36C24818R0140-001.docx
DOCX document 109 KB Posted
- Attached to
- Replace Failing De-Aerating Tank Federal contract opportunity
- Solicitation number
- 36C24818R0140
About this file
36C24818R0140 36C24818R0140_1.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24818R0140-00001000.docx | DOCX document | |
| 36C24818R0140-004.doc | DOC document | |
| 36C24818R0140-006.doc | DOC document | |
| 36C24818R0140-010.pdf | ||
| 36C24818R0140-003.doc | DOC document | |
| 36C24818R0140-012.doc | DOC document | |
| 36C24818R0140-002.pdf | ||
| 36C24818R0140-011.doc | DOC document | |
| 36C24818R0140-005.docx | DOCX document | |
| 36C24818R0140-007.doc | DOC document | |
| 36C24818R0140-009.pdf | ||
| 36C24818R0140-008.docx | DOCX document | |
| 36C24818R0140-000.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24818R0140
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24818R0140 X 02-08-2018 548-18-2-5879-0003 548-18-110 36C248 Department of Veterans Affairs West Palm Beach VA Medical Center 7305 North Military Trail Palm Beach Gardens
FL
33410-6400 Department of Veterans Affairs SAO East, NCO 8 Woodbine 7721 Suite 4 7305 North Military Trail Palm Beach Gardens
FL
33410-6400 Deborah Murphy 561-876-9340 THIS IS A SERVICE-DISABLED, VETERAN-OWNED, SMALL BUSINESS SET-ASIDE. PROSPECTIVE CONTRACTORS ARE CAUTIONED THAT PROPOSAL SUBMITTED IN RESPONSE TO THIS SOLICITATION MUST MEET THE CRITERIA IDENTIFIED BY 38 CFR, PART 74.
ANY PERSON, PERSONS, OR BUSINESS ENTITY SUSPECTED OF MISREPRESENTING ITSELF FOR THE PURPOSE OF SECURING A GOVERNMENT CONTRACT MAY BE CRIMINALLY INVESTIGATED AND PROSECUTED FOR FRAUD AGAINST THE UNITED STATES OF AMERICA. PARTIES FOUND MISREPRESENTING THEIR STATUS ALSO RISK DEBARMENT FROM FURTHER GOVERNMENT CONTRACTS.
The contractor shall provide all design/build services, labor, equipment, materials, supervision, and all other resources necessary to remove and replace the failed de-aerating tank, including controls and instruments as required to replace the existing programmable loop AC controllers in accordance with the Statement of Work, specifications, drawings and this solicitation.
This is a two phase design build solicitation that will use the trade-off source selection process, providing the best value to the government as described in Section 00 11 21 Request for Proposal to Design Build.
At the time of proposal submission, contractors must have current registration/certification in the System for Award Management (SAM) at www.sam.gov and VetBiz at vetbiz.gov. Proposals of contractors not registered/ certified in both data bases will not be considered for award.
Project Magnitude: $500,000 to $1,000,000
NAICS: 236220
There will be no site visit for Phase I of this solicitation.
Phase I Requests for Information (RFI's) are due no later than February 15, 2018 at 12:00 PM EST and shall be submitted via email to Deborah.Murphy3@va.gov. Email subject line shall read: RFIs 36C24818R0140 Replace DA Tank and Controls.
Phase I proposals are due no later than March 08, 2018 and shall be submitted via email to Deborah.Murphy3@va.gov
X X 52.211-10 X email only
4:00 PM
03-08-2018 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
00548 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) West Palm Beach VA Medical Center 7305 North Military Trail Palm Beach Gardens
FL
33410-6400 Department of Veterans Affairs Financial Services Center P.O. Box 149971 Austin
TX
78714-9971 Deborah Murphy
NCO815L2-2275
Table of Contents
| PART I - THE SCHEDULE | 1 | |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 | |
| SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 | |
| REQUEST FOR PROPOSAL TO DESIGN BUILD | 6 | |
| PART I – General | 6 | |
| A1. | Scope of Contract | 6 |
| A2. | Definitions | 9 |
| A3. | Price Range | 10 |
| A4. | Pre-Proposal Conference | 10 |
| A5. | Selection Criteria and Weightings | 11 |
| PART II - RESPONSIBILITIES | 11 | |
| B1. | VA Team | 11 |
| PART III - PROPOSAL REQUIREMENTS | 11 | |
| C1. | General | 11 |
| C2. | Proposal Revisions (FAR 52.215-1) | 13 |
| C3. | Technical Proposal Requirements | 13 |
| PART IV - POST AWARD REQUIREMENTS | 17 | |
| D1. | Construction Document Preparation: | 17 |
| D2. | Construction Period Submittals | 21 |
| D3. | Project Close-Out | 22 |
| D4. | Site Visits and Inspections | 22 |
| A.1 PRICE/COST SCHEDULE | 23 | |
| ITEM INFORMATION | 23 | |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 25 | |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 25 | |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 25 | |
| 2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 25 | |
| 2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 26 | |
| 2.5 52.228-1 BID GUARANTEE (SEP 1996) | 27 | |
| 2.6 52.233-2 SERVICE OF PROTEST (SEP 2006) | 28 | |
| 2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 28 | |
| 2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 29 | |
| 2.9 VAAR 852.215-70 SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESS EVALUATION FACTORS (JUL 2016)(DEVIATION) | 29 | |
| 2.10 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 30 | |
| 2.11 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (JAN 2008) | 30 | |
| 2.12 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (JAN 1998) | 30 | |
| 2.13 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 31 | |
| 2.14 PARTNERING | 31 | |
| REPRESENTATIONS AND CERTIFICATIONS | 32 | |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (NOV 2017) | 32 | |
| 3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013) | 35 | |
| GENERAL CONDITIONS | 37 | |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 37 | |
| 4.2 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013) | 37 | |
| 4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 38 | |
| 4.4 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000) | 38 | |
| 4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013) | 38 | |
| 4.6 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015) | 40 | |
| 4.7 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 40 | |
| 4.8 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008) | 42 | |
| 4.9 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014) | 42 | |
| 4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS | 45 | |
| 4.11 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) | 45 | |
| 4.12 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) ALTERNATE II (APR 1984) | 46 | |
| 4.13 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 47 | |
| 4.14 VAAR 852.203-70 COMMERCIAL ADVERTISING (JAN 2008) | 49 | |
| 4.15 VAAR 852.215-71 EVALUATION FACTOR COMMITMENTS (DEC 2009) | 50 | |
| 4.16 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 50 | |
| 4.17 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012) | 50 | |
| 4.18 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (JUL 2002) | 51 | |
| 4.19 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (JUL 2002) | 51 | |
| 4.20 VAAR 852.236-74 INSPECTION OF CONSTRUCTION (JUL 2002) | 52 | |
| 4.21 VAAR 852.236-76 CORRESPONDENCE (APR 1984) | 52 | |
| 4.22 VAAR 852.236-77 REFERENCE TO "STANDARDS" (JUL 2002) | 53 | |
| 4.23 VAAR 852.236-78 GOVERNMENT SUPERVISION (APR 1984) | 53 | |
| 4.24 VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL (APR 1984) | 53 | |
| 4.25 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 1984) | 53 | |
| 4.26 VAAR 852.236-82 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS) (APR 1984) | 54 | |
| 4.27 VAAR 852.236-84 SCHEDULE OF WORK PROGRESS (NOV 1984) | 57 | |
| 4.28 VAAR 852.236-85 SUPPLEMENTARY LABOR STANDARDS PROVISIONS (APR 1984) | 57 | |
| 4.29 VAAR 852.236-86 WORKER'S COMPENSATION (JAN 2008) | 57 | |
| 4.30 VAAR 852.236-87 ACCIDENT PREVENTION (SEP 1993) | 58 | |
| 4.31 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002) | 58 | |
| 4.32 VAAR 852.236-89 BUY AMERICAN ACT (JAN 2008) | 60 | |
| 4.33 VAAR 852.236-91 SPECIAL NOTES (JUL 2002) | 60 | |
| 4.34 VAAR 852.246-74 SPECIAL WARRANTIES (JAN 2008) | 61 | |
| 4.35 LIMITATIONS ON SUBCONTRACTING-- MONITORING AND COMPLIANCE (JUN 2011) | 61 | |
| 4.36 SUBCONTRACTING COMMITMENTS--MONITORING AND COMPLIANCE (JUN 2011) | 62 | |
| DESIGN BUILD SPECIFICATIONS | 63 | |
| 4.37 SCHEDULE OF PAYMENTS FOR DESIGN SERVICES | 63 | |
| 4.38 OWNERSHIP OF ORIGINAL DOCUMENTS | 63 | |
| 4.39 RETENTION OF REVIEW DOCUMENTS | 63 | |
| 4.40 CONTRACT DRAWINGS AND SPECIFICATIONS GOVERNMENT FURNISHED PLANNING INFORMATION | 63 | |
| 4.41 COORDINATION WITH MEDICAL CENTER | 64 | |
| 4.42 RESPONSIBILITY OF THE DESIGN-BUILD CONTRACTOR | 64 | |
| ATTACHMENTS | 65 |
REQUEST FOR PROPOSAL TO DESIGN BUILD
SECTION 00 11 21
Replace DA Tank and Auxiliary Controls Project No#548-18-110 West Palm Beach VA Medical Center
PART I – General
| The project replaces the DA Tank and Auxiliary controls. | |
| A1. | Scope of Contract |
| Provide all labor, materials, tools and equipment, and design-build services necessary for design and construction of this project as described here in this request for proposal. |
1. Replace the existing programmable loop controllers. Controls for Boilers 1, 2 and 3 were upgraded and replaced with Hays Cleveland UPAC™ controls.
2. The last four AC controllers (drawings attached) will be replaced with UPAC controller(s).
3. Remove and replace the failed DA Tank. Tank replacement can be either in-place with the modified capacity listed below, or purchase a “packaged DA Tank” and consider relocating on the lower level. Both options shall include modified capacity listed below.
Capacity 26,000 lbs. /hr. water output Water in, 110 degree f (160 degree f - 180 degree f normal) Water out, 228 degree f Operating Steam Pressure 5 psig De-aeration to 0.005 cc/liter oxygen Storage capacity, 102 cu. ft. minimum at overflow (20 minutes of capacity) Construction, ASME Code for 50 psig Maximum dimensions (TBD)
Main Control Panel loops and monitoring included in this scope:
Replace steam header pressure master control with firing rate signals to the three boiler control systems. Control to plant steam header pressure.
Replace condensate surge tank level control (single valve) adding makeup water from the plant water softening system.
Monitor the condensate surge tank temperature.
Replace condensate transfer pump control. Pumps CTP1 and CTP2 have integral VFD motor speed drives that are started & stopped (lead-lagged); and speed controlled to maintain a constant pressure on their common header piped to the DA tank makeup level control valve.
Deaerator storage tank level control (single valve) using makeup water from the condensate transfer pumps.
Monitor the DA storage tank temperature and pressure.
Monitor the DA storage tank level alarms and status of its overflow valve system.
Replace boiler feed water pump control. Pumps BFP1, BFP2 and BFP3 have integral VFD motor speed drives that are started & stopped (lead-lagged); and speed controlled to maintain a constant pressure in their single common header piped to the level control valves for the three boilers.
Monitor the natural gas header pressure and temperatures, and provide signals to the three boiler control systems for compensation of the boiler gas flow meter signals.
Monitor and pressure compensate the three (3) boiler steam flow signals and sum (add) them to monitor total steam being produced by the boilers.
Monitor and pressure compensate the six (6) distribution steam flow signals for the Deaerator Tank, Hospital Heat Exchanger, Nursing Home, Basement & Risers, Medium Steam Pressure and Laundry/Kitchen. Sum these signals for comparison with the total amount of steam generated from the boilers.
Monitor OS air temperature. Degree days are computed in the SCADA computer.
Monitor the pressure compensated gas flow signals from each of the three boilers.
Update existing SCADA system to interface with the new controls to include their data for existing graphics, alarms and printed reports. Includes updates as required for the main SCADA computer in the boiler plant supervisor’s office and the auxiliary SCADA computer in the at the main control panel.
Replace red and green indicators in main panel with low voltage LED indicators for seven (7) existing manual-automatic control stations (two fuel oil pumps, two condensate transfer pumps and three boiler feed water pumps).
Replace annunciator in the main panel with a low voltage model using red and yellow LED indicators for alarm and status conditions. Wire to existing alarm bell and panel mounted push buttons (test & acknowledge).
Use existing 4-20 mADC loop powered transmitters including … Steam Header Pressure (control). Suppressed range, 70 to 145 psig Steam Header Pressure (monitoring). 0 to 200 psig Outside air temperature, 0 to 120°F.
Feed water header temperature, 0 to 400°F.
Natural gas header temperature, 0 to 130°F Natural gas header pressure, 0 to 15 psig.
Condensate transfer pump header pressure, 0 to 80 psig.
Condensate surge tank temperature, 0 to 400°F Condensate surge tank level, 0 to 40 IN WC.
Deaerator storage tank level, -20 to 0 to +20 IN WC.
Boiler feed water pump header pressure, 0 to 300 psig.
Deaerator tank steam line flow, 0 to 1000 Lb/Hr Wire to existing powered 4-20 mADC transmitted signals including … Hospital Heat Exchange steam line flow, 0 to 3,500 Lb/Hr.
Nursing Home steam line flow, 0 to 4,500 Lb/Hr.
Medium pressure basement and risers steam line flow, 0 to 3,000 Lb/Hr Medium pressure “DOM” steam line flow, 0 to 4,500 Lb/Hr Laundry & Kitchen steam line flow, 0 to 4,500 Lb/Hr.
Furnish new 4-20 mADC loop powered transmitters for… Deaerator storage tank steam pressure, 0 to 20 psig.
Deaerator storage tank temperature, 0 to 400°F.
Use existing final control elements and provide 4-20 mADC control signals including:
Boiler 1, 2 and 3 master firing rate signals, 0 to 100%.
Boiler 1, 2 and 3 natural gas header pressure.
Boiler 1, 2 and 3 natural gas header temperature.
Condensate transfer pump 1 & 2 speed signals, 0 to 100% Condensate tank level makeup control valve signal, 0 to 100% Boiler feed water pump 1, 2 & 3 speed signals, 0 to 100% Deaerator tank level makeup control valve signal, 0 to 100% Wire existing manual-off-automatic selectors in the main panel for control of the two condensate transfer pumps and the three boiler feed water pumps.
Wire existing steam pressure selector switch to the new master pressure controller.
Additional Information;
All control systems are currently operational.
Hayes/Cleveland UPAC Controllers are the only acceptable controls for the replacement of the AC Controllers.
The DA tank is permanently off-line until replacement is completed.
The following items are anticipated to be replaced with the new DA Tank;
Relief Valves Gauge glass Isolation valves that do not hold
| A2. | Definitions |
| A. | Design-Build (DB) as defined by the Department of Veterans Affairs (VA) is the procurement by the Government, under one contract, with one firm or joint venture (JV) for both design and construction services for a specific project. |
| 1. | Contracting Officer: The services to be performed under this contract are subject to the general supervision, direction, control and approval of the Contracting Officer. |
| 2. | Contracting Officer Representative (COR): The Contracting Officer's authorized representative at the construction site. When more than one COR is assigned to a construction project one is designated as being incharge and is called the COR. The COR is responsible for protecting the Government's interest in the execution of the construction contract work. His duties include surveillance of all construction work to assure compliance with the contract documents, interpretation of the contract documents, approval of changed work, approval of all submittals, samples, shop drawings, etc. |
| 3. | Design Build Contract: This term refers to the contract to perform the design and construction of the project. |
| 4. | Contractor: This term refers to the contractor under this contract. |
| 5. | AE: This term refers to the ArchitectEngineer firm(s) that are a part of the DB team, also referred to as DB/AE. |
| B. | Selection Procedure – |
| During the review of offers the VA may ask for additional information. The VA may initiate action to award a contract at any point after review of the offers. Therefore, offers should reflect the offeror’s best terms both from a technical and cost standpoint. See FAR 52. 215-1, Instructions to Offerors - Competitive Acquisition (Jan 2004. |
C. Tentative Schedule:
| Phase I Request for Proposal Issued |
| 02/08/2018 |
| Phase I Proposal Due |
| 03/08/2018 |
| Phase II Request for Proposal Issued |
| 03/15/2018 |
| Phase II Pre-Proposal Conference |
| 03/22/2018 |
| Phase II Proposal Due |
| 04/13/2018 |
| Contract Award |
| 05/02/2018 |
| Notice to Proceed |
| 05/10/2018 |
| Construction Completion/Final Inspection/ Custody Receipt |
| 01/05/2019 |
| D. | Schedule Objectives - The anticipated completion of this project is 240 days after “Notice to Proceed” (NTP). The proposed schedule may be shorter than this, see Part III, C3, 3c. |
| A3. | Price Range |
| The anticipated cost range for this project is between $500,000 and $1,000,000. | |
| A4. | Pre-Proposal Conference |
| No site visit will be conducted during Phase I of the solicitation. Those offerors selected to participate in Phase II of the solicitation will receive information about the Phase II pre-proposal conference and site visit in the invitation to participate in Phase II. | |
| A5. | Selection Criteria and Weightings |
A. Phase I proposals will be evaluated for professional qualifications/experience and capacity to perform the work, past performance and Safety/Environmental record. All factors are approximately equal in importance. The Phase I evaluation factors are:
Phase I
| Factor 1 – Technical Qualifications/Experience |
| Factor 2 – Capability to Perform |
| Factor 3 – Past Performance |
The maximum number of offerors that will be selected to move into Phase II shall not exceed 5.
B. Phase II proposals will be evaluated in accordance with the Trade-Off source selection process. The technical evaluation factors, when combined, are significantly more important than price.
PART II - RESPONSIBILITIES
B1. VA Team
A. VA Engineering group and Skilled Trades groups B. Edward Snyder will be the Contracting Officer’s Representative.
PART III - PROPOSAL REQUIREMENTS
| C1. | General |
| A. | Proposals shall be based on solicitation documents issued for RFP Solicitation Number 36C24818R0140. Proposals will be in the format stipulated elsewhere in this section. |
| B. | Phase I RFI’s shall be received no later than noon, February 15, 2018. |
C. Phase I Proposals shall be received before 4:00 P.M. EST, March 08, 2018.
D. Phase II Proposals shall be due at the time and date specified in the Request for Phase II proposals sent to those contractors invited to participate in Phase II.
E. Proposals are to be submitted electronically, via email to:
Deborah.murphy3@va.gov No hard copies of the proposals are required.
F. An electronic copy of the bid bond shall be included as part of the electronic submission. Additionally, a hard copy of the bid bond shall be submitted and received by Phase II submission due date and time.
G. Submit a hard copy of the bid bond to:
1. US Postal Service Deliveries/Commercial Delivery Services:
Deborah Murphy, Contracting Officer (90C) NCO 8, West Palm Beach 7301 N. Military Trail Woodbine Suite 7721-4
H. Technical and Price sections of the Offers;’ proposals will be evaluated independently. Offeror submit each section as a separate document. Each section must have the Offeror's:
· Organization name
· business address
· phone number,
· point of contact name and email address
· DUNS
· EIN
· Solicitation Number, and
· VA Project Number
1. Offeror shall submit separate prices for each proposal item indicated on the RFP Offer and award;
2. Technical proposals shall not exceed 20 pages.
| 3. | Offeror shall include all required Representations and Certifications; and |
| 4. | Acknowledge receiving amendments by number. |
| C2. | Proposal Revisions (FAR 52.215-1) |
| A. | If determined to be necessary, proposal revisions will be requested for the proposals received. The Contracting Officer will identify those offerors, whose proposals are within the competitive range, considering the selection criteria identified in this section. Negotiations may be conducted with those offerors falling within the competitive range, after which proposal revisions will be requested. |
| B. | Offerors submitting proposal revisions will not be requested to re-submit any documents which are unchanged from their initial proposals. They should provide necessary changes to individual paragraphs, as briefly as possible, together with a table of contents that clarifies where within the initial proposal the additional information or changed documents would be placed. A new bid bond shall be submitted only if the final proposal revisions offeror’s price proposal is greater than its initial price proposal. |
| C3. | Technical Proposal Requirements |
| A. | The proposal shall address the following evaluation factors |
Phase I . Factor 1: Technical Qualifications/Experience
1. Corporate Project Experience - The Offeror shall demonstrate corporate experience with no more than three projects completed within the last five years by a Design Build contract and/or contract similar in size and scope to this project. Scoring will be more favorable if both criteria are met. In describing project design and construction experience, provide the following information:
0. Project title, location and brief description including the building use (Medical Facility etc.) and contracting method (design build, design bid construct, CM at risk etc.).
0. Project owner and name and telephone number of owner’s contact person.
0. Project Design Architect and Engineers (consultants if utilized) and name and telephone number of contact person(s). Note each firm and employee also proposed for this solicitation.
0. Project Prime Contractor and Major Subcontractors and name and telephone number of contact person(s). Note each firm and managing persons (project manager/superintendent/foreman as the case may be) also proposed for this solicitation.
0. Project Statistics including start and completion dates (original vs. actual) for design and construction; cost (with brief explanation of what is included in the cost); square footage; foundation type; number of levels; and any awards (prizes) received.
1. Project Personnel Experience (Specialized experience and technical competence). The Offeror shall demonstrate the relevant experience of key project personnel.
1. Biographical data shall include the following:
1. Name of individual.
1. Company employed by.
1. Company position title.
1. Years with the company.
1. Describe work experience with projects that; were completed by the design build process, were medical facilities and the company (by name) they worked for when involved in the project.
1. An indication of which (if any) projects submitted under Corporate Experience (above) the individual participated in and what the individuals responsibility was for that project.
1. An indication of which other individuals submitted under Project Personnel Experience this individual has worked with and the project they worked on together, noting if that project has been submitted under Corporate Experience (above).
1. Position that the individual will hold in regard to this contract/project team, description of duties and what percentage of the individual’s time would be committed to the project during both the design and construction phases.
1. Describe job related educational experience including degrees, certificates etc. and granting institutions.
b. Supply this biographical data for key personnel for at least the following: (Note if one individual is proposed for more than one position listed):
| a) | Overall Project Manager. |
| b) | (Architect) Design Project Manager. |
| c) | Construction Project Manager. |
| d) Architect/Engineer Field Representative |
Factor 2: Capability to Perform
| 1. Provide the offeror's total bonding capacity, current available bonding capacity and expected available capacity in 2017. |
| 2. Provide the offeror's current workload and availability of adequate staff listed under Project Personnel Experience to manage the project. Include project schedules for current and pending projects, as well as the anticipated impact of this project on those schedules and staffing plans. |
Factor 3: Past Performance
1. Offeror’s D/B Team (including construction and architect-engineer members) are required to demonstrate recent (within the last five years), successful performance under contracts (ongoing or completed) which are similar in scope, magnitude, and complexity to the subject requirement. Submit a minimum of 1 but no more than 3 references. Past Performance may be from all or any or either of the following categories:
a. Team Past Performance;
b. General Contractor/Construction Past Performance;
c. Design Firm’s Past Performance;
2. The past performance section of the proposal shall include:
1. Government Agency/Company which awarded contract to offeror
1. Contract Number
1. Description of Contract Scope
1. Total Dollar Value
1. Performance Period
1. Place of Performance
1. Contracting Officer/Procurement Official
0. Name
0. Email
0. Phone Number
0. Address
3. Client Satisfaction: Points of contact supplied will be contacted by the Evaluation Team. These contact's responses will be scored based on the following elements with projects participated in by the Prime (Construction Contractor and Architect firm) being more highly rated than projects participated in by consultants, sub-contractors and individuals.
| a. | Client Overall Satisfaction with Project: Contact persons will be asked "does the project fulfill the requirements of the clients stated function, does the project require unexpected maintenance activity, and have latent defects been found?" |
| b. | Client Overall Satisfaction with Design Build Period Services: Contact persons will be asked "Was the team's response time to clients’ questions acceptable? Was the staffing level consistent with the project size and complexity? Was communication of schedule and problem issues adequate and consistent? Was there an established problem solving routine? Would the client like to use this firm again?" |
Phase II Factor 1: Technical/Management Approach In a narrative format, describe the steps the prime contractor will take to successfully complete design/build services for this project in accordance with the Design-Build Scope of Work.
a. Describe in a written narrative, the plan for phasing the work so that the facility remains operational. The narrative will also detail how the contractor intends to prepare the site, renovate and return to use within any specified time limits.
b. Project Organizational Chart and Narrative – include team members submitted under Project Personnel Experience from Phase l. Clearly describe the prime responsible firm (or firms if a J/V) and individuals as well as the roles and responsibilities of individuals proposed as consultants and subcontractors. Provide a list of all consultants and all proposed major subcontractors, including telephone number, address and name of contact.
c. Clarify intended uses of portions of the site indicated to be available to the contractor elsewhere in this solicitation for materials staging, temporary trailer offices, employee parking, and other activities as shown in the design solution material.
d. Clarify procedures and proposed solutions for contingencies, differing site conditions, power outages, scheduling conflicts and temporary work stoppage requests (interference with Medical Center operations).
e. Demonstrate techniques for management of work coordination with subcontractors and measures/corrective action that will be taken for substandard performance.
f. Provide an approach to ensure cost-savings and minimizing issuance of change orders.
g. Provide at least one 24 x 36 schematic illustrating your proposed layout but not a detailed design.
h. Quality Control Plan
Factor 2: Schedule
1. The progress schedule will be in a time scaled bar graph format. The horizontal axis will be scaled for time beginning with the Notice to Proceed and concluding with contract completion. The vertical axis will show the milestones and major portions of the contract work. All schedule items will show a start date and a completion date. The detailed schedule will indicate specific tasks with dates for each step of the process including:
0. Design Period: The design period sub periods (i.e., first and second reviews, other meetings, internal QUALITY ASSURANCE /QUALITY CONTROL plan reviews, etc.).
0. Construction Period: Mobilization; Demolition method and sequencing; Excavation; Structure Completion; Exterior finishing; Procurement and installation of equipment; Provisions for overtime or shift work; Timing of relocation of existing equipment; Site utilities, roadway realignment; and temporary rerouted medical center vehicular and pedestrian routes, Tests and final inspection.
0. General Project Delivery Schedule and Narrative - Show relationships between construction document development/completion (including required review activities) and construction activities for (at a minimum, utility relocation, excavation, substructure, structure, exterior façade, interior finishes, building systems, and site development.
1. The Offeror shall specify how much allowance has been made for bad weather in the schedule, the days of the week and the hours of construction operations during each phase of the work, and the percentage of contract completion that will be achieved at the end of each month of the contract.
1. Short Schedules - The Offeror will provide a written commitment as to the time frame (number of days after receipt of the notice to proceed) within which the Offeror will guarantee completion. The maximum anticipated completion of this project (including design and construction of the entire project) is 240 days.
3. Price All proposals shall include a detailed cost breakdown (materials, labor, and equipment) by trade and include overhead, profit, and bond costs for project completion. In the price proposal, clearly show the portion of the price attributable to the 15% SDVOSB performance obligation. The Government may use various price analysis techniques and procedures to make a price reasonableness determination.
PART IV - POST AWARD REQUIREMENTS
| D1. | Construction Document Preparation: |
| A. | Design Review Submissions: |
| 1. | The Design-Build Team A/E (DB A/E) shall prepare and submit complete construction documents for review and approval by the VA in accordance with standard professional practice, the Department of Veterans Affairs RFP (VA RFP), and prevailing codes. |
| 2. | The documents may be divided into multiple review submission packages. The VA will review as many as six (6) package submissions (examples: demolition, civil, architectural, structural, mechanical, Electrical, plumbing etc.) to facilitate the start of construction. |
| 3. | All submission packages will be reviewed at (50%) and (95%) completion stages. The (95%) review submission packages will incorporate the final review comments from the (50%) review. If any package is not complete for the required stage a post review may be required the cost of which will be borne by the DB Team. |
| 4. | Each review submission package shall include 3 hard copy sets and 3 set on CD-ROM. The package will include an index of drawings (by sheet number and tittle) and specifications (by section number and tittle) submitted. The packages will be distributed to the VA Project Manager, the VA Medical Center, RFP A/E, VA COR and others as determined to be appropriate by the VA Project Manager. |
| B. | Design Review Meetings: |
| 1. | A review meeting to resolve design issues will be held for each design review package submitted. The meeting will include discussion of VA comments on functional relationships and technical peer review comments (by others). |
| 2. | Participants will include RFP A/E, VA Staff and DB team members as appropriate for the specific package to be reviewed and others. The DB team members will each allow for (1) full day for each discipline/package design review meeting. DB team management will be present at each review meeting. |
| 3. | The DB team shall allow a minimum of ten (10) working days for each review cycle. A cycle includes: |
| a. | The VA’s receipt of the design review submission package. |
| b. | The review meeting. |
| c. | DB teams receipt of comments from the VA, either electronically, by fax, or by hard copy delivery. |
| 4. | Coordination of the review meeting schedules will be the responsibility of the VA Project Manager (for the VA and RFP AE) and the DB Team Project Manager (for the DB Team). See section H. Quality Assurance/Quality Control. |
| C. | Electronic Media: |
| 1. | Design review submission drawings and final Construction Document submission drawings will be executed in electronic format AutoCAD version 2000 or later. |
| 2. | The drawings included in the VA RFP will be available to the DB team in electronic format in either PDF or AutoCAD whichever is available. Since data stored on electronic media can deteriorate undetected or be modified without the RFP Architect/Engineer’s knowledge, the CADD drawing files are provided without warranty or obligation on the part of the RFP Architect/Engineer as to accuracy or information contained in the files. The user shall independently verify all information in the files. Any user shall agree to indemnify and hold the RFP Architect Engineer harmless from any and all claims, damages, losses, and expenses including, but not limited to, attorney’s fee arising out of the use of the CADD drawing files. |
| 3. | Design review submission specifications and other 8 1/2 by 11 formatted material and final Construction Document submission specifications and other 8 1/2 by 11 formatted materials will be executed in electronic format Microsoft Word. |
| 4. | The specifications included in the VA RFP shall be available to the DB team in electronic format in Word 6.0, for use in preparing the construction specifications. Since data stored on electronic media can deteriorate undetected or be modified without the RFP Architect/Engineer’s knowledge, the CADD version 2000 drawing files are provided without warranty or obligation on the part of the RFP Architect/Engineer as to accuracy or information contained in the files. The design builder shall independently verify all information in the files and shall agree to indemnify and hold the RFP Architect Engineer harmless from any and all claims, damages, losses, and expenses including, but not limited to, attorney’s fee arising out of the use of the electronic files. |
| 5. | The construction record drawings shall be completed in AutoCAD version 2000 or later. |
| 6. | Construction shop drawings are not required to be completed in AutoCAD version 2000 or later. |
| D. | Professional Licensing: |
| 1. | The DB A/E who prepares the construction documents shall be a professional architect or engineer licensed in the State of Florida. |
| 2. | The professional seal shall appear on the final construction documents. The architect whose seal is shown will be known as the Architect of Record. The DB A/E shall certify compliance with the VA RFP and all applicable codes. |
| E. | Approved Construction Documents: |
| 1. | The final construction document submission package will be submitted by the DB team for approval by the VA after completion of the 95% review cycle for the final package to be submitted by the DB team. The VA will have 5 days to take approval action. |
| 2. | The final construction documents submission package will include a full set of construction documents including all disciplines/packages. |
| 3. | The final construction documents submission package will incorporate all VA supplied comments from the earlier 50% and 95% submission package reviews and will comply with the VA RFP. |
| 4. | If the final construction documents submission package is not complete a post submittal may be required the cost of which will be borne by the DB Team. |
| 5. | The approved final construction documents include such details that the project can be constructed and will be used for construction of the project. |
| 6. | See PART IV, D2 CONSTRUCTION PERIOD SUBMITTALS for Approved Construction Document distribution. |
| F. | Construction Drawing Preparation - Mandatory material and equipment schedules and details may be indicated either on the drawings or in the specifications, at the option of the DB team. The construction drawings shall include a coordinated set of the following: |
| 3. | Structural drawings including foundation/support plans for the new DA Tank. Including schedules, and details, including general notes and all calculations. |
| 4. | Architectural drawings including floor plans, demolition plans and route for removal of the DA Tank. |
| 6. | Plumbing drawings including new valves and fittings where needed. Including details, general notes, and all related calculations. |
| 7. | Boiler control drawings including, one-line flow diagrams, sequence descriptions, equipment schedules, and details, including general notes and all related calculations. |
| 8. | Local steam distribution drawings including demolition plans, system plans and profiles, piping plans, calculations and sections, equipment schedules, and details. |
| G. | Construction Specifications - Project specifications shall include specifications for all products, materials, equipment, methods, and systems shown on the construction drawings in accordance with standard professional practice and the VA RFP. The specification submitted for review shall include: |
| 1. | The name of the manufacturer, the product name, model number, or other identification as appropriate to clearly identify the product that will be used in the construction of the project; |
| 2. | Other data as appropriate to clearly identify the product that will be used in the construction of the project i.e. shop drawings, product data, and samples as required by the VA RFP documents; and |
| 3. | The required stamp of the licensed architect or engineer of record will be considered as certification of compliance with the RFP requirements. |
| H. | Design Requirements - Compliance with codes and standards. |
| 1. | Project design shall be in compliance with applicable standards and codes described in VA Program Guides and design materials included or referenced in the solicitation materials. |
| 2. | See Section E. Approved Construction documents, above, for required inclusion of design review comments. |
| 3. | In the design of new building and alteration work under this contract, the DB team shall consider all requirements (other than procedural requirements) of: |
| l. | Zoning laws: |
| 2. | Environmental and erosion control regulations; and |
| 3. | Laws relating to landscaping, open space, minimum distance of a building from the property line, maximum height of a building, historic preservation, and esthetic qualities of a building. Also, similar laws, of the State and local political division, which would apply to the building if it were not to be constructed or altered by the U.S. Government. |
| 4. | The DB team shall provide prompt, written notification to the Contracting Officer concerning conflicts with, or recommended deviations from codes, laws, regulations, standards, and opinions of review officials as described above. No work altering the scope of this contract shall be undertaken prior to receipt of written approval from the Contracting Officer. |
| 5. | The DB team shall advise the Contracting Officer of any variances with the applicable Department of Labor, Occupational Safety and Health Standards, for occupancy requirements. |
| I. | Quality Assurance/Quality Control: |
| 1. | To reduce design errors and omissions, the DB team shall develop and execute a QA/QC plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort. |
| 2. | Within 2 weeks of receipt of Notice to Proceed, the DB Team will submit a detailed QA/QC plan describing each QA/QC task that will be taken during the development of the various design submission packages and the name of the DB Team member responsible for QA/QC. |
| a. | Upon its completion each task shall be initialed and dated by the responsible DB Team member. |
| b. | A 100% completed QA/QC plan shall be submitted with the final construction document submission package. |
| D2. | Construction Period Submittals |
| A. | The DB contractor shall distribute a total of 5 sets of the approved construction documents prepared by the DB Team to the VA and RFP AE, as directed by the VA Project Manager. |
| B. | Other submittals - The DB team shall submit test results, certificates, manufacturer’s instructions, manufacturers’ field reports, etc. as required by the VA RFP specifications, to the VA R/E. |
| C. | Project record drawings - The DB team will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process as required by the RFP specifications. The project record drawings will be available for review by the VA COR at all times. |
| D. | Shop drawings and submittals - The DB A/E shall check government furnished and/or the DB construction contractor's shop drawings, detail drawings, schedules, descriptive literature and samples, testing labor-laboratory reports, field test data and review the color, texture and suitability of materials for conformity with the RFP Documents and construction documents. The DB A/E shall recommend approval, disapproval, or other suitable disposition to the VA RE. The VA RE will have final approval authority. The DB AE shall evaluate the submittals with reference to any companion submittals that constitute a system. When necessary, the DB A/E will request the DB Construction Contractor to submit related components of a system before acting on a single component. Should this procedure be inappropriate, the DB A/E shall review all prior submittals for related components of the system before acting on a single component. The DB A/E may be required to hold joint reviews with the VA technical staff and /or the RFP AE on complicated system submittals. The DB A/E shall notify the VA COR (RE) in writing of any and all deviations from the requirements of the construction documents that he has found in the submittals. |
| D3. | Project Close-Out |
| The DB team shall comply with the requirements in the “General Conditions”, Section 01001, and “General Requirements”, Section 01010, for submission of final RFP as built drawings, manuals, and other documents as noted. The contractor shall submit required as built drawings and specifications will be submitted in the same format as required for the construction documents. | |
| D4. | Site Visits and Inspections |
| As needed. |
- - - E N D - - -
A.1 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 0001 |
| Install controls and instruments as required to replace existing programmable loop controllers (AC Stations) which are obsolete and no longer able to be repaired. Controls for Boilers 1, 2 and 3 were upgraded and replaced with Hays Cleveland UPAC™ controls in 2011. Plant master controls were not upgraded at that time, and are to be upgraded with UPAC™ controls as specified in standard VA Sections 230911 for Instrumentation and Control for Boiler Plant, and Section 235011 Boiler Plant Mechanical Equipment. Other upgrades to the Main Control Panel are to also be completed as also identified in Section 230911. In additions, replacement of the deaerating feed water tank is also required in this project. Replacement of certain valves on the DA Tank is also required. Work includes general construction, alterations, mechanical and electrical work, utility systems, and removal of existing component structures and construction and certain other items. |
| 1.00 |
| JB |
| __________________ |
| __________________ |
| GRAND TOTAL |
| __________________ |
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 22.4 % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects.