27-421-49 Bid Docs.pdf

PDF 659 KB Posted

Attached to
Tree Services
Solicitation number
BD-27-1459-BTV05-BTV05-132101
Issued by
Middlesex County, Boston City, Massachusetts

About this file

Tree Services Contract Summary

This is a sealed bid invitation for tree services issued by the Town of Burlington Department of Public Works under Massachusetts General Law Chapter 30B. The contract encompasses town-wide tree trimming, cutting, removal, and disposal services on an hourly basis, with an estimated quantity of 60 hours. The sealed bid opening is scheduled for August 26, 2026, at 10:00 AM at Town Hall Annex, 25 Center Street, Burlington, Massachusetts. Work is to commence no later than September 14, 2026, with a completion deadline of September 13, 2027. The contract has a one-year term. No formal bidders' conference or site visit requirement is specified in the documents. Specifications and bid forms are available on the Town's website at https://www.burlington.org/Bids.aspx, with Patrick Duran (pduran@burlington.org, 781-238-5618) designated as the Town's representative for inquiries.

The contract will be awarded to the lowest responsible and responsive bidder with demonstrated experience. Bidders must have a minimum of five years' experience and provide references for five similar completed projects of comparable size and scope; all subcontractors must meet the same requirements. Bid security in the form of a bid bond, cash, or certified check is required. Pricing is submitted on a per-hour basis for the 60-hour estimated quantity, though the Town does not guarantee all items will be purchased during the fiscal year. Payment will be made by invoice with a five percent retainage applied to periodic payments in accordance with Massachusetts General Law Chapter 30, Section 39G. The contract may be terminated with 15 days' notice for unsatisfactory performance or funding unavailability. Contractors must provide all necessary equipment for service delivery and maintain normal work hours of 7:00 AM to 3:30 PM Monday through Friday, with police detail costs covered by the Town. All employees must have completed a minimum 10-hour OSHA construction safety and health course.

View the file

Other files

File Type Posted
27-421-49 Addendum 1.pdf PDF
27-421-49 Legal Notice.pdf PDF
27-421-49 Prevailing Wage.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TOWN OF BURLINGTON

DEPARTMENT OF PUBLIC WORKS

Tree Services Contract 27-421-49

Department of Public Works

25 Center Street

Burlington MA 01803

August 26th, 2026

Town of Burlington 30B Services

Tree Services 26-421-49

August 26th, 2026; 10:00 AM

TABLE OF CONTENTS

INVITATION FOR BID 3

PROJECT DESCRIPTION 4

INSTRUCTIONS TO BIDDERS 5

FORM OF GENERAL BID 10

ADDENDA 11

BID FORM 12

TOTAL BID PRICE 13

CONTRACTOR REFERENCES 14

CONTRACTOR CERTIFICATION 15

AGREEMENT 16

SPECIAL CONDITIONS 17

GENERAL CONDITIONS 19

INVITATION FOR BID

SUPPLIES AND SERVICES

Sealed bids for the Tree Services contract will be received by Department of Public

Works, Town Hall Annex, 25 Center Street, Burlington, Massachusetts, 01803 until

August 26th, 2026; 10:00 AM and will be publicly opened and read aloud at such time.

Specifications and bid forms are available on the Town’s website at https://www.burlington.org/Bids.aspx

This project is bid according to MGL 30B.

Town’s Designated Representative and point of contact for questions is: Patrick

Duran, pduran@burlington.org, 781-238-5618 mailto:pduran@burlington.org

PROJECT DESCRIPTION

The work under this contract shall include all equipment, labor, material, supplies, etc.

necessary to furnish the work described in this contract.

INSTRUCTIONS TO BIDDERS

Receipt and Opening of Bids The Town of Burlington, Massachusetts, herein called the Owner, acting by and through its Department of Public Works, will receive sealed bids as specified in the invitation for Bids at which time bids will be publicly opened and read.

Any bid may be withdrawn prior to the above scheduled time for the opening of bids or authorized postponement thereof. Any bid received after the time and date specified will not be considered. The bidder agrees that this bid shall be good and may not be withdrawn for a period of thirty (30) days, Saturdays, Sundays, and legal holidays excluded, after opening the bids.

Location and Work to be Done

The Location of the Work to be done is described in the project description.

The Contractor shall furnish all labor, services, materials, equipment, plant, machinery, apparatus, appliances, tools, supplies, and all other things necessary to do all work required for the completion of each item of the Work and as herein specified.

The Work to be done and paid for under any item shall not be limited to the exact extent mentioned or described but shall include all incidental work necessary or customarily done for the completion of that item.

Preparation of Bid Each bid must be submitted on the prescribed form. All blank spaces for bid prices must be filled in, in ink or typewritten, in both words and figures.

Each bid must be submitted in a sealed envelope bearing on the outside the name of the bidder, their address, and endorsed with the name of the project as specified in Receipt and Opening of Bids.

If forwarded by mail, the sealed envelope containing the bid must be enclosed in another envelope addressed as specified in Receipt and Opening of Bids.

The following sections need to be filled out and completed as part of the bid package;

Form of General Bid

Acknowledgement of Addenda, if any

Bid Form

Total Bid Price

Contractor Reference

Contractor Certification

Bid Opening Procedure The following list of requirements shall apply to each filed bid. Bids not meeting all the requirements for timeliness and security will be rejected without opening;

bids not meeting signature and addenda requirements will be rejected prior to checking of bid amounts.

Bids shall be filed at the place and before the time specified in Receipt and Opening of Bids.

Properly executed bid security shall be placed in a sealed envelope and shall be attached to the outside of the envelope containing the bid.

Bid signatures will be checked.

The total dollar amount of each bid will be read, and the three apparent lowest bids will be selected for further consideration. These three apparent low bids will be read aloud for the benefit of the other bidders and the bid opening procedure will be closed. All those present at the bid opening may arrange a time to examine all bids after the bid opening and after the reading of the three apparent low bids.

Ability and Experience of Bidder

No award will be made to any bidder who cannot satisfy the Owner that they have sufficient ability and experience in this class of work and sufficient capital and plant to enable them to complete the work successfully within the time named. The

Owner’s decision or judgment on these matters will be final, conclusive, and binding.

Bidder shall have a minimum of five (5) years’ experience and have completed satisfactorily five (5) jobs within that time of similar size and scope.

All Subcontractors shall have a minimum of five (5) years’ experience and have completed satisfactorily five (5) jobs within that time of similar size and scope.

The Contractor must submit with their bid proposal a list of five (5) jobs which they have successfully completed, giving the name and the address of these projects so they can be investigated prior to the award of the contract.

The Owner may make such investigations as they deem necessary, and the bidder shall furnish to the Owner, under oath if so required, all such information and data for this purpose as the Owner may request.

Condition of Work

Each bidder must familiarize themselves fully with the conditions relating to the construction of the project and the employment of labor thereon. Failure to do so will not relieve a successful bidder of their obligation to furnish all material and labor necessary to carry out the provisions of their Contract. Insofar as possible the

Contractor, in carrying out their work, must employ such methods or means as will not cause any interruption of or interference with the work of any other Contractor.

Addenda and Interpretations No interpretation of the bid documents will be made orally. Every request for such interpretation should be in writing addressed to the Town’s Designated

Representative listed in INSTRUCTION TO BIDDERS and to be given consideration must be received at least seven (7) days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the Contract Documents. Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under this bid as submitted. All addenda so issued shall become part of the Contract Documents.

Laws and Regulations

The bidder’s attention is directed to the fact that all applicable State laws, municipal ordinances, and the rules and regulation of all authorities having jurisdiction over construction of the project shall apply to the Contract throughout, and they will be deemed to be included in the Contract the same as though herein written out in full.

Bid Security-Reserved Each bid must be accompanied by a BID BOND, CASH, or, CERTIFIED CHECK, payable to the Town, in the amount stated in INVITATION TO BID. Such checks will be returned to all except the three (3) lowest responsible and eligible bidders within five (5) days, Saturday, Sundays, and legal holidays excluded, after the opening of bids, and the remaining checks will be returned promptly after the

Owner and the accepted bidder have executed the Contract, or if no notice of intent to award has been presented to the selected contractor within thirty (30) days, Saturdays, Sundays and holidays excluded, after the date of the opening of bids, upon demand of the bidder at any time thereafter.

The said amount is fixed and agreed upon by and between the Contractor and the

Owner because of the impracticability and extreme difficulty of fixing and ascertaining the actual damages the Owner would in such event sustain, and said amount is agreed to be the amount of damages which the Owner would sustain and said amount shall be retained from time to time by the Owner from current periodical estimates.

Right to Reject Bid

The Owner reserves the right to waive any informality or reject any and all bids and alternate bids, should the Owner deem it to be in the public interest to do so.

The Owner also reserves the right to reject the bid of any bidder that the Owner considers to be unqualified based on the criteria set forth in Article 5 herein.

Time for Completion

The bidder must agree to commence work and to fully complete the project within the time limit stated in SPECIAL CONDITIONS.

Comparison of Bids In the event that there is a discrepancy in FORM OF GENERAL BID between the lump sum or unit prices written in words and figures, the prices written in words will govern.

Rule for Award of Contract

The Contract will be awarded to “the lowest responsible and responsive bidder” for the Total Price Bid pursuant to General Laws Chapter 30B as amended. Such a bidder shall possess the skill ability and integrity necessary for the faithful performance of the work, shall be able to furnish labor that can work in harmony with all other elements of labor employed, or to be employed, in the work, and shall otherwise comply with all applicable provisions of law. Bidder shall execute formal agreement within ten (10) days of the Notice of Award.

Statutes Regulating Competitive Bidding Any bid that does not comply with the provisions of Massachusetts General Laws

Chapter 30B as amended, need not be accepted and the Owner may reject every such bid.

Specifications

All specifications and bid items are based on Massachusetts Highway Departments

“Standard Specifications for Highway & Bridges” edition as revised in the 1995

Publication.

Bid Items Not Guaranteed

The successful bidder is not guaranteed all items or the total bid price under this contract. Bidders must understand that like items will be bid under other contracts specifically packaged as one complete project. The successful bidder has no right to similar items bid under other projects. The Town Superintendent will specify where and when this contract will be applied to undertake a particular improvement.

Tie Bids In the event of tied bids, wherein two or more responsive and responsible vendors provide the same bid price a coin toss will be used to break the tie.

Unforeseen Office Closure

If, at the time of the scheduled bid opening, Town Offices are closed due to uncontrolled events, the bid opening will be postponed until the next normal business day at the original time specified in the documents. Bids will be accepted until that date and time.

FORM OF GENERAL BID

Bid of ____________________________________ (hereinafter called “Bidder”)*

(____) a corporation, organized and existing under the laws of the state of ___________.

(____) a partnership

(____) a joint venture

(____) an individual doing business as ___________________________________

To the Town of Burlington, Massachusetts (hereinafter called “Owner”).

Bidders:

The bidder, in compliance with your invitation for bids, having examined the Contract

Documents and being familiar with all of the conditions surrounding the construction of the proposed project including the availability of materials and labor, hereby propose to furnish all labor, materials, and supplies, and to construct the project in accordance with the Contract Documents within the time set forth in the agreement, and at the prices stated below. These prices are to cover all expenses incurred in performing the work required under the Contract Documents, or which this proposal is a part.

*Insert corporation, partnership or individual as applicable.

ADDENDA

Bidder acknowledges receipt of the following addenda:

No.______________________Dated:______________________

No.______________________Dated:_______________________

No.______________________Dated:______________________

BID FORM

ITEMS QT. UNIT PRICE TOTAL

ITEM 1.

Tree trimming, cutting, removal and disposal services 60 Hrs.

Per

HR $ EA $

TOTAL BID PRICE

Total Price Bid: $

Bid Price in Words:

Name:

Signature:

Title:

Company:

Address:

Phone: _______________________________________________________

Email:

CONTRACTOR REFERENCES

The undersigned offers the following information as evidence of their qualifications to perform the work as bid upon according to all the requirements of the plans and specifications.

1. Have been in business under present name for ___years.

2. The names and addresses of all persons interested in the bid (if made by a partnership or corporation) as Principals are as follows:

(Attach supplementary list if necessary)

3. The bidder is requested to state below what work of a similar character to that included in the proposed contract they have done, and give references that will enable the Owner to judge their experience, skill and business standing (add supplementary page if necessary).

# Completion

Date Project Name Contract

Amount Reference

Name Telephone No.

4. Bank reference ____________________________

(Name)

(Bank)

(Address) (Telephone No.)

CONTRACTOR CERTIFICATION

NON-COLLUSION

I certify under penalties of perjury that this bid or proposal has been made and submitted under good faith and without collusion or fraud with any other person. As used in this certification, the word “person” shall mean any natural person, business, partnership, corporation, union, committee, club, or other organization, entity, or group of individuals.

TAX COMPLIANCE

Pursuant to Massachusetts General Law Chapter 62C, Section 49A, I certify under the penalties of perjury that, to the best of my knowledge and belief, I am in compliance with all laws of the Commonwealth relating to taxes, reporting of employees and contractors, and withholding and remitting child support.

LABOR HARMONY / OSHA 10-HOUR

I will furnish labor that can work in harmony with all other elements of labor employed or to be employed in the work, and all employees to be employed in the work subject to this bid have successfully completed a course in construction safety and health approved by the

United States Occupational Safety and Health administration that is at least 10 hours in duration.

Signature: __________________________________________________________

(Person Signing Bid)

(Name of Business)

AGREEMENT

THIS AGREEMENT, by and between the party of the first part, the Town of Burlington, hereinafter called “OWNER”, acting herein through its Town Administrator, and the party of the second part hereinafter called “CONTRACTOR”.

WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned, to be made and performed by the OWNER, the CONTRACTOR hereby agrees with the OWNER to commence and complete the project described by these bid documents hereinafter called the project, for the sum of the contract price and all extra work in connection therewith, under the terms as stated in the Contract Documents; and at their (its and their) own proper cost and expense to furnish all the materials, supplies, machinery equipment, tools, superintendence, labor, insurance, and other accessories and services necessary to complete the said project in accordance with the conditions and prices stated in FORM OF GENERAL BID, GENERAL CONDITIONS, Contract Documents as prepared by the Owner.

IN WITNESS WHEREOF, the parties to these presents have executed this contract.

Contract Price

AGREED:

Town of Burlington

Owner Date

Contractor

Contractor Date

Company Name:

Address:

In accordance with M.G.L. C. 44, Section 31C, this is to certify than an appropriation in the amount of this contract is available therefore and that the Town Administrator has been authorized to execute the contract and approve all requisitions and change orders.

Account # Town Accountant Date

SPECIAL CONDITIONS

1. The Town of Burlington, acting through its Select Board, an awarding authority, reserves the right to accept or reject any and/or all bids or portions thereof, and to waive any informalities in bidding, and/or to make the award as appears in the best interest of the Town of Burlington.

2. Payment will be made as invoice, unless otherwise specified.

3. Normal Hours of work: Work hours shall be between the hours of 7:00 AM and

3:30 PM Monday through Friday, unless otherwise specified. The successful

Contractor shall not work on Saturdays, Sundays, Holidays or other hours, without express authority from the Director of Public Works.

4. Unless otherwise specified, the cost of the Police Detail Officer(s) will be paid for by the Town of Burlington.

5. This Contract includes estimated quantities that may or may not be purchased during Fiscal Year. Additionally, quantities are used for comparison of bids and establishing the Bid Deposit.

6. This Contract may be terminated, with fifteen (15) days’ notice, for unsatisfactory performance and/or availability of funds. The contractor will hold the Town harmless from all damages as a result of funding restraints.

7. The Contractor will provide all needed equipment to perform the tree trimming/removal/disposal services on a per hour basis.

Attention is directed to the following parts of the contract;

Description Location in Contract Preparation of Bid Instructions to Bidders; Part 3 Experience of Bidders Instructions to Bidders; Part 5 Bid Security Instructions to Bidders; Part 10 Execution, Correlation and Intent General Conditions; Article 1 Contract Administration General Conditions; Article 2 Superintendent General Conditions; Article 4 Project/Progress Schedule General Conditions; Article 4, Section 9 Project Plans N/A

Summary Table of Important Contract Dates

Item Date Amount Bid Opening August 26, 2026 N/A Commencement of Work will be no later than September 14, 2026 N/A

Completion of Work September 13, 2027 N/A

GENERAL CONDITIONS

ARTICLE 1

CONTRACT DOCUMENTS

1.1 DEFINITIONS

1.1.1 THE CONTRACT DOCUMENTS

The Contract Documents consist of the Owner-Contractor Agreement, the Conditions of the Contract (General, and other Conditions), the Drawings, the Specifications, all

Addenda issued prior to and all Change Orders issued after execution of the Contract, and all applicable laws, ordinances and regulations. The Contract Documents include Bidding

Documents such as the Advertisement or Invitation to Bid, the Instructions to Bidders, sample forms, the Contractor’s Bid or portions of Addenda relating to any of these, or any other documents, specifically enumerated in the Owner-Contractor Agreement.

1.1.2 THE CONTRACT

The Contract Documents form the Contract for Construction. This Contract represents the entire and integrated agreement between the parties hereto and supersedes all prior negotiations, representations, or agreements, either written or oral. The Contract may be amended or modified only by a written Change Order.

1.1.3 THE WORK

The Work comprises the completed construction required by the Contract Documents and includes all labor necessary to produce such construction, and all materials and equipment incorporated in such construction.

1.1.4 THE PROJECT

The project is the total construction of which the Work performed under the Contract

Documents may be the whole or a part.

1.1.5 OR EQUAL

The use of the words “Or Equal” following the name of any manufacturer, vendor or proprietary product shall be understood to mean that articles or materials may be substituted which, in the opinion of the Owner, are equal in quality, durability, appearance, strength, design and performance to the articles or materials named or described and will perform adequately in providing a first-class facility.

When submitting shop drawing information on articles or materials which are being proposed as substitutes for specified items, the Contractor shall clearly identify them as such. If the articles or materials are accepted as equal to those on which dimensions on the drawings are based, any dimensional variance from those shown and/or specified shall be shown on the shop drawings prepared by the Contractor, illustrating the manner in which conformity to dimensions and design is to be obtained. All such drawings shall be subject to the approval of the Owner and the installation of the article shall not proceed without first obtaining said approval.

1.2 EXECUTION, CORRELATION AND INTENT

1.2.1

By executing the Contract, the Contractor represents that they have visited the site, familiarized themselves with the local conditions under which the Work is to be performed, and correlated their observations with the requirements of the Contract Documents.

1.2.2

The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work. The Contract Documents are complementary, and what is required by any one shall be as binding as if required by all. Work not covered in the Contract Documents will not be required unless it is consistent therewith and is reasonably inferable there from as being necessary to produce the intended results. Words and abbreviations which have well-known technical or trade meanings are used in the

Contract Documents in accordance which such recognized meanings.

1.2.3 The Notice to Proceed will come in the form of a written letter to the Contractor. Once the written Notice to Proceed has been received by the Contractor, that date will be the legal start date for work under the Contract.

In the event of a failure to issue a Notice to Proceed written document specifying the commencement date, the pre-construction meeting date will serve as the Notice to Proceed date.

1.3 OWNERSHIP AND USE OF DOCUMENTS

1.3.1

All Drawings, Specifications and copies thereof furnished by the Owner are and shall remain the Owner’s property. They are to be used only with respect to this Project and are not to be used on any other project without prior written consent of the Owner. With the exception of one contract set for each party to the Contract, such documents are to be returned or suitably accounted for to the Owner at the completion of the Work. Submission or distribution to meet official regulatory requirements or for other purposes in connection with the Project is not to be construed as publication in derogation of any reserved rights.

ARTICLE 2

ADMINISTRATION

2.1 ADMINISTRATION OF THE CONTRACT

2.1.1

The designated representative of the Owner or its Superintendent will visit the site at intervals appropriate to the stage of construction to familiarize themselves generally with the progress and quality of the Work and to determine in general if the Work is proceeding in accordance with the Contract Documents. However, the Owner’s Representative or

Superintendent will not be required to make exhaustive or continuous on-site inspections to check the quality or quantity of the Work.

2.1.2

The Owner shall at all times have access to the Work whenever it is in preparation and progress. The Contractor shall provide facilities for such access so the Owner may perform its functions under the Contract Documents.

2.1.3

The Owner shall make payments for completed work, as approved by the Owner, in accordance with M.G.L. Ch. 30, Sec. 39G. A five percent retainage will be deducted from periodic payments to the Contractor.

2.1.4

The Owner will render information necessary for the proper execution or progress of the

Work within twenty (20) days of any request by the contractor or in accordance with any time limit agreed upon.

2.1.5

The Owner will have authority to reject Work which does not conform to the Contract

Documents. Whenever, in their opinion, they consider it necessary or advisable for the implementation of the intent of the Contract Documents, they will have authority to require special inspection or testing of the Work whether or not such Work is then fabricated, installed or completed. Any such rejection of work shall not relieve the Contractor of the responsibility for maintaining protection of the Work and the Owner’s property.

2.1.6

The Owner or its Superintendent will review and approve or take other appropriate action upon Contractor’s submittals such as Shop Drawings, Product Data and Samples, but only for conformance with the design concept of the Work and with the information given in the Contract Documents. Such action shall be taken with reasonable promptness so as to cause no delay. The Owner’s approval of a specific item shall not indicate approval of an assembly of which the item is a component.

2.1.7

The Owner will conduct inspections to determine the date of Substantial Completion and

Final Completion, will review written warranties and related documents required by the

Contract and assembled by the Contractor, and will issue a final Certificate for Payment.

ARTICLE 3

OWNER

3.1 DEFINITION

3.1.1

The Owner is the person or entity identified as such in the Owner-Contractor Agreement and is referred to throughout the Contract Documents as if singular in number and masculine in gender. The term Owner means the Town of Burlington or its designated representative.

3.2 INFORMATION AND SERVICES REQUIRED OF THE OWNER

3.2.1

The Owner shall, at the time of execution of the Agreement and any subsequent Change

Orders, certify for the Contractor that financial arrangements have been made to fulfill the

Owner’s obligations under the Contract.

3.2.2

The Owner shall furnish all documents describing the work.

3.2.3

Except as provided in Subparagraph 4.7.1. Owner shall secure and pay for necessary approvals, easements, assessments and charges required for the construction, use or occupancy of permanent structures or for permanent changes in existing facilities.

3.2.4

Information or services under the Owner’s control shall be furnished by the Owner with reasonable promptness to avoid delay in the orderly progress of the Work.

3.2.5

The Owner will furnish the Contractor with three (3) copies of all Drawings and

Specifications and revisions issued during the progress of the Work; all additional copies will be furnished upon request at the cost of reproduction.

3.2.6

The Owner, through its designated agent or Superintendent, shall forward all instructions directly to the Contractor.

3.3 OWNER’S RIGHT TO STOP THE WORK

3.3.1

If the Contractor fails to correct defective Work as required by the Owner or fails to carry out the Work in accordance with the Contract Documents or if the Owner shall for any other reason so require, the Owner, by a written order signed personally or by an agent specifically so empowered by the Owner in writing, may order the Contractor to stop the

Work, or any portion thereof, until the cause for such order has been eliminated or until further written notice from the Owner; however, this right of the Owner to stop the Work shall not give rise to any duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity. The Contractor shall resume the Work after such stoppage promptly upon written notice to do so from the Owner. If such stoppage is required through no fault of the Contractor, the Contract Time (and the dates for achieving

Substantial Completion and Final Completion) shall be extended by a period equal to the period of the stoppage, and the Contractor shall be compensated for its reasonable and justifiable cost incurred as a result of such stoppage.

3.4 OWNER’S RIGHT TO CARRY OUT THE WORK

3.4.1

If the Contractor defaults or neglects to carry out the Work in accordance with the Contract

Documents and fails within seven days after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, without prejudice to any other remedy they may have, perform such work or cause such work to be performed and/or make good such deficiencies. In such case an appropriate Change Order shall be issued deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies, including compensation for additional services made necessary by such default, neglect or failure. If the payments then or thereafter due the Contractor are not sufficient to cover the amount, the Contractor shall pay the difference to the Owner.

3.5 OWNER’S RIGHT TO TERMINATE CONTRACT

3.5.1 The Town reserves the right to terminate this Contract at their discretion with thirty (30) days written notice to the contractor. In the event of Contract termination, all finished or unfinished work, or un-used material, already paid for under Contract prices, shall become the property of the Town of Burlington.

ARTICLE 4

CONTRACTOR

4.1 DEFINITION

4.1.1

The Contractor is the person or entity identified as such in the Owner-Contractor

Agreement and is referred to throughout the Contract Documents as if singular in number and masculine in gender. The term Contractor means the Contractor or their authorized representative.

4.2 REVIEW OF CONTRACT DOCUMENTS

4.2.1

The Contractor shall carefully study and compare the Contract Documents and shall at once report to the Owner any error, inconsistency or omission they may discover. The Contractor shall not be liable to the Owner for any damage resulting from errors, inconsistencies or omissions in the Contract Documents which they discover but shall be liable for damage to the extent they reasonably should have but failed to discover such errors, inconsistencies or omissions. The Contractor shall perform no portion of the Work at any time without

Contract Documents or, where required, approved Shop Drawings, Product Data or

Samples for such portion of the Work.

4.3 SUPERVISION AND CONSTRUCTION PROCEDURES

4.3.1

The Contractor shall supervise and direct the Work, using their best skill and attention which shall not be less than such state of skill and attention generally rendered by the contracting profession for projects similar to the Project in scope, difficulty and location.

The Contractor shall maintain adequate supervisory personnel at the Site during the performance of the Work. The Contractor shall be solely responsible for all construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract.

4.3.2

The Contractor shall be responsible to the Owner for the acts and omissions of their employees, Subcontractors and their agents and employees, and other persons performing any of the Work under a contract with the Contractor. This obligation shall also extend to the presence on the Site of suppliers of materials or equipment, their employees, contractors, and agents engaged in the work.

4.3.3

The Contractor shall not be relieved from their obligations to perform the Work in accordance with the Contract Documents either by the activities or duties of the Owner in its administration of the Contract.

4.4 LABOR AND MATERIALS

4.4.1

Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for all labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and service necessary for the proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work.

4.4.2

The Contractor shall at all times enforce strict discipline and good order among their employees and shall not employ on the Work any unfit person or anyone not skilled in the task assigned to them including all persons on the Site controlled directly or indirectly by the Contractor.

4.5 WARRANTY

4.5.1

The Contractor warrants to the Owner that all materials and equipment furnished under this

Contract will be new and of recent manufacture unless otherwise permitted in writing by the Owner and that all Work will be of good quality, free from faults and defects and in conformance with the Contract Documents. All Work not conforming to these requirements, including substitutions not properly approved and authorized, may be considered defective and, promptly after written notification of non-conformance, shall be repaired or replaced by the Contractor with Work conforming to such requirements. If required by the Owner, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment.

4.6 TAXES

4.6.1

The Contractor shall pay all applicable sales, consumer, use and other similar taxes for the

Work or portion thereof provided by the Contractor which are legally enacted at the time bids are received, whether or not yet effective.

4.7 PERMITS, FEES AND NOTICES

4.7.1

Unless otherwise expressly provided in the SPECIAL CONDITIONS, the Contractor shall secure and pay for all permits and fees, licenses and inspections necessary for the proper execution and completion of the Work which are customarily secured after execution of the Contract and which are legally required at the time the bids are received, and the same shall at all times be the property of the Owner and shall be delivered to the Owner upon completion of the Project.

4.7.2

The Contractor shall give all notices and comply with all federal, state and local laws, ordinances, rules, regulations and lawful orders of any public authority bearing on the performance of the Work. The Contractor shall provide the Owner with reproductions of all permits, licenses and receipts for any fees paid. The Owner represents that it has disclosed to the Contractor all orders and requirements known to the Owner of any public authority particular to this Contract.

4.7.3

If the Contractor observes that any of the Contract Documents are at variance with applicable laws, statutes, codes and regulations in any respect, they shall promptly notify the Owner in writing, and any necessary changes shall be accomplished by appropriate

Modification.

4.7.4

If the Contractor performs any Work which they know or should know is contrary to such laws, ordinances, rules and regulations, and without such notice to the Owner, they shall assume full responsibility therefore and shall bear all costs attributable thereto.

4.8 SUPERINTENDENT

4.8.1

The Contractor shall employ a competent superintendent and necessary assistants who shall be in attendance at the Project site at all times during the progress of the Work. The superintendent shall represent the Contractor and all communications given to the superintendent shall be as binding as if given to the Contractor. Important communications shall be confirmed in writing. Other communications shall be so confirmed on written request in each case.

4.9 PROGRESS SCHEDULE

4.9.1

The Contractor, immediately after being awarded the Contract, shall prepare and submit for the Owner’s information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract

Documents, and shall provide for expeditious and practicable execution of the Work.

No work shall start without the Project schedule. The Contractor shall submit the project schedule five days prior to start the work.

4.10 DOCUMENTS AND SAMPLES AT THE SITE

4.10.1

The Contractor shall maintain at the site for the Owner one record copy of all Drawings, Specifications, Addenda, Change Orders and other Modifications, and “As-Built”

Drawings and Specifications in good order and marked currently to record all changes made during construction, and approved Shop Drawings, Product Data and Samples. These shall be available to the Owner upon completion of the Work.

4.11 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES

4.11.1

Shop Drawings are drawings, diagrams, schedules and other data specially prepared for the

Work by the Contractor or any Subcontractor, manufacturer, supplier or distributor to illustrate some portion of the Work.

4.11.2

Product Data are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate a material, product or system for some portion of the Work.

4.11.3

Samples are physical examples which illustrate materials, equipment or workmanship and establish standards by which the Work will be judged.

4.11.4

The Contractor shall review, approve and submit, with reasonable promptness and in such sequence as to cause no delay in the Work or in the work of the Owner or any separate contractor, all Shop Drawings, Product Data and Samples required by the Contract

Documents.

4.11.5

By approving and submitting Shop Drawings, Product Data and Samples, the Contractor represents that they have determined and verified all material, field measurements, and field construction criteria related thereto, or will do so, and that they have checked and coordinated the information contained within such submittals with the requirements of the

Work and of the Contract Documents.

4.11.6

The Contractor shall not be relieved of responsibility for any deviation from the requirements or the Contract Documents by the Owner’s approval of Shop Drawings, Product Data or Samples or the Superintendent’s approval of the same unless the

Contractor has specifically informed the Owner or Superintendent in writing of such deviation at the time of submission and the Owner or Superintendent has given written approval to the specific deviation. The Contractor shall not be relieved from responsibility from errors or omissions in the Shop Drawings, Product Data or Samples by the Owner’s approval thereof.

4.11.7

The Contractor shall direct specific attention, in writing or on resubmitted Shop Drawings, Product Data or Samples, to revisions other than those requested by the Owner or its

Superintendent on previous submittals.

4.11.8

No portion of the Work requiring submission of a Shop Drawing, Product Data or Sample shall be commenced until the submittal has been approved by the Owner or Superintendent.

All such portions of the Work shall be in accordance with approved submittals.

4.12 USE OF SITE

4.12.1

The Contractor shall confine operations at the site to areas permitted by law, ordinances, permits and the Contract Documents and shall not unreasonably encumber the site with any materials or equipment.

4.13 CUTTING AND PATCHING OF WORK

4.13.1

The Contractor shall be responsible for all cutting, fitting or patching that may be required to complete the Work or to make its several parts fit together properly.

4.13.2

The Contractor shall not damage or endanger any portion of the Work or the work of the

Owner or any separate contractors by cutting, patching or otherwise altering any work or by excavation. The Contractor shall not cut or otherwise alter the work of the Owner or any separate contractor except with the written consent of the Owner and of such separate contractor. The Contractor shall not unreasonably withhold from the Owner or any separate contractor their consent to cutting or otherwise altering the Work.

4.14 CLEANING UP

4.14.1

The Contractor at all times shall keep the premises free from accumulation of waste materials or rubbish caused by their operations. At the completion of the Work they shall remove all their waste materials and rubbish from and about the Project in full compliance with all applicable laws and regulations as well as all their tools, construction equipment, machinery and surplus materials and the Project shall be thoroughly cleaned and ready for immediate occupancy by the Owner.

4.14.2

If the Contractor fails to clean up at the completion of the Work, the Owner may do so as provided in Paragraph 3.4 and the cost thereof shall be charged to the Contractor.

4.15 COMMUNICATIONS

4.15.1

The Contractor shall forward all communications to the Owner’s designated representative.

4.15.2

The Contractor shall at all times have a designated representative in the field that is authorized to act on behalf and make decisions for the Contractor under this contract agreement.

4.16 ROYALTIES AND PATENTS

4.16.1

The Contractor shall pay all royalties and license fees. The Contractor shall defend all suits or claims for infringement of any patent rights and shall save the Owner harmless from loss on account thereof, except that the Owner shall be responsible for all such loss when a particular design, process or the product of a particular manufacturer or manufacturers is specified, but if the Contractor believes or has reason to believe that the design, process or product specified is an infringement of a patent, they shall be responsible for such loss unless they promptly gives such information to the Owner, and thereafter the Owner insists on the use of the design, process or products specified.

4.17 INDEMNIFICATION

4.17.1

To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Owner, the Superintendent and their agents and employees from and against all claims, damages, losses and expenses, including but not limited to attorney’s fees, arising out of or resulting from the performance of the Work, provided that any such claim, damage, loss or expense (1) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself) including the loss of use resulting there from, and (2) is caused in whole or in part by any negligent act or omission of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified there under. Such obligation shall not be construed to negate, abridge, or otherwise reduce any other right or of indemnity which would otherwise exist as to any party or person described in this Paragraph 4.17.

4.17.2

In any and all claims against the Owner the Superintendent or any of their agents or employees by any employee of the Contractor, any Subcontractor anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, the indemnification obligation under this Paragraph 4.17 shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Contractor or any Subcontractor under workers’ or workmen’s compensation acts, disability benefit acts or other employee benefit acts.

4.17.3

The obligations of the Contractor under this paragraph 4.17 shall not extend to the liability of the Owner, the Superintendent, their agents or employees, arising out of (1) the preparation or approval of maps, drawings, opinions, reports, surveys, change orders, designs or specifications, or (2) written directions or instructions given by the Owner, the

Superintendent, their agents or employees, provided they are the sole cause of the injury or damage.

ARTICLE 5

INSURANCE

Contractor shall provide insurance as specified below:

GENERAL LIABILITY

Includes:

Comprehensive form

Premises/Operations

Underground Explosion & Collapse

Hazard

Products / Completed Operations

Independent Contractors

Broad From Property Damage

Personal Injury

Each Occurrence $1,000,000

Aggregate $2,000,000

Automobile Liability

Includes:

All Owned Vehicles

Hired Vehicles

Non-owned Vehicles

Bodily Injury & Property

Damage Combined

$1,000,000

Workers Compensation & Employers Liability

As Required by State of Massachusetts

Each Accident $100,000

Bodily Injury by Disease

(Policy Limit)

$500,000

Bodily Injury by Disease

(Each Employee)

$100,000

Additional Insurance / Requirements

The Town of Burlington Shall be named as Additional

Insured

File details come from the government source that posted it. Updated .