklahoma City Veterans Affairs Medical Center (VAMC) is seeking General Contractor firms to provide all construction services for the upgrade of existing fire alarm system. It is the intent of this solicitation to follow the design and specifications. Verification of all existing conditions shall be done, and anything overlooked or not included in the proposal required for code compliance should be verified and promptly reported to the COR.
Scope of Work:
The Oklahoma City Veterans Affairs Medical Center (OKCVAMC) will undergo a fire alarm system upgrade. This project includes construction items for addition, modification, and upgrade to bring the facility into compliance with NFPA 72. The Contractor shall furnish all labor, tools, materials, transportation, and equipment, disposal of waste, supervision and personnel to meet the requirements for the upgrade of the fire alarm system. No work outside the Statement of Work (SOW) is authorized, the contractor is responsible for contracting the Contracting Officer (CO) if they believe additional work outside the original scope is necessary.
Architectural:
This project provides a design to bring the current fire alarm system into compliance with NFPA 72.
Performance Requirements:
The contractor shall perform all requirements listed below. Refer to the Attachments sections below for a list of all the drawings and specifications.
· Basis of design for construction reference NFPA 72 version 2020.
· Building #20 fire alarm system is brought into the new fire alarm system with new devices, detectors, flow switch, tampers switches and audio visual.
· Sub-Basement upgrade of components of fire service and fire pump are being upgraded, with regard to tamper and flow switches.
· Building #1 select stairwells pull stations and strobes added.
· AHU duct detectors added at select locations.
· Carbon monoxide system is being added to Boiler Plant area to comply with VA standards and NFPA 72.
· Speakers have been added to increase audibility throughout the hospital, and existing speakers are being replaced on a one for one basis.
· Visual notification has been added in select portions of the facility to increase visibility.
· Server Room smoke detectors to be replaced to create a more accessible device for maintenance.
Performance Standards:
Proper adherence to all safety procedures is required prior to, during, and after work being performed. The contractor shall furnish all personal protective equipment (PPE) as required. The contractor shall safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to contractor operations and activities, and avoid interruptions of Government operations in the performance of services. The contractor shall be solely responsible for the management, including all associated labor, equipment, materials, mailing costs, and inspection, to meet the requirements of this project.
Phasing Schedule & Continuity of Medical Center Operation:
The contractor shall coordinate and communicate with the Contracting Officer Representative (COR) to develop an approved phasing schedule to minimize interference with medical center operations and ensure Veteran’s healthcare is not impeded. Additionally, the contractor shall give a minimum of 24 hours’ notice to commencement of work by notifying the COR by both telephone and an email.
Pre-Construction Conference:
The contractor agrees to attend the pre-construction conference convened by the CO in accordance with FAR 42.5. The CO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the CO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
Place of Performance:
Veterans Affairs (VA) Medical Center, Oklahoma City 921 NE 13th Street Oklahoma City, Ok 73104
Period of Performance:
The period of performance for this project shall be 300 days from the Notice to Proceed (NTP).
Hours of Work:
The hours of work shall take place during the normal business hours of 7:30 AM and 4:00 PM, Monday through Friday, Federal Holidays excluded. Request for weekend, after-hour, and Federal holiday work is permitted with a request in writing submitted beforehand. Off hours are not to billed as overtime. Federal Holidays and any other day declared a federal holiday by the President of the United States are defined below.
| New Year’s DayMartin |
| Luther King Jr’s Day |
| Presidents Day |
| Memorial Day |
| Independence Day |
| Labor Day |
| Columbus Day |
| Veterans Day |
| Thanksgiving Day |
| Christmas Day |
| Juneteenth Day |
If a holiday falls on Sunday, the following Monday will be observed as the National Holiday. When a holiday falls on a Saturday, the preceding Friday is observed as a National Holiday by the U.S. Government.
All work is to have a limited impact on the facility, veterans, and employees. This may require evening or weekend hours and will be identified in the schedule. All after hours work should be scheduled in advance.
Postponement/Delays: In the event climate or weather conditions become unsuitable for work or may induce an environmental hazard, then the entire work shall be rescheduled to a date and time satisfactory to the Contractor and the COR. Postponement due to inclement weather will not cause assessment of the penalty provision outlined above, nor should there be an additional cost to the Government.
All work shall be scheduled and performed within the date and time approved by the COR, in conjunction with the department occupying the space served by this equipment.
Roles and Responsibilities:
The Contracting Officer (CO) is responsible for monitoring contract compliance, contract administration, cost control and for resolving any differences between the observations documented by the COR and the contractor. The CO will designate one full-time COR as the government authority for performance management. The number of additional representatives serving as technical inspectors depends on the complexity of the services measured, as well as the contractor’s performance, and must be identified and designated by the CO.
The COR The COR is designated in writing by the KO to act as his or her authorized representative to assist in administering a contract. COR limitations are contained in the written appointment letter. The COR is responsible for technical administration of the project and ensures proper government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the government’s behalf. Any changes that the contractor deems may affect contract price, terms, or conditions shall be referred to the KO for action. The COR will have the responsibility for completing QA monitoring forms used to document the inspection and evaluation of the contractor’s work performance. Government surveillance may occur under the inspection of services clause for any service relating to the contract.
CODES, STANDARDS AND EXECUTIVE ORDERS
The Contractor shall follow all applicable codes and standards to this type of work including but not limited to Health Care System Memorandums (HCSM), OSHA Guidelines, NFPA 101, NFPA 70, Lock-out-Tag-out, and Rules of Station. VA has adopted the latest edition of the following codes and standards as a minimum for all projects performed in the modernization, alteration, addition, or improvement of its real property and the construction of new structures. VA design Manuals and Master Specifications specify other codes and standards that VA follows on its projects:
| VA Directives, Design Manuals, Master Specifications, VA National CAD Standard Application Guide, and other Guidance on the Technical Information Library (TIL) http://www.cfm.va.gov/til/ PG-18-1 | Master Construction Specifications | |
| PG-18-3 | Design and Construction Procedures PG-18-4 | Standard Details and CAD Standards VA BIM Manual V2.2 |
| PG-18-5 | Equipment Guide List H-18-8 VA Seismic Design Handbook PG-18-9 | Space Planning Criteria |
| PG-18-10 | Design Manuals (by discipline) | |
| PG-18-12 | Design Guides (graphical, by function) PG-18-13 | Barrier Free Design Guides |
| PG-18-14 | Room Finishes, Door, and Hardware Schedules (consult COR for local standards) | |
| PG-18-15 | Minimum Requirements for A/E Submissions PG-18-17 | Environmental Compliance Manual |
H-7545 VA Cultural Resource Management VA Handbook 0056, Sustainable Building Program VA Directive 0056, Sustainable Building Program VA Directive 0055, VA Energy and Water Management Program
NFPA 101 Life Safety Code
NFPA National Fire Codes
International Building Code (IBC) and all other International Code Series (IPC, IMC, IECC, IFGC, etc.) when applicable or referenced in VA Design documents/ guides.
Occupational, Safety and Health Administration (OSHA) Standards.
National Electrical Code (NEC)
Safety Code for Elevators and Escalators, American Society of Mechanical Engineers (ASME) A 17.1.
ASME Boiler and Pressure Vessel Code
ASME Code for Pressure Piping
Architectural Barriers Act Accessibility Standards (ABAAS) including VA supplement, Barrier Free Design Guide (PG-18-13)
Building Code Requirements for Reinforced Concrete, American Concrete Institute and Commentary (ACI 318)
Manual of Steel Construction, Load and Resistance Factor Design Specifications for Structural Steel Buildings, American Institute of Steel Construction (AISC)
Energy policy Act of 2007 (EPAct)
DOE Interim Final Rule: Energy Conservation Standards for New Federal, Commercial and Multi- Family High-Rise Residential Buildings and New Low-Rise Residential Buildings, 10 CFR Parts 433, 434 and 435.
Federal Leadership in High Performance and Sustainable Buildings: Memorandum of Understanding (MOU)
Executive Order 13423: Strengthening Federal Environmental, Energy, and Transportation Management.
The Provisions for Construction and Safety Signs. Stated in the General Requirements Section 01010 of the VA Master Construction Specification.
Ventilation for Acceptable Indoor Air Quality – ASHRAE Standard 62.1- 2013.
Safety Standard for Refrigeration Systems – ASHRAE Standard 15 – 2016.
Quality Control:
Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this SOW. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract.
Acceptance Standards:
The VA reserves the right to dispute completion of contract scope if contract work is found not in accordance with manufacturer recommendations, is not satisfactorily executed, or if the system is not properly tested and inspected to achieve certification. All work completed by the Contractor must be reviewed and approved by the VA. Work must be approved for one location of each type of fixture prior to proceeding with all other locations specified. If conditions that exist that are not like the location previously approved the contractor shall get approval prior proceeding with work in locations with similar conditions.
Contractor Employee Qualifications/Licenses:
Contractor shall provide personnel who have the knowledge, qualifications, and working experience to perform the functions outlined in this SOW. Contractor must be licensed and certified to work on fire alarm panels, and systems per:
· Oklahoma Administrative Code: Title 380 Department of Labor, chapter 75 alarm and locksmith industry rules, subchapter 3 license requirements.
Safety and Prevention:
In the performance of this contract, the contractor shall take such safety precautions as necessary to protect the lives and health of occupants of the building.
The Contractor shall immediately correct any fire and safety deficiencies caused by his/her personnel. If the Contractor fails or refused to correct deficiencies promptly, the Contracting Officer may issue an order stopping all or any part of the work and hold the contractor in default of the contract.
The Contractor shall comply with applicable Federal, State and local safety and fire regulations and codes which are in effect at the beginning of the contract. The contractor shall keep abreast of and comply with changes in these requirements and codes applicable to the contract. The requirements include but are not limited to, those found in Federal and State Occupational Safety and Health Act (OSHA) statutes and regulations, such as applicable provisions of Title 29, Code of Federal Regulations (CFR) Parts 1910 and 1926. Contractor is solely responsible for determining the legal requirements that apply to activities, and shall ensure safe and healthful working conditions for its employees
The Contractor’s personnel shall follow applicable facility policies concerning fire/disaster programs.
All materials and equipment will be removed from the facility or stored properly at the end of the workday and secured during the workday. Under no circumstances will the Contractor allow for any equipment to be left unattended for any length of time.
The Contractor shall comply with all applicable Federal, State and local legal requirements regarding workers health and safety.
The Contractor shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government Property.
The Contractor shall perform the work in a manner consistent with the area security and fire safety regulations especially with regard to exits and exit way access. Utility shutdowns shall not compromise security, communication, or fire safety for occupants.
No flammable liquids shall be stored or used in the medical center.
The necessary number and appropriate types of portable fire extinguishers are required per National Fire Protection Agency (NFPA) 10 and NFPA 241. Contractor shall keep certification onsite at all times of extinguisher inspections.
The Contractor shall receive from the COR a permit for all cutting, welding, and soldering 24 hours in advance. All permits shall be prominently displayed during all construction.
All necessary precautions shall be taken by the contractor to prevent accidental operation of any existing smoke detectors or sprinkler heads.
The Contractor shall assume responsibility of environmental protection of all material storage.
Accident Prevention:
Precaution shall always be exercised for the protection of persons (including employees) and property. These shall include, but not be limited to, the installation of adequate safety guards and protective devices for all equipment and machinery, whether used in the performance of work or permanently installed as part of the work. Contractor shall comply with all applicable laws relating to safety precautions, including the safety regulations of the Division of Industrial Safety, Department of Industrial Regulations of the state.
Environmental Protection:
In order to provide for abatement and control of all environmentally hazardous materials arising from demolition and/or construction activities, the Contractor shall comply with all applicable environmentally hazardous material control and abatement and all applicable provisions of the Corps of Engineers’ Manual EM 385-1-1, “General Safety Requirements” as well as the specific requirements stated elsewhere in the Contract Documents.
The Contractor is responsible for daily cleanup of all areas affected by its work. Areas in use or affected shall be returned to condition in which they were turned over or initially found. VA Housekeeping shall not be dispatched for cleaning associated with contractor work.
The Contractor shall take every precaution in preserving flooring, finishes, equipment, and furniture in areas of work. The Contractor shall repair or replace any damage incurred during its work at their expense.
Contractor shall use freight elevators for transmission of materials and personnel. Contractor shall take every precaution in preserving the elevators, including the hoist way and lobby doors, interior finishes, and shall conduct all good practices in observing lifting and motor components tolerances. Any damage incurred to any elevator component due to negligence will be repaired at expense of the contractor, within the workday of incurred damage.
ICRA:
Classification of type B, Class 2. Contractor to maintain an active means to prevent air-borne dust from dispersing into atmosphere with the use of control cubes or other dust barriers. Water mist work surfaces to control dust while cutting. Seal unused doors with masking tape. Block off and seal air vents (if any). Place walk-off mat or carpet at work area entrances to prevent tracking of construction dust into surrounding areas. Remove or isolate HVAC system in areas work is performed. Upon completion of work, wet mop and/or vacuum with HEPA-filtered vacuum before leaving work area and wipe work surfaces with disinfectant. Contain construction waste before transport in tightly covered containers. Tape may be used to ensure tight cover. Remove isolation of HVAC system in areas when work has been completed.
Badges and Parking:
All Contractor personnel are required comply with VAAR 852.273-74 (Available online at VA Technical Information Library) which covers the following requirements: background checks, and the wearing of identification (I. D.) badges issued by the VA Sheridan VAMC. Contractor must acquire badge, of appropriate level, for all staff onsite prior to work beginning. While on VA Facilities grounds, temporary or official I.D. badges shall be worn continuously. Failure of the background check may result in specific personnel being disallowed to work on VA premises and the Contractor will need to provide replacement personnel.
It is the responsibility of the Contractor’s personnel to park in the appropriate designated parking areas. The designated parking area will be specified by COR and VA Police upon award of contract. While performing under this contract, all vehicles used by the contractor shall be locked and the keys removed when not in use. This is intended to protect the contractor’s property and the safety of the patients at the medical center. Due to parking constraints, the number of contractor vehicles on site might be limited per the COR or VA Police.
Building Access:
The COR shall issue the contractor one key. The COR shall provide the Contractor access to all buildings and rooms required in the provisions of this contract. The Contractor shall notify the COR when leaving these areas. The contractor shall ensure to return all keys that were issued issued back to the COR after work is completed, failure to return key(s) will result in a charge of $150 per key which the contractor will be responsible for paying.
Clearances/Access Controls: Contractor and all personnel shall comply with the security clearances or access controls of areas within the Medical Center. In the event that the Contractor has to obtain access to areas that require special security precautions the COR will notify the contractor prior to access.
Attachments:
· Stamped and Sealed Construction Drawings
· Construction Specifications
· Construction Design Narrative
“End of Statement of Work”
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
PART I/SECTION A – REQUEST FOR PROPOSAL
I.1A JOINT VENTURES
If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ prior to award.
I.2A SELECTION PROCEDURES
This acquisition will be a competitive acquisition utilizing FAR Part 15 source selection employing tradeoff source selection procedures. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, representations, and certifications. All such offers shall be treated equally except for their prices and performance records. Failure to meet a requirement may result in an offer being determined non-compliant. It is the intent of the Government to award without discussions; however, the Government will reserve the right to have discussions if such are needed.
I.3A PRE-PROPOSAL SITE VISIT
See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation. Please leave extra time to complete COVID-19 screening process when entering the building. Masks are required to be worn by all employees and contractors while on VA property.
I.4A SELECTION CRITERIA
This acquisition will utilize the tradeoff process in accordance with FAR 15.101-1. This process permits tradeoffs between non-cost factors and cost/price and allows the Government to accept other than the lowest priced proposal or other than the highest rated proposal to achieve a best value contract award based on established evaluation criteria. Inherent in this process is the necessity to make tradeoffs considering the non-cost strengths and weaknesses, risks, and the cost (or price) offered in each proposal.
The source selection process will be conducted utilizing FAR part 15.101-1 Trade-off Process Source Selection Procedures with Special Standards of Responsibility. Offers will be evaluated using the following evaluation factors:
Factor 1 – Past Performance Factor 2 – Price
In addition to the general standards of responsibility found at FAR 9.104-1, in accordance with FAR 9.104-2, the special standards of responsibility described below apply to this procurement. Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.
Past performance will be evaluated on a basis of significantly more important than, cost or price.
Past Performance Evaluation For Factor 1, based on the evaluation of all recent and relevant past performance for an offeror, an overall performance confidence rating shall be assigned. The performance confidence ratings are defined below:
| ASSESSMENT |
| DESCRIPTION |
| Substantial Confidence | |
| Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort. |
| Satisfactory Confidence |
| Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort. |
| Limited Confidence |
| Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort. |
| No Confidence |
| Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort. |
| Unknown Confidence (Neutral) |
| No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. |
Note: In the case of an offeror without a record of past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall receive an unknown confidence (neutral) performance confidence rating.
(a) Aspects of Past Performance Evaluation. The past performance evaluation is an assessment based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. There are two aspects of the past performance evaluation.
| (1) The first is to evaluate whether the offeror’s present/past performance is relevant or not relevant to the effort to be acquired. The criteria to establish what is relevant is unique to each source selection. | |
| (2) The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts. In addition, the Government reserves the right to obtain information for use in the evaluation of past performance from all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror. | |
| (b) Source Selection Evaluation Board (SSEB) members will review past performance information to determine the quality and usefulness as it applies to the performance confidence assessment. |
Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system.
Factor 1-Past Performance
(a) Solicitation Submittal Requirements:
Offerors shall provide a maximum of five (5) recent and relevant projects (as defined below) to demonstrate their ability to perform the proposed work identified within the Specifications, drawings, and Statement of Work. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted. The Government will evaluate past performance based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THERE IS NOT A PAST PERFORMANCE EVALUATION IN PPIRS or FAPPIIS, then the offeror shall submit Past Performance Questionnaires (PPQ) for each project. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Jared Detton, Jared.Detton@va.gov.
Recency – a recent project is defined as being completed within five years of the due date of this solicitation.
Relevant – includes performance of efforts in a project of upgrading fire alarm systems in an active medical facility that are similar or greater in scope, magnitude, and complexity than the effort described in this solicitation.
Offerors are cautioned to submit enough information in the format specified in the solicitation. Offerors may be asked to clarify certain aspects of their proposal (for example, the relevance of past performance information) or respond to adverse past performance information to which the offeror has not previously had an opportunity to respond. Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system. Communication conducted to resolve minor or clerical errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for proposal revision.
(b) – Basis of Evaluation:
The contracting officer shall review recent and relevant performance information on each offeror based on past efforts provided by the offeror and may obtain data independently from other government and commercial sources. Past performance regarding predecessor companies, key personnel who have relevant experience, or sub-contractors that will perform major or critical aspects of the requirement will not be considered as highly as past performance information for the principal offeror. Offerors with no past performance history or the offeror’s performance record is so limited that no confidence assessment rating can be reasonably assigned shall receive the rating "Unknown Confidence," meaning the rating is treated neither favorably nor unfavorably.
Initially offers shall be ranked according to price, including any option prices if applicable. The lowest price offer’s past performance shall be evaluated to determine its performance confidence rating.
If the lowest priced evaluated offer is judged to have a Substantial Confidence performance assessment, that offer represents the best value for the government and the evaluation process stops at this point. Award shall be made to that offeror without further consideration of any other offers.
If the lowest price offer does not receive a Substantial Confidence performance confidence rating, the past performance evaluation continues until an offeror’s past performance is judged to have a Substantial Confidence performance rating. The Government reserves the right to award a contract to other than the lowest priced offeror if the lowest priced offeror is judged to have a performance confidence assessment of "Satisfactory Confidence" or lower. In that event, the Source Selection Authority shall make an integrated assessment best value award decision.
Factor 2 – Price:
(a) Solicitation Submittal Requirements:
· Standard Form 1442, Solicitation Offer and Award
· All pages of the SF1442 Continuation Sheet
(b) Basis of Evaluation: The Government will evaluate price based on the total price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
· Comparison of proposed prices received in response to the RFP
· Comparison of proposed prices with the IGCE.
· Comparison of proposed prices with available historical information.
Special Standard of Responsibility Solicitation Submittal Requirements:
The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)
1. OSHA or EPA Violation(s):
Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.
2. Experience Modification Rate (EMR):
Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.
PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
I.1B COST RANGE: Between $1,000,000.00 and $2,000,000.00
I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.
I.3B METRIC PRODUCTS:
Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.
If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.
I.4B REQUESTS FOR INFORMATION:
All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.
I.5B PROPOSAL REQUIREMENTS
General – Both past performance information and price proposal shall be submitted in response to this solicitation. Proposals shall be submitted via email Jared.Detton@va.gov. Emails are limited to 15 MB. The proposal, in its entirety, shall be one email (one attachment for price proposal, and one attachment for past performance information) not to exceed 15MB. Failure to submit in the format required and clearly address those factors may result in rejection of the offer. An original Bid Bond, in the amount of twenty (20%) percent (but not to exceed $3,000,000) of the bid price shall be mailed to the address listed in block 8 of the SF1442 and be received at the address no later than the closing date and time. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for due date, will require rejection of the proposal in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. SEE FAR Provision 52.228-1, Bid Guarantee, of this Solicitation. Electronic copies of the proposals will be time/date stamped by Microsoft Outlook upon receipt of email. Further details on electronic submission are outlined below.
Proposals shall be received by 2:00 P.M. Mountain Time on December 2nd, 2022. There will be no public opening of the proposals. Submit proposals to: Jared.Detton@va.gov.
Submit bid bonds to:
Department of Veterans Affairs
NCO 19
ATTN: Jared Detton 6162 S Willow Dr., Ste 300 Greenwood Village, CO 80111
Past performance information and price sections of the offeror’s proposal will be evaluated independently. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.
Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the Department of Veteran Affairs CVE at the time of offer submission. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.
I.6B PROPOSAL REVISIONS
If it is determined to be necessary, proposal revisions will be requested from the offers received. The Contracting Officer may identify those offerors, whose proposals are within the competitive range based upon the selection criteria identified in this solicitation. Negotiations may be conducted with those firms falling within the competitive range, after which proposal revisions may be requested. Offerors submitting proposal revisions will not be required to re-submit any documents which are unchanged from their proposals. They should provide necessary changes to individual paragraphs, as briefly as possible, together with the Table of Contents that clarifies where within the initial proposal the additional information and/or changed document would be placed. A new bid bond shall be submitted only if the final cost proposal revisions are greater than its initial cost proposal.
1.7B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER
Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.
In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.
Acceptable Electronic Formats (Software) for Submission of Offers
1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files).
2. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.
3. Another electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation.