S02 - Combined Specs - 655-20-204.pdf
PDF 2 MB Posted
- Attached to
- Z1DA--Dental HVAC Upgrade - 655-20-204
- Solicitation number
- 36C25023B0008
About this file
This document outlines specifications for a dental HVAC upgrade project at the Department of Veterans Affairs Medical Center in Saginaw, Michigan. Key requirements include upgrading and replacing HVAC systems and equipment in the dental clinic; complying with applicable codes and regulations for mechanical, plumbing and electrical work; and adhering to strict infection control protocols throughout construction. Contractors must be licensed, have competent supervision staff, and ensure all personnel complete required safety training. The project is to be completed within 90 calendar days of the notice to proceed.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 10 Table of Contents 12-20 00 01 15 List of Drawing Sheets 12-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-20 01 01 10-FSS FSS Fire Safety 12-20 01 01 10-IC IC Infection Control 12-20 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 12-20 01 33 23 Shop Drawings, Product Data, and Samples 12-20 01 35 26 Safety Requirements 02-20
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 12-20
DIVISION 09 – FINISHES
09 51 00 Acoustical Ceilings 12-20
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 12-20 22 05 12 General Motor Requirements for Plumbing Equipment
12-20
22 08 00 Commissioning of Plumbing Systems 12-20 22 13 00 Facility Sanitary and Vent Piping 12-20
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 12-20 23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment 12-20
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment
12-20
23 05 93 Testing, Adjusting, and Balancing for HVAC 12-20 23 07 11 HVAC and Boiler Plant Insulation 12-20 23 08 00 Commissioning of HVAC Systems 12-20 23 09 23 Direct-Digital Control System for HVAC 12-20 23 21 13 Hydronic Piping 12-20 23 21 23 Hydronic Pumps 12-20 23 31 00 HVAC Ducts and Casings 12-20
00 01 10-2
23 36 00 Air Terminal Units 12-20 23 37 00 Air Outlets and Inlets 12-20
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 12-20 26 05 19 Low-Voltage Electrical Power Conductors and Cables 12-20 26 05 33 Raceway and Boxes for Electrical Systems 12-20 26 08 00 Commissioning of Electrical Systems 12-20 26 27 26 Wiring Devices 12-20 26 51 00 Interior Lighting 12-20
LIST OF DRAWING SHEETS
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
1 COVER SHEET WITH LOCATION MAP
1-AD2.2 SECOND FLOOR REFLECTED CEILING PLAN DEMOLITION
1-A2.2S SECOND FLOOR REFLECTED CEILING PLAN
1-M0.0 MECHANICAL LEGEND
1-MD1.2S DEMOLITION HVAC
1-M3.2.3 HVAC SECOND FLOOR
1-MD2.2S DEMOLITION HYDRONIC DENTAL
1-M2.2S HYDRONIC DENTAL
1-M4.0 MECHANICAL DETAILS
1-M4.1 MECHANICAL DETAILS
1-M4.2 MECHANICAL DETAILS
1-M4.3 MECHANICAL DETAILS
1-M4.4 MECHANICAL DETAILS
1-ME1.0 MECHANICAL & ELECTRICAL SCHEDULES
1-ME1.1 MECHANICAL & ELECTRICAL SCHEDULES
1-P0.0 PLUMBING LEGEND
1-PD1.2S DEMOLITION DRAIN & VENT SECOND FLOOR PLAN SOUTH
1-P1.2S DRAIN & VENT SECOND FLOOR PLAN SOUTH
1-E0.0 ELECTRICAL LEGEND
1-ED3.2S DEMOLITION ELECTRICAL LIGHTING SECOND FLOOR PLAN – SOUTH
1-E3.2S ELECTRICAL LIGHTING
LIST OF DRAWING SHEETS
00 01 15 - 2
- - - E N D - - -
THIS PAGE LEFT BLANK
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1. SAFETY REQUIREMENTS
1.2. GENERAL INTENTION
1.3. STATEMENT OF BID ITEM(S)
1.4. SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5. ADMINISTRATIVE WORKING HOURS
1.6. CONTRACTOR EMPLOYEE BEHAVIOR ON VA MEDICAL CENTER SITE
1.7. IDENTIFICATION OF CONTRACTOR'S AND MATERIAL SUPPLIERS MECHANIZED
EQUIPMENT
1.8. MEDICAL CENTER STAFF, PATIENTS, VISITOR SAFETY
1.9. DRAWINGS AND SPECIFICATIONS
1.10. ENTERTAINMENT SYSTEMS
1.11 GREEN ENVIRONMENTAL MANAGEMENT SYSTEM (GEMS)
1.12. CONSTRUCTION SECURITY REQUIREMENTS
1.13. FIRE SAFETY
1.14. OPERATIONS AND STORAGE AREAS
1.15. USE OF CELLULAR PHONES
1.16. ALTERATIONS
1.17. GOVERNMENT EQUIPMENT, TOOLS and MATERIALS
1.18. RECEIPT OF CONTRACTOR'S MATERIALS
1.19. INFECTION PREVENTION MEASURES
1.20. DISPOSAL AND RETENTION
1.21. PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
01 00 00 -2
1.22. RESTORATION
1.23. AS-BUILT DRAWINGS
1.24. WARRANTY MANAGEMENT
1.25. USE OF ROADWAYS
1.26. TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.27. TEMPORARY USE OF EXISTING ELEVATORS
1.28. AVAILABILITY AND USE OF UTILITY SERVICES
1.29. TESTS
1.30. INSTRUCTIONS
1.31. PHOTOGRAPHIC DOCUMENTATION
1.32. GOVERNING REGULATIONS AND AUTHORITIES
1.33. WEB-BASED CONSTRUCTION DOCUMENT MANAGEMENT SERVICE
01 00 00 -3
SECTION 01 00 00
1.1. SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2. GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish all labor, materials, equipment, management, supervision, tools, and all other necessary resources to construct the project as required by drawings and specifications. The contractor is responsible to perform a site survey and investigation to satisfy themselves as to the extent of the work. The place of work is located at Aleda E.
Lutz VA Medical Center, Saginaw, Michigan. Performance period is 90 calendar days.
B. Visits to the site by offerors shall be as specified in solicitation provision 52.236-27 Site Visit (Construction).
C. All references to Resident Engineer (RE), Senior Resident Engineer (SRE), Engineer, COTR, or Project Manager shall all be referred to as Contracting Officers Representative (COR).
D. Prior to commencing work, general contractor shall provide proof that an OSHA certified “competent person” (CP) (29 CFR 1926.20(b)
(2) will maintain a presence at the work site whenever the general or subcontractors are present.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA
Police, be identified by project and employer, and restricted from unauthorized access.
F. All testing and sampling during the construction period is the sole responsibility of the contractor; prior to placement and installation of work subject to testing and or sampling, a laboratory shall be retained by the Contractor. The Contractor shall notify the COR in sufficient time to be present at the site in time
01 00 00 -4 for field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
G. Training:
1. All on-site workers of the prime and sub-contractors shall have completed and received a certificate of completion of the 10 hour OSHA certified Construction Safety course or other equivalent competency training. The Construction Superintendent shall have completed and received certification of completing the 30 hour OSHA Construction Safety course.
2. Submit OSHA certifications for all on-site workers to the COR prior to any worker beginning on-site work.
3. All tradesmen shall be licensed in the line of work they are performing. The General Contractor shall provide proof that all tradesmen are licensed in their field of work. Journeyman to apprentice ratio is minimum 1:1.
1.3. STATEMENT OF BID ITEM(S)
A. The Statement of Bid Item(s) is located within the solicitation Information and Instructions to Bidder section.
B. ALL PRICING IS TO BE ENTERED IN BLOCK 17 OF THE SF1442 SOLICITATION
OFFER PAGE (BLOCK 17) OR THE BID SCHEDULE IF SO INCLUDED WITH THE
SOLICITATION.
1.4. SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Contractor may make the number of sets he has need of from the electronic set furnished to him during the bidding process. The contractor shall only reproduce entire sets of the contract documents. Partial sets are not allowed.
B. Refer to drawing list table in specification section 00 01 15.
1.5. ADMINISTRATIVE WORKING HOURS
A. Administrative working hours for the Medical Center are normally between the hours of 8:00 A.M. to 4:30 P.M. excluding Saturday and
Sunday. This project involves work at different shift hours (24 hour construction) as required in drawings and specifications. If the
Contractor desires to work during periods other than above, which he may, the Contractor shall make his/her request to the VA Contracting officer three (3) days in advance of his/her intention to work during other periods and await approval from contracting officer.
01 00 00 -5
B. No work will be scheduled on the following federal holidays or any other day specifically declared a federal holiday by the President of the United States.
New Year’s Day Birthday of Martin Luther King, Jr.
Washington’s Birthday Memorial Day Independence Day
Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
1.6. CONTRACTOR EMPLOYEE BEHAVIOR ON VA MEDICAL CENTER SITE
A. Objectionable Employees: The VA Contracting Officer, in writing, may require the Contractor to remove from the work site, area, or
Medical Center employees deemed objectionable regarding dress, language and/or behavior. VA Police will investigate any alleged criminal behavior of any contractor employee that occurs on VA property.
1.7. IDENTIFICATION OF CONTRACTOR'S AND MATERIAL SUPPLIERS MECHANIZED
EQUIPMENT
A. All Contractor's machinery, motor vehicles, and mechanized equipment shall have acceptable identification showing the owner's name and identifying number. This identification shall be posted in a conspicuous location on each piece of equipment as may be required by the Contracting Officer. The Contractor shall submit a listing of his vehicles intended for use on this project by listing type of vehicle, color, and license number.
1.8. MEDICAL CENTER STAFF, PATIENTS, VISITOR SAFETY
A. Contractor and/or Sub-Contractors shall not expose VA workers, patients, and visitors to unsafe or unhealthy conditions during
Construction operations. Contractor should be reminded that adherence to OSHA regulations may not be sufficient in some situations, and more stringent regulations (Veterans Affairs, Veterans Health Administration, local Veterans Affairs Medical
Center) may apply. Extra precautions should always be observed to insure patient, visitor, and employee safety when working in a medical center/hospital environment. Make sure to secure all tools and follow all safety and infection control requirements.
1.9. DRAWINGS AND SPECIFICATIONS
01 00 00 -6
A. The drawings show the general arrangement, general design, and extent of the work for the project and are diagrammatic. Exact location of piping, ductwork and equipment, not located by dimensions on drawings, shall be determined in the field considering interference’s and appearance.
B. In general, the horizontal pipe and ductwork indicated on drawings is intended to be installed above the ceiling unless otherwise noted.
C. The drawings are not intended to be scaled for rough-in measurements.
D. The drawings are not to be reproduced or marked-up, to serve or submitted as “shop drawings”.
E. The Contractor shall take Field measurements necessary for securing materials and fitting the installation to the building construction and arrangement. The Contractor shall be responsible for the correct fit of the work installed.
1.10. ENTERTAINMENT SYSTEMS
A. Contractor or subcontractor employees shall not be allowed to bring into the job site AM/FM radios, cassette player, compact disc player, mp3 player, any sound/audio producing equipment, nor operate aforementioned equipment from vehicles on VA Medical Center property.
1.11 GREEN ENVIRONMENTAL MANAGEMENT SYSTEM (GEMS)
A. The following is the Green Environmental Management System Mission Statement for the Aleda E. Lutz VA Medical Center which is shared with all contractors working on our medical center site and it is expected to be adhered to too the greatest extent possible by the contractors.
B. The mission of the VA Medical Center, Saginaw, Michigan is to deliver quality health care to our nation’s veterans. In order to accomplish this mission, the Medical Center recognizes that it must operate so as to protect both the environment and the health and safety of patients, employees and visitors. In order to accomplish this, the VA Medical Center is committed to the following actions:
01 00 00 -7
Operating a Green Environmental Management System (GEMS) that meets requirements of Presidential Executive Order 13148 and the guidance provided by Veterans Health Administration.
C. Being a good steward of the environment by complying with federal, state and local environmental laws and other requirements, preventing pollution, minimizing waste, conserving cultural and natural resources and continually improving environmental programs.
While working on station it is the contractor’s responsibility to follow all of the same environmental laws and requirements.
D. It is the contractor’s responsibility to recycle all products to the maximum extent possible. The contractor shall record the amount of material recycled in lbs and the amount of material trashed in lbs on the waste tracking sheet provided by the VA COR. With each application for progress payment, submit a summary of construction and demolition debris diversion and disposal including beginning and ending dates of period covered to the VA COR.
E. The contractor shall purchase Recycled content products before purchasing virgin material (a list of these products can be found at www.epa.gov/cpg).
F. The following list of standards/certifications shall be utilized when purchasing any equipment or material and shall be purchased instead of any equipment or material of the like without the certification:
1. Energy Star / Energy Efficient Products
2. Water Efficient Projects/ Water Sense
3. Bio-based / Bio-preferred Products
4. SNAP / Non-ozone depleting products
5. EPA Priority Chemicals
6. Environmentally Preferable Products (EPP)
7. Electronic Product Environmental Assessment Tool (EPEAT)
G. The official environmental policy document is MEDICAL CENTER
MEMORANDUM NO.00-08 and any other questions regarding the GEMS
Program can be obtained by contacting FMS at (989)497-2500.
1.12. CONSTRUCTION SECURITY REQUIREMENTS
A. Security:
http://www.epa.gov/cpg
01 00 00 -8
1. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They shall also be subject to inspection of their personal effects when entering or leaving the project site.
2. No photography of VA premises is allowed without permission of the COR.
3. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
4. For working outside the “regular hours” as defined in the contract, the contractor shall give 5 working days prior notice to the COR so that security and any necessary escort arrangements can be provided for the workers. This notice is separate from any notices required for utility shutdown described later in this section.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for any locked storage area, office or storage trailer, and any other locks installed by permission of the COR at the project site.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
1. The General Contractor is responsible for safekeeping of all drawings, project manuals and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. Should any documents, drawings, specifications, photographs, or other project documents are marked “Law Enforcement Sensitive” or “Sensitive Unclassified”, secure such information in separate containers and limit the access to only those who will need it for the project. Any such marked security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer. All shall be returned to the Contracting Officer upon project completion.
i. Notify the Contracting Officer immediately when there is a loss or compromise of “sensitive information”.
01 00 00 -9
ii. AT THE PRE-CONSTRUCTION CONFERENCE ALL PROCEDURES
INVOLVING THE STORAGE, ENCRYPTION, SECURITY, VA
STANDARDS, OF SENSITIVE DOCUMENTS AS WELL AS THE
SAFEKEEPING OF ALL CONSTRUCTION DOCUMENTS NOT CLASSIFIED
AS SENSITIVE, WILL BE DISCUSSED IN DETAIL AND
APPROPRIATE DOCUMENTATION PROVIDED FOR CONTRACTOR’S USE
AND COMPLIANCE.
1.13. FIRE SAFETY
A. Fire Safety Plan (Accident Prevention Plan): Establish and maintain a fire protection program in accordance with 01 35 26. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to VA COR and Facility Safety Manager for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES.
B. For any hot work or activity that will affect fire alarm / sprinkler system, contractor shall fill out the attached permit in Section 01
01 10 Fire Safety and obtain necessary approval by the VA before starting work.
1.14. OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature
Working space and space available for storing materials shall be as shown on the drawings or as determined by the COR.
B. Workmen are subject to the rules of the Medical Center applicable to their conduct.
C. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
D. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building
01 00 00 -10 structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and
Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
E. Contractor shall perform all work in or adjacent to VA occupied areas in such a manner to ensure:
1. Protection of patients and personnel in occupied areas from the hazards and dust associated with a construction environment.
F. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing (dates) on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such phasing (dates) to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center
1. All corridors to stay open during hours of 6AM-6PM.
G. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and
01 00 00 -11 equipment. Coordinate alteration work in areas occupied by
Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
H. When an area is turned over to Contractor, Contractor shall accept entire responsibility therefore.
1. Contractor shall maintain a minimum temperature of 13 degrees C (55 degrees F) at all times, except as otherwise specified.
2. In areas affected where owner still occupies during construction, the contractor shall maintain a minimum temperature of 70 degrees F at all times.
3. Contractor shall maintain in operating condition existing fire protection and fire alarm equipment. In connection with fire alarm equipment.
I. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers, electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.
Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the COR’s prior knowledge and written approval of the Contracting Officer. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 calendar days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
01 00 00 -12
4. Major interruptions of any system must be requested, in writing, at least 7 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
J. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions;
so that they are completely behind the finished surfaces. Remove all unused hangers and supports.
K. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks, and entrances must be approved by the COR.
L. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article 1.12, USE
OF ROADWAYS.
M. In order to minimize the exposure to veterans, visitors, VA employees, and workmen directly on the construction site it shall be required that all vehicles and construction equipment left running and unused or unattended shall not be allowed to sit idling more than three minutes otherwise they shall be turned off.”
N. Contractor Parking: Parking shall be allowed on the project site on the north parking lot unless designated or approved otherwise by the
Saginaw VAMC COR. Saginaw VAMC COR reserves the right to limit the number of vehicles allowed on the project site.
01 00 00 -13
1.15. USE OF CELLULAR PHONES
A. Cellular telephones are permitted in the Building 1-HOSPITAL except [3rd floor (Surgery area), 2nd floor (Clinical Laboratory) and 1st floor (Urgent Care Area)], and Building 22-Community Living Center except 2nd floor Acute Care Telemetry Unit. Cellular phones in these areas must be completely turned off, not on stand-by.
1.16. ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer.
This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of
COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Prior to the furnishing of any new items and any related work thereof, a mutual agreement between the Contractor and
Contracting Officer on the total cost shall first be negotiated and a contract modification executed incorporating the changed work.
Contractor is cautioned only the Contracting Officer has the authority to make changes to the contract related to this section.
Any changed work performed or new items provided prior to
Contracting Officer authorization shall result in no adjustment to the contract price.
01 00 00 -14
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.17. GOVERNMENT EQUIPMENT, TOOLS AND MATERIALS.
A. Contractors shall not use Government materials, equipment, tools, or supplies.
1.18. RECEIPT OF CONTRACTOR'S MATERIALS
A. Contractors shall not have materials, equipment, tools, or supplies shipped to them care of the VA Medical Center as they will be rejected and returned.
1.19. INFECTION PREVENTION MEASURES
A. Implement the requirements of VAMC’s Infection Control Risk Assessment (ICRA) team. ICRA Group may monitor dust in the vicinity of the construction work and require the Contractor to take corrective action immediately if the safe levels are exceeded.
B. Establish and maintain a dust control program as part of the contractor’s infection preventive measures in accordance with the
01 00 00 -15 guidelines provided by ICRA Group, in this section and specification
01 01 10 Infection Control. Prior to start of work, prepare a plan detailing project-specific dust protection measures, including periodic status reports, and submit to VA COR and Facility ICRA team for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES.
1. All personnel involved in the construction or renovation activity shall be educated and trained in infection prevention measures established by the medical center.
1.20. DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
i. Copies of the following listed CFR titles may be obtained from the Government Printing Office:
40 CFR 261 Identification and Listing of Hazardous Waste 40 CFR 262 Standards Applicable to Generators of Hazardous Waste 40 CFR 263 Standards Applicable to Transporters of Hazardous Waste 40 CFR 761 PCB Manufacturing, Processing, Distribution in Commerce, and use Prohibitions 49 CFR 172 Hazardous Material tables and Hazardous Material Communications Regulations 49 CFR 173 Shippers General Requirements for Shipments and Packaging 49 CRR 173 Subpart A General
01 00 00 -16
49 CFR 173 Subpart B Preparation of Hazardous Material for Transportation 49 CFR 173 Subpart J Other Regulated Material; Definitions and Preparation TSCA Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7
1.21. PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,
AND IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract.
The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.22. RESTORATION
01 00 00 -17
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
1.23. AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in higher level detail as compared to the contract drawings. To insure compliance, as-built drawings shall be made available for the VA COR's review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings to the VA COR within 15 calendar days after each completed phase.
D. After the acceptance of the project by the VA COR, contractor shall provide two sets (hard copy) of “as-built” drawings. Contractor
01 00 00 -18 shall also provide to VA COR a CD containing electronic copies of all “as-built” drawings. VA COR shall review the “as-built” drawings and electronic CADD files to verify all work is in accordance with the contract documents. Scanned drawings converted to AutoCAD dwg files are unacceptable. All files shall be vector format.
E. The “as-built” drawings shall indicate the following and their accurate location: Walls, Doors, Windows, Ceilings, Equipment, Ductwork, Piping, Fixtures, Sensors, Piping diagrams, Conduits, Receptacles, Circuit Identification, Ceiling Mounted Items, Data, Switches, Lighting, Panels, Utilities, Roads, Buildings, Structures, Structural Members, and System Accessories as installed / modified under this project.
F. Paragraphs A-E shall also apply to all shop drawings.
1.24. WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of
Construction at least 30 days before the planned pre-warranty conference, submit one set (electronic and printed copy) of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
01 00 00 -19
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
01 00 00 -20
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for
Contractor response, and other details deemed necessary by the
Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
Following oral or written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the
Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
01 00 00 -21
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
Code 1-Life Safety Systems
a. Fire suppression systems.
b. Fire alarm system(s).
Code 1-Air Conditioning Systems
a. Air conditioning leak in part of the building, if causing damage.
b. Air conditioning system not cooling properly.
Code 1 Doors
a. Overhead doors not operational, causing a security, fire or safety problem.
b. Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
Code 3-Doors
a. Overhead doors not operational.
b. Interior/exterior personnel doors or hardware not functioning properly.
Code 1-Electrical
a. Power failure (entire area or any building operational after 1600 hours).
b. Security lights.
c. Smoke detectors.
Code 2-Electrical
a. Power failure (no power to a room or part of building).
b. Receptacles and lights not operational (in a room or part of building).
Code 3-Electrical
01 00 00 -22
a. Exterior lights not operational.
Code 1-Gas
a. Leaks and pipeline breaks.
Code 1-Heat
a. Power failure affecting heat.
Code 1-Plumbing
a. Hot water heater failure.
b. Leaking water supply pipes.
Code 2-Plumbing
a. Flush valves not operating properly
b. Fixture drain, supply line or any water pipe leaking.
c. Toilet leaking at base.
Code 3- Plumbing
a. Leaky faucets.
Code 3-Interior
a. Floors damaged.
b. Paint chipping or peeling.
c. Casework damaged.
Code 1-Roof Leaks
a. Damage to property is occurring.
Code 2-Water (Exterior)
a. No water to facility.
Code 2-Water (Hot)
a. No hot water in portion of building listed.
Code 3
a. All work not listed above.
01 00 00 -23
E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting
Officer Representative; approximate size is 2 inches wide by 5 inches long. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Type of Product / Material
Model Number
Serial Number
Contract Number
Warranty Period From / To
Inspector’s Signature
Construction Contractor
Address
Telephone Number
Warranty Contact
Address
Telephone Number
Warranty Response Time Priority Code
1.25. USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the Saginaw VAMC COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the Contractor at
01 00 00 -24
Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well constructed bridges.
1.26. TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to compliance with the following provisions:
1. Permission to use each unit or system must be given by VA COR.
If the equipment is not installed and maintained in accordance with the following provisions, the VA COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary
01 00 00 -25 facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.27. TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing Service Elevator, in Building No.1, for handling building materials and Contractor's personnel will be permitted subject to following provisions: Contractor makes all arrangements with the Saginaw VAMC COR for use of elevator. The Saginaw VAMC COR will ascertain that elevator is in proper condition. Contractor shall clean the elevator at the twice per shift or as needed to remove debris buildup.
B. Contractor shall cover and provide maximum protection of following elevator components:
1. Entrance jambs, heads soffits and threshold plates.
2. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
3. Finish flooring.
1.28. AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting
01 00 00 -26
Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the
Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Heat: Contractor shall furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials.
1. Obtain heat by connecting to Medical Center heating distribution system.
D. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
E. Water (for Construction…
This is the start of the file's text. The full file is on GovTribe.