About this file

36C25818B0324 S02_Utility Shutdown SOP Process Rev 1.pptx

View the file

Other files for this federal contract opportunity

Other files attached to PROJECT 605-15-351 Steam Distro Def Corrections: PLACE OF PERFORMANCE IS LOMA LINDA CALIFORNIA, newest first.
File Type Posted
36C25818B0324-018.docx DOCX document
36C25818B0324-019.pdf PDF
36C25818B0324-0002004.pdf PDF
36C25818B0324-0002003.pdf PDF
36C25818B0324-0002000.docx DOCX document
36C25818B0324-0002005.doc DOC document
36C25818B0324-0002001.pdf PDF
36C25818B0324-0002006.docx DOCX document
36C25818B0324-0002007.pdf PDF
36C25818B0324-0002002.pdf PDF
36C25818B0324-0001003.pdf PDF
36C25818B0324-0001000.docx DOCX document
36C25818B0324-0001002.pdf PDF
36C25818B0324-0001001.pdf PDF
36C25818B0324-012.pdf PDF
36C25818B0324-004.pdf PDF
36C25818B0324-014.pdf PDF
36C25818B0324-006.pdf PDF
36C25818B0324-007.pdf PDF
36C25818B0324-011.pdf PDF
36C25818B0324-017.docx DOCX document
36C25818B0324-009.pdf PDF
36C25818B0324-003.pdf PDF
36C25818B0324-010.pdf PDF
36C25818B0324-008.pdf PDF
36C25818B0324-001.docx DOCX document
36C25818B0324-013.pdf PDF
36C25818B0324-016.pdf PDF
36C25818B0324-005.pdf PDF
36C25818B0324-002.pdf PDF
36C25818B0324-000.docx DOCX document
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Utility Shutdown Process LLVAMC FMS-Project SOP

Click to see Slide Click to see Slide

Permit Process (Form SSP 605-25-1) Step 1: Contractor fills out Part I and sends to COR by 21-Days from required shutdown date.

Step 2: COR reviews and does initial assessment of impacted areas outside the work area.

Step 3: COR coordinates with appropriate staff from effected services and FMS shops to ensure the plan for the shutdown, resource requirements and staff responsibilities.

(Print Name and Initial are annotated in section C)

Step 4: COR signs and submits permit to supervisors in section A of Part III

Step 6: Chief of Projects will review and make recommendation.

Step 6: Assistant Chief, will review and make recommendation.

Step 7: Chief FMS reviews, signs and returns COR Step 8: COR provides copy to Contractor

14-Day Service Chief Notice Project: project Name Outage Type: List utility service to be shutdown Planning Date and Time: Time and Date (Estimated)

Actions to occur: The contractor renovating the Cath Lab, AMB Contractors, will conduct a shutdown of the fire sprinkler system on 26 Jan 16. The Project PM, PM NAME, is coordinating with your staff the details of the shutdown.

Operational Impacts: List all possible clinical or service operational impacts.

L/S Impacts: List possible impacts.

Coordination: The VALLMC team with the FMS PM as the lead will plan and coordinate all operational and L/S impact mitigation actions and provide details approximately 3-days out from the planned outage.

POC: PM Contact info

Submitted by COR Via email to Chief of Projects NLT 14-days out

Include Map of effected area

**************CONSTRUCTION NOTICE (Utility Shutdown)************

WHEN: Tuesday, January 26, 2016 from 7 am to 9 am WHO: Advanced Medical Builders WHAT: Fire Sprinkler shutdown to facilitate renovations for the 4E-60 Angio Lab Siemens Artis Q Biplane project ACTIONS: Fire sprinkler shutdown by FMS will begin Tuesday morning at 7:00 AM. An ILSM is not required because the system will be down for less than 4 hours. All alert and notification systems remain operational, and employees will follow the same procedures for a fire incident.

WHERE: Fire Zone 2-3-5 (See Attached Map)

If you have any further questions, feel free to call Adrienne Dunfee, FMS-Project Manager, at extension 4423.

3-Day General Notice Submitted by COR Via email to Chief of Projects NLT 5-days out

Include Map of effected area

Map Examples

Project Name: Triage Sink Shutdown Type: Domestic Water Date and Time: 1/12/16 , 4am to 6am Legend

Effected Area

Work Area

System Shutoff Points

ILSM Symbols

Access Denied Alternate Route

Egress Points

1st Floor

Project Name:

Shutdown Type:

Date and Time:

Legend

Effected Area

Work Area

System Shutoff Points ILSM Symbols

Access Denied Alternate Route

2nd Floor

Date and Time:

Legend

Effected Area

Work Area

System Shutoff Points ILSM Symbols

Access Denied Alternate Route

3rd Floor

Date and Time:

Legend

Effected Area

Work Area

System Shutoff Points ILSM Symbols

Access Denied Alternate Route

4th Floor image1.png image2.emf image3.emf image4.emf image5.emf image6.png