- Solicitation number
- 36C25221B0027
About this file
This solicitation package includes a notice of a federal contract opportunity to construct a campus water softening plant and the related solicitation documents. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12 is seeking bids to construct a new water softening plant building and install water softening equipment at the VA Illiana Health Care System campus in Danville, Illinois. The solicitation requests bids for construction of a building to house three water softening tanks, brine storage, and associated equipment. The period of performance is 240 calendar days from notice to proceed. The bid opening will be held on September 9, 2021. The contract is set aside for Service-Disabled Veteran-Owned Small Businesses. The estimated value is between $1,000,000 and $5,000,000. The NAICS code is 237110 for water and sewer line construction.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Continuation Pages
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 550-21-4-6949-1260 550-20-103 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders
36C25221B0027 08-10-2021
X X X
Solicitation:36C25221B0027 Project: 550-20-103 Campus Water Softening Plant
The purpose of this amendment is to incorporate the following:
1) Change the Period of Performance from 180 calendar days to 240 calendar days after NTP. See Continuation pages.
2) Provide Clarification to Bid submission instructions. See Continuation pages.
3) Provide responses to RFI Questions. RFI's are no longer accepted as of Augu st 26, 2021
4) Provide revised specifications and drawings. See attachments
The Bid due date and time remains September 09, 2021 at 1:00PM (CST). Bid opening location-See Block 7 of this form.
Kristi Kluck
SOLICITATION 36C25221B0027
AMENDMENT 0002
08/31/2021
BID SCHEDULE
| SOLICITATION: | 36C25221B0027 |
| PROJECT: | 550-20-103 (Construction) Campus Water Softening Plant |
The contractor shall provide for and furnish all labor, supervision, materials, tools, equipment, licenses, certification, insurance and temporary protection to construct a campus water softening Plant as required by the drawings and specifications and other terms and conditions as applicable. Provide work in accordance with federal, state, and local authorities as detailed in the attached project scope of work, specifications and drawings at the VA Illiana Health Care System, Danville, IL 61832.
All work shall be completed within 240 calendar days after receipt of the Notice to Proceed.
All-Inclusive Base Bid LUMP SUM: $ ___________________________
NOTICE TO BIDDERS: Award will be made to the responsible bidder who submitted the lowest responsive bid.
NOTICE TO BIDDERS: Work shall not commence until all required submittals are approved by the Contracting Officer or the Contracting Officer’s Representative (COR). An approved cost-loaded, Critical Path Method (CPM) construction schedule is required prior to commencement of construction. See specifications for details. CPM schedule shall be approved by the Contracting Officer or the Contracting Officer’s Representative. See specifications for details.
BID SUBMISSION INSTRUCTIONS: Only hard copy and mailed bid submissions will be accepted. All submissions must be received no later than the required bid due date and time. All submissions must be received in a sealed envelope and addressed to the following:
ATTN: Juan C. Gaytan and Kristi Kluck Solicitation: 36C25221B0027 Great Lakes Acquisition Center (GLAC) 115 S. 84th Street, Suite 101 Milwaukee, WI 53214-1476
BID OPENING: The bid opening will be held in-person at the Great Lakes Acquisition Center (GLAC), Milwaukee, WI. The Bid Opening will be held on the same date and time that the bids are due, Thursday, September 09, 2021 at 1:00PM CST. Contractors will check-in at the front desk and escorted to a designated conference. It is the responsibility of all contractors to arrive prior to the Bid Opening time, as the Bid Opening will start promptly at the time listed above. GLAC address is as follows:
Great Lakes Acquisition Center (GLAC) 115 S. 84th Street, Suite 101 Milwaukee, WI 53214-1476
BID DUE DATE: The Bid Due Date and Time remains Thursday, September 09, 2021 at 1:00PM CST.
Solicitation # 36C25221B0027 550-20-103 Campus Water Softening Plant RFI Questions and Answers (As of 08/26/2021)
1. Your Specs call out 25 gpm softener w 10 gpm backwash, FRP twin system. Operating pressure is listed as 15-25 psig, which will not work. Did you mean 125psi?
100 PSI is correct pressure. Water softener system to be per drawings. Refer to revised specifications section.
2. Operating temperature is listed to go to 120F. This won’t work unless you go to stainless tanks.
Temperature maximum shall be 100 F
3. The controller called out is the cheap off the shelf one that can’t control the recirc pump. Should be Allen Bradley 1400 PLC.
Controller will be changed. Refer to revised specifications.
4. Piping is called out as galvanized, which we can do, but I’d STRONGLY suggest SS internally and externally.
Piping shall be 304 SS. Refer to attached revised specifications.
5. Valves are called out as diaphragm. They should be butterfly.
Refer to question 12 response
6. There’s no skid mounting, which I would suggest we do.
Skid mounting called out in schedule. Refer to Drawing P001.
7. Is this system supposed to be a triple? 2 tanks are called out in specs, 3 on PID and 4 on the schedule Three tanks required per drawings. Refer to revised specifications and Drawings.
8. Model 1500 has the following characteristics: which do not match the attached schedule (Attachment 1). 54” diameter tanks, 405 GPM Continuous flow per tank, Minimum flow for preventing channeling is 32 GPM, Brine Tank Size is 56” x 63”. Please confirm how many tanks there are so we can confirm system dimensions Refer to response in question 7.
9. Is this system skid mounted?
Yes, refer to response to question 6
10. What piping material is preferred? 304 SS should be used for face piping and internals 304 SS. Refer to revised specifications.
11. What controller is to be used? AB1400 is required for above system Controller shall be AB 1400.
12. Are the valves to be air actuated butterfly or electric actuated butterfly?
Electric actuated.
13. Are the inlet and outlets on the tanks to be 4” to match the model number?
a. Yes, reference detail.
14. Will there need to be any filtration devices installed in the Domestic Water system?
No, UV system only per drawings
15. Spec/Dwg. Reference (s): Solicitation section "Instructions, Conditions, and other statements to bidders/offers" The original Solicitation allowed emailed bid submissions to the Contracting Officer and Contract specialist under paragraph Bid Due Date and Bid Submission. Amendment 1 changed the bid submission to 'only hard copy' bid submissions. Since the number of COVID 19 cases and infections has significantly risen within the last 60 days, for sake of personal safety, will the VA provide the alternate method of email bid submission? This email bid submission method was stated as an original solicitation requirement. Amendment 1 changed the bid submission to hard copy, which is usually in-person.
Unfortunately, we will not accept email submissions. However, you can mail your submission to the address on block 8 on 1442 form or deliver it by the bid opening due date.
16. Spec/Dwg. Reference (s): Solicitation section "Instructions, Conditions, and other statements to bidders/offers" Bid opening stated be held 'in-person' at the GLAC in Milwaukee, WI in Solicitation and in amendment 1. Will the VA be hosting / providing a live bid opening conference so bidders can listen to bid opening? Please provide a call in number.
At this time, there is no teleconference schedule for bid opening. However, if we are able to obtain a call-in number before bid opening due date then we will publish one.
17. Spec/Dwg. Reference (s): Solicitation section "Instructions, Conditions, and other statements to bidders/offers" If email bid is allowed, will the VA accept bid bond with bid and original hard copy mailed to the VA?
Unfortunately, we will not accept email submissions. However, you can mail your submission to the address on block 8 on 1442 form or deliver it by the bid opening due date.
18. Spec/Dwg. Reference (s): Solicitation section "Instructions, Conditions, and other statements to bidders/offers" The RFP states that we are to submit written RFIs in email to the contracting officer and specialist. A VA RFI Form is not attached with the Solicitation. Are we to submit using typical VA RFI forms?
There is no official RFI form to be used during solicitation phase. A simple email is sufficient.
19. Is this project tax exempt? Will the CO/COR provide the necessary tax exempt certificates?
Yes, this project is tax exempt, and tax-exempt certificate information will be provided after award.
20. Spec/Dwg. Reference (s): Contracting Officers Special Instructions, Page 8 of solicitation The Contracting Officer will provide a NTP after the contract award is made. What is the approximent duration between issuing the award and issuing the NTP?
We expect to issue NTP two to four weeks after award, however, this timeline is flexible.
21. UV Question/Request for clarification: 1,095 GPM UV System at 94% UVT We are concerned that with such a large UV System, much of the flow to the hospital (all flows less than 55gpm) won’t be treated by the UV System. This system turns off with less flow than 55 gpm to prevent from overheating. We would advise the following: Instead of one large UV unit, we suggest scope be changed to one 120gpm that would have a minimum flow of 6gpm for normal flow. The other could treat up to 1,000gpm, but would only be turned for flows over 120 gpm. This would require a controls package that includes valving and flow meters.
UV to be revised. Refer to revised drawings.
22. Could you please verify the dimensions of the softener? The dimensions should be 8’5” height, 6’2” width, and 24’0” length. The schedule lists W156”x85”HxD42” Refer to revised drawings.
23. Masonry for this project: Bricks – Drawings say the bricks are Sioux City Mountain Shadow What is the finish? Velour or smooth? Velour
24. CMU – There are no structural requirements called out for the CMU. Will vertical rebar, grouting, or reinforcing wire be required in the block?
Grout at 48” o.c. with vertical #5 bar. Horizontal reinforcing @ 16” per structural general notes
25. Is there a minimum embedment depth for dowels into the concrete foundation?
3” if epoxy-drilled with epoxy to be approved by A/E, 18” if placed before pour.
26. Air barrier is called out in the drawings to be on the block, but there is no spec.
Should this be a fluid applied per spec section 07 27 26 such as WR Meadows Air-Shield LSR? Yes, spec attached.
27. Specification Section 11-07-11 The specifications call for cellular glass (foamglas) and/or polyisocyanurate pipe insulation. Can we substitute Owens Corning Fiberglass pipe insulation with all-service jacket as an equivalent material? The fiberglass is more readily available than the cellular glass (foamglas) and/or polyisocyanurate insulation in addition to being more efficient.
Refer to revised Specifications. FRP are not acceptable. Tanks are to be steel.
28. Specification Section 22 31 11 – C.1 and C.2 7 (page 7) Please confirm that fiberglass; FRP tanks are acceptable in lieu of the steel tanks under as listed in section C. 1. Also, the schedule on Drawing P001 does not indicate if the Nancrede NHC-1500-4 system is steel or fiberglass. Please confirm that steel is acceptable.
Refer to revised Specifications. FRP are not acceptable. Tanks are to be steel.
29. Spec Section 01 00 00 1.17 Resident Engineers Field Office, mentions the requirements does this spec section pertain to this solicitation? Please advise.
Not required for this project.
30. Spec: General Conditions Topic: Management Question: Please confirm personnel requirements for this project. Can (1) superintendent fulfill SSHO requirements? Or does (1) superintendent and (1) SSHO need to be on site full-time? Is a QCM required?
For this project the superintendent can fulfill the SSHO requirements. Provided that the superintendent is qualified to fulfill the role, a separate QCM is not required for this project. Provide documentation to the COR for the superintendent’s qualifications.
31. Sheet: SB101 Spec: N/A Topic: Design Question: Plan page SB101 – foundation plan Note 3 states that ‘footing sizes may be required to change based on loads received from pre-engineered metal building manufacturer.’ In the event these will need to be adjusted due to the manf. Recommendations, will this be issued as an after-award change?
Yes, this will be issued as after-award if resize is necessary
32. Spec: Pre-Engineered Building Topic: Basis of Design Question: Is it acceptable to provide a substitute for the ‘basis of design – butlerib II’ pre-engineered building system if it meets the performance requirements in the specifications. Or, is there a sole source justification to be provided?
It is acceptable to provide a substitute that meets or exceeds the basis of design specifications. VA to make final approval of substitute.
33. Topic : Soils Question: IS prime contractor to assume clean soils for exterior work?
Yes, assume clean soils for bid with topsoil requirements noted. Note that a geotechnical consultant hired by GC is required per 014219 spec.
34. Topic : Material Lead Times Question: Due to current market conditions, prime contractors are seeing extensive lead times for materials, especially with pre-engineered building systems. With the 180d PoP constraint, this timeline is not feasible with the engineering, procurement, and installation. Will the VA provide an interim NTP to release materials and issue a full NTP once materials are made available?
The VA shall amend the solicitation to change the Period of Performance (POP) from 180 calendar days after NTP to 240 calendar days after NTP to allow additional time for the pre-engineered building system. Any additional time shall be addressed through standard contracting processes as a modification to the contract.
35. Spec/Dwg. Reference (s): 07 22 00 2.1 A 1 & 2- Wall and roof details for the PEMB on AE311 for insulation refer to the specs. Spec section shows R-33 for Roof and other areas R-10. This building is an unoccupied space for equipment. Typically, on unoccupied buildings the roof insulation is R-19 and the walls are R-13. Please clarify correct R value for the roof and walls.
Continue with R values called out in the specification.
36. Due to the unprecedented and unpredictable material price increases occurring in the nation, will the CO/VA/Owner allow a fixed price contract with economic price adjustments per FAR 16.203 to be used as the basis for contract award? This will allow the most competitive price to be offered at this time.
No, this solicitation is for a Firm Fix price contract.
37. Period of Performance (POP) for this solicitation is 180 calendar days after NTP. Pre-engineered metal building companies, along with industry understanding, are saying the PEMB delivery dates after approval are now 20 to 30 weeks. Also, the production of shop drawings from the manufacturer, after award, is taking 6 to 8 weeks. Will the VA provide some type of administrative NTP to allow for submittals and building order prior to NTP commencement of construction? Otherwise, the period from PEMB award to delivery could take up most of the 180 pop, not allowing for follow on activities. Please consider extending the pop days or other means to account for PEMB long lead times.
Refer to response to question 34.
38. Spec/Dwg. Reference (s): P101 Does the bulk brine storage tank set on a concrete pad? Isometric detail 1/P103 shows grey lines that look like a pad. Details or written notes not provided for pad. Please provide pad dimensions, size, and thickness if required.
Yes, pad dimensions are on revised drawing.
39. Spec/Dwg. Reference (s): P101 Does the brine storage and pressure vessels set on a concrete pad? Isometric detail 1/P103 shows grey lines that look like a pad. Details or written notes not provided for pad. Please provide pad dimensions, size, and thickness if required.
Yes, pad dimensions are on revised drawings.
40. Spec/Dwg. Reference (s): P101 Does the triple water softener tanks set on a concrete pad? Isometric detail 3/P103 shows grey lines that look like a pad. Details or written notes not provided for pad. Please provide pad dimensions, size, and thickness if required.
Yes, pad dimensions are on revised drawings
41. Spec/Dwg. Reference (s): SF101/SF301 Drawings SF101 and SF301 are marked 'not for construction' in the title block. What does not for construction mean in this solicitation RFP drawings?
Drawings will be reissued with stamp. Bidders may assume that what is shown on drawings is for construction.
42. Spec/Dwg. Reference (s): SB101 Structural foundation drawings do not show how the 8"CMU walls are installed, anchored, supported to the foundation. Are the 8" CMU walls fully grouted or grouted with dimensions? What is the rebar type/size of dowels into footing? How are the CMU walls supported vertically and horizontally with rebar, dowels, and grout?
Grout at 48” o.c. with vertical #5 bar. Horizontal reinforcing @ 16” per structural general notes. 3” if epoxy-drilled with epoxy to be approved by A/E, 18” if placed before pour.
43. Spec/Dwg. Reference (s): 1/AE311 Detail 1/AE311 shows 2x10PT wood cap on top of cmu backup wall, resting on top of steel angle attached with construction adhesive. Are the CUM walls fully grouted to the top? If not, the 2x10 will not be able to adhere to the block/angle. Typically for PEMB, a steel girt is installed at this location (in lieu of angle/wood) and attached to fully grouted CMU top course of the wall and to the PEMB structural column.
Exempt 2x10 wood cap and replace steel angle with z girt. See attached detail.
44. Can you provide the site observation report along with the geotechnical report for foundations, soils, and existing conditions?
Topographical survey is attached. A geotechnical investigation is not available for this site. A report from an adjacent area can be provided.
45. The Contracting Officer will provide a NTP after the contract award is made. What is the approximant duration between issuing the award and issuing the NTP?
We expect to issue NTP two to four weeks after award, however, this timeline is flexible.
46. For planning the preliminary project schedule, can you please provide an anticipated award date?
We estimate 10 calendar days after bid opening due date.
47. What is the anticipated duration between issuance of contract award and issuance of the NTP?
We expect to issue NTP two to four weeks after award, however, this timeline is flexible.
48. How many calendar days should be included in the critical-path method schedule for owner and A/E review and respond to RFIs?
Provide review period per specification section 01 33 23.
49. How many calendar days should be included in the critical-path method schedule for owner and A/E submittal review?
Provide review period per specification section 01 33 23.
50. Will the owner provide 3-D REVIT Design model in native file format, for creation of coordination documentations?
3-D REVIT models are not available for this project. The VA shall provide the available AutoCad drawing files for coordination.
51. Will the owner provide the contract drawings in the native 3D Revit format for use by the GC?
3-D REVIT models are not available for this project. The VA shall provide the available AutoCad drawing files for coordination.
52. Will owner require GC’s to develop and submit coordination drawings in 3D Revit?
3-D REVIT models will not be required for this project; however the GC shall provide As-Built documents per the specification section 01 00 00.
53. Where will the designated parking & laydown area be for workers accessing the construction site?
The project site plan indicates the limits of construction for this project. If additional space is required it must be requested from the COR based on the GC providing the total amount of area needed, type of use, duration of need, and the additional space shall be returned to pre-existing conditions before being released from contractor use.
54. Does the contract includes liquidated damages? If the owner temporarily shuts down or suspends the project (i.e. for noise), will extended general conditions cost and time be added to the contract?
Liquidated damages are not included in the contract.
55. We anticipate certain construction activities to generate high levels of noise. Please confirm that only the Contracting Officer can suspend work via written notification to the Contractor.
Contracting Officer is the only authorized official to suspend work. Depending on circumstances, CO may verbally suspend, and then provide written notification.
56. Is AISC (American Iron and Steel Certification) required for the structural steel fabrication and/or erection for this project?
AISC is not required, but a record of experience is required per 13 34 19 metal building spec for both the manufacturer and installer.
57. Spec/Dwg. Reference (s): 01 33 24 1.6 Will the owner accept the use of the industry leading Procore Project Management software as the primary submittal and data tracking tool for this project?
Yes, this software is considered approved for this application.
58. As a result of the effect of COVID-19 throughout the U.S., and the resulting Federal, State and local governments’ responses / requirements of safe distancing and potential advocations of working remotely and/or complete organization closures, please advise how the Government intends to address delays resulting there as it pertains to the current solicitation schedule for this and all future projects.
Due to the nature of the pandemic it is not possible to forecast future requirements related to working conditions. This is a medical facility and has remained operational to date throughout the pandemic. During the course of this project the current facility requirements shall be observed unless updated in writing as follows: Contractor employees (including project design team members) accessing the VA facility in person must participate in VHA’s COVID-19 vaccination program as described in VHA Directive 1193, Coronavirus Disease 2019 Vaccination Program for Veterans Health Administration Health Care Personnel. This VHA directive mandates that all Contractor employees must be fully vaccinated against COVID-19. To verify compliance, it is required that a COVID-19 Vaccination VA Form 10-263 found in Appendix B of the directive be filled out, signed, and submitted to the COR of the project (form should be filed prior to site visit to avoid delays). By signing the Appendix B, Contractor employees acknowledge that they have read, understood, and agree to comply with the requirements. In addition, all visitors to the facility must abide by the current facility requirements regarding masks and other protective measures. All visitors are currently required to wear masks provided by VAIHCS to ensure compliance with the FDA, OSHA, and VA regulations while working in VAIHCS facilities. Masks may be obtained at the entry points to Buildings 58, 98, and 102. Contractor employees that would like to wear a self-supplied mask shall contact the COR for guidance on how to obtain approval. During the review and approval process, the requested masks will not be worn, and the requestor shall wear a compliant mask supplied by VAIHCS.
59. Spec/Dwg. Reference (s): 01 00 00 1.17 Spec section 01 00 00 paragraph 1.17 calls for contractor to provide 'where shown on drawings' a temporary field office, furniture, 2" deep gravel surfaced area for resident engineer. The drawings do not show or indicate a location or requirement for a resident field office. Is a resident field office with required equipment, and gravel parking required for this project of this size and 180 day duration?
Not required for this project.
60. Spec/Dwg. Reference (s):01 00 00 1.28 Spec section 01 00 00 paragraph 1.28 photographic documentation requires commercial photographic company with demonstrated 3 years documented portfolio of work throughout North America. Further, the spec section requires indexing and navigation system utilizing actual AutoCAD construction drawings, making such drawings interactive on an online interface. This requirement seems extreme for this type of project and pop duration. Is spec section 1.28 a requirement for this project?
Not required for this project.
61. Spec/Dwg. Reference (s): 01 81 13 1.5 D. Spec 01 81 13 1.5D Construction Indoor Air Quality Plan (IAQ) required not more than 30 days after preconstruction meeting. The project is a construction of a new pre-engineered metal building. The spec requires plans/procedures/documentation/photos to existing air handler systems, HVAC, filters, grilles, system flush out, etc. This project contains no existing / indoor construction /renovations. Is an IAQ plan, procedures, testing, sampling, reporting required for this type of project?
Not required for this project.
62. Spec/Dwg. Reference (s): Finish Color for Pre-engineered building metal wall panels, roof panels, trim, gutters, and downspouts are shown in spec section 09 06 00 as manufacturer standard colors. The pre-engineered structural frame in 13 34 19 will have manufacturers shop prime paint. Final paint finish/color for the Pre-engineered building structural frame including columns, beams, girts, purlins, and channel framing is not addressed in section 09 06 00 Schedule for finishes for division 13 34 19. There is reference for structural steel 05 12 00 as being exposed galvanized with color to be determined. (TBD). However, 05 12 00 is not the steel of spec section 13 34 19 pre-engineered metal buildings. We assume the pre-engineered metal building structural members will be provided with manufactures standard shop paint/color.
Pre-engineered metal building structural members to be manufactures standard shop paint color to be approved by VA.
63. Spec/Dwg. Reference (s): E100 to E103/E200 Drawings E100 to E103 and E200 title the drawing as "Fully Sprinklered" in the tile boxes. There is not a spec section or drawings requiring fire sprinkler system. Please verify this building is not fire sprinklered.
Building is not sprinklered
See attached document: Attachment 1. Addendum 1 - Arch set.
See attached document: Attachment 2. Addendum 1 - MEP set.
See attached document: Attachment 3. Addendum 1 - Struct set.
See attached document: Attachment 4. 22 31 11 ADD.
See attached document: Attachment 5. 07 27 26 - Vapor Barrier.
See attached document: Attachment 6. VA Danville Water Softener Plant - Bid RFI 43.
See attached document: Attachment 7. 010000 General Requirements 08-17-2021.