This is an Authorization to Advertise document issued by Collier County Board of County Commissioners, on behalf of the Public Utilities Department and Engineering and Project Management Division, authorizing the release of Request for Professional Services solicitation 26-8635 for the South County Water Reclamation Facility (SCWRF) Treatment Technology & Flow Management Improvements project. The selected firm will serve as Engineer of Record and provide comprehensive design and construction administration services, including preliminary design, geotechnical surveys, surveying, subsurface utility engineering, hydraulic and wastewater treatment process modeling, final design, permitting, bidding packages, opinion of probable costs, public involvement services, construction administration, and one-year construction warranty services. The project encompasses comprehensive plant capacity expansion from 16 million gallons per day to 21.1 MGD average flow and 56 MGD peak flow, incorporating membrane bioreactor technology and improvements to preliminary treatment facilities, coarse screening, grit removal, fine screening, secondary treatment enhancements, activated sludge processes, tertiary filtration, disinfection systems, flow equalization and pumping systems, electrical and odor control systems, effluent and reject water storage and pumping, deep injection well pumping, sludge storage, pumping, and dewatering, plus a material storage building. The proposal submission deadline is March 9, 2026, at 3:00 P.M. EST, with a pre-proposal conference scheduled for February 19, 2026, at 10:00 A.M. Design must be completed within one year of Notice to Proceed, with construction targeted for completion by 2031.
The Authorization to Advertise was signed February 4, 2026, by Sandra Srnka, Procurement Director, confirming that budgetary resources have been identified and a cost estimate was obtained to fund the resulting award. No local vendor preference or grant funding is designated in this authorization. The preliminary cost estimate for the overall capacity expansion improvements totals approximately $30.0 million, though the specific budget for design and construction administration services is not explicitly stated. Permitting fees will be paid by the Public Utilities Department for county permits and by the Engineer of Record team with reimbursement by PUD for state and federal permits. The evaluation will utilize the Consultants' Competitive Negotiation Act methodology, scoring submissions on six criteria: Ability of Professional Personnel (20 points), Certified Woman and/or Minority Business Enterprise status (5 points), Past Performance (25 points), Project Approach and Willingness to Meet Time and Budget Requirements (20 points), Location (10 points), and Recent, Current, and Projected Workloads (20 points), totaling 100 points.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Authorization to Advertise Date: ______________
Solicitation No.: Title:
Due Date and Time:
Utilizing Local Vendor Preference: Yes No Grant Funded: Yes No
By signing, I am acknowledging that I have reviewed the above referenced solicitation prior to being released to advertisement, and that the approach, scope and specifications are acceptable.
I also acknowledge that a cost estimate or opinion of cost was obtained, and that budgetary resources have been identified to fund any resulting award within the budgeted or reasonable Threshold.
The approach being taken with this solicitation and intended end use of the contract is intended to support the management and operational needs of the Division and takes other potential using Divisions’ needs into consideration (when applicable).
Required Signatures
Design Professional:
Project Manager:
Division Director:
Procurement Strategist:
Grants Office: Required grantor conditions have been provided in the solicitation, grantor approvals have been obtained, and the package appears compliant with federal/state funding requirements.
Sandra Srnka, Procurement Director
Procurement Services Division
February 4, 2026
26-8635 SCWRF Treatment Technology & Flow Management Improvements
March 9, 2026, at 3:00 PM (EST)
N/A
N/A
Docusign Envelope ID: 7AC525E3-9C4D-4A7E-97D8-BA9025920E3B
2/4/2026
2/4/2026
2/4/2026
2/4/2026
| 2026-02-04T14:51:51-0800 | |
| Digitally verifiable PDF exported from www.docusign.com |
File details come from the government source that posted it. Updated .