36C25221B0018 0001.docx
DOCX document 32 KB Posted
- Solicitation number
- 36C25221B0018
About this file
This document includes an amendment to a solicitation and questions and answers related to a federal construction project. The solicitation amendment provides changes to project specifications and drawings for a renovation project involving approximately 3,100 square feet of space on the first floor of Building 1 at the William S. Middleton Memorial Veterans Hospital in Madison, Wisconsin. The scope of work includes phasing, demolition, hazardous material removal, interior finishes, doors and windows, mechanical and electrical systems work. The pre-bid date remains unchanged, and all correspondence should be sent to the address in Block 8. The questions and answers provide clarifications on personnel requirements, responsibility for controls and integration contractors, material staging, order of precedence, submittal software, specifications for casework and lockers, signage schedule, work phasing timelines, and other project details.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 607-21-3-6936-0137 607-19-101 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 36C252 Department of Veterans Affairs Wm S. Middleton VA Hospital Attn: John Meyers (90C) Overlook Terrace Madison WI 53705-2254 To all Offerors/Bidders
36C25221B0018 07-29-2021
X X X
X
SEE ATTACHED SUMMARY OF CHANGES
The Bid Opening date remains unchanged at 18 August 2021 at 1:00 PM Local time.
*REMINDER: The bid opening will occur at the main VA hospital in Madison WI (address listed in block 8 of the SF 1442).
Ensure all correspondence is mailed to or hand-carried to the address listed in block 8 of the original solicitation.
ACCOMPANYING AMENDMENT 36C25221B0018 – 0001
RELOCATE PHARMACY COMPOUNDING AREA
WILLIAM S. MIDDLETON VA HOSPITAL, MADISON, WI
I. THE FOLLOWING CHANGES ARE TO BE MADE TO THE SOLICITATION:
1. Delete from the Project Specification the following: Specification 01 45 00, Para 3.4.B and the associated ‘Experience Matrix’. Delete from the Project Specification the following: Specification 01 45 00, Para 3.4. D.
II. THE FOLLOWING CHANGES ARE TO BE MADE ON THE PROJECT DRAWINGS :
1. Revise drawing sheet A-751 with interior signage schedule, accompanying this amendment.
III. THE FOLLOWING QUESTIONS AND ANSWERS/CLARIFICATIONS ARE THE RESULT OF BIDDERS REQUEST(S) FOR INFORMATION :
Question #: 01 Please confirm personnel requirements for this project. Can (1) superintendent fulfill SSHO requirements? Or does (1) superintendent and (1) SSHO need to be on site full-time?
A01. The Prime Contractors Superintendent can also be the designated SSHO.
Question #: 02 Does prime contractor need to directly hire 23 09 23 controls?
A02. No Prime Contractor does not need to direct hire the Div 23 Controls Contractor.
Please confirm GC needs to directly hire DIV25 integration.
A02a. General Contractor does need to direct hire the Div Integration Contractor.
Question #: 03 Please confirm if contract has material staging location at facility. If so, where is it? Is prime contractor responsible for any costs associated with staging?
A03. Material staging and storage shall be limited to the project areas within phased area.
Question #: 04 Please confirm order of precedence for the contract documents. Does SOW prevail over all documents?
A04. IAW with FAR 52.236-21 “In case of difference between drawings and specifications, the specifications shall govern”.
Question #: 05 Is prime contractor responsible for providing Submittal Exchange and all costs associated with software?
A05. Contractor is responsible for the cost of the electronic FTP file sharing system. See specification 01 33 23, 1.6.
Question #: 06 The drawings indicate that there are new countertops and casework on this project, as well as new lockers, however there are no specifications provided for these trades. Please provide specifications for countertops, casework, and lockers.
A06. Refer to Sheet A721 for all basis of design materials requested above. Refer to equipment item #24 for metal locker basis of design product.
Refer to specification 062000 – Finish Carpentry and 123600 – Countertops, attached to the response herein.
Question #: 07 Please provide schedule for signs dictated to be installed in specs.
A07. Signage locations and designations have been added to sheet A751
Question #: 08 How much time will work be required to stop between phases?
A08. Upon completion of each phase. Contractor to allow 5 working days for the VA to coordinate and relocate the pharmacy functions.
Question #: 09 Does workspace in the G-Wing need to be turned over at the end of each shift? Noting that this is during off-hours, will work area need to be clean and ceiling tiles in prior to the following day’s business hours?
A09. Yes, workspace in G-wing as indicated by Detail 2 on AD1010 shall be clean and turned over prior to the following days business hour.
Question #: 10 Please confirm that contractor is responsible for both furnishing and installing the S-Den-O steel defender security screen called out on Keynote 8 / A101.
A10. General contractor is responsible for furnishing and installing the S-Den-O steel defender security screen called out on Keynote 8 / A101.
Question #: 11 What is the height of the deck in the work area relative to the floor slab?
A11. First Floor C-Wing Project area floor to deck height: 11’ 6”.
Question #: 12 What is the thickness of the floor slab?
A12. First Floor C-Wing Project area slab thickness: 6.5”.
Question #: 13 Can EdgeGuard be used for infection control barriers?
A13. See Drawing AD101 Demo Note 1B for barrier requirements.
Question #: 14 Does contractor owe final clean?
A14. Contractor shall perform a final cleaning prior to final inspection and turn over to next phase. VA to perform the final -final sterile cleaning.
Question #: 15 Drawings dictate for pneumatic tube system; however, per sheet A101, it appears to be in the same location. Please confirm if system is to be removed and replace in the same location and with same orientation (facing north).
A15. Tube Station shall be removed and re- orientated 180 degrees to face south from current position (facing North) in the same location.
Question #: 16 Is there any sequencing associated with the automatic sliding doors? (i.e. only one can be opened at a time)
A16. The design team is not aware of interlocking requirements for the automatic sliding doors.
Question #: 17. Please confirm the GC is to provide a CQC Manager full time on site during work. And the CQC Manager can also serve as project Superintendent if the requirements called out in spec section 01 45 00 3.4 B, are met.
A17. The Prime Contractors Superintendent can also be the designated CQC Manager.
Question #: 18. Please confirm the requirement for Additional CQC Personnel as called out in section 01 45 00 3.4 C per definable features of work as described in the experience matrix of this section. This will require most GC’s to hire added staff and or employ the services of an Engineering firm above and beyond project A/E.
A18. Delete from the Project Specification the following: Specification 01 45 00, Para 3.4.B and the associated ‘Experience Matrix’.
Question #: 19. Please confirm the GC CQC manager will need to provide certificate of completion of CQM Construction Course prior or within 90 days after award.
A19. Delete from the Project Specification the following: Specification 01 45 00, Para 3.4. D.
IV. GENERAL INFORMATION :
· PRE-BID/SITE VISIT ATTENDANCE SHEET
· THE ATTACHED REVISED WAGE DETERMINATION IS HEREBY INCORPORATED INTO SUBJECT SOLICITATION
THERE ARE NO FURTHER CHANGES
See attached document: S06 - A751 Pharmacy.
See attached document: S06 - Spec 06 20 00.
See attached document: S06 - Spec 12 36 00.
See attached document: S06 - Pre-Bid Attendance List.
See attached document: S06 - Wage Determination Revised.