4.29 DESIGN BUILD SPECIFICATIONS.docx
DOCX document 245 KB Posted
- Attached to
- Y1DA--Ramp Replacement Bldg 12 & 16 Federal contract opportunity
- Solicitation number
- 36C24623R0059
About this file
This document contains specifications for a design-build construction project. The project involves replacing ramps B12 and B16 at the Salem VA Medical Center located in Salem, Virginia. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6. Responses are due on July 6, 2023, with evaluations scheduled for July 21, 2023 and contract award anticipated on August 3, 2023. The cost range for the project is estimated between $250,000 and $500,000. The specifications provide requirements for the project schedule, shop drawings and submittals, samples, operation and maintenance documentation, VA review processes, and other standard construction documentation and compliance topics. Completion of the project is required within 180 days of the notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S05 RFI Questions _ Answers 6-27-2023.docx | DOCX document | |
| 36C24623R0059 0003.docx | DOCX document | |
| S05 RFI Questions _ Answers.pdf | ||
| 36C24623R0059 0002.docx | DOCX document | |
| Historic Resources Management Plan -NOV 1991.pdf | ||
| S04 Site Visit 5-31-2023.pdf | ||
| 36C24623R0059 0001.docx | DOCX document | |
| P09 SOW upd. 5-31-23.pdf | ||
| 36C24623R0059.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24623R0059
4.29 DESIGN BUILD SPECIFICATIONS
DESIGN-BUILD SPECIFICATIONS
SECTION 00 11 21
REQUEST FOR PROPOSAL TO DESIGN BUILD
Replace Ramps B12 & B16 658-23-103 Salem VAMC, Salem Virginia
| A. | PART I - General |
| A1. | Scope of Contract |
| Provide all labor, materials, tools and equipment, and design-build services necessary for the design and construction of a project described here in other specific tasks as further defined by this request for proposal (RFP). |
| A2. | Definitions |
| A. | Design-Build (DB) as defined by the US Department of Veterans Affairs (VA) is the procurement by the Government, under one contract, with one firm or joint venture (JV) for both design and construction services for a specific project. |
| 1. | Contracting Officer: The services to be performed under this contract are subject to the general supervision, direction, control, and approval of the Contracting Officer. |
| 2. | Project Manager: The Contracting Officer's representative responsible for administering contracts under the immediate direction of the Contracting Officer. |
| 3. | Resident Engineer: The Contracting Officer's authorized representative at the construction site. When more than one Resident Engineer is assigned to a construction project one is designated as being incharge and is called the "Senior Resident Engineer". The Resident Engineer is responsible for protecting the Government's interest in the execution of the construction contract work. His duties include surveillance of all construction work to assure compliance with the contract documents, interpretation of the contract documents, approval of changed work, approval of all submittals, samples, shop drawings, etc. The Resident Engineer may issue change orders to the Contractor within the limitations set forth in his delegation of authority from the Contracting Officer. |
| 4. | Design Build Contract: This term, as used herein, refers to the Contract(s) to perform the design and construction of the project. |
| 5. | Contractor: This term, as used herein, refers to the contractor under this contract or the DB team. |
| 6. | AE: This term, as used herein, refers to the ArchitectEngineer firm(s)that are a part of the DB team, also referred to as DB/AE. |
| 7. | RFP/AE: The firm(s) directly hired by the VA for the preparation of the RFP Documents and to provide other technical assistance to the VA. |
| B. | Selection Procedure - During the review of offers the VA may ask for additional information. The VA may initiate action to award a contract at any point after review of the offers. Therefore, offers should reflect the offeror’s best terms both from a technical and cost standpoint. See FAR 52.215-1, Instructions to Offerors - Competitive Acquisition (Jan 2017.) |
| C. | Tentative Schedule: |
| Request for proposal issued |
| 5/23/2023 |
| Pre-proposal conference |
| 5/31/2023 |
| Proposal submitted |
| 7/6/2023 |
| Evaluations |
| 7/21/2023 |
| Contract award |
| 8/3/2023 |
| Notice to proceed |
| 9/2/2023 |
| Construction completion/final inspection/ custody receipt |
| 2/29/2024 |
| D. | Schedule Objectives - The anticipated completion of this project is 180 days after the “Notice to Proceed” (NTP). The proposed schedule may be shorter than this, see Part III, C3, 3c. |
| A3. | Cost Range |
| The anticipated cost range for this project is between $250,000 and $500,000. | |
| A4. | Pre-Proposal Conference |
| A pre-proposal conference will be held on 5/31/2023. All offerors, consultants, subcontractors, manufacturers, and suppliers are invited to attend. The following agenda is furnished for this meeting: | |
| 1. | Open meeting; |
| 2. | Review of project and design-build method for construction contracting; |
| 3. | Specifications, Network analysis system, and project phasing; |
| 4. | General requirements, Solicitation Documents, and Offer Submission Procedure; |
| 5. | Review of "Buy American Act"; |
| 6. | Questions and answers; |
| 7. | Close; and |
| 8. | Site walkthrough – attendance is optional. |
*Please note that attendance for the pre-proposal conference and/or the site walkthrough is voluntary if your company plans to attend. Offerors shall wear surgical masks at all times in the facility.
A6. Selection Criteria and Weightings A. The Government will award a contract resulting from this solicitation to the responsible Offeror whose offer conforming to the solicitation will be most advantageous to the Government, price, and other factors considered. The following factors shall be used to evaluate offers Phase I: Factor I – Corporate Experience, Factor II – Technical Approach, Factor III – Past Performance (Client Satisfactions); Phase II: Factor I – Technical Solution, Factor II – Construction Management, and Factor III – Schedule. Responsibility determination will be made in accordance with FAR 9.1, Responsible Prospective Contractors.
B. BASIS FOR CONTRACT AWARD: This is a competitive Best Value Tradeoff (Tradeoff) source selection in which technically acceptable competing Offerors will be assigned a Past Performance Confidence Assessment Rating and will then be evaluated for Price fairness and reasonableness. All evaluation factors other than price, when combined, are significantly more important than price alone. The government reserves the right to award a contract to other than the lowest priced offer if the lowest priced Offeror is determined to have a performance confidence assessment of "Satisfactory Confidence" or lower. In that event, the Source Selection Authority shall make an integrated assessment best value award decision, where the perceived benefits of the higher priced proposal, and the rationale for tradeoffs, shall be documented in the contract file in accordance with FAR 15.406.C. Cost Proposal - Offerors are advised that if the technical proposals are essentially equal, the award will be made on the basis of the lowest cost.
*See Section M—EVALUATION FACTORS FOR AWARD
| B. | PART II - RESPONSIBILITIES |
| B1. | VA Team |
| A. | The VA team is comprised of the NCO6 Contracting Officer and Contract Specialist, COR and Project Engineer who will be located at the construction site, and VA Medical Center staff. |
| B2. | Design-Build Team: |
| A. | The DB team includes all J/V partners, consultants, and sub-contractors to the one firm. The DB team shall provide Architectural and Engineering disciplines for the preparation of construction documents, and construction contractor capabilities for the construction of the project. |
| B. | If the DB Team A/E and contractor are a J/V (not one and the same firm) engineering and other technical consultants shall be subcontractors of the J/V Architect - not the Design-Build construction contractor or sub-contractors. If the DB Team A/E and contractor are one and the same firm (not a J/V) those consultants shall be subcontractors of the DB ,firm not the construction subcontractors. |
| C. | The RFP documents are intended to define existing conditions, certain required items, and design parameters to be included in the project. It is the DB Team’s responsibility to complete the documents and construction in a manner consistent with the intent of the RFP documents within the required time period (contract length). |
| C. | PART III - PROPOSAL REQUIREMENTS |
| C1. | General |
| A. | Proposals shall be based on solicitation documents issued for RFP Solicitation Number 36C24623R0059. Proposals will be in the format stipulated elsewhere in this section. |
| B. | Proposals shall be received on or before the date listed on the SF 1442. There will be no public opening of the proposals. |
| C. | Submit proposals via email to: |
1. Bryant.Guerrant@va.gov, Contract Specialist
2. Emails are limited to ten (10) MB.
| D. | Technical and Cost sections of the Offers proposals will be evaluated independently. Offeror shall separately bind each section. Each section must therefore be labeled with the Offeror's organization, business address, and VA Project Number. Offerors shall name each section when attaching to an email. |
| C2. | Proposal Revisions (FAR 52.215-1) |
| A. | If determined to be necessary, proposal revisions will be requested from the proposals received. The Contracting Officer will identify those offerors, whose proposals are within the competitive range, considering the selection criteria identified in this section. Negotiations may be conducted with those offerors falling within the competitive range, after which proposal revisions will be requested. Those selected as within the competitive range will be given 7 calendar days to prepare their proposal revisions. Sealed proposal revisions will be submitted as per Part III.C1.C, above, except as noted below and will be due at a time and place to be determined. |
| B. | Offerors submitting proposal revisions will not be requested to re-submit any documents which are unchanged from their initial proposals. They should provide necessary changes to individual paragraphs, as briefly as possible, together with a table of contents, that clarifies where within the initial proposal the additional information or changed documents would be placed. Proposal revisions shall include a completed Standard Form 1442(Solicitation, Offer, and Award – Construction, Alteration, or Repair) and Standard Form 30 Amendment of Solicitation that acknowledges receiving all amendments, by number. A new bid bond shall be submitted only if the final proposal revisions offeror’s price proposal is greater than its initial price proposal. |
Phase I, Factor 1, Corporate Experience
1. The proposal shall address the following evaluation factors. Evaluation scores will be based, in order of importance, upon the criteria in Part I - Factor 1 consists of two subfactors: 1A, Project Experience and 1B, Personnel Experience. The evaluation of subfactors 1A and 1B are of equal importance to the determination of Factor 1 rating.
| 1. | Project Experience: |
| i. a. | Submit a maximum of five (5) completed construction projects within the last ten (10) years by a Design Build contract and/or contract similar in size ($250,000-$500,000) and scope to this project. (Design Build as defined by the VA, see article A1.2). The Offeror shall demonstrate their experience on relevant Design/Build and projects that are similar in size, scope, and complexity to the RFP. Scoring will be more favorable if both criteria are met. Indicate the number of design/build projects construction contractor and AE have completed together. Page limitation: One page (in 12-point Courier font) for each project. In describing project design and construction experience, provide the following information: |
| 1) | Project title, location and brief description including the building use (Medical Facility etc) and contracting method (design build, design bid construct, CM at risk etc). |
| 2) | Project owner and name and telephone number of owner’s contact person. |
| 3) | Project Design Architect and Engineers (consultants if utilized) and name and telephone number of contact person(s). Note each firm and employee also proposed for this solicitation. |
| 4) | Project Prime Contractor and Major Subcontractors and name and telephone number of contact person(s). Note each firm and managing persons (project manager/superintendent/foreman as the case may be) also proposed for this solicitation. |
| 5) | Project Statistics including start and completion dates (original vs. actual) for design and construction; cost (with brief explanation of what is included in the cost); square footage; foundation type; number of levels; and any awards (prizes) received. |
| ii b. Project Personnel Experience (Specialized experience and technical competence). The Offeror shall demonstrate the relevant experience of key project personnel. Page limitation: One page (in 12-point Courier font) for each person. | |
| 1) | Biographical data shall include the following: |
| a) | Name of individual. |
| b) | Company employed by. |
| c) | Company position title. |
| d) | Years with the company. |
| e) | Describe work experience with projects that; were completed by the design build process, were medical facilities and the company (by name) they worked for when involved in the project. |
| f) | An indication of which (if any) projects submitted under Corporate Experience (above) the individual participated in and what the individuals responsibility was for that project. |
| g) | An indication of which other individuals submitted under Project Personnel Experience this individual has worked with and the project they worked on together, noting if that project has been submitted under Corporate Experience (above). |
| h) | Position that the individual will hold in regard to this contract/project team, description of duties and what percentage of the individual’s time would be committed to the project during both the design and construction phases. |
| i) | Describe job related educational experience including degrees, certificates etc and granting institutions. |
| 2) | Supply this biographical data for key personnel for at least the following: (Note if one individual is proposed for more than one position listed): |
| a) | Overall Project Manager. |
| b) | (Architect) Design Project Manager. |
| c) | Construction Project Manager. |
| d) | Architect/Engineer Field Representative. |
Phase I, Factor II, TECHNICAL APPROACH Factor II - Technical Approach - The Offeror shall demonstrate the following, relevant to the subject procurement. Submission Requirements: Provide a brief narrative (page limitation: one page (in 12-point Courier font) for brief narrative) describing the Offeror’s method to manage the project to achieve design and construction design objectives as described in the RFP. Include at minimum all aspects covered in the scope of work. The following shall be included in the narrative:
1) Design Approach: Describe the techniques and methods for an efficient, effective design to include interface and coordination with the existing building systems, appropriate equipment sizing, and DDC controls integration.
2) Construction Approach: Describe the techniques and methods for this phased construction project to include coordination with the design packages, the synchronization of phases, and integration with the existing building systems.
b. Basis of Evaluation: Phase I, Factor 2, Technical Approach: The basis of evaluation will include the Offeror’s proposed technical approach for this design build project as defined in the solicitation submittal requirements. The assessment of the Offeror’s method to manage the project shall be used as a means of evaluating the Offeror’s ability to successfully meet the requirements of the RFP
Phase I, Factor iii, Past PERFORMANCE
Past Performance (Client Satisfaction) - Contact persons supplied for Phase 1, Subfactor 1A - Corporate Project Experience projects will be contacted by the Evaluation Panel and asked the questions listed below at 3.a.1)–3) and 3.b.1)– 4). The contact's responses will be scored based on the following elements with projects participated in by the Prime (Construction Contractor and Architect firm) being weighted more heavily than projects participated in by consultants, sub-contractors, and individuals If Offeror has PPIRS reports, printed copies of these reports shall be submitted for this factor and included on the CDs.
a. Client Overall Satisfaction with Project: Contact persons will be asked:
i. Did the project fulfill the requirements of the clients stated function?
ii. Was the team's response time to client’s questions acceptable?
iii. Was the staffing level consistent with the project size and complexity?
iv. Was communication of schedule and problem issues adequate and consistent?
v. Was there an established problem-solving routine? Would the client like to use this firm again?
vi. ii. Did the project require unexpected maintenance activity?
vii. iii. Have any latent defects been found?
In addition to the above, the VA may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/ affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror. While the VA may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
b. Basis of Evaluation: Phase I, Factor 3, Past Performance: The basis of evaluation will be the degree to which past performance evaluations and all other past performance information reviewed by the Government (e.g., FAPIIS, eSRS, performance recognition documents, and information obtained from any other source) reflect a trend of satisfactory performance considering a) a pattern of successful completion of tasks; b) a pattern of deliverables that are timely and of good quality; c) a pattern of cooperativeness and teamwork with the Government at all levels (task managers, contracting officers, auditors, etc.); d) tasks that are identical to, similar to, or related to the task at hand; e) and fiscal responsibility of Government funds. If the offeror lacks a record of relevant or available past performance history or there is no expectation of either successful or unsuccessful performance based on the offeror’s past performance record, the past performance evaluation will be given a neutral rating.
Phase Two Evaluation Factors (36.303-2)
1. Phase II, Factor 1, Technical Solution:
A. Submission Requirements: Provide detailed narrative (not to exceed 60 double-sided pages (or 120 single-sided pages in 12-point Courier font) of conceptual design addressing requirements of the RFP. The evaluation of the conceptual facilities design will be based on the criteria set forth in the project program contained in the RFP. Complying with and exceeding project program requirements by providing structural, architectural, and historically compliant construction will be most highly rated. Include in the discussion, but do not limit to the following:
i. Conceptual drawings shall be provided to supplement the narrative (i.e., floor plan, exterior elevation, and site plan).
ii. Physical building modifications. Indicate how disruptions to occupants will be minimized and how process will work to correct.
iii. Warranties
B. Basis of Evaluation: Phase II, Factor 4, Technical Solution: The basis of evaluation will include the narrative and conceptual drawings considering the extent to which the Offeror demonstrates a clear understanding of the architectural and engineering requirements of the project. The Government will evaluate the effectiveness of the construction and design team’s technical solution to determine the likelihood that the work will be performed in accordance with the technical requirements of the RFP.
2. Phase II, Factor 2, Construction Management: Factor 2 consists of three Subfactors: 2A: Ability to Staff Project; 2B: Management Approach; and 2C, Capability to Perform. The evaluation of subfactors 2A, 2B, & 2C are of equal importance to the determination of Factor 2 rating.
A. Subfactor 2A: Ability to Staff Project:
i. Submission Requirements:
a. Demonstrate the ability to staff the project for the scope of work required; describe how the Design-Build Team will be structured, i.e., how many firms are involved and the responsibility of each firm for this project. Indicate the extent to which resources and personnel will be drawn from various sources: in-house, subcontractor, and/or separate consultant firms. Describe D/B management approach, including but not limited to management of multiple designers and subs/trades working in parallel on several different facilities at one time.
b. Project Personnel Experience (Specialized experience and technical competence proposed in Phase I). The Offeror shall describe the job related and educational experience for each Phase I proposed key project personnel who will be assigned to this project including degrees, certificates, etc., and granting institutions
B. Subfactor 2B, Management Approach:
i. Submission Requirements: The Offeror shall demonstrate the following, relevant to the subject procurement.
a. Project Delivery Approach - Include statements concerning the proposed Design Period Peer Review technical/administrative by VA & RFP AE)
b. Quality Assurance/Quality Control Plan, see section 1.3, General requirements (01 00 00).
c. Project Organizational Chart and Narrative - Include team members submitted under Project Personnel Experience above. Clearly describe the prime responsible firm (or firms if a J/V) and individuals as well as the roles and responsibilities of individuals proposed as consultants and sub-contractors. Provide a list of all consultants and all proposed major subcontractors, including telephone number, address, and name of contact.
d. Offeror shall clarify its intended uses of the portions of the site indicated to be available to the contractor elsewhere in this RFP for materials staging, temporary trailer offices, employee parking, and other activities as shown in the design solution material.
C. Subfactor 2C, Capability to Perform:
i. Submission Requirements:
a. Provide the offeror's total bonding capacity (from Offeror’s surety), current available bonding capacity and expected available capacity in 2023/2024.
b. Provide the offeror's current workload and availability of staff proposed in Phase I, Factor 2 Project Personnel Experience to manage the project. Include project schedules for current and pending projects, as well as the anticipated impact of this project on those schedules and staffing plans.
D. Basis of Evaluation: Phase II, Factor 5, Construction Management: The basis of evaluation will include the assessment of the Offeror’s ability to staff, Offeror’s management approach, and Offeror’s capability to perform the project as defined in the solicitation submittal requirements. The assessment of the firm and proposed personnel’s experience will be used as a means of evaluating the relative capability of the Offeror’s personnel to successfully meet the requirements of the RFP.
3. Phase II, Factor 3, Schedule:
A. Submission Requirements:
i. The progress schedule will be in a time scaled bar Gantt chart format. The horizontal axis will be scaled for time beginning with the Notice to Proceed and concluding with contract completion. The vertical axis will show the milestones and major portions of the contract work. All schedule items will show a start date and a completion date. The detailed schedule will indicate specific tasks with dates for each step of the process.
ii. Design Period: The design period sub periods (i.e., first and second reviews, other meetings, internal QUALITY ASSURANCE /QUALITY CONTROL plan reviews, etc.).
iii. Construction Period: Mobilization; Demolition method and sequencing; Demolition; Preparing areas for construction; Site utilities, Tests, and final inspection. Indicate each Phase.
iv. General Project Delivery Schedule and Narrative - Show relationships between construction document development/completion (including required review activities) and construction activities for, at a minimum utility relocation, excavation, substructure, structure, exterior façade, and site development.
v. Schedule shall indicate all elements of the design and construction timeline, from notice to proceed (NTP) (in order to establish a common baseline among all offerors, assume NTP date of February 01, 2022) to contract completion, including but not limited to preconstruction meetings and submittals, design, and any SHPO permits and approvals, utilities, demolition, material lead times, utility installations, abatement, testing/adjusting/balancing, commissioning, construction and postconstruction submittals, close-out.
vi. Short Schedules - The Offeror will provide a written commitment as to the time frame (number of days after receipt of the notice to proceed) within which the Offeror will guarantee completion. The maximum anticipated completion of this project (including design and construction of the entire project) is indicated in Section A2, D. Shorter schedules (must include required Government review times), if obtainable, will receive more favorable scoring. The offeror’s schedule will establish the contract completion date and will be incorporated into the award. The assessment of liquidated damages will be based on that date.
B. Basis of Evaluation: The basis of evaluation will include the Gantt chart schedule considering the extent to which the Offeror demonstrates a clear understanding of the architectural and engineering requirements for the construction period and general project delivery. The Government will evaluate the likelihood that the work will be performed in accordance with the stated schedule given the technical requirements of the RFP.
4. Phase II, Non-Technical Factor 1, Price A. Submission Requirements: The offeror is required to prepare and submit the following price documents in a SEPARATE SEALED ENVELOPE MARKED: “PRICE PROPOSAL – DO NOT OPEN IN MAILROOM.” The price proposal shall be submitted in a separate binder from the technical proposal. The price proposal shall be tabbed using the following list:
PRICE PROPOSAL BINDER SUBMITTAL CHECKLIST (One original and two copies)
i. RFP: VA101-13-R-0121
ii. Project: BUILDINGS 1 & 2 RENOVATION, PROJECT # 520-317U INTRO PAGE
iii. First page of TAB 1 MUST clearly indicate:
a. Name and Address of Proposer
b. Business Arrangement (Joint Venture or Teaming Arrangements clearly identified)
c. Contact Name and Phone Number
d. Email Address
e. DUNS Number
f. CAGE Code
g. Tax Identification Number
B. Basis of Evaluation: Phase II, Factor 1, Price: Price will be evaluated on the basis of its realism, and/or reasonableness, and acceptability to the Government subject to availability of funds. Pricing shall be entered onto the Offer Schedule located within the SF1442. Analysis will be performed using one or more of the below techniques to ensure a fair and reasonable price: (a) Comparison of proposed prices received in response to the RFP. (b) Comparison of proposed prices with the Independent Government Cost Estimate. (c) Comparison of proposed prices with available historical information. (d) Comparison of market survey results.
| D. | PART IV - POST AWARD REQUIREMENTS |
| D1. | Construction Document Preparation: |
| A. | Design Review Submissions: |
| 1. | The Design-Build Team A/E (DB A/E) shall prepare and submit complete construction documents for review and approval by the VA in accordance with standard professional practice, the US Department of Veterans Affairs RFP (VA RFP), and prevailing codes. |
| 2. | The documents may be divided into multiple review submission packages. The VA will review as many as six (6) package submissions (examples: demolition, civil, architectural, structural, mechanical, Electrical, plumbing etc.) to facilitate the start of construction. |
| 3. | All submission packages will be reviewed at (50%) and (95%) completion stages. The (95%) review submission packages will incorporate the final review comments from the (50%) review. If any package is not complete for the required stage a post review may be required the cost of which will be borne by the DB Team. |
| 4. | Each review submission package shall include 2 hard copy sets and 2 sets sent electronically in PDF and AutoCAD 2022 formats. The package will include an index of drawings (by sheet number and tittle) and specifications (by section number and tittle) submitted. The packages will be distributed to the VA Project Manager, the VA Medical Center, RFP A/E, VA Resident Engineer and others as determined to be appropriate by the VA Project Manager. |
| B. | Design Review Meetings: |
| 1. | A review meeting to resolve design issues will be held for each design review package submitted. The meeting will include discussion of VA comments on functional relationships and technical peer review comments (by others). |
| 2. | Participants will include RFP A/E, VA Staff and DB team members as appropriate for the specific package to be reviewed and others. The DB team members will each allow for (1) full day for each discipline/package design review meeting. DB team management will be present at each review meeting. |
| 3. | The DB team shall allow a minimum of ten (10) working days for each review cycle. A cycle includes: |
| a. | The VA’s receipt of the design review submission package. |
| b. | The review meeting. |
| c. | DB teams receipt of comments from the VA, either electronically, by fax, or by hard copy delivery. |
| 4. | Coordination of the review meeting schedules will be the responsibility of the VA Project Manager (for the VA and RFP AE) and the DB Team Project Manager (for the DB Team). See section H. Quality Assurance/Quality Control. |
| C. | Electronic Media: |
| 1. | Design review submission drawings and final Construction Document submission drawings will be executed in electronic format AutoCAD version 2022. |
| 2. | The drawings included in the VA RFP will be available to the DB team in electronic format in AutoCAD version 2022 for use in preparing the construction drawings. Since data stored on electronic media can deteriorate undetected or be modified without the RFP Architect/Engineer’s knowledge, the CADD drawing files are provided without warranty or obligation on the part of the RFP Architect/Engineer as to accuracy or information contained in the files. The user shall independently verify all information in the files. Any user shall agree to indemnify and hold the RFP Architect Engineer harmless from any and all claims, damages, losses, and expenses including, but not limited to, attorney’s fee arising out of the use of the CADD drawing files. |
| 3. | Design review submission specifications and other 8 1/2 by 11 formatted material and final Construction Document submission specifications and other 8 1/2 by 11 formatted material will be executed in electronic format Microsoft Word. |
| 4. | The specifications included in the VA RFP shall be available to the DB team in electronic format in Microsoft Word, for use in preparing the construction specifications. Since data stored on electronic media can deteriorate undetected or be modified without the RFP Architect/Engineer’s knowledge, the CADD drawing files are provided without warranty or obligation on the part of the RFP Architect/Engineer as to accuracy or information contained in the files. The design builder shall independently verify all information in the files and shall agree to indemnify and hold the RFP Architect Engineer harmless from any and all claims, damages, losses, and expenses including, but not limited to, attorney’s fee arising out of the use of the electronic files. |
| 5. | The construction record drawings shall be completed in AutoCAD. |
| 6. | Construction shop drawings are not required to be completed in AutoCAD. |
| D. | Professional Licensing: |
| 1. | The DB A/E who prepares the construction documents shall be a professional architect or engineer licensed in the state in which the design work is completed. |
| 2. | The professional seal indicating such license by the state shall appear on the final construction documents. The architect whose seal is shown will be known as the Architect of Record. The DB A/E shall certify compliance with the VA RFP and all applicable codes. |
| E. | Approved Construction Documents: |
| 1. | The final construction document submission package will be submitted by the DB team for approval by the VA after completion of the 95% review cycle for the final package to be submitted by the DB team. The VA will have 5 days to take approval action. |
| 2. | The final construction documents submission package will include a full set of construction documents including all disciplines/packages. |
| 3. | The final construction documents submission package will incorporate all VA supplied comments from the earlier 30% and 95% submission package reviews and will comply with the VA RFP. |
| 4. | If the final construction documents submission package is not complete a post submittal may be required the cost of which will be borne by the DB Team. |
| 5. | The approved final construction documents include such details that the project can be constructed and will be used for construction of the project. |
| 6. | See Part IV, D2 Construction Period Submittals for Approved Construction Document distribution. |
| F. | Construction Drawing Preparation - Mandatory material and equipment schedules and details may be indicated either on the drawings or in the specifications, at the option of the DB team. The construction drawings shall include a coordinated set of the following: |
| 1. | Civil engineering drawings including demolition plans, grading and drainage plans, paving plans, utility plans, schedules calculations and details. |
| 2. | Landscape drawings including demolition plans, landscape plans, plant schedule and list, special landscape elements, proposed materials to be used for each special landscape element, calculations and details. |
| 3. | Structural drawings including foundation plans, framing plans, schedules, and details, including general notes and all calculations. |
| 4. | Architectural drawings including floor plans, building elevations, building sections, wall sections, reflected ceiling plans, stair details, toilet and bath details, door schedules and details, window schedules and details, room finish schedules, auto transport and other details. |
| 5. | Asbestos abatement drawings including site demolition plans and floor plans indicating asbestos abatement method. |
| 6. | Parking Control drawings including paving plans, schedules calculations and details for the parking fee collection/parking control system for the entire Salem VAMC Campus. |
| G. | Construction Specifications - Project specifications shall include specifications for all products, materials, equipment, methods, and systems shown on the construction drawings in accordance with standard professional practice and the VA RFP. The specification submitted for review shall include: |
| 1. | The name of the manufacturer, the product name, model number, or other identification as appropriate to clearly identify the product that will be used in the construction of the project; |
| 2. | Other data as appropriate to clearly identify the product that will be used in the construction of the project i.e., shop drawings, product data, and samples as required by the VA RFP documents; and |
| 3. | The required stamp of the licensed architect or engineer of record will be considered as certification of compliance with the RFP requirements. |
| H. | Design Requirements - Compliance with codes and standards. |
| 1. | Project design shall be in compliance with applicable standards and codes described in VA Program Guides and design materials included or referenced in the solicitation materials. |
| 2. | See Section E. Approved Construction documents, above, for required inclusion of design review comments. |
| 3. | In the design of new building and alteration work under this contract, the DB team shall consider all requirements (other than procedural requirements) of: |
Zoning laws:
| 1. | Environmental and erosion control regulations; and | |
| 2. | Laws relating to landscaping, open space, minimum distance of a building from the property line, maximum height of a building, historic preservation, and esthetic qualities of a building. Also, similar laws, of the State and local political division, which would apply to the building if it were not to be constructed or altered by the U.S. Government. | |
| 3. | The DB team shall consult with appropriate officials of the Federal, state, and political subdivision, and submit plans under the rules prescribed by those reviewing authorities. The A/E and VA shall give due consideration to the recommendations of the referenced building officials. VA will also permit inspection by the officials described above during the construction period in accordance with the customary schedule of inspections in the locality of the building construction. Such officials shall provide VA with a copy of the schedule before construction begins or give reasonable notice of their intention to inspect before conducting an inspection. | |
| 4. | The DB team shall provide prompt, written notification to the Contracting Officer concerning conflicts with, or recommended deviations from codes, laws, regulations, standards, and opinions of review officials as described above. No work altering the scope of this contract shall be undertaken prior to receipt of written approval from the Contracting Officer. | |
| 5. | No action may be brought against the DB Team or VA and no fine or penalty may be imposed for failure to carry out any of the previously described recommendations of Federal, state, or local officials. VA and its contractors, including RFP A/E, shall not be required to pay any amount for any action taken by a state or political division of a state in carrying out functions described in this article, including reviewing plans, carrying out on-site inspections, issuing permits, and making recommendations. | |
| 6. | The DB team shall advise the Contracting Officer of any variances with the applicable US Department of Labor, Occupational Safety and Health Standards, for occupancy requirements. | |
| I. | Quality Assurance/Quality Control: | |
| 1. | To reduce design errors and omissions, the DB team shall develop and execute a QA/QC plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort. | |
| 2. | Within 2 weeks of receipt of Notice to Proceed, the DB Team will submit a detailed QA/QC plan describing each QA/QC task that will be taken during the development of the various design submission packages and the name of the DB Team member responsible for QA/QC. | |
| a. | Upon its completion each task shall be initialed and dated by the responsible DB Team member. | |
| b. | A 100% completed QA/QC plan shall be submitted with the final construction document submission package. |
| D2. | Construction Period Submittals |
| A. | The DB contractor shall distribute a total of 2 sets of the approved construction documents prepared by the DB Team to the VA and RFP AE, as directed by the VA Project Manager. |
| B. | Other submittals - The DB team shall submit test results, certificates, manufacturer’s instructions, manufacturers field reports, etc. as required by the VA RFP specifications, to the VA R/E. |
| C. | Project record drawings - The DB team will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process as required by the RFP specifications. The project record drawings will be available for review by the VA Resident Engineer at all times. |
| D. | Shop drawings and submittals - The DB A/E shall check government furnished and/or the DB construction contractor's shop drawings, detail drawings, schedules, descriptive literature and samples, testing labor-laboratory reports, field test data and review the color, texture and suitability of materials for conformity with the RFP Documents and construction documents. The DB A/E shall recommend approval, disapproval, or other suitable disposition to the VA RE. The VA RE will have final approval authority. The DB AE shall evaluate the submittals with reference to any companion submittals that constitute a system. When necessary, the DB A/E will request the DB Construction Contractor to submit related components of a system before acting on a single component. Should this procedure be inappropriate, the DB A/E shall review all prior submittals for related components of the system before acting on a single component. The DB A/E may be required to hold joint reviews with the VA technical staff and /or the RFP AE on complicated system submittals. The DB A/E shall notify the VA Resident Engineer (RE) in writing of any and all deviations from the requirements of the construction documents that he has found in the submittals. |
D3. Project Close-Out
The DB team shall comply with the requirements in the “General Requirements”, Section 01 00 00, for submission of final RFP as built drawings, manuals, and other documents as noted. VA requires as built drawings and specifications to be submitted in the same format required for the construction documents. The DB team shall comply with the requirements in FAR 4.804 Closeout of Contract Files, for submission of final RFP as built drawings, manuals, and other documents as noted. Required as built drawings and specifications will be submitted in the same format required for the construction documents.
D4. Site Visits and Inspections
During the construction period the DB A/E shall make weekly visits to the project site when requested by the Resident Engineer (RE). The Resident Engineer (RE) may also request visits for special purposes. Only registered architects and engineers thoroughly familiar with the project may make these site visits. The Resident Engineer (RE) has the prerogative to determine the professional discipline(s) required for any visit. The DB A/E shall observe the construction, advise the Resident Engineer of any deviations or deficiencies or solutions to issues discussed. A site inspection report which includes the purpose of the inspection, items reviewed, deficiencies observed, recommendations and additional actions required, shall be furnished to the Resident Engineer (RE) within three workdays following the site visit date.
- - - E N D - - -
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for 658-23-103 Replace Ramps B12 & B16 as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Contracting Officers Representative (COR).
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, Replace Ramps B12 & B16: Work includes general construction, alterations, walks, grading, drainage, masonry construction, necessary removal of existing structures and construction and certain other items.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of patients and staff is permitted at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued by the COR for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR .
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
G. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied by patients, except as permitted by COR.
H. Do not store materials and equipment in other than assigned areas.
I. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
J. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor.
3. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
K. Construction Fence: Before construction operations begin, Contractor shall provide a modular panel temporary chain link construction fence, 6 ft minimum height, around the construction area. Provide gates as required for access with necessary hardware, including hasps and padlocks. Remove the fence when directed by COR.
L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 50 degrees F at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for preinspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
M. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc.