36C24818R0140-003.doc

DOC document 57 KB Posted

Attached to
Replace Failing De-Aerating Tank Federal contract opportunity
Solicitation number
36C24818R0140
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8

About this file

36C24818R0140 Attachment 02 Contractors Closing Statement and Release of Claims.doc

View the file

Other files for this federal contract opportunity

Other files attached to Replace Failing De-Aerating Tank, newest first.
File Type Posted
36C24818R0140-00001000.docx DOCX document
36C24818R0140-004.doc DOC document
36C24818R0140-006.doc DOC document
36C24818R0140-001.docx DOCX document
36C24818R0140-010.pdf PDF
36C24818R0140-012.doc DOC document
36C24818R0140-002.pdf PDF
36C24818R0140-011.doc DOC document
36C24818R0140-005.docx DOCX document
36C24818R0140-007.doc DOC document
36C24818R0140-009.pdf PDF
36C24818R0140-008.docx DOCX document
36C24818R0140-000.docx DOCX document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 2: Contractor’s Closing Statement Template and

Contractor’s Release of Claims Template

Contractor’s Closing Statement

Per FAR 4.804-5(a)(13)

CONTRACT/ORDER NO. _______________________

Dear Contractor, Per FAR 4.804-5(a) (13) we are required to document a “Contractor’s Closing Statement”.

Our records indicate the following: (check to indicate your agreement)

1. [ ] all commodities or services have been delivered or performed and accepted

2. [ ] all invoices submitted have been paid

3. [ ] there are no outstanding invoices or issues

We are ready to close this contract and de-obligate any remaining funds. Please confirm that our records are in agreement with yours. If we do not hear from you within 7 days, we will continue with the closeout of this contract.

Concur/Do Not Concur

Contractor’s Signature [ ] No Response from Contractor within 7 (seven) Calendar Days

Contracting Officer’s Signature

Date

CONTRACTOR’S RELEASE OF CLAIMS

CONTRACT NO. _______________________

Pursuant to the terms of Contract No. ______________________________ and in consideration of the sum of Dollars ($ __________________), which has been or is to be paid under the said contract to ____________________________ (hereinafter called the Contractor) or its assignees, if any, the Contractor, upon payment of the said sum by the UNITED STATES OF AMERICA (hereinafter called the Government) does remise, release and discharge the Government, its officers, agents, and employees of and from all liabilities, obligations, claims and demands whatsoever arising out of or under this contract, subject only to the following exceptions:

1. Specified claims in stated amounts, or in estimated amounts where the amounts are not susceptible of exact statement by the contractor, as follows:

NONE__________________________________________________________________

2. Claims, together with reasonable expenses incidental thereto, based upon the liabilities of the contractor to third parties arising out of the performance of this contract, which are not known to the contractor on the date of the execution of this release, and of which the contractor gives notice in writing to the Contracting Officer not more than six (6) years after the date of the release or the date of any notice to the Contractor that the Government is prepared to make final payment, whichever is earlier; and

3. Claims for reimbursement of costs (other than expenses of the Contractor by reason of his indemnification of the Government against patent liability), including reasonable expenses incidental thereto, incurred by the Contractor under the provisions of the contract relating to patents.

The Contractor agrees, in connection with patent matters and with claims which are not released as set forth above, to comply with all of the provisions of the said contract, including without limitation those provisions relating to notification to the Contracting Officer and relating to the defense of prosecution and of litigation.

This release of claims is effective this ___________ day of__________________ 20____.

[Contractor Name]

BY:

TITLE:

CERTIFICATE

I, _________ [name], certify that I am the ________________________________ [official title] of the corporation named as Contractor in the foregoing release; that ______________________ [name], who signed said release on behalf of the Contractor was the ______________________ [official title] of said Corporation; that said release was duly signed for and in behalf of said corporation by authority of its governing body and is within the scope of its corporate powers.

Signed: ____________________________

(CORPORATE SEAL)

SAMPLE CONTRACTOR’S RELEASE OF CLAIMS

CONTRACT NO. GS-35F-0600J

TASK ORDER NO. VA118-11-F-0492 for $ 979,471.43

TASK ORDER NO. VA118-11-F-1483 for $1,783,586.50

TASK ORDER NO. VA118-12-F-0381 for $1,545,914.46

TASK ORDER NO. VA118-13-F-1748 for $ 474,701.08

TASK ORDER NO. VA118-13-F-1983 for $ 46,935.65

TASK ORDER NO. VA118-14-F-0274 for $ 96,197.68

TASK ORDER NO. VA118-15-F-0383 for $ 193,435.10

TASK ORDER NO. VA118-16-F-0210 for $ 128,105.72

TOTAL: $5,248,347.62

Pursuant to the terms of Contract No. GS-35F-0600J and the Task Order Numbers listed above for work contained in the Task Orders for Health Information Engineering, and in consideration of the sum of Dollars $5,248,347.62, which has been or is to be paid under the said contract to Patriot Technologies LLC (hereinafter called the Contractor) or its assignees, if any, the Contractor, upon payment of the said sum by the UNITED STATES OF AMERICA (hereinafter called the Government) does remise, release and discharge the Government, its officers, agents, and employees of and from all liabilities, obligations, claims and demands whatsoever arising out of or under this contract, subject only to the following exceptions:

1. Specified claims in stated amounts, or in estimated amounts where the amounts are not susceptible of exact statement by the contractor, as follows:

NONE__________________________________________________________________

2. Claims, together with reasonable expenses incidental thereto, based upon the liabilities of the contractor to third parties arising out of the performance of this contract, which are not known to the contractor on the date of the execution of this release, and of which the contractor gives notice in writing to the Contracting Officer not more than six (6) years after the date of the release or the date of any notice to the Contractor that the Government is prepared to make final payment, whichever is earlier; and

3. Claims for reimbursement of costs (other than expenses of the Contractor by reason of his indemnification of the Government against patent liability), including reasonable expenses incidental thereto, incurred by the Contractor under the provisions of the contract relating to patents.

The Contractor agrees, in connection with patent matters and with claims which are not released as set forth above, to comply with all of the provisions of the said contract, including without limitation those provisions relating to notification to the Contracting Officer and relating to the defense of prosecution and of litigation.

This release of claims is effective this ___________ day of__________________ 20____.

[Contractor Name]

BY:

TITLE:

CERTIFICATE

I, ______________________________________________________ [name], certify that I am the ______________________________________________________________ [official title] of the corporation named as Contractor in the foregoing release; that ______________________ [name], who signed said release on behalf of the Contractor was the ______________________ [official title] of said Corporation; that said release was duly signed for and in behalf of said corporation by authority of its governing body and is within the scope of its corporate powers.

Signed: ____________________________

Contract Closeout SOP Revision 02

Original Date: 10/15/2010

Revision 02 Date: 01/11/2016