2P26-060 Project Schedule.pdf

PDF 58 KB Posted

Attached to
Construction Manager at Risk for Edgewood PreK Academy
Solicitation number
2P26-060
Issued by
Hartford County, Connecticut

About this file

This is a workplan schedule document for the City of Bristol, Connecticut's renovation project of the Edgewood Pre-Kindergarten Academy facility located at 345 Mix Street. The project encompasses multiple phases beginning in November 2025 and extending through August 2027, including schematic design, design development, land use approvals, early abatement and demolition, construction documents, bidding and contract awards, and construction. Key milestones include completion of schematic design by February 6, 2026; design development completion by March 20, 2026; land use approvals by May 8, 2026; abatement and demolition work from June 29 through August 7, 2026; and construction from August 10, 2026 through July 9, 2027 with substantial completion targeted. The project schedule identifies distinct phases with defined durations ranging from 2 to 22 weeks for various components, with furniture delivery and move-in scheduled for early August 2027 and the first day of school targeted for August 26, 2027.

The schedule outlines coordination requirements between the Design Team, Bristol Reviews and Approvals, Bristol Administration, Department of Administrative Services/Office of General Assembly (DAS/OGA), and the Construction Manager. The document indicates that cost estimating and budget reconciliation activities occur throughout the design and pre-construction phases, with OGA preparation meetings and project coordination team meetings scheduled at key intervals. The early abatement and demolition package is scheduled to proceed following advertising and bidding activities from May 11 through June 26, 2026, with contract awards and approval of guaranteed maximum price (GMP) occurring by early August 2026 prior to construction mobilization.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORKPLAN SCHEDULE

# WEEKS DESIGN TEAM SCOPE / DOCUMENT PRODUCTION COST ESTIMATING BRISTOL REVIEWS & APPROVALS BRISTOL ADMINISTRATION DAS / OGA BIDDINGBIDDING CM - CONSTRUCTION WORK

PHASE /TASK START FINISH

3 10 1 8 15 5 2 2 23 30 6 13 4 11 18 1 29 6 13 3 3 31 7 5 12 19 2 30

LOCAL PROJECT APPROVALS 13-Nov

SCHEMATIC DESIGN 1-Dec 6-Feb

Document Development 1-Dec 16-Jan

Issue 90% SD set

Cost Estimating 19-Jan 6-Feb

Budget Reconciliation

OGA: PREP Meeting

DESIGN DEVELOPMENT 9-Feb 20-Mar

Document Development 9-Feb 20-Mar

Document Review: Town Staff

Issue 100% DD set

Cost Estimating + Budget Reconciliation 23-Mar 10-Apr

LAND USE APPROVALS (IF REQUIRED) 23-Mar 8-May

Document Submission 23-Mar

P & Z: Site Plan Review (1st Tuesdays) 6-Apr 5-May

EARLY ABATEMENT & DEMOLITION PKG 9-Mar 7-Aug

Documents 9-Mar 3-Apr

Cost Estimating + Budget Reconciliation 6-Apr 24-Apr

OGA: PCT Meeting / Approval to Bid

Advertising / Bidding / Scope Reviews 11-May 26-Jun 1

Abatement/Demo work 29-Jun 7-Aug

CONSTRUCTION DOCUMENTS 23-Mar 29-May

Document Production 23-Mar

Issue 90% CD set

Cost Estimating + Budget Reconciliation 11-May 29-May

APPROVALS

SCG-042 Approvals/Sign-Off

OGA: PCT Meeting

Document Revisions

Approval to Bid Letter

BIDDING & CONTRACT AWARDS 22-Jun 7-Aug

Advertising / Bidding / Scope Reviews 1

Approval of GMP

CONSTRUCTION 10-Aug-26 13-Aug-27

Building Construction 10-Aug-26 9-Jul-27

Substantial Completion

Commissioning 19-Jul 6-Aug

Furniture Delivery & Set up 2-Aug 13-Aug

MOVE-IN 2-Aug 25-Aug

FIRST DAY OF SCHOOL

PHASE /TASK START FINISH

Construction Manager on Board

Special Legislation

Updated Educational Specifications

BRISTOL - RENOVATIONS TO EDGEWOOD PRE-K SCHOOL

2026 2027

DURATION NOV DEC SEPT

10 WEEKS 10

JUL AUG MAY JUN JUL AUGJAN FEB MAR APR MAY JUN

by Feb 13 week of Feb 16

10 WEEKS 7

7 + 3 WKS 7 3

16-Jan

7 + 3 WKS 7

2.5

7 WEEKS

22 WEEKS 7 2 7

week of Feb 16

20-Mar

4 2

6 WEEKS 6

10 WEEKS 10

2.5 by May 8 2 by Jun 5 week of Jun 1 week of Jun 8

7 + 3 WKS 7

8-May

12 MOS 12 MONTHS

11 MOS 11 MONTHS

by Jun 19

7 WEEKS 7

4 2

DURATION

9-Jul

2 WEEKS 2

4 WEEKS 4

JUL AUG

Thur 8/26/27

2.5

SEPT

2025 2026 2027

MAY JUN JUL AUG MAY JUNNOV DEC JAN FEB MAR APR