36C24618R0669-0003001.xlsx
XLSX spreadsheet 29 KB Posted
- Attached to
- Upgrade Generator Capacity H. H. McGuire VAMC 1201 Broad Rock Blvd. Richmond, VA Federal contract opportunity
- Solicitation number
- 36C24618R0669
About this file
36C24618R0669 0003 RFI Responses.xlsx
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| # | QUESTION | RESPONSE | COMMENTS |
| 1 | The current specifications require previous experience for projects in the $500,000 Range. Is it the governments expectation that the contractor who is awarded this project has generator replacement and hospital experience. Especially experience with keeping a building up and running and coordinating shutdowns with the owner. | I do not know what “current specifications” you are referring to. |
If you’re referring to the “EVALUATION FACTORS FOR AWARD”, One of the sub-factors under “PART I – TECHNICAL CAPABILITY”, states :“CRITERIA: Offeror must provide an organizational block identifying key on-site personnel with a description of their work experience relating to projects similar in scope (commercial building remodel/renovation; minimum threshold value of $500,000) to those expected under this proposal. Additionally, the Offeror must provide a narrative describing the organization’s program management policies, procedures, and processes, along with the performance history of similar scope and sized projects (commercial building remodel/renovation; minimum threshold value of $500,000), the Offeror’s Site Superintendent, Quality Assurance Manager and Safety Manager have accomplished.”
The minimum threshold value is $500,000; nowhere is “projects in the $500,000 Range” stated. The RFP clearly & thoroughly describes the project requirements and evaluation factors for contract award.
| 2 | As this is a federal government facility improvement project, will sales tax be applicable or not? | Offerors shall include all federal, state and local taxes shall be include in their price proposal. |
| 3 | The RFP states that offerors must supply an offer guarantee, OSHA certification/logs, and Experience Modification Rates. Should these items be bound in the technical or price proposals or bound separately? If in the technical proposal do these Items count towards the page limits of the proposal? | CO WILL RESPOND |
| 4 | Based on the details needed in the above RFI's for accurate pricing, we are respectably requesting a 30 day extention to the bid proposal due date. | CO WILL RESPOND |
| 5 | The contract documents do not define or address this project's Commissioning Requirements. Please provide a Commissioning Specification and a Commissioning Script for the project. | CO WILL RESPOND |
| 6 | Section 01 00 00; FAR 52.236-4 C. Please provide contact information for Engineering Officer at VA medical Center for obtaining "soil report", Civil General Note 1/C-001 mentions a geotechnical report. Will this be provided to the contractor for review ? | CO WILL RESPOND |
| 7 | Joint commission testing requires a larger load bank than the previous answer RFI stated. Can you verify the load bank size required for this bid is 2000KW at 13.2KV? | 2000KW Permanent Load Bank is required at 13.2KV. Load bank must be able to communicate and be controlled via the OIT on the new and existing paralleling switchgear. |
| 8 | Please reference these Sections: 26 23 13 2.1 G5, 26 23 13 2.1 I, 26 23 13 2.1 J & 26 23 13 2.3 A and confirm the following: As the new parallel control system is integrated into the existing chiller system, the HMI will display: All the features as described in the aforementioned paragraphs and all one lines and ATS functionality. These features will on the new master control screens, existing master control screens and the new remote screens. The intent will be for an operator from any HMI to see the functionality of the total system. Is this correct? | Yes. |
| 9 | Please reference Section 26 05 41 2.1 Section 03 30 00 and Drawing ES102: Construction Note 2 on the referenced drawing requires that we “… new manhole shall be cast in place around existing feeder.” | See responses in a, b, c below. |
| 9a. | Please provide a detail for the new cast in place manhole. | See detail provided as an attachment. |
| 9b. | Please provide an approximate depth for the new cast in place manhole. | Approximately an eight foot depth. Field verify depth and location of existing electrical feeder prior to install of new cast-in-place manhole. |
| 9c. | Will the owner allow for an electrical outage for safety during the installation of the new cast in place manhole? | No. There will be no outage allowed for this work. |
| 10 | Please reference Sheets ES102- ES105: The underground conduit containing the fiber optic cabling is shown without manholes or pull boxes. One should be installed near the new switchgear enclosure, one should be installed behind the existing switchgear enclosure, and one should be installed at the bend to the north of the gate. Does the designer agree? | Yes. We agree. |
| 11 | Please provide a specification for the Fiber Optic Cabling. | See specification for fiber optic cabling provided as an attachment. |
| 12 | Please reference drawing E-601 electrical one-line diagram: MV Cable Schedule # 1 Please provide the detail of existing 15KV AL cable. (Contract specification section 26 05 13(MV cables)para 2.1B. state that the new MV cable shall be single conductor stranded copper conforming to ASTM B3). Please provide type of connection (whether bus duct or cable) between new generator (2MW 132.2KV) & Generator paralleling switchgear breakers. If it is a bus duct or cable please provide us the detail drawing & specification. | The existing cable shall be investigated by the contractor. Connections will be via conduit and cable. |
| 13 | Please reference drawings ES-102 through ES-104 Electrical Site Plan New Work: Construction Note 3: Please clarify whether the contractor have to account for filling generator fuel tank (13,400 Gallons capacity) for testing purpose only: 138GPH x 8 hours: 1,110 Gallons or fill full tank: 13,400 Gallons. | Contractor is responsible for filling the generator fuel tank for testing purposes, only. |
| 14 | Please reference drawings E-701: Sequence of Operation: The sequence of operation for the paralleling switchgear is not indicated on the drawing or in the specifications. Is this available? | Yes. |
| 15 | Please reference drawing CD103 demolition note 6 which states that we are to remove bollards, key pads, sliding gate and posts as necessary to allow clearance for new equipment to enter complex. Bollards, key pads, sliding gate and posts are required to be reinstalled after equipment is on site. However, there are no drawings or photographs that determine the extent of work for removal and reinstallation. Can you please provide ? | See pictures attached. |
| 16 | There are three low voltage ATS’s shown on the one lines. We assume they are existing, but would like to confirm this. | Yes. They are existing. There are more than three transfer switches. These are shown as typical for each. |
| 17 | The bid specs for the permanent load bank is not shown. Is this available. We are assuming a 600 kW resistive load bank for 30% testing, but would like clarification of this. | Duplicate question. See response to Question #7. |
| 18 | Seismic rating is mentioned in the switchgear and generator set. Will seismic certification be required at this site? | Yes. |
| 19 | Will the factory tests on the generator sets also be witnessed by the owner? The specifications do not request this, but the switchgear does. | Owner reserves the right. |
| 20 | Section 263213.2.12.B Is this a description of a paralleling breaker mounted in the paralleling switchgear, or does this breaker need to be mounted inside of the genset enclosure? The one line shows only the breakers in the switchgear. | 13.2KV breakers in each genset enclosure are required. |
| 21 | Section 263213 2.13.3.f and g reference a daytank and main tank. Is there a main tank on the site that the sub base fuel tanks are drawing fuel from, or should the reference to the daytank be deleted? | Genset sub base tanks will be provided. No external tank will be used. |
| 22 | The generator enclosure specification does not reference what material it should be constructed from. Should this be aluminum or steel | Manufacturer to provide standard aluminum or galvaneal. |
| 23 | In Spec Section 26 32 13, Engine/Generators, in Part 1.H (Page 6), UL2085 is referenced, but this conflicts with E-501 drawing which calls out UL 142. Please clarify that UL142 will be the specified standard? | UL142 base tanks are required. |
| 24 | In Spec Section 26 32 13, Part 2 2.1 C1 (Page 6) Power rating is stated as Emergency standby , however C3 says “continuous.” Please confirm the rating requirement is for standby rated as defined in ISO 8528. | Emergency Standby is required. |
| 25 | In Spec Section 26 32 13, Part 2.12A (Page 12): Please clarify that A is N/R as a spec item. The MV generator breaker would be mounted in the PSG | Duplicate question. See response to Question #20. |
| 26 | In Spec Section 26 23 13, Generator Paralleling Controls, Part 2.3 A (Page 10): The existing ATS’s (LS,CR,EQ) are identified on drawing E601. As the system is designed for transition to standby generation upstream of the existing ATS’s, their purpose seems to be as a stop gap means for termination relative to B503 future work. Please clarify the intent on the ATS’s remaining in service? | The existing ATS shown are examples of the transfer switches currently installed and all ATS remain. |
| 27 | In Spec Section 26 23 13, Part 3.1 B: “Mount generator paralleling controls on concrete slab”. There is conflict between the Paralleling switchgear enclosure as it defined here and on Drawing E-501 a drop-over type enclosure with “base” and in Spec Sec. 26 13 13 (Page 5) 2.1 where a “walk in Protected Aisle” is specified, and further conflicts with (Page 7) 2.2 B, and Page 8 item 4 “shall be provided with a steel floor.” Please clarify the required construction of the floor for the PSG/Switchgear enclosure. | Pre- fabricated and assembled switchgear enclosure with full sub base frame and steel floor with no slip coating will be provided similar to chiller switchgear house currently at site and shown during walkthrough. |
| 28 | In Drawing E-601, there is a load bank symbol shown. There is not permanent load bank specified. Please clarify. | Duplicate question. See response to Question #7. |
| 29 | In the Generator Set Spec. 26 32 13, Part 3.2 Acceptance Checks & Tests: | See responses in a, b, c below. |
| This requires load bank(s) for 13.2 KV testing, (resistive) 6 hrs total , with 2 hrs at 100% load, (4) hrs at 80 % load. In this section, the narrative weaves back and forth between the load bank as a load source and actual building load as the load source (e.g., paragraph d page 21 “perform the on-site installation acceptance test for the existing occupied building in accordance w/ NFPA 110 …) Considering the above, please clarify the following: | See responses in a, b, c below. | |
| 29a | Is each generator to be individually tested at its 100 % rating for the 6 hr duration? | Yes. |
| 29b | K. Parallel Operation test: How much load bank capacity is required? We assume 2000 based on earlier. Is this correct ? | Duplicate question. See response to Question #7. |
| 29c | K.1. This references measuring reactive load, but resistive load bank is earlier specified. Please clarify. | Duplicate question. See response to Question #7. |
| 30 | On Page 23, Para 4 states “connect each engine generator is parallel with the utility for 15 minutes, however the system is not specified as that mode of operation. We request clarification on sequence of operations as well as testing parameters. | System design is closed transition with utility transfer time required less than 100ms. See newly published sequence of operation for full sequence and testing parameters. |
| 31 | In reference to Section 01 33 32: What are the model and serial numbers of existing switchgear equipment? | This information could have been obtained at site walkthrough. |
| 31a | What is the specification between the new master controller and existing ASCO switchgear? | Reference specification 262313 2.1.I. New switchgear master PLC and existing switchgear master PLC will be redundant of each other. Modification to existing PLC required for this operation. |
| 31b | What is the existing sequence of operations for the switchgear? | The existing chiller plant switchgear allows closed transiton softload with utility source. This operation must be modified to include only momentary closed transition (100ms or less). |
| 31c | What are the distances from old gear to new gear location? | Bidder to determine based on route of conduit they install and could have been verified at walk through. |
| 31d | What is the pitch of the existing Caterpillar gensets on location? | 0.667, 2750 frame, two bearing, form wound. |
| 32 | Please reference drawing S-101, plan key note 7. Please provide details for new stair and platform. | Design/details provided by generator supplier. This is a performance specified, pre-fabricated stair and platform. The details of construction would vary manufacturer to manufacturer. The intent is to match the existing stairs and platforms and the design requirements are in the specifications. The manufacturer shall submit shop drawings detailing the assembly of the stair and platforms for approval. |
| 33 | Please reference drawing ES-102, plan notes 6,7 and 9. How many conduits are in each of the existing runs, which have to be relocated? Please provide more details for this work. | Contractor shall verify existing conduit runs. For pricing purposes Note 6 contains communications ductbank, Note 9 is a 277V lighting circuit in PVC and Note 7 is a 120V circuit in PVC from Pole #343D101. Coordinate with Dominion on this work. |
| 34 | Div. 26, ES102, E-601; No size or specification is furnished for the loadbank. Please provide a Loadbank Size and Specification. | Duplicate question. See response to Question #7. |
| 35 | ES102, E-601; No Grounding Plan is shown on the drawings. Please provide a Grounding Plan. | See grounding plan provided as part of the attachments. |
| 36 | ES102, E-601; The drawings do not indicate the size of the existing Utility feeder UTIL-1. Please provide the conductor size for for UTIL-1. | Duplicate Question. See response to Question #12. |
| 37 | ES102, E-601; The following breakers in Gen Paralling Gear are indicated as Spare or Future: UTIL-2, A2, A3, B4, B5, B6, G5, G6. No pathways are shown exiting the GP Gear for these breakers. Should pathways for these breakers be provide? If yes, then please indicate what pathway(s) should be provided for each on drawing ES102. | Yes, pathways should be provided for future breakers. Contractor shall stub conduit outside of generator switchgear and cap for future. |
| 38 | ES102, E-601, E-501; Neutral Ground Resistors for the Generators are not Shown or Specified. The 'Generator and Enclosure Electrical Equipment' list on sheet E-501 references a "Connection for Customer Neutral Grounding Resistor". Should NGR's be provided for the Gens? If yes, then please show the NGR locations on drawing ES102 and provide a NGR Specification. | NGR shall be provided matching in type and size NGR’s currently installed in existing units, bidders could have verified at site walkthrough. |
| 39 | ES102; Notes 6, 7 and 9 on drawing ES102, and note 6 on CD101 each show an existing underground utility that is to be relocated (lowered). These 2 EUC's and one EUE are not define. Please define what each of these utilities are (duct bank, direct burial, conduit, fiber) what each serves, difine any critical loads or application that will be impacted by the relocation. We have reviewed SOLICITATION #36C24618R0669 Amendment #1 06/21/2018 RFI response #4 under #3 RFI responses this does not provide the detail requested for arcurate bidding. | Duplicate Question. See response to Question #33. |
| 40 | Section 26 05 73; Section 26 05 73 requires an Overcurrent Protective Device Coordination Study. Please confirm the Government will furnish an up-to-date Study to the Contractor to be use to develop a new Study for this Contract. Please provide a clear definition of equipment to be included in new coordination study. | Confirmed. Equipment new as shown on one line diagrams to be included in new coordination study. |
| 41 | Section 26 23 13 paragraph 2.4 Paralleling Operation states: "REFERENCE SEPARATE SEQUENCE DOCUMENT." E-701 states "Design-not for construction" and does not depict any "Sequence of Operations" please provide a detailed sequence of how the system is intended to operate in all modes. | Sequence of Operations will be provided as part of the RFI responses. |
| 42 | Section 26 23 13 paragraph 2.3 A specifies integration to existing switchgear and PLC and DI/O upgrades. Please define "upgrade" is this a replacement of hardware, or a software and logic upgrade to facilitate new "Sequence of Operations". | Existing switchgear PLC must be modified for redundant operation with new switchgear. The switchgear must also be modified to include redundant I/O |
| 43 | Section 26 23 13 paragraph 2.3 A specifies intetration to existing ATS's. Please define what functionallity, control and or monitoring is required of the ATS. Please define what has to be reported back to new switchgear. Are hardware upgrades required for this section. | All existing ATS will be fully integrated into HMI system of new and existing chiller plant gear. Bidders responsibility to verify existing ATs capabilities and modify if required. |
| 44 | Section 26 23 13 paragragh 2.3 A requires integration to existing ATS's. Please define manufacture,size,designation and location of all ATS's covered by this section. | Bidders responsibility to verify existing ATS, availability and access at walk through was provided. |
| 45 | Section 26 32 13 paragraph 2.12.A specifies an engine mounted circuit breaker. ES-601 does not depict and engine mounted circuit breaker, please confirm there is not a breaker located in the generator enclosures. | Duplicate question. See response to Question #20. |
| 46 | Section 26 13 13 paragraph 3,4 and 5 specifies reqirement for protection. Please provide a protective relay ANSI designation for all funtions and protections required for Utility and gererator main circuit breaker, and required protection dictated by Dominion for inter-tie agreement. | Bidders responsibility to provide Dominion required devices. |
| 47 | Section 26 23 13 paragraph 2.2 A specifies 2@ 24'' annuciator panels to be installed. Please specify location for remote annuciators. | One will be located in the electric shop and one will be located in the boiler plant. Coordinate with COR for exact locations. |
| 48 | Section 26 13 13 paragragh 2.1.A.1 Specifies a weather proof outdoor type switchgear assembly with metal housing and walk in protective aisle. Drawing E-501 details NEMA 1 indoor switchgear with a drop over house. Please specifiy what is required a NEMA 3R aisle construction or NEMA 1 switchgear with drop over house. | Fully assembled switchgear house similar to chiller plant existing switchgear house will be provided see drawing E501 showing structural base with lifting rings and switchgear enclosure electrical equipment. |
| 49 | Section 26 13 13 paragraph 2.2.A.2.a Specifies an individual cubicle for each breaker. Drawing E-601 depicts multiple cubicles with 2 breakers, please confirm that two breakers in one cubicle is acceptable. | Confirmed. Two breakers in one cubicle is acceptable in the designations as indicated on E-601. |
| 50 | Drawing E-601 GPS elevation shows Life safety breaker B-2 and Critical breaker B-1 in the same verticle section. Unless critical load B-1 qualifies as NFPA-70 article 701 Leagally required standby it can not be in the same verticle section per 700.10(B)(5)c.. Please confirm ctirtical load B-1 meets NFPA 70 article 701 requirements. | Critical loads meet NFPA 70 Article 701 requirements. |
| 51 | Section 26 13 13; 2.2.A.2.b Specifies test blocks for circuit breaker wiring, please confirm the test blocks must provide CT and PT wiring for isolation of relays during testing. | Yes. |
| 52 | Section 26 13 13; 2.4.2 Please define "off" position specified on 3 way door mounted circuit breaker. | Off is the spring return center off, remains in last state. |
| 53 | Section 26 13 13; 2.8 Station batteries are specified @ 48 VDC, please advise if 125 VDC system is acceptable to lower current draws on circuits and wire sizing. | Yes. |
| 54 | Section 26 13 13 ; 2.10 Specifies 14 AWG is specified, current industry standards for PLC's and DI/O only accept 16 AWG wire or smaller. Please confirm 16 AWG is acceptable for wiring related to PLC's and DI/O. | 16 AWG acceptable under conditions it has the current carrying capacity required. |
| 55 | Specification 26 32 13; section 2.4.F calls for lube oil heater. Engine manufactures do not recommend lube oil heater for this type of application. Jacket water heater and space heaters are provided to ensure engine is at necessary temperature to start accordance with NFPA guidelines. Please confirm lube oil heaters are not required in this case. | Lube oil heaters are required and are installed on current chiller plant generator set packages. |
| 56 | Specification 26 32 13; section 2.7.E calls for calcium silicate insulation on exhaust pipe and muffler. Calcium silicate insulation is most often used when generators are mounted inside a building. Please confirm exhaust blankets can be used to wrap exhaust pipe and mufflers with internal insulation are acceptable when mounted inside generator enclosure. | Yes. |
| 57 | Specification 26 32 13; section 2.14.C lists sound requirement as both 85dBA at 5ft and 75dBA at 50ft. 85dBA at 5ft equates to 65dBA at 50ft. Please clarify sound level required. | 75dBA at 23’ is required. |
| 58 | What is the wire size/designation of the existing underground MV line referred to in the MV Cable Schedule on E-602 that will be spiced into the new switchgear in the new cast-in-place manhole? | Duplicate Question. See response to Question #12 and Question #36. |
| 59 | Is the existing underground electric line that is to be spliced the property of the VA or Dominion? If Dominions property, will they require the spicing of the existing and new lines to the new switchgear to be done by Dominion? | Contractor is responsible for coordinating with Dominion on work indicated as well as providing closed transition requirements. |
| 60 | Is a pre-cast manhole an acceptable alternative to cast-in-place? | No. Manhole must be cast-in-place. |
| 61 | ES102 Note 2 requires a MV splice and new manhole. Does the VA have a redundant utility power supply that will allow the MV to be spliced with all MV lines in the new manhole completely de-energized? | No, there is no redundant utility power but there is generator backup. |
| 62 | What is the max and average load for the entire campus? Do you intend to be able to run the 4 new generators in tandem/ in parallel with other generators on the site? If so, which generators will run in parallel and which will run in tandem? | No, the 4 generators will not run in parallel with any other generators on site. |
| 63 | ES102 note 7 and 9 indicates that an existing underground communication/electric lines that will require to be moved vertically/horizontally. How long can these lines be decommissioned? Are these existing lines encased in concrete? | Duplicate Question. See response to Question #33. |
| 64 | ES102 note 6 indicates that an existing underground communication line will require movement during construction. How long can this line be decommissioned during construction? Is this existing line encased in concrete? | Duplicate Question. See response to Question #33. |
| 65 | What is the expected depth of the existing sanitary sewer line that runs directly under the berm (North-South)? Is this sanitary sewer in use or abandoned? Should we expect to encounter this line during berm removal? | See sheet CG101 Site Grading Plan. The finished depth of cover is approximately 6 feet to 7 feet. This is an active main serving the VAMC campus. |
| 66 | Is there a preference to the manufacturer of the generators and/or switchgear? | Generators and/or switchgear must meet the requirements of the drawings and specifications. There is no preferred manufacturer. |
| 67 | Can excess soil from the removal of the berm be spread on site? | Excess soils material shall be removed off VAMC campus. |
| 68 | Please provide existing MV one-lines for the site. | One-line drawing indicated in the E-6XX sheets is all that is required for this scope of work. |
| 69 | Please refer to sheet ES102 which shows in the ductbank section between the new switchgear and new manhole, is this a 4 or 6 way ductbank? Are all raceways in this ductbank to be 5” PVC conduit? | This is a 4-way ductbank with 5" conduit. |
| 70 | The first note in the MV Cable Schedule note on E-601 states “One 5” way in 4-way ductbank with 15 kV AL cables to match existing”. In this context, what does ‘5” way’ mean? What is the size of the existing 15kV AL wire? | Duplicate Question. See response to Question # 58 and Question #69. |
| 71 | Per previous RFI, the contractor is to supply a load bank and load bank pad. Is the contractor also required to perform the required monthly testing of the generators? If so for what length of time after install? | No, the VA will have testing performed under a separate service & maintenance contract following expiration of the 1 year construction warranty period. |
| 72 | Please reference Sheet E-601, MV cable schedule. What is the size of the existing 15KV AL cable? | Duplicate Question. See response to Question # 58. |
| 73 | The ductbank from the paralleling gear to the new manhole would appear to indicate 6-way ductbank, which references note 1 on drawing E-601, MV Feeder Schedule indicating a 4-way ductbank. Also note 1 on the MV Feeder Schedule indicates the cable is to match existing and to be Aluminum and the specifications call for copper. Please clarify the number of ducts in the ductbank and the MV wire size and type to be used. | Duplicate Question. See response to Question # 69. |
| 74 | Drawing ES-102, shows 3 existing duct banks that will need to be relocated, according to notes 6, 7, & 9. We need information as to size of existing duct banks, number of cables and types, and cable sizes, also services that will be impacted by this work. | Duplicate Question. See response to Question #33 and Question #39. |
| 75 | On the electrical riser drawing E-606, indicates that the incoming MV feeder from MV/SW 361V163 is to be tapped, on drawing E-104, on the SW corner of the pad mounted switch located behind generator #1, it would appear to require a manhole to tap the existing MV cable. No where on the site drawings does it show work needed for the manhole, ductbank or cable size. Please clarify manhole size, ductbank size and cable size required for this work. | Duplicate Question. See response to Question #9a, #12, and #88. |
| 76 | Who is responsible for fuel in these generators? Is the contractor responsible for fuel for testing? Or filling the units complete after all testing? | Duplicate question. See response to Question #13. |
| 77 | On sheet ES101 where the conduit enters the building, wouldn't it be less expensive and easier to bring the conduit up the outside wall to the ceiling line then penetrate rather than core drilling through the foundation then bringing the conduit up through a second core drill through the loading dock floor before going up to the ceiling? | Provide work as indicated on the drawings. |
| 78 | Please Clarify where the concrete and sitework is to be deleted for Proposal Item 2 on Drawing ES102 and what is the revised site plan to be for the removal of generator # 4. | All new features shown for the civil/site shall be constructed as per the civil/site plans. Finished grades shall conform to the civil/site plans without the generators #3 and #4. |
| 79 | Please clarify where the concrete and sitework is to be deleted per proposal number 3 and what is the revised site plan for removal of generators # 3 and # 4. | All new features shown for the civil/site shall be constructed as per the civil/site plans. Finished grades shall conform to the civil/site plans without the generators #3 and #4. |
| 80 | Per sheet C-104, we see a need to install a haul road from the construction entrance to the work area, because of this, we will be unable to sod that area and maintain it. Please confirm that it is acceptable to not immediately sod and maintain the construction entrance until after the equipment is installed in that area? | Yes. |
| 81 | Per sheet C-105, Is it acceptable that this existing electronic gate be temporarily left open so that the GC can install a temporary gate in its place for site access? | Communicate with COR for access to electronic gate. |
| 82 | Sheet C-501 shows two details of driven in and non-driven in temporary construction fence for this site, please clarify what style is needed. | Either style is acceptable or can be used in combination. |
| 83 | Note 7/S101 references stairs and platform to be installed between the generators. Please provide a detail of how they are supposed to be attached to the new Concrete Pad. | Attachment shall be per manufacturers recommendations. |
| 84 | At the Pre-Bid walk-thru, several Con-Ex boxes were observed to be within the Construction Limits of the project. Is the contractor to assume the cost of relocating these boxes? If so, please specify where they are to be relocated. | Contractor is not responsible for relocating these boxes. Government will relocate. |
| 85 | Sheet E-501 references Generator and Switch Gear enclosures. Please provide a detail of how new Enclosures are to be attached to new Concrete pad. | Attachment shall be per manufacturers recommendations. |
| 86 | Spec section 01 00 00, parts 1.10 & 1.11 states the Contractor is to retain services for Survey & Layout. Please confirm. | That is correct, confirmed. |
| 87 | Spec section 01 45 29, part 1.1 states Testing & Inspections services are to be retained by the VAMC. Please confirm. | NOTE : On past projects, services under this spec section were provided by the prime contractor, not the VA. |
| 88 | In the Electrical specs, 260541 “Underground Electrical Construction” 2.3 (Ducts) it specifies duct banks. It is not very clear on what they want in terms of psi of concrete, rebar, and spacing. Can a detail be provided for a typical duct bank? | See ductbank detail provided as part of the attachments. |
| 89 | In the Electrical specs, 260541 “Underground Electrical Construction” 2.1 (Manholes) does not specify the size of the manhole we are to use and not detail is provided on the drawing. Please specify size of new Manhole. | Duplicate Question. See response to Question #9a. |
| 90 | On ES102 a 6 Way Duct Bank runs form the new Manhole to New MV Switchgear. Per E601 new 15kV MV Cable schedule it notes that the cables are to match the existing. Can a cable type and size be given for this run to the new MV Switchboard at 13.2kV and 1200A? | Duplicate question. See response to Question #12. |
| 91 | On E001 it shows the legend for the Duct Banks and references the MV Cable Schedule on E-601. ES102 shows a 6 Way Duct Bank with (2) 5” Conduits with (4) spares and E-601 lists a 4 Way Duct Bank with (1) 5” conduit and (3) spares. Please advise which Duct Bank is to be assumed by the contractor? | Duplicate Question. See response to Question #69. |
| 92 | Note 6 on ES102 & Note 2 on ES105 shows a Comm line that ties into an existing Comm Vault 36” below grade. No cable, conduit size, or encasement is specified for this line. Please advise. | Note 6 on ES102 refers to an existing line that is required to be lowered due to berm removal. Note 2 on ES105 inidcates the requirements of the new comm line to be provided. |
| 93 | In the Electrical specs, 260541 “Underground Electrical Construction” 3.3, B1 specifies installation of duct banks. It notes that medium voltage, low voltage, and signal systems are to be encased. On ES102, Notes 4 & 6 and ES105, Notes 1 & 2 do not specifically call for encasement. Please advise if we are to encase or if normal compaction is acceptable. | Encasement is required for this work. |
| 94 | A note on ES102 calls for Communication cables between the MV Switchgear Enclosure and new Generator Enclosures to be direct buried. This is contrary to the specs, please advise. Please provide cable size and type for these cables as well. | Communications should be provided and installed per manufacturer's recommendations. This cable should comply with the specifications. |
| 95 | Detail E3/C501 shows pouring a minimum of 8” concrete at trenches (@500 LF). Should we assume the existing concrete to be a minimum of 8” that we need to remove? | Bid existing concrete to be removed as 8” thick with reinforcing. |
| 96 | Per note 5/CD101, what is the mixture of the existing concrete pavement? Concrete at the front of the building has a quartz mixture which is VERY hard and tough on saw blades. With over a 1000 lf of saw cutting the quartz added mixtures usually allow about 30’ per blade. | Existing concrete mixture is unknown. |
| 97 | Sheet CD102 shows concrete to be trenched at a very sharp curve. This would be next to impossible for concrete that is 6-8” thick. Can these trenches be cut straight with overlapping cuts? | Yes, this is acceptable. |
| 98 | Delivery Drive is a very heavily used area. Saw Cutting, trenching, excavating and conduit placing as well as safety plate usage is very time consuming. The bedding of conduits, filling and compacting and other drilling for rebar, and pouring of new concrete will be time consuming as well. Should any of this work be performed outside of normal working hours? | Coordinate with COR to perform work during normal hours, however weekend and night work may be required. |
| 99 | Note 6/CD103 Pipe bollard removal would most likely require the entire island to be removed and replaced due to bollards being embedded in 2’ of concrete below grade. Should the contractor assume the entire Island and Bollards will need to be replaced? | Bid according to plans and specifications. |
| 100 | Per Foundation Notes 2 & 9/S001, should the contractor treat this as PCO work? Please advise. Note #3/ES102 requires tanks to be fueled on generators by the contractor. Please confirm this is for all four tanks? | Any unanticipated rock removal and/or additional excavation and backfilling would be additional work per specifications. |
| 101 | ES105, Note #1 shows direct buried cable on the drawings and then note says 4” PVC. Which method should be used? | 4" PVC is required for this cable. |
| 102 | Details B1 & B3/C-501 show Joint Sealant at Expansion Joints. Will a Joint Sealant spec be provided? | Provide joint sealant as specified in section 03 30 00 Cast-In-Place Concrete. |
| 103 | Note 2/ES102 has the contractor intercepting the existing utility feeder to building 500 and setting a new manhole around the feeder; this is confirmed on the Riser Diagram on E-601. The feed comes directly from Dominion and we cannot make splices to their conductors, please advise who is responsible for this work, coordination, and cost? | Contractor is responsible for all coordination with Dominion power on required work. |
| 104 | Generator spec 26 32 12 (Section 2.12B) references “Continuous”. Confirm generator shall be “ Standby Rated”. | Duplicate question. See response to Question #24. |
| 105 | Please confirm that breakers G1, G2, G3, G4 are to be located within medium voltage switchgear while the generator alternator connections are to be terminated via stress cone. | Each generator will have a 13.2KV breaker inside the enclosure. |
| 106 | Spec 26 32 18 (Section 2.14) Sound attenuated Enclosure calls out 85 dBA @ 5 Feet. Confirm sound attenuation level to be 75 dBA @ 25 feet. | Duplicate question. See response to Question # 57. |
| 107 | 262313 2.2 (Remote Annunciator Panel) - Please provide location of two 24” touchscreen remote annunciator panels and provide one-line diagram for required fiber connection. | Fiber connections shall be per manufacturer recommendations. |
| 108 | 262313 2.3 (Existing Equipment Integration) - Please confirm the drawings indicate ALL required modifications. The paragraph indicates a PLC and I/O upgrade to existing paralleling switchgear is required. | Yes. |
| 109 | Reference page 16 of 55 of the solicitation - Please confirm the project requires two (2) separate full-time on-site individuals (i.e. Site Superintendent and QA Manager/Safety Manager) | That is correct, confirmed. |
| 110 | Please confirm the Contractor is responsible for providing all fuel required for load bank testing and complete filling/top-off of Generators. | That is correct, confirmed. |
| 111 | Please provide model and serial number for any existing equipment referenced in the specification that we must integrate with. | Bidders responsibility to verify existing switchgear and ATS. |
| 112 | The new paralleling gear requires closed transition transfer not to exceed 100ms. Will a modification to the existing chiller plant gear be required to convert it from softload to closed transition in 100s or less? | Yes. |
| 113 | Please confirm there is no 3rd Party Electrical Testing required for the Project. | That is correct, confirmed. |
| 114 | The new paralleling gear requires closed transition transfer not to exceed 100ms. Will a modification to the existing chiller plant gear be required to convert it from softload to closed transition in 100s or less? | Duplicate question. See response to Question #112. |
| 114a | The parallel switchgear specification states the sequence of operations will be in a separate document, could you post a copy of the sequence of operations? | Duplicate question. See response to Question #41. |
| 114b | Drawing ES101 - This drawing indicates that the conduit enters the building. As a suggestion, please consider the less expensive and easier option of bringing the conduit up the outside wall to the ceiling line then penetrate; as appose to core drilling through the foundation then bringing the conduit up through a second core drill through the loading dock floor before going up to the ceiling. | Duplicate question. See response to Question #77. |
| 115 | There are three low voltage ATS’s shown on the one lines. We assume they are existing, but would like to confirm this. | Duplicate question. See response to Question #16. |
| 116 | The bid specs for the permanent load bank is not shown. Is this available. We are assuming a 600 kW resistive load bank for 30% testing, but would like clarification of this. Seismic rating is mentioned in the switchgear and generator set. Will seismic certification be required at this site? | Duplicate question. See response to Question #7 and #18. |
| 117 | Will the factory tests on the generator sets also be witnessed by the owner? The specifications do not request this, but the switchgear does. | Duplicate question. See response to Question #19. |
| 118 | 26 32 13 Engine Generators Part 1 H (Page 6) - References UL2085 but is in conflict with E-501 drawing which calls out UL 142; please clarify that UL142 will be the specified standard? | Duplicate Question. See response to Question #23. |
| 118a | Part 2 2.1 C1 (Page 6) - Power rating is stated as Emergency standby, however C3 says “continuous”. Please confirm the rating requirement is for standby rated as defined in ISO 8528 | Duplicate question. See response to Question #24. |
| 118b | Part 2.12A (Page 12) - Please clarify that A is N/R as a spec item; The MV generator breaker would be mounted in the PSG. | Duplicate question. See response to Question #105. |
| 119 | 26 23 13 Generator Paralleling Controls: 2.3 A (Page 10) - The existing ATS’s (LS, CR, EQ) are identified on drawing E601. As the system is designed for transition to standby generation upstream of the existing ATS’s, their purpose seems to be as a stop gap means for termination relative to B503 future work. Please clarify the intent on the ATS’s remaining in service? | Duplicate question. See response to Question #16. |
| 119a | 2.4 - Paralleling Operation - We assume sequence document referred to is drawing E701; is there a narrative that would clarify the intended sequence? | Duplicate question. See response to Question #41. |
| 119b | 3.1 B - “Mount generator paralleling controls on concrete slab”; There is conflict over the Paralleling switchgear enclosure as it defined her and on E501 described as a drop over type enclosure with “base” and 26 13 13 page 5 2.1 where a “walk in Protected Aisle” is specified and further on page 7 2.2 B, and Page 8 item 4 “shall be provided with a steel floor “. Please clarify the required construction as regards a floor for the PSG/Switchgear enclosure. | See drawing E501 showing a fully assembled with structural base assembly as well as switchgear and enclosure electrical equipment. Basis of design similar to existing chiller plant switchgear enclosure seen at site walk through. |
| 120 | Requires load bank (s) for 13.2 KV testing, (resistive) 6 hours total, of that 2 hours at 100% load, (4) hours at 80 % load; In this section paragraphs weave back and forth between load bank as a load source and actual building load as a load source (i.e. paragraph d page 21 “perform the on-site installation acceptance test for the existing occupied building in accordance w/ NFPA 110); Please clarify as follows: | See responses in a, b, c below. |
| 120a | Is each generator to be individually tested at its 100 % rating for the 6 hour duration? | Duplicate question. See response to Question #29a. |
| 120b | K. Parallel Operation test – what load bank capacity is required …we assume 2000 based on earlier? | Duplicate question. See response to Question #29b. |
| 120c | Also K1 references measuring reactive load, but resistive load bank is earlier specified? Please clarify. | Duplicate question. See response to Question #29c. |
| 120d | Page 23 Para 4 says “connect each engine generator is parallel with the utility for 15 minutes , however the system is not specified as that mode of operation as the sequence is not clear on that ; Please clarify as PSG spec 26 23 13 pages 7 and 9 are also contradictory ; page 7 para L 3 references 100 MS or less parallel time , page 9 para P mentions “Base load , Utility import/export”; Bidder requests clarification on sequence of operations as well as testing parameters. | Duplicate question. See response to Question #30 |
| 121 | Section 01 33 32 - 2.3 Existing Equipment Integration: A. It is the responsibility of the switchgear manufacturer to modify all existing automatic transfer switches and paralleling gear line-ups to ensure proper sequence of operation and integration with new paralleling gear. A PLC and I/O upgrade to existing paralleling switchgear is required. | See responses in a, b, c, d, e below. |
| 121a | What are the model and serial numbers of existing equipment (switchgear)? | Duplicate question. See response to Question #31. |
| 121b | What is the specification between the new master controller and existing ASCO switchgear? | Duplicate question. See response to Question #31a. |
| 121c | What is the existing sequence of operations for the switchgear? | Duplicate question. See response to Question #31b. |
| 121d | What are the distances from old gear to new gear location? | Duplicate question. See response to Question #31c. |
| 121e | What is the pitch of the existing Caterpillar gensets on location? | Duplicate question. See response to Question #31d. |