27-0015 Attachment E- Estimated Schedule.PDF
PDF 71 KB Posted
- Solicitation number
- RFP DET 260000002457 3
- Issued by
- Wayne County, Detroit City, Michigan
About this file
This is an estimated project schedule for the General Contractor procurement for Cass Tech Athletic Field Renovation in Michigan. The project timeline spans from September 30, 2026, through October 29, 2027, encompassing multiple phases including procurement, contract execution, contractor onboarding, construction, and closeout activities. The General Contractor procurement phase is scheduled for 130 days, extending from September 30, 2026, to March 30, 2027. Following procurement, the Board vote is allocated 30 days (September 30 to November 10, 2026), with contract signing and purchase order issuance both scheduled for 30 days (November 11 to December 22, 2026). The General Contractor onboarding phase, which includes pre-construction activities, submittals, and materials procurement, is budgeted for 70 days (December 23, 2026, to March 30, 2027).
Construction activities are scheduled to commence on March 31, 2027, and continue for 98 days through August 13, 2027. The project closeout phase follows immediately thereafter, allocated 55 days from August 16 through October 29, 2027. The schedule was prepared as of July 13, 2026, and reflects a sequential progression through procurement, contracting, pre-construction preparation, active construction, and final project closeout stages. No additional pricing, funding, or contractual terms are detailed in this schedule document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task
Mode
Task Name Duration Start Finish
1 GC Procurement 130 days Wed 9/30/26 Tue 3/30/27
2 Board Vote 30 days Wed 9/30/26 Tue 11/10/26
3 Contract Signed 30 days Wed 11/11/26Tue 12/22/26
4 PO Issued 30 days Wed 11/11/26Tue 12/22/26
5 GC Onboard for Pre-Con /
Submittals / Materials
70 days Wed
12/23/26
Tue 3/30/27
6 Construction 98 days Wed 3/31/27 Fri 8/13/27
7 Closeout 55 days Mon 8/16/27 Fri 10/29/27
W T F S S M T W T F S S M T W T F
Oct 4, '26 Oct 11, '26
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Cass Tech Bidding Sche
Date: Mon 7/13/26
File details come from the government source that posted it. Updated .