This document is an amendment narrative for the Water Main Replacement between Building 43 and Building 102 project at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The amendment modifies drawings, specifications, and responses to requests for information. The drawings were changed to note the location and type of a stormwater inlet, modify a concrete sidewalk detail, adjust the elevation graph for a water main replacement line, and revise a fire hydrant installation detail. The table of contents and specifications for laboratory testing requirements and earthwork were also edited. The related federal contract opportunity is solicitation number 36C25222B0013 for the Water Main Replacement between Building 43 and Building 102 project under contract number 695-21-108 from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLEMENT J. ZABLOCKI VA MEDICAL CENTER
MILWAUKEE, WI
PROJECT NAME: Watermain Replacement between Building 43 and Building 102
VA PROJECT NO: 695-21-108
Amendment No. 4 – Watermain Replacement between Building 43 and 102
Page | 1
AMENDMENT NO. 4
ISSUE DATE: 2/24/2022
This Amendment consists of:
1. Narrative – (1) Page
2. Drawings – (4) Drawings have been MODIFIED
3. Specifications – (3) Specifications have been EDITED/ADDED
4. RFI Responses – (7) Pages
The following instructions herein and the listed documents below are hereby modified to be incorporated as part of the contract documents.
CHANGES TO DRAWINGS:
1. CD101 – CIVIL DEMOLITION PLAN
a) MODIFIED DRAWING TO NOTE LOCATION, TYPE OF STORMWATER INLET
2. CS501 – CIVIL PAVING AND CONSTRUCTION DETAILS (1 OF 2)
a) MODFIED DETAIL 2/CS-501 “CONCRETE SIDEWALK”
3. CU201 – WATER LINE PLAN & PROFILE (1 OF 2)
a) MODIFIED “WATER MAIN REPLACEMENT LINE” ELEVATION GRAPH
4. CU501 – WATER LINE DETAILS
a) MODIFIED DETAIL 1/CU501 “FIRE HYDRANT INSTALLATION”
CHANGES TO SPECIFICATIONS:
1. 00 01 10 TABLE OF CONTENTS – Modified
2. 01 45 29 LABORATORY TESTING REQUIREMENTS – Added
3. 31 20 00 EARTHWORK – Modified
END OF AMENDMENT NO. 4 NARRATIVE