36C25521R0023 0001.docx
DOCX document 312 KB Posted
- Attached to
- Z2DA--657-19-110JC, FCA Replace Windows Building 1 Federal contract opportunity
- Solicitation number
- 36C25521R0023
About this file
This solicitation requests proposals for a construction project to replace exterior windows in a Veterans Affairs building. The contractor will fabricate and install approximately 1,100 new energy efficient windows in Building 1, including demolition, hazardous material abatement, and safety measures. The period of performance is 730 calendar days from notice to proceed. Offerors must provide pricing for the base bid and an alternate deducting certain infilled windows from scope. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 15 is the agency, with the project located at the John Cochran Veterans Affairs Medical Center in St. Louis, Missouri.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25521R0023
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
12-08-2020
36C25521R0023
657-19-110JC
36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway
Leavenworth KS 66048
36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway
Leavenworth KS 66048 To all Offerors/Bidders
12-08-2020
X
RFI ANSWERS AND ADDITIONAL SPECIFICATIONS
x
AMENDMENT
Project Number 657-19-110 Replace Windows Building 1
See attched Solicitation document
Tim Fitzgerald Contract Specialist
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
12-07-2020
657-19-110JC
Network 15 Contracting Office 3450 S. 4th Street
Leavenworth KS 66048 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street
Leavenworth KS 66048
FITZGERALD,TIM
913-946-1145 Request for Quote for project 657-19-110JC, FCA Replace Windows Building 1 at the St. Louis VA Medical Center in St. Louis, Missouri.
See attached Schedule, Statement of Work, Specifications and Drawing.
Period of Performance is 730 days after Notice to Proceed.
Payment and Performance bonds are required.
There will be only one site visit for this project. The site visit is scheduled for 12/11/2020 at 9:00 am CST Building 1 Loading Dock (The dock is located on the North side, along Bell St.), AT JOHN COCHRAN ST. LOUIS VAMC All Questions pertaining to this project are due 12/17/2020 2:30PM CST .
Provide Contractor Duns Number:__________________________ Contractors working on this project are exempt from state sales tax, and a Project exemption Certificate will be issued upon award of this contract.
Note: The term offer and bid are interchangeable.
The NAICS code and size standard for this project are: NAICS 236220 - Construction Contractors with a size standard of $39.5 million.
Magnitude of VA Project: Between $5,000,000.00 to $10,000,000.00
Facility COR: Mike Gomez (314) 652-4100x58720 michael.gomez4@va.gov Contracting Officer: Tim FItzgerald 913-946-1145 timothy.fitzgerald@va.gov
X X
52.211-10 X
12:00 01-06-2021
X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(See Specification Section 01 00 00 Paragraph 1.3)
Price to be submitted on Page 3 of this solicitation
$0.00
36C255
Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway
Leavenworth KS 66048
Department of Veterans Affairs Financial Services Center http://www.fsc.va.gov/einvoice.asp
Austin TX 78714
512-460-5545
SUBMIT PROPOSALS THROUGH VENDOR PORTAL
SEND CONFIRMATION E-MAIL AFTER UPLOADING
TO PAULINE.CZAJKOWSKI@VA.GOV
TIM FITZGERALD
Table of Contents
| PART I - THE SCHEDULE | 2 |
| SECTION A - SOLICITATION/CONTRACT FORM | 2 |
| SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 2 |
| STATEMENT OF WORK | 6 |
| VA St. Louis Health Care System | 6 |
| Purpose of Project: | 6 |
| Criteria: | 6 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 7 |
| 1.1 52.228-1 BID GUARANTEE (SEP 1996) | 7 |
| TASK ORDER TERMS AND CONDITIONS | 8 |
| A.1 52.215-1 INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION (JAN 2017) | 8 |
| A.2 PROJECT SPECIFIC INFORMATION | 12 |
| A.3 PROPOSAL SUBMITTAL INSTRUCTIONS FOR GENERAL CONSTRUCTION SOLICITATION | 14 |
| A.4 CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL | 17 |
| A.5 CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK, PROJECT # 657-19-110JC | 18 |
| A.6 LIMITATIONS ON SUBCONTRACTING-- MONITORING AND COMPLIANCE (JUN 2011) | 20 |
| A.7 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS (OCT 2015) | 20 |
| A.8 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012) | 22 |
| A.9 VAAR 852.237-70 CONTRACTOR RESPONSIBILITIES (APR 1984) | 23 |
| A.10 PROJECT WAGE DETERMINATION | 24 |
| A.11 STATEMENT OF WORK (LIST OF SPECIFICATIONS AND DRAWINGS) | 52 |
Page 1 of
Page 1 of Page 1 of
1 STATEMENT OF BID ITEM(S)
QUANTITY/JOB TOTAL PRICE
Page 1 of Page 1 of
Page 1 of Page 1 of Page 1 of Page 1 of A. BID ITEM 1, (BASE BID): Work includes general construction and alterations necessary for replacement of all existing exterior windows, repair of adjacent finish surfaces, associated electrical and mechanical work affected by window replacement, and hazardous material abatement as necessary for complete window installations (all conditions). Refer to both the “window schedule” and the “window schedule- infilled windows” on Sheet AE-114 for total window counts. Work is to be completed in 2 years (730 days) from NTP
QUANTITY/JOB TOTAL PRICE
Page 1 of Page 1 of
Page 1 of Page 1 of Page 1 of Page 1 of Page 1 of B. BID ITEM 2, (DEDUCT ALTERNATE A): All items in bid items 1 except existing exterior windows that cannot be replaced from the interior due to existing infill conditions. Refer to ‘WINDOW SCHEDULE – INFILLED WINDOWS’ on Sheet AE-114 for windows removed from scope of work. All other work per base bid is still to be completed. Accepting this alternate will also subtract 45 days from the allotted number of days to complete this project (685 days)
Page 1 of Page 1 of Page 1 of
STATEMENT OF WORK
VA St. Louis Health Care System Scope of Work: 657-19-110 FCA - Replace Windows in Building 1, John Cochran 31 December 2019 Purpose of Project:
The VA St. Louis Health Care System, John Cochran Division, will replace approximately 1,100 existing exterior windows, located in building 1, with new energy efficient windows. The existing windows were rated D in the last Facility Condition Assessment completed and are in poor condition and at the end of their useful life.
Criteria:
The Construction Firm shall provide construction services to fabricate new windows, remove existing window systems, install new window systems in Buildings 1. The Contractor shall abide by Construction Documents to meet applicable design standards and building codes. The Scope of Work for this project shall include, but not limited to, the following items and the necessary disciplines to accomplish these tasks:
· The Contractor shall complete a Pre-Construction Risk Assessment to determine the requirements for Infection Control, Interim Life Safety Measures, occupational safety and health, patient safety, public safety, security controls for physical and logical access, and environmental controls and limitations on vibrations, noise, and disruptions to operations and utilities.
· The Contactor shall provide to the VA resident engineer a definitive project schedule consistent with information contained within the construction documents. The VA reserves the right to define work zone availability and the Contractor’s schedule will work in a collaborative fashion to ensure that the on-going operational needs of Building 1 within the work scope are not negatively affected in any way. The building will remain occupied during the duration of this project.
· The Contractor remains responsible throughout the project life for protecting all surfaces and items, either VA owned or personal, from damage or destruction. The movement of items will not be allowed outside of the room of origin unless the Contractor accepts responsibility for storing said material at an offsite location at their cost.
· The VA will perform Construction period services including periodic construction progress inspections, hazardous material abatement monitoring, final inspections and submittals.
· The Contractor shall replace existing exterior windows with a new, energy efficient window system in Building 1. Coordination shall be made with the VA resident engineer to identify project schedule, logistics, physical security, confirmation of hours of operations and method of construction. The construction includes demolition, hazardous material abatement (Industrial Hygiene) and safety and infection control measures as required in the documents.
· The project period of performance is 618 calendar days from receipt of Notice to Proceed.
Page 1 of Page 1 of Page 1 of Page 1 of
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
1.1 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be percent of the bid price or , whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
Page 1 of Page 1 of
Page 1 of Page 1 of
Page 1 of
TASK ORDER TERMS AND CONDITIONS
A.1 52.215-1 INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION (JAN 2017)
(a) Definitions. As used in this provision— Discussions are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.
In writing, writing, or written means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
Proposal modification is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
Proposal revision is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
Time, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals.
(1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show—
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, revision, and withdrawal of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is "late" and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and—
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall—
(1) Mark the title page with the following legend:
This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed—in whole or in part—for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of—or in connection with—the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend:
Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award.
(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(2) The Government may reject any or all proposals if such action is in the Government’s interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government’s best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency’s evaluation of the significant weak or deficient factors in the debriefed offeror’s offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
(End of Provision)
A.2 PROJECT SPECIFIC INFORMATION
?.## PROJECT SPECIFIC INFORMATION
PROJECT TITLE AND NO: 657-19-110JC, FCA Replace Windows Building 1 PROJECT DESCRIPTION The VA St. Louis Health Care System, John Cochran Division, will replace approximately 1,100 existing exterior windows, located in building 1, with new energy efficient windows.
Location: John Cochran Veterans Affairs Medical Center (VAMC) 915 N. Grand Blvd St. Louis, Mo. 63106.
MAGNITUDE OF PROJECT: $5,000,000 - $10,000,000 (VAAR 836.204)
TYPE CONSTRUCTION: General Construction
NAICS: 236220, – (Commercial and Institutional Building Construction) SMALL BUSINESS SIZE: $39.5 Million
PERFORMANCE PERIOD: 730 Calendar Days, after receipt of Notice to Proceed
SITE VISIT: A site visit will be conducted on: 12/11/2020 at 9:00 A.M. CST.
Location: Building 1 Loading Dock (dock is located on the north side, along Bell St, approximately in the middle of building). The facility POC is Mike Gomez 314-652-4100 x58720 A pre-bid meeting will be held once all personnel are admitted into the facility Only a max of 10 people allowed in the conference room . Please meet at the loading dock. All Visitors to JC must first check in through the Loading dock.
· Visitors will be temperature checked and a wrist band will be issued, if they pass the VA screening, those who don’t will be dismissed from the pre-bid.
· All visitors must wear their mask, whether inside or outside on Federal property, at all times.
· The Loading Dock is located on the north side of JC property, along Bell Street, approximately in the middle of the city lot.
· Mike Gomez will meet all visitors at the Loading dock first, those who can’t pass the VA screening will not be allowed to go further.
PERFORMANCE & PAYMENT BONDS: In accordance with FAR 28.102-1 and Contract Clause 52.228-15, Contractors are reminded that any amount awarded over $30,000 shall require Payment Bonds, and awards exceeding $100,000 shall require both Payment and Performance Bonds. All bonds are due no later than 10 days after award.
AFFIRMATIVE ACTION GOALS AND GEOGRAPHICAL AREA (reference 52.222-23):
Goals for Minority Participation for each trade. __14.7__% Goals for Female Participation for each trade. __6.9__% The Geographical covered area for this solicitation (project) is _St. Louis County, Missouri___
LIQUIDATED DAMAGES: (__ ) YES or (_X_ ) NO (reference Contract Clause 52.211-12)
Amount Per Day: _____NA_______
WARRANTY OF CONSTRUCTION FOR GUARANTEE PERIOD SERVICES: ( ) YES or ( X ) NO (reference VAAR 852.246-75).
RESTRICTION ON SUBMISSION AND USE OF EQUAL PRODUCTS: ( ) YES or ( X ) NO (reference VAAR 852.236-90)
Description: ____NA__________________________________________
WAGE DETERMINATION APPLICABLE TO THIS PROJECT:
General Decision Number: MO20200056 10/09/2020
METRIC PRODUCTS: Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch/pound units, providing they fall within tolerances specified using conversion tables contained in the latest revision of Federal Standard NO. 376B, and all other requirements of this document are met. If a product is manufactured to metric dimensions and those dimensions exceed the tolerances specified in the inch/pound units, a request should be made to the contracting officer to determine if the product is acceptable. The contracting officer, in concert with the Contracting Officer’s Technical Representative, will accept or reject the product.
PROPOSAL SUBMITTAL CONTENTS SHALL INCLUDE:
1. Payment Bond
1. Any other information called out by this request for proposal documents
SAFETY OR ENVIRONMENTAL VIOLATIONS AND EXPERIENCE MODIFICATION RATE:
All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record. The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
Self insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.
A Determination of Responsibility will be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines above or submit this information will result in a determination of “Non-Responsibility” for the bidder/offeror. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility will make the bidder/offeror ineligible for award.
This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
Page 1 of Page 1 of
A.3 PROPOSAL SUBMITTAL INSTRUCTIONS FOR GENERAL CONSTRUCTION SOLICITATION
PROPOSAL SUBMITTAL INSTRUCTIONS FOR GENERAL CONSTRUCTION SOLICITATION
SOLICITATION: 36C25521R0023
PROJECT: 657-19-110JC, FCA Replace Windows Building 1 LOCATION:. John Cochran Veterans Affairs Medical Center (VAMC) 915 N. Grand Blvd St. Louis, Mo. 63106.
1. PREPARATION AND SUBMITTAL OF PROPOSALS
a. GENERAL INFORMATION.
Selection of an offeror for contract award will be made based on an assessment of each offeror’s response to the Request for Proposal (RFP). As a Request for Proposals (RFP) based on Lowest Price Technically Acceptable (LPTA) Source Selection Process, in accordance with Federal Acquisition Regulation (FAR) Part 15.101-2, the VA will make the award based on the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-price factors. The FIVE (5) evaluation factors for determination of technical acceptability consist of:
| 1. | Relevant Past Performance of Prime Contractor | |
| 2. | Technical Construction Experience of Prime Contractor | |
| 3. | Technical Qualifications of Proposed Key Staffing. | |
| 4. | Prime Contractor Safety Plan. |
5. Prime Contractor Quality Control Plan NOTE: Failure to comply with the RFP requirements may be grounds to eliminate the proposal from further consideration for contract award.
NOTE: Failure to comply with the RFP requirements will raise serious questions regarding an Offeror’s technical ability to perform the services and may be grounds to eliminate the proposal from further consideration for contract award.
b. THE OFFER.
The submission of the documentation specified below will constitute the Offeror’s acceptance of the terms and conditions of the RFP, including the Plans & Specifications for the construction of this project. These instructions prescribe the format for the proposal, and describe the approach for the development and presentation of proposal data. These instructions are designed to ensure the submission of necessary information to provide for the understanding and comprehensive evaluation of proposals.
c. AWARD BASED ON INITIAL OFFERS.
Pursuant to clause 52.215-1 the Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price, and technical qualifications standpoint. The VA reserves the right to conduct discussions if the Contracting Officer later determines such discussions to be necessary.
d. NUMBER OF COPIES TO SUBMIT.
Prospective offerors shall submit a SINGLE PACKAGE proposal in the Electronic Contract Management System (eCMS) Vendor Portal located at the following web link https://www.vendorportal.ecms.va.gov . * To ensure timely delivery due to electronic system malfunctions the contractor shall also provide the proposal in two separate binders along with a CD of the proposal content by the due date – at the NCO 15 Contracting Office 3450 S 4th Street Leavenworth KS 66048 containing the technical and price information by the request due date.
The package shall include:
(a) One (1) submittal will be marked Technical: ORIGINAL - RESPONSE TO RFP 36C25521R0023 657-19-110JC, FCA Replace Windows Building 1
This submittal is to contain the signed original copy of the documents and the technical response. *Original copies of required Payment and Performance bonds will be sent hard copy to the NCO15 Office address stated above.
(b) One (1) submittal attachment containing the pricing information for each Bid item as indicated on the price schedule.
2. DOCUMENTS TO SUBMIT.
| a. | STANDARD FORM 1442. Submit the SF 1442 issued under this solicitation, with Blocks 10 (DUNS Number) and Blocks 14 through 20 properly filled-out by the Offeror. Include acknowledgment of any and all Amendments that may have been issued, either by: (1) listing them in Block 19 of the SF 1442, or (2) including copies of the Amendment document(s) (Standard Form 30) with Blocks 8 and 15 filled in and signed, or (3) including signed acknowledgement in the form of a separate letter that includes a reference to the solicitation and amendment numbers. NOTE: Failure to acknowledge any and all Amendments issued pursuant to this solicitation may be cause for rejection of your offer. |
| b. | OFFER GUARANTEE (BID BOND). In accordance with solicitation provision 52.228-1, Bid Guarantee, failure to furnish a bid guarantee, in the proper form and amount, by the deadline established for submitting offers, may be cause for rejection of the offer. |
| c. | DOCUMENTATION OF TECHNICAL ACCEPTABILITY. Proposals received in response to this solicitation will be evaluated in accordance with procedures outlined in Federal Acquisition Regulations (FAR) Part 15.101-2 Lowest Price Technical Acceptable. |
Task Order award will be made based on the lowest price technically acceptable and best value to the Government in accordance with the criteria described in the RFP/RFQ. When price is the only factor considered, award will be based on the lowest reasonable and realistic price received. Proposals unrealistically high or low in price, when compared to the Government estimate, and market conditions evidenced by other competitive proposals received, may be indicative of an inherent lack of understanding of the solicitation requirements and may result in proposal rejection without discussion. The basis of award of each task order will be stated in the RFP/RFQ. Depending upon the requirements of each Task Order, the Contractor will typically provide a price proposal in response to an RFP/RFQ. Contractors shall respond within the number of calendar days stated in the RFP/RFQ by submitting an *electronic proposal to the Contracting Officer through the VA Vendor Portal in accordance with requirements stated in the RFP/RFQ.
PROPOSAL DUE DATE: January 06, 2021 at 12:00 PM CST
PROPOSAL SUBMITTAL CONTENTS SHALL INCLUDE:
· Signed copy of the 1442 (front and back) with amendments
· 52.209-5 Representation by Corporations Regarding an Unpaid Tax Liability or a Felony Conviction under any Federal Law (DEVIATION) (MARCH 2012).
· Calculation Worksheet for Self-Performed and Subcontracted Work
· * Proposal in two separate binders along with a CD
· Bid Bond
· Any other information called out by this request for proposal
d. PRICE PROPOSAL.
Offerors must provide a price for each bid item. In addition, offerors shall include a breakdown of material and labor costs, by specification division for each bid item. Overhead, profit and bond costs shall be added after a subtotal of materials and labor costs has been calculated. Price is to be submitted in accordance with the instructions in Block 17 of the Standard Form 1442. The Government's payment for the items listed in the Pricing Schedules of individual Task Orders will constitute full compensation to the Contractor for-- (1) Furnishing all plant, labor, equipment, services, appliances, and materials; and (2) Performing all operations required to complete the work in conformity with the drawings and specifications. The contractor shall include in the prices for the items listed in the Pricing Schedule all costs for work in the specifications, whether or not specifically listed in the Pricing Schedule.
3. BASIS OF AWARD.
VA will make the award based on the Lowest Price Technical Acceptable process to select the best evaluated price proposals meeting or exceeding the acceptability standards for the evaluation factor and significant subfactors in the solicitation when and if they are provided. Note that offers that do not meet the evaluation standards of the solicitation cannot be selected, regardless of price.
* Denote additional instructions
(END OF PROPOSAL SUBMITTAL INSTRUCTIONS)
A.4 CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL
Contractor Safety and Environmental Record Evaluation Form Information provided below is current and applicable to Solicitation 36C25521R0023 Company Name: ______________________________________________ Address: _____________________________________________________ Telephone: ______________________ Fax: ________________________ Email: _______________________________________________________ Contact: ______________________________________________________
1. Utilizing your OSHA 300 Forms, please complete the following information:
| Category |
| 2016 |
| 2017 |
| 2018 |
| 2019 |
Number of man hours (jobsite and office).
Number of cases involving days away from work, restricted activity, or both (Column H and I of OSHA 300).
Days away, restricted, or transferred rate (# of days away, restricted, or transferred cases x 200,000/# of man hours) (DART Rate).
Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations.
Please attach copies of the following documents: OSHA 300 and 300a Forms. These forms can be accessed through the OSHA publications search page: http://www.osha.gov/pls/publications/publication.html.
2. Provide six-digit North American Industrial Classification System (NAICS) Code for this acquisition: __________________________________
3. Who administers your company’s Safety and Health Program? ____________________________
4. Company’s Insurance Experience Modification Rate (EMR): ____________________________
A.5 CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK, PROJECT # 657-19-110JC
Offerors for General Construction (NAICS code 236220) must provide at least 15 percent (25% for NAICS codes 238210 & 238220) of the cost of the contract performance incurred for personnel will be spent on the concern's employees or the employees of other eligible service-disabled veteran-owned small business concerns. Provide a breakdown of material and personnel costs, by specification division listed for the project. Home Office overhead, profit/fee and bond costs shall be added after a subtotal of personnel and material/Equipment costs has been calculated. Clearly identify the personnel costs you will be performing, and the personnel costs of other eligible service disabled veteran-owned small business concerns. Below is a suggested format.
| Specification Division |
| SDVOB Vendor (Y or N) |
| Personnel Cost |
| Material/Equipment Costs |
Division 01
| $ |
| $ |
Division 02
| $ |
| $ |
Division 03
| $ |
| $ |
(Add additional lines as necessary for each Division applicable to this project)
| $ |
| $ |
| $ |
| $ |
| Sub Total (Personnel Costs, Material/Equipment Costs) |
| $ |
| Profit |
| $ |
| Home Office Overhead |
| $ |
| Bond |
| $ |
| Grand Total |
| $ |
Calculation of self-performed personnel costs:
1. Total personnel costs * both prime and all subcontractors: $_________________
2. Subtract all subcontractor personnel costs* that are not SDVOSB companies that will perform work on this contract: $__________________
3. Remainder is ‘Total amount of work to be self-performed under the Contract’: $__________________
4. Self-performed work = Line 3/Line 1 x 100 = __________%
*personnel costs include labors, mechanics, other tradesmen, and office personnel directly charged to the project (includes project manager, job superintendent, administrative, estimators, etc.)
I certify the above representations are true and correct to the best of my knowledge.
| ___Signature_________________________________ | ___________ | |
| (Typed Name of Authorized Representative) | Date |
(Title of Authorized Representative)
A.6 LIMITATIONS ON SUBCONTRACTING-- MONITORING AND COMPLIANCE (JUN 2011)
This solicitation includes VAAR 852.219-10 VA Notice of Total Service- Disabled Veteran-Owned Small Business Set-Aside. Accordingly, any contract resulting from this solicitation will include this clause. The contractor is advised in performing contract administration functions, the CO may use the services of a support contractor(s) retained by VA to assist in assessing the contractor's compliance with the limitations on subcontracting or percentage of work performance requirements specified in the clause. To that end, the support contractor(s) may require access to contractor's offices where the contractor's business records or other proprietary data are retained and to review such business records regarding the contractor's compliance with this requirement. All support contractors conducting this review on behalf of VA will be required to sign an “Information Protection and Non-Disclosure and Disclosure of Conflicts of Interest Agreement” to ensure the contractor's business records or other proprietary data reviewed or obtained in the course of assisting the CO in assessing the contractor for compliance are protected to ensure information or data is not improperly disclosed or other impropriety occurs. Furthermore, if VA determines any services the support contractor(s) will perform in assessing compliance are advisory and assistance services as defined in FAR 2.101, Definitions, the support contractor(s) must also enter into an agreement with the contractor to protect proprietary information as required by FAR 9.505-4, obtaining access to proprietary information, paragraph (b). The contractor is required to cooperate fully and make available any records as may be required to enable the CO to assess the contractor's compliance with the limitations on subcontracting or percentage of work performance requirement.
(End of Clause)
A.7 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS (OCT 2015)
(a)(1) The Offeror certifies, to the best of its knowledge and belief, that—
(i) The Offeror and/or any of its Principals—
(A) Are [ ] are not [ ] presently debarred, suspended, proposed for debarment, or declared ineligible for the award of contracts by any Federal agency;
(B) Have [ ] have not [ ], within a three-year period preceding this offer, been convicted of or had a civil judgment rendered against them for: commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State, or local) contract or subcontract; violation of Federal or State antitrust statutes relating to the submission of offers; or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, tax evasion, violating Federal criminal tax laws, or receiving stolen property (if offeror checks "have," the offeror shall also see 52.209-7, if included in this solicitation);
(C) Are [ ] are not [ ] presently indicted for, or otherwise criminally or civilly charged by a governmental entity with, commission of any of the offenses enumerated in subdivision (a)(1)(i)(B) of this provision; and
(D) Have [ ], have not [ ], within a three-year period preceding this offer, been notified of any delinquent Federal taxes in an amount that exceeds $3,500 for which the liability remains unsatisfied.
(1) Federal taxes are considered delinquent if both of the following criteria apply:
(i) The tax liability is finally determined. The liability is finally determined if it has been assessed. A liability is not finally determined if there is a pending administrative or judicial challenge. In the case of a judicial challenge to the liability, the liability is not finally determined until all judicial appeal rights have been exhausted.
(ii) The taxpayer is delinquent in making payment. A taxpayer is delinquent if the taxpayer has failed to pay the tax liability when full payment was due and required. A taxpayer is not delinquent in cases where enforced collection action is precluded.
(2) Examples.
(i) The taxpayer has received a statutory notice of deficiency, under I.R.C. Sec. 6212, which entitles the taxpayer to seek Tax Court review of a proposed tax deficiency. This is not a delinquent tax because it is not a final tax liability. Should the taxpayer seek Tax Court review, this will not be a final tax liability until the taxpayer has exercised all judicial appeal rights.
(ii) The IRS has filed a notice of Federal tax lien with respect to an assessed tax liability, and the taxpayer has been issued a notice under I.R.C. Sec. 6320 entitling the taxpayer to request a hearing with the IRS Office of Appeals contesting the lien filing, and to further appeal to the Tax Court if the IRS…
This is the start of the file's text. The full file is on GovTribe.