9)_Infection_Control_Risk_Assessment_(ICRA).pdf
PDF 245 KB Posted
- Attached to
- Upgrade Electrical-C Transformers Building 200 Federal contract opportunity
- Solicitation number
- 36C25219R0002
About this file
36C25219R0002 9) Infection Control Risk Assessment (ICRA).pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25219R0002-A00002000.docx | DOCX document | |
| 36C25219R0002-A00002002.pdf | ||
| 36C25219R0002-A00002003.pdf | ||
| 36C25219R0002-A00002001.pdf | ||
| 36C25219R0002-A00001000.docx | DOCX document | |
| 8)_Interim_Life_Safety_Measures_(ILSM).pdf | ||
| 10)_PIV_Badging_at_Hines.pdf | ||
| 7)_Above_Ceiling_Entry_and_Wall_Construction_Permit.pdf | ||
| 13)_-_57813001_01_Final_Bid_Specs.pdf | ||
| 5)_Cutting_Welding_and_Other_Hot_Work.pdf | ||
| 3)_Pre-Construction_Checklist.pdf | ||
| 1)_Hines_VA_Campus_Site_Plan.pdf | ||
| 36C25219R0002_3.docx | DOCX document | |
| 6)_Dig_Permit_SOP_Form_2015.pdf | ||
| P07_General_Decision_Number_IL190009_01-04-2019__IL9.pdf | ||
| 4)_Safety_and_Health_During_Construction_Activities.pdf | ||
| 11)_Contractor_Parking.pdf | ||
| 12)_Rev._578-13-001_BidDocument_Drawings_05012018.pdf | ||
| 2)_Hines_Underground_Utility_Plan.pdf | ||
| 36C25219R0002-000.docx | DOCX document |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FAX to Infection Control x22481 and to Safety x25613 or scan & attach via e-mail to “Hines Infection Control Service”
Infection Control Risk Assessment for Construction / Renovation Projects Project Name: Project/ Work-Order Number:
Project Planner or Technician: Extension:
Building Number: Floor(s)/Room(s):
Start date: Projected completion date: / /
Construction Activity Infection control risk group
TYPE A: Non-invasive activity, low noise, no vibration
DUST LEVEL Low
GROUP 1: Low office areas, FMS areas, all non-patient care areas.
TYPE B: Small scale, short duration, low-moderate noise, low-moderate vibration
DUST LEVEL: Moderate to High
GROUP 2: Medium All other patient care areas including general medicine floors, ultrasound, Rehab, Occupational Therapy.
TYPE C: Requires more than one work shift to complete, low-moderate noise, moderate–high vibration DUST LEVEL Moderate to High
GROUP 3: Medium/High ED, Radiology/MRI, admissions, food service areas, laboratories.
TYPE D: Major demolition and construction activities Requiring consecutive work shifts, moderate-high noise, moderate-high vibration
DUST LEVEL High
GROUP 4: Highest Operating rooms, SPS, ICU’s, Outpatient areas, oncology, anesthesia, post anesthetic recovery, all endoscope areas, Pharmacy, Renal Dialysis
Project Class Determination Matrix Construction Activity
Risk Level
Type
“A”
Type
“B”
Type
“C”
Type
“D”
Group 1 I II II III
Group 2 I II III IV
Group 3 I III III IV
Group 4 III IV IV IV
Contractors Actions by Project Class
CLASS
I
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace any ceiling tile displaced for visual inspection.
3. Contain construction waste before transport in tightly-covered containers.
4. Emergency Preparedness training/posting/ID card.
CLASS
II
1. Provide active means to prevent air-borne dust from dispersing into atmosphere.
2. Water mist work surfaces to control dust while cutting.
3. Seal unused doors with duct tap
4. Block off and seal air vents.
5. Wipe surfaces with disinfectant.
6. Contain construction waste before transport in tightly-covered containers.
7. Emergency Preparedness training/posting/ID card.
CLASS
III
1. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.
2. Complete all critical barriers before any work begins.
3. Maintain negative air pressure within work area utilizing
HEPA-equipped air filtration units.
4. Provide dust mat at entrance and exit of work area.
5. Contain construction waste before transport in tightly-covered containers.
6. Wet mop or vacuum with HEPA-filtered vacuum before leaving work area.
7. Cover transport receptacles or carts. Tape covering.
8. Emergency Preparedness training/posting/ID card.
CLASS
IV
1. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.
2. Complete all critical barriers before any work begins.
3. Maintain negative air pressure within work area utilizing
HEPA-equipped air filtration units.
4. Provide adhesive walk-off mat at entrance and exit of work area.
5. Seal holes, pipes, conduits and punctures appropriately.
6. Vacuum the entire work area with HEPA vacuums or wet mop with disinfectant at the completion of project.
7. Do not remove barriers from work area until completed project is thoroughly cleaned by housekeeping and inspected by the Infection
Control Department, Safety Section, and Engineering Service.
8. Remove barrier materials carefully to minimize spreading dust and debris associated with construction.
9. Contain construction waste before transport in tightly-covered containers.
10. Cover transport receptacles or carts. Tape covering.
11. Remove isolation of HVAC system in areas where work was performed at the end of the project.
12. Emergency Preparedness training/posting/ID card.
Risk Assessment for TB exposure: Does the project involve the building’s: a) HVAC Yes No ; b) HEPA filters Yes No____ ;
c) Negative Pressure Room (s) Yes No ? If any checked yes, an N95 mask will be required.
Classification ___________ Contractor’s signature (for Projects only)
Project Planner or Technician Signature__________________________
Supervisor signature _________________________________________ Date_________________
Upgrade Electrical Building 200 Joseph Tumpis
Building 200 Estimated June 2018
578-13-001 x20855
Basement of 200 Estimated June 2019
VHAHINDoyleL Typewritten Text 3/24/18