This solicitation is for a minor construction project to construct a replacement community living center at a Veterans Affairs medical center. The contractor will furnish all labor, materials, equipment, and expertise to complete the project in accordance with contract documents, specifications, and drawings. The project scope involves general construction, alterations, site utilities, parking, and infrastructure for a new long-term rehabilitation facility containing 20 bedrooms. The period of performance is 480 calendar days from notice to proceed. The solicitation is designated for a service-disabled veteran-owned small business and is being procured using lowest price technically acceptable procedures. The award amount is estimated between $10-20 million.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
1 72
36C24921R0059
X
03-12-2021
596-21-3-1001-0003
596-333
Department of Veterans Affairs Network Contracting Office 9 (90C) c/o: Roxie Ann Keese 1639 Medical Center Parkway, Suite 400 Murfreesboro TN 37129
Department of Veterans Affairs Network Contracting Office 9 (90C) c/o: Roxie Ann Keese 1639 Medical Center Parkway, Suite 400 Murfreesboro TN 37129
Roxie Ann Keese 615.873.6341
Minor Project #596-333, Construct Replacement Community Living Center (CLC)-Long Term Rehab Lexington VA Medical Center Frank R. Sousley 2250 Leestown Road Lexington, KY 40511
NAICS Code is 236220 is applicable to this project. The product service code (PSC) is Y1DA. The small business size standard is $39.5M. This is a 100% set-aside for a Service-Disabled Veteran Owned Small Business (SDVOSB) concern under the authority of 38 U.S.C. 8127 (d). To be eligible for award the contractor must be listed and have an active viewing in the Vendor Information Pages at https://vip.vetbiz.va.gov/. All offerors must submit proof of current (as of time of Offer) SAM and VETBIZ registries with their offer. Any Offeror/Bidder that fails to submit proof of current registries will be rendered technically unacceptable/non-responsive outright and will not be considered for award.
Prior to award, all Offerors/Bidders will be required to submit evidence of enrollment in the VETS4212, and an Experience Modification Rating (EMR) of less than one (1).
Questions/Request for Information (RFI) must be submitted in writing to the Contracting Officer. The solicitation number, project number, project name shall be in the subject line of the email. Request for Information (RFI) must be chronologically ordered and references a specific statement, section, drawing relative to the solicitation document.
The last day to submit questions/RFI's relative to this solicitation is: Monday March 29, 2021 at 12:00pmET
This project is being procured in accordance with Federal Acquisition Regulation (FAR) Part 15, as a Lowest Price Technically Acceptable" source selection process, and in accordance with FAR Part 36.2 "Special Aspects of Contracting For Construction". Additional information may be found under the section heading titled "Instructions, Conditions And Other Statements to Bidders/Offerors".
The magnitude of the estimated range of construction is between $10,000,000.00 and $20,000,000.00.
An organized site visit is planned. Additional information on the site visit may be found on page 17 of this solicitation.
10 480
X X 52.211-10
X 10 Calendar Days
1 Compact Disc 1200 PM ET
04-12-2021
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Base Offer: $___________________________________________
596-36X0111-1001-854200-3220
90C
Network Contracting Office 9 Department of Veterans Affairs c/o: Roxie Ann Keese, CO 1639 Medical Center Parkway Suite 400 Murfreesboro TN 37129
90C FSC e-Invoicing Payment http://www.fsc.va.gov/fsc/einvoice.asp Invoice Setup Information 1-877-489-6135 Invoice must be submitted electronically
Setup 1-877-489-6135
Roxie Ann Keese, FAC-C Level III, FE-C
VA-VHA-2020-11BF2E0E
Minor Project 596-333 Construct Replacement Community Living Center (CLC)-Long Term Rehab Solicitation No. 36C24921R0059
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.215-5 FACSIMILE PROPOSALS (OCT 1997)
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE
OF THE WORK (MAY 2014)
2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE
EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
2.5 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS UNDER TRADE AGREEMENTS (MAY 2014)
2.6 52.228-1 BID GUARANTEE (SEP 1996)
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
2.10 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND
VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) ..18
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS
AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (OCT 2020)
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—
CERTIFICATION (JUL 2020)
GENERAL CONDITIONS
4.1 52.203-14 DISPLAY OF HOTLINE POSTER(S) (JUN 2020)
4.2 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND
CERTIFICATIONS (DEC 2014)
4.3 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE,
AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER
COVERED ENTITIES (JUL 2018)
4.4 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING
RESPONSIBILITY MATTERS (OCT 2018)
4.5 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984) ALTERNATE I (APR 1984)
4.6 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000)
4.7 52.211-13 TIME EXTENSIONS (SEPT 2000)
4.8 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE
AGREEMENTS (OCT 2019) ALTERNATE I (MAY 2014)
4.9 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014)
AND ALTERNATE II (JUN 2009)
4.10 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(NOV 2020)
4.11 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)
4.12 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL
LABOR RELATIONS ACT (DEC 2010)
4.13 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER
SERVICE AND CONSTRUCTION CONTRACTS (SEP 2013)
4.14 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT
FOR EPA-DESIGNATED ITEMS (MAY 2008)
4.15 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE
AGREEMENTS (OCT 2019)
4.16 52.236-4 PHYSICAL DATA (APR 1984)
4.17 SUPPLEMENTAL INSURANCE REQUIREMENTS
4.18 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
4.19 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN
2020)
4.20 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)
4.21 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND
COMPLIANCE (JUL 2018)
4.22 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV
2018)
4.23 VAAR 852.219-75 SUBCONTRACTING COMMITMENTS MONITORING AND
COMPLIANCE (JUL 2018)
4.24 VAAR 852.219-76 SUBCONTRACTING PLANS MONITORING AND
COMPLIANCE (JUL 2018)
4.25 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(APR 2019)
4.26 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)
4.27 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)
4.28 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT
(SEP 2019)
4.29 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN
2008)
4.30 MANDATORY WRITTEN DISCLOSURES
4.31 IT CONTRACT SECURITY
ATTACHMENTS
19009 CLC Phase 2 - 100 CD - Specifications-2-12-2021.
Rev Drawings pp 1-28 (19009 CLC Phase 2).
Rev Drawings pp 29-60 (19009 CLC Phase 2).
Rev Drawings pp 61-90 (19009 CLC Phase 2).
Rev Drawings pp 91-120 (19009 CLC Phase 2).
Rev Drawings pp 121-128 (19009 CLC Phase 2).
P07-General Wage Decision KY20210090 01.01.2021.
S02-Price Schedule (Minor Project 596-333) FY2021.
S15-PPQ-Template (Minor Project 596-333) Construct Replacement CLC-Long Term Rehab.
596-333 Geotechnical Report.
Solicitation No. 36C24921R0059
Statement of Work Project 596-333 Construct Replacement CLC – Long Term Rehab
Lexington VA Health Care System, Leestown Road
Project Description:
This project will construct one Long Term Rehab Facility. The project will also include site utilities, parking, and infrastructure. The new units/houses will be designed using the latest “Small Home” patient centered care concepts and contain 20 bedrooms.
General Scope:
The construction firm is to provide construction services for Project No. 596-333 Construct Replacement CLC – Long Term Rehab. Construction disciplines anticipated include general construction, plumbing, mechanical, electrical, exterior improvements, utility systems, and certain other items.
Furnish all labor, tools, materials, and expertise to complete Project 596-333 in strict accordance with the contract documents, specifications, and drawings. Some work will be required after standard administrative hours; work may be limited to periods shorter than a standard shift for specific items in the project. This is a medical environment and the contractor shall take into consideration infection control, demolition noise, environmental dust control, and specialized facility requirements as a medical environment requires. Using the available space, it will be necessary to phase as indicated by the contract documents. The hospital shall remain in continuous operation at all times and any utility interruptions shall be planned in advance and executed as required, so as to minimize staff, patient, traffic disruptions.
The Contracting Officer (CO) is the only person authorized to bind the Federal Government, and then only to the extent of the authority invested by appointment. No other office or individual has the authority to act in any manner in behalf of the Federal Government on the performance of the contract. Any changes or questions regarding this contract will be referred to the Contracting Officer by the COR, who in turn, will initiate necessary action. Contractor employees shall not be considered Government employees for any purpose under the resulting contract.
Statement of Bid Items:
A. Bid Item No. 1: Base Bid All Work: The contractor shall provide all resources necessary to accomplish and furnish all labor, material, equipment, transportation, and expert supervision necessary for project 596-333, Construct Replacement CLC – Long Term Rehab at the Lexington VA Health Care System located at 2250 Leestown Road, Lexington KY 40511 in accordance to the statement of work, project specifications, and drawings. Work includes general construction, alterations, roads, walks, grading, drainage along with certain other items.
The period of performance for the work in the base offer is 480 calendar days from receipt of notice to proceed.
To address US Fish and Wildlife requirements on endangered bats nesting in the bark of trees, the removal of trees shall be restricted to the months of October through March unless a bat survey is conducted and the trees are certified free of nesting bats prior to the tree removal.
The contractor shall provide a site map showing the location of new emission sources, summary of emission factors (SO2, N2O, NO3, CO2, CO, CH4, VOC and lead) for each emissions emitting unit, safety data sheets for each fuel source, obtain a U.S. EPA Certificate of Conformity for each generator from the manufacturer, obtain in conjunction with the VA a KY State Fire Marshall plan & specification approval letter. It is also the expectation that the contractor will assist the Lexington VA Health Care System by providing the necessary information to complete the required forms to request a permit revision. At a minimum the following forms shall be submitted will include the following:
DEP7007A – Combustion Engine, DEP7007J – Volatile Liquid Storage and DEP7007N – Emissions and Stacks.
END STATEMENT OF WORK
Solicitation No. 36C24921R0059
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO
BIDDERS/OFFERORS
This section describes the evaluation process, proposal preparation, the significant factors and sub-factors and criteria to be used in the evaluation process. This section is titled “Instructions, Conditions, and Other Statements to Bidder/Offeror” in the solicitation document. The subject procurement action shall be a Lowest Price Technically Acceptable source selection process in accordance with Federal Acquisition Regulation (FAR) Part 15.101-2. Award will be made to the offeror whose proposal conforms to the solicitation and is determined to be “Technically Acceptable” for all Non-Cost/Non-Price Evaluation Factors. Proposals will be evaluated for acceptability, but not ranked using the non-price factors/sub-factors. In order to be considered for award, an offeror must have an “acceptable” rating in every non-price factor/sub-factor under consideration.
The Government intends to award a single contract to a qualified Service Disabled Veteran Owned Small Business (SDVOSB) determined responsible in accordance with the Federal Acquisition Regulation (FAR), whose proposal conforms to all the requirements in this solicitation, and is further determined to meet or exceed the standards of acceptability at the lowest offered price. The Government intends to evaluate proposals and award a contract without discussions with Offerors. Therefore, the Offeror’s initial proposal should contain the Offeror’s best terms from both a technical and cost standpoint.
The evaluation of offers submitted in response to this Request for Proposal (RFP) solicitation will be conducted utilizing the Lowest Price Technically Acceptable (LPTA) selection process.
Utilization of this source selection process may result in not all offers being evaluated. The Contracting Officer upon receipt of offers, will determine eligibility and compliance to the solicitation requirements. The Vendor Information Pages (vetbiz registry) will be checked to ensure that any offeror submitting a proposal to perform the work is both listed and verified. All proposals received will also be checked for an active registration in the System for Award Management (SAM). Thereafter, the Contracting Officer will review all proposals to ensure that the minimum proposal submission requirements have been met. Once these requirements have been satisfied, the Contracting Officer will select and submit for review to the Technical Evaluation Board (TEB) the technical proposal of the lowest priced offeror for consideration.
Initially, the TEB will not receive any pricing information, only the technical portion of the Offeror’s proposal. The Offeror’s proposal will be rated against each evaluation factor as set forth in this solicitation.
If the selected Offeror’s proposal is determined to be acceptable based on the standards of acceptability, and that Offeror’s price is the lowest of all offers submitted, then no further evaluation of offers shall occur and the Contracting Officer will document these findings, and proceed with the responsibility determination of the offeror. Pricing information will only be provided to the TEB upon notification to the Contracting Officer that the technical proposal as submitted meets or exceeds the acceptability standard necessary to fulfill the objective of the requirement.
Solicitation No. 36C24921R0059
Should the initial Offeror’s proposal be determined to be unacceptable according to the standards of acceptability, then the TEB will be required to provide to the Contracting Officer a summary evaluation sheet that documents how the Offeror’s proposal fails to meet the standards of acceptability, and request to the Contracting Officer that another selection be made for consideration of award. This process shall continue until such time that an award is made.
Offerors shall respond in writing to the evaluation factors listed below, in the same order as they appear in this solicitation document. Failure to provide all information will adversely affect the evaluation of an offer. The information contained in the technical proposal should be complete, concise, and address each factor. If information is applicable to more than one evaluation factor, it must be repeated for each factor, unless stated otherwise.
Technical and Price sections of an Offeror’s proposal will be evaluated independently. Offeror shall separately bind each section. All pages containing text shall be consecutively numbered, type-written on 8-1/2x11 inch paper with margins of at least once inch and created using a Times New Roman 12-point font. The submitted package should contain two sections, separately bind:
a.) Technical Proposal b.) Price Proposal. The Offeror’s Technical proposal shall be no more than 50 pages total, which is not inclusive of the solicitation and any amendments issued thereof.
The Offeror’s Price Proposal shall be no more than 25 pages inclusive of the bid bonds required.
The Offeror is hereby advised that the “S02-Price Schedule” attached worksheet shall be considered as one page, regardless of the overall total. Each section must therefore be labeled with the following:
1. Construction Company Name
2. Physical Address of the Company
3. Telephone Number
4. Email address
5. VA Project Number (Project 596-333)
6. VA Project Name (Construct Replacement CLC-Long Term Rehab)
7. Solicitation number (36C24921R0059)
The Technical Evaluation Board (TEB) shall evaluate the Offeror’s proposal against all non-price factors/sub-factors to determine whether the proposal is acceptable or unacceptable, using the “ACCEPTABLE” or “UNACCEPTABLE” ratings based upon the standard of acceptability that follows each factor/sub-factor below. In order to obtain a “ACCEPTABLE” rating an offeror must meet the standard of acceptability that is listed for each factor/sub-factor.
The evaluation process and criteria stated in this section will be strictly adhered to. Evaluators will make no assumptions regarding an Offeror’s proposal. Therefore, an Offeror must demonstrate understanding by the thoroughness, soundness, comprehensiveness and price reasonableness of technical approach. There will be no public opening of offers.
The following evaluation factors and sub-factors will apply to this procurement:
Project #596-333, Construct Continuous Living Center (CLC)-Long Term Rehab
Solicitation No. 36C24921R0059
FACTOR 1 –Construction Management
The offeror shall provide a narrative that describes the Offeror’s overall organization, organizational chart, as well as number of personnel and the duties of proposed technical staff to determine if offeror has the ability to manage multi-discipline projects without significant difficulty. The proposal narrative must adequately address functions, responsibilities and authorities for performing such duties as overall project management, site superintendence, quality control, safety, administration and in-house trade capabilities.
Sub-Factor 1a – Relevant Experience: The Prime Contractor shall provide demonstrated experience in new construction or the addition of a hospital/medical center and/or health care facility for two (2) completed projects within the past five (5) years with a contract value equal to or greater than $5,000,000.00. The subject project must have involved multiple trades so as to demonstrate the management and coordination of trades by the Prime Contractor.
Standard for Acceptability: Relevant experience indicates that the Offeror/Bidder demonstrates the management of multi-disciplinary projects, successfully coordinating multiple trades without significant difficulty.
Sub-Factor 1b - Key Personnel: Provide the names of the Prime Contractor’s Project Manager and on-Site Superintendent, including name with title, years with prime contractor, and total work experience as it relates to the new construction or the addition of a hospital/medical center and/or health care facility. Both Project Manager and Site Superintendent must demonstrate (by way of professional resume) experience in managing and providing oversight with new hospital construction or construction additions with a project magnitude equal to or greater than $5M or more over the past 5 years.
Standard for Acceptability: Project Manager and the on-Site Superintendent must have a minimum of five (5) or more years of experience managing new hospital construction and/or construction additions in a hospital or medical center environment.
FACTOR 2 - Technical Management Approach: The offeror shall provide a narrative that outlines the proposed technical approach for this project, including assumptions and rationale for choosing the preferred approach.
Sub-Factor 2a-Project & Construction Quality Control: Include a discussion of how the duration of project time was achieved; provide a Gantt chart of contract times broken into schedule of values by trade discipline and by General Wage Decision (formerly Davis-Bacon Act). Offeror must include identification of proposed personnel for project management, site superintendence, and quality control; including role in commissioning, safety during construction, and in-house trade capabilities.
Standard for Acceptability: This standard is met when the Offeror/Bidder submits a Gantt chart achieving successful project completion in 480 calendar days, with all requirements met for contract. The submission of a Quality Control Plan (QCP) that
Solicitation No. 36C24921R0059 demonstrates sound logic with minimal disruption to medical center operations at all times.
Sub-Factor 2b-Project Management: Based on your experience in hospital construction of a project of this magnitude and scope, involving multiple trades and the coordination thereof, the commissioning of various systems involved in the new construction of a facility and your review of the project specifications and the proposed work you viewed at the site visit. Discuss potential changes or any unforeseen conditions or work not considered.
Standard for Acceptability: When the offeror proposes a reasonable view of potential changes or unforeseen conditions or work not considered. This standard demonstrates the Contractor’s capacity to gauge the project work, and discuss best practices, processes base on the contractor’s experience on past projects of similar scope and magnitude.
FACTOR 3 - Past Performance: Offeror shall list only three (3) prior clients for completed projects of new construction or new addition of hospital/healthcare facility, medical clinics where the projects dollar magnitude equal to or greater than $5,000,000.00 within the last five (5) years on the VA Past Performance questionnaire and ask the client to forward directly to the CO via email at Roxie. Keese@ va.gov by 2:00PM, Eastern Time on April 1, 2021.
NOTE: The past performance evaluation results is an assessment of the Offeror’s probability of meeting the minimum past performance solicitation requirements. This assessment is based on the Offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. The government may also obtain past performance information through the Past Performance Information Retrieval System (PPIRS) other sources known to the Government.
RELEVANT: The government will perform an independent determination of data relevancy, provided or obtained. The main assessment of relevancy shall focus on capability and magnitude. Capability assesses whether the work being performed in the reference is similar to the work in the requirement.
Magnitude defines whether the amount of work in the reference is similar to the amount of work that is to be performed in the requirement.
RECENT Recent past performance shall be defined as successful performance under contracts similar in scope to the subject requirement completed within the last five (5) years through proposal due date
Standard for Acceptability: This factor is met when up to three (3) past performance questionnaires that the offeror has worked with in the past five (5) years are submitted and are determined to be relevant in both scope and magnitude, relative to the subject procurement, and recent in regard to the timeframe-within the past 5 years. The Government will evaluate the relative merits of each project listed under past performance as well as verify the information provided through direct contact, as well as other government websites.
Solicitation No. 36C24921R0059
Price: The offeror shall provide itemized pricing for all offer items provided, as well as the deduct alternates in the schedule on the enclosed price schedule worksheet. Offerors shall provide a detailed breakout of pricing on the “S02-Price Schedule” worksheet provided with the solicitation. If a detailed price breakdown is not included in the Offeror’s price proposal, the contractor shall be excluded from further consideration of contract award. Any offeror failing to submit an itemized breakdown shall automatically render the proposal technically unacceptable and the offer will not be considered for award.
The Government will evaluate offers for award purposes by the base offer item 1. The price proposal is assumed to include the S02-Price Schedule Worksheet (3 pages), the signed SF 1442, with acknowledgment of any amendments, plus the Offeror’s Bid Guarantee documents.
Price will be evaluated to determine fairness and reasonableness.
2.1 52.215-5 FACSIMILE PROPOSALS (OCT 1997)
(a) Definition. "Facsimile proposal," as used in this provision, means a proposal, revision or modification of a proposal, or withdrawal of a proposal that is transmitted to and received by the Government via facsimile machine.
(b) Offerors may submit facsimile proposals as responses to this solicitation. Facsimile proposals are subject to the same rules as paper proposals.
(c) The telephone number of receiving facsimile equipment is: Not Applicable (email transmission only).
(d) If any portion of a facsimile proposal received by the Contracting Officer is unreadable to the degree that conformance to the essential requirements of the solicitation cannot be ascertained from the document—
(1) The Contracting Officer immediately shall notify the offeror and permit the offeror to resubmit the proposal;
(2) The method and time for resubmission shall be prescribed by the Contracting Officer after consultation with the offeror; and
(3) The resubmission shall be considered as if it were received at the date and time of the original unreadable submission for the purpose of determining timeliness, provided the offeror complies with the time and format requirements for resubmission prescribed by the Contracting Officer.
(e) The Government reserves the right to make award solely on the facsimile proposal.
However, if requested to do so by the Contracting Officer, the apparently successful offeror promptly shall submit the complete original signed proposal.
(End of Provision)
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
Solicitation No. 36C24921R0059
(End of Provision)
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—
SECONDARY SITE OF THE WORK (MAY 2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO
ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION
(FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
10.8 % 6.9 %
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
(End of Provision)
Solicitation No. 36C24921R0059
2.5 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—
CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "designated country construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials Under Trade Agreements" (Federal Acquisition Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested—
Solicitation No. 36C24921R0059
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.6 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, shall be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be Twenty (20%) percent of the bid price or $3,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Roxie Ann Keese Contracting Officer
Hand-Carried Address:
Department of Veterans Affairs Network Contracting Office - 9 1639 Medical Center Parkway, Ste 400
Solicitation No. 36C24921R0059
Mailing Address:
Department of Veterans Affairs Network Contracting Office - 9 1639 Medical Center Parkway
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB
1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— Thursday March 18, 2021 at 3:00pmET
(c) Participants will meet at— 2250 Leestown Road, Building 2, Room #216
(End of Provision)
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY
REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/ https://beta.sam.gov/
(End of Provision)
FAR
Number
Title Date
52.204-7 SYSTEM FOR AWARD MANAGEMENT OCT 2018
52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE
REPORTING
AUG 2020
52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017
52.215-1 INSTRUCTIONS TO OFFERORS—COMPETITIVE
ACQUISITION ALTERNATE II (OCT 1997)
JAN 2017
52.236-28 PREPARATION OF PROPOSALS—CONSTRUCTION OCT 1997
Solicitation No. 36C24921R0059
2.10 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED
AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC
2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.
(End of Clause)
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.
(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.
(End of Provision)
PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:
Deputy Assistant Secretary for Acquisition and Logistics, Risk Management Team, Department of Veterans Affairs 810 Vermont Avenue, N.W.
Washington, DC 20420 Or for solicitations issued by the Office of Construction and Facilities Management:
Director, Office of Construction and Facilities Management 811 Vermont Avenue, N.W.
Washington, DC 20420
FAR
Number
Title Date
852.223-70 INSTRUCTIONS TO OFFERORS—SUSTAINABLE
ACQUISITION PLAN
SEP 2019
852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE
RESOLUTION
OCT 2018
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR
2020) (a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $39.5 Million.
Solicitation No. 36C24921R0059
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
Solicitation No. 36C24921R0059
(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations— Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
Solicitation No. 36C24921R0059
(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals-- Representation. This provision applies to solicitations that include the clause at 52.204-7.)
(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xxi) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate.
(Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the…