36C25218Q1052 Attachment F - P01 - Telecom Cabling Addition and Expansion Policy.docx

View the file

Other files

File Type Posted
36C25218Q1052-0003000.docx DOCX document
36C25218Q1052-0002000.docx DOCX document
36C25218Q1052-00001000.docx DOCX document
36C25218Q1052-013.docx DOCX document
36C25218Q1052-010.doc DOC document
36C25218Q1052-009.docx DOCX document
36C25218Q1052-008.docx DOCX document
36C25218Q1052-014.docx DOCX document
36C25218Q1052-011.pdf PDF
36C25218Q1052-012.doc DOC document
36C25218Q1052-016.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Telecommunications cabling Addition/expansion

GENERAL

1.1 RELATED DOCUMENTS

Drawings and General Provisions of the contract, including General and Supplementary Conditions and Division 1 Specification Sections.

1.2 SUMMARY

A. This section includes installation, testing, documentation and training for a fully functional local area network cabling system.

B. Furnish and install Horizontal UTP Copper cabling, patch panels, patch cords, termination units, horizontal cross-connects, information outlets, respective cable termination connections, and other items necessary to "terminate" selected information outlets (IO) as shown on the Drawings.

1.3 SUBMITTALS

A. Submit a complete list of all proposed equipment and materials, including manufacturer’s specifications and product cut sheets.

B. Submit a labeling scheme approved by the owner.

C. Telecommunications Maintenance Manual: Furnish one (1) complete Telecommunications Maintenance Manual containing the following:

Descriptions of network cabling equipment and normal operating procedures.

Riser Diagrams showing complete installed UTP and Fiber cabling.

Proof of Performance Report outlining the operating parameters tested, complete test results, and a summary of industry standards used for each parameter.

Warranty information.

1.4 applicable publications, STANDARDS, CODES, TESTING LABORATORIES, GUIDELINES A. ANSI/EIA/TIA Standard 568B.1, 568B.2, AND 568B.3 B. ANSI/EIA/TIA Standard 569 C. ANSI/EIA/TIA Standard 606 D. ANSI/EIA/TIA Standard 607 E. Technical Service Bulletins TSB-36, TSB-40, TSB 67 F. NFPA 70 National Electrical Code.

G. Provide products specified in this section that are listed and labeled.

The terms "listed" and "labeled": As defined in the "National Electrical Code", Article 10G0.

1.5 GUARANTEES AND WARRANTIES

A. Guarantee system, in writing, against defects in workmanship and associated material not covered by cabling system warranty, for one year after final acceptance. During this time, the entire system shall be kept in proper operating condition at no additional labor or material cost to the Owner.

B. The manufacturer of the major components shall maintain a replacement parts department and provide test equipment when needed. The parts department shall be located in a geographical proximity consistent with rendering service within the stated period of time. An ample stock of individual components and equivalent unit replacement shall be carried for as long a period as demand warrants. This period shall extend beyond the normal life expectancy of the equipment.

1.6 QUALITY ASSURANCE

A. Contractor shall be currently licensed to install low-voltage cabling systems in the state of Wisconsin.

B. Contractor shall meet manufacturer's requirements for the provision and installation of specified equipment.

C. Contractor shall provide proof of certification as a structured cabling system installer for the system provided under this bid.

D. Contractor shall utilize the following test equipment and shall have operators trained for use of such equipment:

Copper Cable Test Equipment:

Fluke / MicroTest (level 3 tester) Agilent WireScope 350 (level 3 tester).

Prior approved equal.

Fiber Optic Cable Test Equipment:

Approved OTDR.

Approved OLS/OPM.

1.7 PROJECT/SITE CONDITIONS

A. Examine areas and conditions under which the system is to be installed, and notify COTR in writing of conditions detrimental to proper completion of the work. Do not proceed with that portion of the work affected until unsatisfactory conditions have been corrected in an acceptable manner.

1.8 MANUFACTURER

A. Subject to compliance with specified requirements, provide specified materials, or prior approved equal to the referenced products included for the design of the Local Area Network Cabling system.

1.9 UPGRADED PRODUCTS

A. Due to the fast-changing technology, products shall be the most current and up-to-date quality and labor-saving versions available for the application, unless otherwise restricted.

B. Provide necessary supplies, mounting hardware and accessories required to install specified materials.

1.10 MANUFACTURER'S CERTIFICATION

A. Manufacturer of cabling products shall be ISO9001 Certified.

1.11 UTP COPPER CABLE LENGTHS, TERMINATIONS, MARKINGS

A. Copper Cable runs shall be compliant with EIA/TIA recommended lengths: Horizontal cables shall not exceed 295 feet. Cable runs shall be continuous with no allowance for splicing.

B. For construction on Milwaukee VAMC Campus: Copper cable Eight-Position Jack Pin/Pair Assignments shall match the VA Hospital’s existing facilities. Coordinate with the owner prior to installation.

PRODUCTS

1.12 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide a certified structured cabling system by: General Cable or approved equal.

B. Data Cable: Part Number 7131688, Cat 6, bright green.

1.13 eQUIPMENT RACK:

A. Rack: Free-standing, 19”Wx84”H, self-supporting, constructed of high-strength aluminum, black in color. 5/8” – 5/8” – ½” alternating hole pattern compatible with EIA 1 1/4” – ½” alternating hole patterns. Includes 50 pilot point #12-24 mounting screws. Anchor to floor and provide connection to electrical ground bus bar, green, #6, 19-strand.

Provide products manufactured by one of the following:

Chatsworth Products (CPI) #46053-703 series Prior approved equal.

B. Wire Management: Furnish and install cable management ducts on side of racks as noted. Vertical ducts shall be 3” or 6” wide, as indicated on drawings, with integrated molded plastic cable guides and a hinged door/cover. Furnish and install horizontal wire management panel for each modular patch panel. Horizontal duct shall be black plastic with removable top cover.

Provide products that mate and match the existing racks.

Provide products manufactured by one of the following:

Vertical Management: Chatsworth products (CPI) #30094-703 series.

Horizontal Management: Chatsworth Products (CPI) #13075-719 series.

Prior approved equal.

1.14 CABLE SUPPORT

A. Supply velcro straps, length and strength as required to properly organize and bundle cables. Vinyl/plastic tie wraps are prohibited throughout.

B. Install cables in conduit and wireway systems unless otherwise directed by the VA COTR and/or VA project manager.

1.15 category 6 CHANNEL A. The Category 6 - 4 pair UTP channel consists of all cable and components with up to four connections that comprise the full 100 meter circuit from the LAN Electronics to the work station device. The channel shall support applications such as 10BaseT, 100BaseT, 155 Mbs ATM, 77 channel broadband video, 1.0 Gbps Ethernet, 1.2 Gbps, and proposed 2.4 Gbps ATM technologies.

B. The channel shall include the patch panels, horizontal cabling, and the station cord, and shall have a positive PSACR across the full frequency range of 1MHz - 250MHz.

C. All components shall be backward compatible with existing Category 3, 4 and 5 networks.

D. The cabling channel with specified manufacturers above shall exceed Category 6 requirements.

1.16 INFORMATION jacks

A. Where data/voice jacks are fished into a hollow wall space without a raceway, Arlington LV-1 or approved equal shall be used. Metal types such as Caddy brand are not allowed

1.17 MODULAR PATCH PANELS

A. Furnish and install Modular Patch Panels. All cables shall be secured to the strain relief bar using vinyl/plastic tie wraps. Provide labeling strip above each jack. Contractor shall be responsible for sizing the modular patch panels according to the following specifications:

Number of Modular Patch Panel Ports shall be 125 percent of the total number of terminated information outlets required for the VRT project.

Patch panels shall be 24 port or 48 port.

1.18 PATCH CORDS

A. Provide Patch Cords, Gigaspeed, 24 AWG, polyfin, twisted, jacketed, with 8-position Modular Plug at each end.

Data Color: Bright Green B. Lengths of patch cords shall comply with EIA/TIA 568A recommended lengths: Patch cords shall not exceed 20 feet. Provide varying lengths to suit data closet installation. Coordinate final length selection with COTR prior to ordering.

1. Data Lengths: Assume 50% 3 ft, 50% 5 ft.

C. Provide 1 patch cord for each activated information outlet.

1.19 FIBER OPTIC CABLE:

A. Fiber optic cable shall be Avaya LazrSPEED ABC-0012D-ZHX or equal. The cable shall have (2) strands of multimode fiber. Provide fiber with the following optical characteristics:

Multi Mode:850nm:Maximum Attenuation3.5 dB/km
1300nm:Maximum Attenuation1.5 dB/km
850 nmMinimum Bandwidth:1500 MHz/km
1300 nmMinimum Bandwidth:500 MHz/km

Supports 10Gb/s Ethernet using 850nm VCSEL to 300m.

Fiber tension rating - 600 lbs.

Fiber minimum bending radius during installation - 20 x diameter.

The fiber cable shall meet the following technical specifications:

Multi-Mode Fiber Dimensions: 62.5 micron core 125 micron cladding 250 micron coating 900 micron buffering Fiber Identification: Individually color-coated PVC buffer.

Buffer Material: Plenum PVC Jacket Material: Plenum PVC (color as selected by owner).

Strength Material: Aramid Yarn Operating Temperature: 0 to + 50 deg. C Storage Temperature: -40 to +70 deg. C EIA Fiber Cable tests:

TESTREFERENCE
ImpactEIA-RS-455, FOTP-25
CompressionEIA-RS-455, FOTP-41
FlexureEIA-RS-455, FOTP-104
Tensile BendingEIA-RS-455, FOTP-33
Temperature BendingEIA-RS-455, FOTP-37
Twist TestingEIA-RS-455, FOTP-85
Flame Test (OFNP)UL 910 (NEC) [CSA OFN-FT4, FT6]

1.20 FIBER TERMINATION UNITS:

Furnish and install Avaya 600BLS front access sliding shelf connector panel equipped with SC couplings and cover plate for all Data racks. Units shall provide top or bottom cable entry, fiber termination, cross connection, interconnection, routing, fiber identification labels, fiber storage and radius organizers.

EXECUTION

1.21 GENERAL

Install equipment and components in accordance with manufacturer's written instructions, in compliance with NEC, and with recognized industry practices. Ensure that all work complies with specifications and serves the intent of the construction documents. Cabling and equipment shall be installed in accordance with good engineering practices as established by the EIA/TIA and the NEC.

1.22 INSTALLATION

A. Cabling - General:

Provide dedicated horizontal cable runs from data closets to all “terminated" information jacks as described above and indicated on the Drawings.

Where data or voice outlets are shown on plans, this Contractor shall provide jack termination, faceplate, and cabling.

Provide Modular Information Outlets in outlet boxes for all "terminated" data information jacks.

Excess cable behind faceplate connections shall be pulled back into ceiling spaces and secured in such a manner as to prevent damage to cabling or connections.

A minimum 10 foot loop of extra horizontal cable shall be secured in the accessible ceiling space.

Tighten connectors and terminals, including screws and bolts, in accordance with equipment manufacturer's published torque tightening values for equipment connectors.

Avoid excessive and sharp bends that may damage cabling. Do not exceed manufacturer's recommended pulling tensions for backbone and horizontal cables.

Allow sufficient slack (10 feet) in cable to prevent premature deterioration of cable system components and to assist in the maintenance and servicing of cable and/or other building systems and components.

Provide Cable Distribution J-Hooks as necessary to route and support cables within the data closet. All cables shall be properly supported.

Provide Velcro straps to bundle and organize cabling for a quality and professional installation. Vinyl/plastic tie wraps are prohibited.

Fittings or connections are allowed only at the input and output of devices. Splicing shall not be accepted in cable runs. Spliced cable runs shall be rejected and replaced with continuous cables, prior to acceptance.

Separation of Wires: Comply with EIA/TIA569 rules for separation of UTP cables from potential EMI sources.

All cabling outside the data closet shall be routed in conduit or wire way, installed by the electrical contractor.

Conduit fill shall not exceed 40%. This applies to both raceways and sleeves. Each conduit end not terminated in a box shall be equipped with a protective insulator or sleeve to cover the conduit end to protect the wire or cable during installation and remaining in the conduit.

B. Sleeving: All cabling penetrating a wall or floor and not in a raceway shall be sleeved. A penetrator sleeve system and method for using same provides an encasement for wires and cables passing through a wall or floor. The system should include appropriate securing devices for tightly retaining the penetrating element in place. This will also create a space between the penetrating element and surrounding structure, which must be fire stopped in order to restore the fire-resistance rating of the parent assembly. The penetrating element shall be one of the following;

1. EMT conduit with bushed ends.

2. Prefabricated fire-rated pathway. Recommend the following or approved equivalent. Follow manufacturer’s conduit fill recommendations.

EZ-PATH Fire Rated Pathway Spec Seal Ready Sleeve C. Fire stopping: Provide fire stopping after cabling installation at all fire wall/floor penetrations. Contact VA project manager to determine acceptable fire stopping materials for use during the installation.

D. Grounding: The general contractor shall be responsible for installing a ground bus adjacent to the rack. Ground all racks and cable runway to this ground bus. The contractor shall provide a #6 copper conductor from each rack/runway to the ground bus. Ground equipment per manufacturers’ instructions and NEC requirements.

E. Labeling, in accordance with VA Standards:

Label patch panel terminations with the identical numbers used at the outlets.

Label both ends of each cabling run within 6 inches of termination points with marker and flag ties, a label machine, or approved equal. Label the room end of the cable with the data closet identification number (closet number and jack number) and label the data closet end of the cable with the room jack number (room number, voice and data jack number).

Whenever possible, cross connect riser pairs shall be run sequentially.

---end---