Summary

This is a Request for Professional Services (RPS) issued by the Collier County Board of County Commissioners Procurement Services Division on behalf of the Public Utilities Department for comprehensive design and construction administration services for the South County Water Reclamation Facility (SCWRF) Treatment Technology & Flow Management Improvements project located in Naples, Florida. The selected firm will serve as Engineer of Record and perform preliminary design, geotechnical surveys, surveying, subsurface utility engineering, hydraulic modeling, wastewater treatment process modeling, final design, permitting, bidding packages, construction administration services, and one-year warranty services. The project scope includes comprehensive plant capacity expansion from 16 million gallons per day (MGD) to 21.1 MGD average flow and 56 MGD peak flow, incorporating membrane bioreactor (MBR) technology and various facility improvements including preliminary treatment facilities, flow equalization tanks, secondary treatment enhancements, tertiary filtration, disinfection systems, electrical and odor control systems, solids handling, reject and reclaimed water storage, and a material storage building. A pre-proposal conference is scheduled for February 19, 2026, at 10:00 A.M., and RPS opening is March 9, 2026, at 3:00 P.M. The design must be completed within one year of the Notice to Proceed, with construction targeted for completion by 2031. Proposals must be submitted online through the Collier County Procurement Services Division Online Bidding System.

The RPS evaluation will utilize a shortlist development process with scoring based on six criteria: ability of professional personnel (20 points), certified woman and/or minority business enterprise status (5 points), past performance (25 points), project approach and willingness to meet time and budget requirements (20 points), location (10 points), and recent, current, and projected workloads (20 points), for a total of 100 points. Permitting fees will be paid by the Public Utilities Department for county permits and by the EOR team (with reimbursement by PUD) for state and federal permits from FDEP, SFWMD, and USACOE. Prices shall remain firm for the contract term with no surcharges accepted. The contract will commence upon issuance of the Notice to Proceed and conclude upon acceptance and approval of final payment. County reserves the right to modify the scope during negotiations for budgetary reasons. All proposals must address the stated specifications and scope of work, and proposers are referred to as consultants, firms, offerors, contractors, or vendors.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(Template Version 1)

COLLIER COUNTY

BOARD OF COUNTY COMMISSIONERS

REQUEST FOR PROFESSIONAL SERVICES (RPS)

In accordance with Florida Statute 287.055 Consultants’ Competitive Negotiation Act

FOR

SCWRF Treatment Technology & Flow Management Improvements

RPS NO.: 26-8635

DANIAGUERRERO, PROCUREMENT STRATEGIST, III

PROCUREMENT SERVICES DIVISION

3295 TAMIAMI TRAIL EAST, BLDG C-2

NAPLES, FLORIDA 34112

TELEPHONE: (239) 252-7989

Dania.Guerrero@collier.gov (Email)

SOLICITATION PUBLIC NOTICE

REQUEST FOR

PROFESSIONAL SERVICES

(RPS) NUMBER:

26-8635

PROJECT TITLE: SCWRF Treatment Technology & Flow Management Improvements

PRE-PROPOSAL

CONFERENCE:

February 19, 2026, at 10:00 A.M (EST)

LOCATION: PROCUREMENT SERVICES DIVISION, CONFERENCE ROOM A,

3295 TAMIAMI TRAIL EAST, BLDG. C-2, NAPLES, FL 34112

RPS OPENING

DAY/DATE/TIME:

March 9, 2026, at 3:00 P.M (EST)

PLACE OF RPS OPENING: PROCUREMENT SERVICES DIVISION

3295 TAMIAMI TRAIL EAST, BLDG. C-2

NAPLES, FL 34112

All proposals shall be submitted online via the Collier County Procurement Services Division Online Bidding System: https://procurement.opengov.com/portal/collier-county-fl.

INTRODUCTION

As requested by the Engineering and Project Management Division (hereinafter, the “Division or Department”), the Collier County Board of County Commissioners Procurement Services Division (hereinafter, “County”) has issued this Request for Professional Services (hereinafter, “RPS”) with the intent of obtaining proposals from interested and qualified Proposers in accordance with the terms, conditions and specifications stated herein, in the Solicitation and/or attachments. The Proposers at a minimum, must achieve the requirements of the Specifications, Scope of Services or Scope of Work stated. All references to “Proposer” are also referred to as “Consultant,” “Firm,” “Offeror,” “Contractor,” and “Vendor.”

The selected firm shall perform comprehensive design and construction administration services to construct improvements of the Collier County Water–Sewer District’s (CCWSD’s) South County Water Reclamation Facility (SCWRF). Improvements contemplated include, but not limited to the following: Comprehensive plant capacity expansion of peak flow and average flow capacity, flow equalization and pumping; preliminary treatment, coarse screening, grit removal, fine screening; secondary treatment, incorporation of membrane bioreactor (MBR) technology into the plant design, activated sludge processes, filtration, disinfection, effluent and reject water storage and pumping, deep injection well pumping, sludge storage, pumping, and dewatering

The selected firm will perform preliminary design, geotechnical surveys, surveying, subsurface utility engineering, hydraulic modeling, wastewater treatment process modeling, final design, permitting, bidding packages, opinion of probable costs, public involvement services, construction administration services, and construction warranty services.

The selected firm will also coordinate with Public Utilities Department staff, Engineering and Project Management Division (“PUD”) staff, neighboring community, local electrical utilities, and the Growth Management and Community Development Department to deliver the planned infrastructure improvements

Specific sections of this scope may be deleted during contract negotiations.

BACKGROUND

The CCWSD owns and operates the South County Water Reclamation Facility (SCWRF). The SCWRF original construction was completed in 1991. It was expanded to its current maximum month average daily flow (MMADF) permitted capacity of 16 million gallon per day (MGD) in 2005.

The 2025 Annual Update and Inventory Report identified a planned treatment technology and flow management improvement project at SCWRF is expected to increase the plant's treatment capacity by 5.1 MMADF MGD resulting in a total treatment capacity of 21.1 MMADF MGD and is anticipated to be online in FY 2031.

https://procurement.opengov.com/portal/collier-county-fl

The goal of this project is to implement the necessary upgrades to manage current and projected wet weather demands effectively. This initiative ensures continuous regulatory compliance and expands the capacity to provide treated, reclaimed water for beneficial reuse to customers.

The SCWRF is a modified activated sludge domestic wastewater treatment plant consisting of two (2) 1.25-million-gallon (MG) flow equalization tanks (total capacity 2.5 MG), and odor control system, influent screening, grit removal system, fourteen (14) biological treatment basins consisting of anoxic and aerobic (total capacity 7.0 MG), six (6) turbo blowers and two (2) multi-stage centrifugal blowers to provide process air to the aerations basins, clarifier splitter structure, four (4) circular center feed clarifiers, eight (8) sand filters each 960 sq. ft. (total area 3,840 sq. ft.), sodium hypochlorite chemical feed system, four (4) chlorine contact tanks (total volume 412,000 gallons), two (2) 330,000-gallon aerated sludge holding tanks (total capacity 660,000 gallons), and four (4) belt filter presses for residuals handling. The treatment facility can be operated in modified Ludzack-Ettinger mode or in conventional activated sludge mode.

The SCWRF’s permitted capacity of 16 MGD MMADF could handle influent flows as high as 40 MGD peak hour (wet weather) through the preliminary treatment facility prior to flow equalization. The wet weather peak flows are managed using two (2) preliminary treatment train facilities, two (2) equalization tanks and the use of four (4) existing aeration basins as additional flow equalization.

Effluent disposal consists of the County’s slow rate of public access reclaimed water system and two (2) Class 1 injection wells.

Treatment Technology and Flow Management Improvements

The County has explored the use of Membrane Bioreactor (MBR) to increase peak and average capacity. The selected firm will incorporate MBR technology improvements, or other treatment technology as otherwise approved by the Department, into this project.

The primary goal of the project is to improve wet weather plant capacity to treat a minimum peak flow prior to flow equalization of 56.0 MGD with a minimum average capacity of 21.1 MGD MMADF, or as otherwise approved by the County. The goal of the project is to complete construction by 2031. The design shall include preliminary plans for future improvements including increases in capacity, conversion to advanced wastewater treatment for nutrient removal, and additional or full MBR capacity conversion. The firm selected to complete design within one year (365 days) of issuance of the Notice to Proceed, or as otherwise approved by the Department.

As outlined in a Technical Memorandum dated February 2011, the conceptual concept for capacity expansion at the SCWRF is the potential conversion of a portion of the aeration basin passes to MBR (membrane bioreactor) mode of operation. The proposed work for this conceptual conversion would be the installation of new equipment in some of the existing aeration basins, thus not requiring construction of new aeration basins. The remaining components of the facility expansion would be those which have the potential to be constructed inside a building and other structures located to the north of the aeration basins. A copy of this memorandum is included as attachment 26-8635 Exhibit - Tech Memo #9 Capacity Expansion Considerations February 2011to this solicitation.

The design shall be comprehensive and be integrated and consistent with the entire treatment facility. The firm will be expected to coordinate with the Department (PUD) to define and determine the size, capacity, redundancy, and reliability criteria for the new, existing or improved facilities.

Preliminary Treatment Facility Improvements

The design shall include reliable new preliminary treatment facilities with the capability to take one (1) new treatment train out of service while maintaining wet weather criterion. The preliminary treatment facilities for the MBR treatment trains shall incorporate coarse screening (6 mm), grit removal, and fine screening (2 mm) or as otherwise approved by the Department. The constructed capacity of the new preliminary treatment facilities shall be large enough to treat the entire plant flow, or to reliably take the existing preliminary treatment trains out of service for rehabilitation.

The preliminary design shall include the future expansion of the preliminary treatment facility to handle all plant flow and future consideration of increased peak flow capacity.

Flow Equalization Facility Improvements

Review and provide recommendations on flow equalization facilities required for the proposed facilities. At a minimum, subject to review and approval by the County:

• Addition of at least one additional flow equalization tank shall be included.

• Modifications to the existing flow equalization tanks to provide pump stations for each tank dedicated to mixing systems and return of equalized flow to the treatment process.

• Review and modification of the existing flow control facilities that send flow to flow equalization.

Receiving Facility for Vactor Trucks and Pumper Trucks

A facility to receive material from County-owned vactor trucks has been designed by others. The project shall include assumption of this engineering design with a revised location on site at the SCWRF in coordination with the proposed facilities. The design shall be reviewed and modified as necessary to be incorporated in the plant site.

Additionally, at times, the plant receives wastewater from pumper trucks hauling sewage from the CCWSD’s sewerage system. The design shall include facilities to allow for receiving and preliminary treatment of this wastewater along with pumping to the plant’s preliminary treatment facility.

Reclaimed Water Pump Station Improvements:

Evaluate and design improvements to the existing combined reclaimed water and deep injection well pump station to expand its pumping capabilities.

Deep Injection Well Pump Station

Design shall include an independent deep injection well (DIW) pump station to provide effluent disposal at the full rated capacity of the existing DIW systems two (2) wells, at approximately 18 MGD each, and reliable backup for reuse pumping to the existing slow rate public access reclaimed water system. Design shall evaluate the need to mitigate hydraulic pressures.

Existing Activated Sludge Secondary Treatment Improvements

• Evaluate and design improvements to the existing aeration basin tank drainage system including the associated valves and pumping systems.

• Design a comprehensive rehabilitation of the activated sludge treatment mixed liquor splitter structure including flow splitting gates, weirs, aeration system, and structural considerations.

• Evaluate and as necessary, design improvements to the existing clarifiers, associated return pumping systems, and sludge wasting systems. Provide recommendations for improvements to be included in the design.

Tertiary Filtration and Effluent Disinfection

The plant utilizes shallow bed traveling bridge sand filters for tertiary filtration and sodium hypochlorite with chlorine contact basins for effluent disinfection.

• Evaluate and design improvements and replacement equipment for the existing tertiary filtration systems.

• Provide design of tertiary filtration and effluent disinfection to accommodate increased plant average and peak flows as required.

• In the preliminary design, evaluate Ultraviolet Light (UV) Disinfection as an alternative means of effluent disinfection.

Electrical Service and Power Systems

Design shall provide an additional electrical service for the plant including reliable double-ended switchgear, motor control centers, and generators sized for final build out of all passes converted to MBR, as well as meeting all project needs.

Odor Control

Design to include Odor Control System(s) to treat odors for new or modified facilities, and project improvements.

The requirement is to remain in compliance with FDEP requirements and County goals to prevent discharge of odors offsite.

Reject and Reclaimed Water Storage

The existing plant uses a repurposed oxidation ditch structure for reject water and reclaimed water storage. The outer ring, 3 million gallons (MG), is generally used for reject water storage, which can either be disposed of by pumping into the deep injection wells or drained to the reject pond for retreatment. The inner passes (3 MG) are used for reclaimed water storage. The effluent pump station draws from the tanks and discharges to either the CCWSD’s slow rate public access reuse system, or to the deep injection wells. The plant has a 4 MG reject water storage pond. Reject water from the pond is returned to the plant though a plant drain pump station.

This project includes modifications of existing tanks and ponds to provide minimum of 3 MG of additional reclaimed water storage (minimum of 6 MG of reclaimed water storage is required) and a minimum of 3 MG of reject water storage in a tank(s) to allow for pumping to the DIW system or retreatment though the plant. The existing reject pond can be modified, retained or eliminated as required for the comprehensive facility design.

Solids Handling Improvements

• Design to include additional aerated sludge holding tank(s) and associated pumping systems to supplement the existing systems as required to provide the required capacity for the facility.

• Design shall include and allocate space for the ultimate future capacity expansion.

• Additional sludge dewatering system(s) potential using belt filter press or screw press technology to provide additional sludge dewatering capacity.

Material Storage Building

Design a material storage building on the SCWRF site. Conceptual size is minimum 40’ x 60’, or as otherwise approved by the Department.

Comprehensive Services and Components

The improvements include, but are not limited to the following components:

• Tanks

• Pumping facilities

• Buildings

• Pumps, piping, valves, and other appurtenances

• Mechanical Systems including plumbing and Heating, Ventilation and Air Conditioning (HVAC)

• Odor Control facilities

• Structural

• Electrical and Supervisory Control and Data Acquisition (SCADA)

• Generator/fuel systems

• Chemical feed systems

• Storm Water improvement and treatment concepts, quantity attenuation, storage, and runoff rate management and reduction

• Access Roads

• Pathway/sidewalk

• Landscaping

• Security

• Site improvements

• Coordination with other construction projects, designed by other professionals

AWARD AND TERM OF AGREEMENT

County reserves the right to modify this scope during negotiations for budgetary reasons.

The agreement term, if an award is made is intended to be for will commence on the date of the Notice to Proceed, and end upon acceptance and approval of the final payment.

Prices shall remain firm for the term of the awarded contract.

Surcharges will not be accepted in conjunction with this award, and such charges should be incorporated into the pricing structure.

DETAILED SCOPE OF SERVICES

The Public Utilities Department (PUD) is interested in contracting with a qualified firm to become the Engineer of Record (EOR) for the design, permitting, bidding and construction services to develop and implement the South County Water Reclamation Facility Treatment Technology & Flow Management Improvements project located at 5600 Warren Street, Naples, Florida 34113.

Scope of Services

The Design team will provide professional services throughout the project consisting of, but not limited to:

1. Project management

2. Data gathering

3. Site Visits

4. Graphics/exhibit preparation

5. Project phasing for Construction

6. Project meeting assistance

7. Public meeting assistance

8. Project Management Plan preparation

9. Public Involvement Services

10. Modeling

11. Scheduling

12. Preliminary design

13. Final design

14. Bidding Services

15. Equipment evaluation and selection

16. Subsurface investigations of underground utilities

17. Geotechnical exploration and engineering

18. Land surveying

19. Environmental Impacts

20. Permitting

21. Preparation of Bid packages

22. Construction Administration Services

23. Post Design Services

Project Meetings: Project meetings with PUD staff will be conducted, as requested by the Project Manager, throughout the project to keep staff informed of the progress, schedule and to obtain input and direction as required for outstanding project issues.

a. A firm day and time will be established for all progress meetings.

b. The meeting objectives will be to provide progress updates and reach decisions on pertinent issues related to the specific topics being addressed.

c. The Engineer of Record (EOR) will prepare and distribute Agendas and Meeting Minutes for each meeting. The EOR team shall prepare an Agenda that will be submitted to the project delivery team at least two (2) days prior to the meeting. Meeting Minutes summarizing the discussion and Project action plan shall be prepared and distributed by the EOR no more than two (2) working days following the meeting. PUD staff will provide comments for no more than two (2) working days after receipt of meeting minutes. EOR will make the revisions and re-distribute the revised Meeting Minutes no later than two (2) business days after receiving all comments from PUD staff.

Project Schedule: The EOR shall provide an initial project schedule and update the schedule monthly or as otherwise accepted by the County throughout the duration of the design and construction.

Cost Estimating: Project cost estimates shall be provided for all phases of the project or as otherwise determined by the County Project Manager.

TASK 1: Preliminary Engineering Design

1.1 Project Initiation

a. Initial Kick-Off Meeting – The EOR will organize an initial Kick-off Meeting with PUD staff to review the project scope, operational flexibility objectives and requirements, operational issues, known single points of failures, project objectives/goals, project standards and project schedule for completing the work.

b. Initial Project Schedule – The EOR team will prepare an initial project schedule and submit to PUD staff at the Initial Kick-off Meeting for review and acceptance.

1.2 Data Collection

a. Utility Record Drawings – The EOR team will review the CCWSD’s utility record drawings and other documents related to the project prior to the kick-off meeting.

b. Data Gathering & Review – F Gather and review all available existing documentation, including record drawings (piping, structural, mechanical, electrical, SCADA), operation and maintenance manuals, and historical performance data.

c. Site Investigation – Conduct site visits and field inspections to verify existing conditions, collect necessary measurements, determine the location of existing utilities, identify potential site constraints, access problems. Meet with PUD staff to obtain knowledge of the existing facility, operational practices, existing conditions, confirm record drawing information, confirm assumptions.

1.3 Preliminary Engineering Design Report(s)

Preliminary Design Progress Meetings - Weekly meetings will be conducted with PUD representatives to review progress and discuss the preliminary design phase.

The Engineer of Record (EOR) shall perform the following services to develop a comprehensive Preliminary Design Report:

1) Technical Memorandums (TMs)

The Engineer of Record (EOR) is responsible for preparing Technical Memorandums (TMs) for this project.

These TMs will be incorporated into the Preliminary Design Report. The EOR shall schedule meetings with PUD staff to review, discuss, and update these documents as needed.

The content and scope of the TMs shall include, but are not limited to, the following tasks and areas of focus:

a) Data Gathering & Review- Gather and review all record drawings of the SCWRF treatment facilities, including piping, structural, mechanical, electrical, instrumentation and control (SCADA) systems, and other relevant infrastructure.

b) Define Project Needs-Clearly articulate the need for the project based on identified deficiencies, regulatory compliance issues, and capacity requirements.

c) Regulatory Coordination- Coordinate with local and state regulatory agencies to identify applicable design criteria and permitting requirements.

d) Recommendations for Improvements- Provide recommendations for process configurations and enhancements that improve efficiency, optimize the facility footprint, and enhance cost-effectiveness. This evaluation will serve as the basis of design for all future improvements.

e) Hydraulic Profile Analysis- Review and update the facility's hydraulic profile for County review and approval.

f) Process Flow Diagram Update- Identify and update the Overall Plant Process Flow Diagram of the existing facility.

g) Flow and Loading Design Basis- A draft and final technical memorandum shall be prepared to document the flow and load design basis and effluent requirements.

h) Process Modeling - Wastewater process modeling using the defined flows and loads. An overall process flow diagram will be developed. The purpose of the model is to develop a mass balance for use in evaluation of solids process alternatives, to size all major unit processes, and define process design criteria.

i) Included detailed analyses of the proposed membrane bioreactor (MBR) and activated sludge biological treatment systems under both seasonal and non-seasonal loadings. Provide recommendations and sequencing to ensure treatment facilities remain operational and incompliance with FDEP operating permits.

j) Define space and design concepts for future capacity expansion and treatment process improvements.

k) Identify all necessary electrical systems and expansion needed for this project.

l) Preliminary design of proposed Supervisory Control and Data Acquisition (SCADA) System

m) Review existing tertiary treatment facilities and existing effluent transfer pumping systems and confirm adequacy and identify and design needed improvements.

n) Civil/Site Improvements including vactor and pumper truck disposal site

o) Long Lead Procurement register/Direct Material Purchase (DMP) considerations

p) Determine zoning and/or environmental ramifications to the site, and impacts to the existing permits. Review and revise the existing Site Development Plan.

q) Odors, Noise, Dust, Light-Identify improvements to ensure no offsite odors, no offsite dust or mist, noise levels do not exceed code/ordinance standards and lighting pollution does not exceed code/ordinance standards.

r) Reliability Considerations- All facilities shall be designed to meet a minimum of EPA Class 1 reliability or as otherwise directed by the County. The reliability of each unit process shall be presented, reviewed and discussed as part of the preliminary design phase.

s) Identify/Ensure Operational Flexibility

t) Determine Performance Driven Standards- EOR is required to identify, establish, and incorporate specific, measurable criteria for the project's success that are based on desired operational outcomes rather than just prescriptive design rules. The engineer shall define the minimum acceptable performance levels that the final wastewater treatment facility (or its components) must achieve to satisfy the owner's needs and regulatory requirements.

u) Cost-Benefit Analysis- Investigate and provide a cost-benefit analysis comparing existing processes, proposed processes, and design components. This analysis should benchmark against Membrane Bioreactor (MBR) technology currently used in other Florida treatment facilities or similar wastewater treatment facilities. A full Life Cycle Cost Analysis (LCCA) shall be performed for all feasible alternatives to compare present worth costs (capital, O&M).

v) Construction Phasing/Sequencing- Develop and provide a written construction phasing and sequencing plan to the County to complete all treatment improvements, including the Maintenance of Plant Operation (MOPO) plan.

w) Specific Facility Improvements- The content of the technical memorandums shall address the following systems:

1. Capacity Expansion to a minimum of 21.1 MGD MMADF and 56 MGD peak flow prior to flow equalization.

2. Treatment Plant Capacity Analysis Report

3. Preliminary Treatment Facility

4. Flow Equalization Facilities

5. Effluent Filtration Facilities

6. Effluent Disinfection

7. Receiving Facility for Vactor and Pumper Trucks

8. Reclaimed Water Pump Station

9. Deep Injection Well Pump Station

10. Existing Activated Sludge Secondary Treatment

11. Electrical Service and Power Systems

12. Odor Control

13. Reject and Reclaimed Water Storage

14. Solids Handling

15. Site Planning, Zoning and Permitting

2) Preliminary Design Report (PDR)

a) The EOR shall prepare a comprehensive PDR that summarizes all preliminary work completed under this project and incorporates all finalized TMs.

b) Prepare the PDR with evaluation of the existing treatment system(s), recommendations of proposed improvements.

c) Provide a cost analysis and project phasing/sequencing plan for the improvements.

d) The Report shall consist of, but not be limited to, the following sections, incorporating results from the

Technical Memorandums tasks, or as otherwise approved by the Department:

1. Executive Summary

2. Introduction

3. Basis of Design/Design Criteria

4. Existing Facilities and Current Situation

5. Need for the Project

6. Alternative Analysis

7. Proposed Improvements

8. Environmental and Permitting

9. Cost Estimation and Financial Considerations

10. Implementation Plan and Schedule

11. Appendices

e) Review and Submission- The EOR will submit draft copies of the PDR to County staff for review. The EOR shall then organize and conduct meetings with County staff to review and discuss the report.

f) Final Deliverable- The EOR will revise the report as required based on County comments. The EOR shall submit the final, signed, and sealed reports (by a professional engineer registered in Florida), including electronic files of the final report in PDF format.

1.4 30% Plans Preparation

The EOR shall prepare 30% construction plans.

a. Incorporate the findings from the Preliminary Design Report (PDR) into the 30% construction plans.

b. Incorporate all record drawings within the project area and the soft dig investigation into the 30% construction plans.

c. Incorporate the boundary and topographic survey into the 30% construction plans.

d. Prepare 30% of the construction plans detailing the proposed yard piping and facility conceptual plans.

e. Submit three (3) full-size and one (1) half-size of the 30% construction plans at least two (2) weeks prior to the meeting with PUD Staff. Provide electronic copy in scalable PDF format.

f. Organize and conduct a 30% plan review meeting with PUD staff to discuss the preliminary construction plans. Revise construction plans as required to reflect PUD comments.

1.5 Surveying Services.

Tasks may include, but are not limited to:

a. EOR will provide PUD a site survey of the treatment facility area. The Site Survey shall be performed by a qualified Florida-licensed surveyor. The survey will establish baseline conditions for the design and serve as control of hydraulic points and miscellaneous items during construction.

b. Establish vertical and horizontal controls throughout project area. Elevations will be in either NAVD 1988 or NGVD 29 Datum and Coordinates, as required by the permitting agency’s regulations or otherwise directed by the County.

c. As soon as the survey is available, the EOR will submit two (2) full size, one (1) half size, and electronic files in PDF Format of legible copies of the Site Survey to PUD staff. Submit an AutoCAD file (dwg) of the Site Survey to PUD staff. The Site Survey shall include the latest aerial photography as a background and/or layer.

1.6 Geotechnical Investigation

a. Perform all necessary soil borings within the project area to construct proposed improvements. Soil borings shall be completed as per the latest American Society for Testing and Materials ASTM standards.

b. Perform all necessary laboratory testing and geotechnical work associated with the characterization of soils for structural design and laboratory testing of materials during construction.

c. Prepare a complete Geotechnical Investigation Report detailing soil conditions, water table elevations, soil classifications, rock elevation and other items that will affect the construction. The report shall also include recommendations from the Geotechnical Engineer on foundations, subsurface conditions and any other items that pertain to the construction project.

d. The EOR team shall submit two (2) signed and sealed reports to PUD Staff plus an electronic copy in PDF format.

1.7 Soft Dig Investigation

a. Meet with PUD Staff on-site to review procedures to complete the soft dig investigations.

b. Excavate existing utilities within the project area to include, but not be limited to, horizontal and vertical location of existing underground infrastructure, including but not limited to, electric duct-bank, utility pipe, type of utility pipe, size of utility pipe, utility pipe material and condition of existing pipe material. Soft Dig Investigations shall be performed using an approved air/vacuum piece of equipment that will keep the disturbance to a minimum and shall not damage any existing facilities.

c. Field Mark all existing utilities found either by wooden lathes or by marking on the pavement (nail & paint).

Marks need to remain during the design phase, but lathes need to be removed after the final plans have been approved. EOR is responsible for replacing all field marks up to two (2) times.

d. EOR shall repair all excavation holes in the natural ground and/or pavement to a condition as equal to or better than the original condition.

e. EOR shall provide one (1) full size, one (1) half size copies of the Soft Dig Investigation Map and one copy of the Soft Dig Investigation Report to PUD Staff. Provide additional copy of all information in electronic PDF format.

TASK 2: Design

2.1 Final Design

a. Based on the accepted PDR and 30% construction plans, EOR will prepare final drawings and specifications, which provide the general scope, extent, and character of the work to be furnished and performed by the Contractor. EOR will prepare and submit drawings and specifications at the 60-, 90-, and 100-percent complete stages for review and approval.

b. An engineer’s opinion of probable construction cost will accompany each submittal.

c. EOR shall meet with PUD’s design and operations staff and obtain their written acceptance (signature approval) at the 60-, 90-, and 100-percent complete stages.

d. The EOR shall ensure the drawings and specifications address reliability, operational flexibility and single points of failure identified in the Preliminary Design Report.

e. Technical specifications will be based on the latest format of the Construction Specifications Institute (CSI) in MS Word format. In addition to technical specifications, EOR will coordinate with PUD staff to develop necessary General Conditions, Supplemental Conditions, and Special Provisions specifically for the project being constructed and review of all lessons learned from similar completed projects. Standard Collier County Specifications may be used for reference, but the Engineer shall not rely on them as a replacement for sound engineering judgment and responsibility. Current County Right-of-Way construction specifications shall be utilized.

f. Drawings shall be consistent with Collier County standards, including, but not limited to, the following, or as approved by the Project Manager:

1. Cover sheet, index, and key map

2. Existing Conditions map

3. Civil Site Plan and Details

4. Landscaping Plans and Details

5. Demolition Plans and Details

6. Architectural Plans and details

7. Structural Plan and details

8. Mechanical Plan and details

9. Electrical Plan and details

10. SCADA/Instrumentation Plan and details

11. Generator Plan and details

12. Erosion Control Plan

13. Maintenance of Traffic Plan

14. Infrastructure Plan and Profile

15. Details

16. Operational Contingency Plans

17. Phasing/Sequencing Plans

g. Furnish copies of Contract Documents that include engineering drawings and specifications. Present and review them in person with PUD staff at the agreed-upon completion stages in the project, and make appropriate changes requested.

2.2 Permitting

EOR will prepare and submit all required construction permit applications to the governmental/regulatory agencies pertaining to this project.

a. Prepare and submit applications for all Growth Management Community Development’s (GMCD) Right-of- Way permits, Zoning, Conditional Use, Site Development Permits when required from Collier County Growth Management Division and respond to requests for additional information. Prepare all other required permit applications. Permitting fees will be paid by PUD.

b. Prepare and submit permit applications to the Florida Department of Environmental Protection (FDEP) and provide backup documentation, including drawings and specifications. Respond to all requests for additional information (RAI) from the FDEP. Permitting fees will be paid by the EOR team and reimbursed by PUD staff.

c. Prepare and submit permit applications and drawing packages to Collier County Growth Management for building permits required for the project. Coordinate and conduct a building permit preapplication review meeting with Collier County permitting staff. Permitting fees will be paid by PUD. Building permits will be assigned to the construction contractor(s). Provide the necessary permit documents and drawings to the construction contactor(s) as needed for permitting purposes.

d. Prepare permit applications and submit to the South Florida Water Management District (SFWMD) and provide backup documentation, including drawings and specifications. Respond to all requests for additional information (RAI) from agency. Permitting fees will be paid by the EOR team and reimbursed by PUD staff.

e. Prepare permit applications for submittal to the United States Army Corps of Engineers (USACOE) and provide backup documentation, including drawings and specifications. Respond to all requests for additional information (RAI) from the USACOE.

f. Obtain all applicable regulatory permits at the local, state, and federal levels, as required for the scope of work.

g. Prepare all necessary written responses to the regulatory agencies Request for Additional Information (RAI) regarding each permit application. Provide copies of all RAIs to the County Project Manager.

2.3 Bidding and Award Phase

It is the intent of this project to have multiple bid packages, with the exception of the following, bid/quote services that will be performed by the Collier County Procurement Services Division. EOR will assist the County with the following:

a. Assist in preparing addenda, as required, to interpret, clarify, or expand the Bidding Documents.

b. Review and provide proposed responses to questions asked by bidders for review by the County. Draft responses shall be provided to the County within two (2) business days of receipt. Track Questions and Answers to ensure timely and accurate responses.

c. Prepare Minimum Qualifications list for Bidders and provide to the County to include in the Bidding Documents.

d. Consult with and advise the County as to the acceptability of the contractor and subcontractors, suppliers, and other people and organizations proposed by the Prime Contractor for those portions of the work as to which such acceptability is required by the Bidding Documents.

e. Consult with the County concerning, and determine the acceptability of, substitute material and equipment proposed by the Contractor when substitution prior to the award of contracts is allowed by the Bidding Documents.

f. Attend the pre-bid/quote conference.

g. Attend the bid opening, review bids, and qualifications.

h. Provide a recommendation letter of award along with a “Reference Log” showing date, time, and comments of all contacted references provided by the prospective contractor.

TASK 3 – Construction Administration and Project Closeout

EOR shall provide experienced, competent engineer(s) needed during construction and project close-out. EOR will provide resumes of selected individuals for County staff review and approval prior to construction commencing. The following activities outline the construction administration services to be provided by the EOR during the construction and project close-out for the project:

3.1 Post-Design Services/Construction Administration

a. Contractor Coordination – EOR to coordinate with Contractor during the construction of the Project.

b. SCWRF Staff Coordination – EOR will assist the Plant Staff and Contractor to coordinate all construction field activities with a minimum of two (2) weeks’ notice so as not to interfere with operations of the facility.

EOR shall assist Contractor with notices to County staff for review and approval prior to the construction activity commencing.

c. Pre-Construction Meeting - The EOR will conduct the Pre-Construction Meeting to review the project scope, discuss project submittals and identify issues that need to be addressed prior to the start of construction. EOR shall prepare and distribute Meeting Agenda and Meeting Minutes.

d. Engineering Construction Progress Meetings - The EOR will conduct weekly/bi-weekly Engineering Construction Progress Meetings, (time/date to be determined by County Project Manager), to review project status and identify issues that may affect the Project EOR shall prepare and distribute Meeting Agenda and Meeting Minutes.

e. Construction Progress Meetings – The EOR will attend weekly/bi-weekly Construction Progress Meetings, (time/date to be determined by County Project Manager), to review project status and identify issues that may affect the Project. EOR shall provide updated Submittal Register Log, Request for Information (RFI) Log, Design Status Log, Drawing Register Log, Project Deviations Notices Log, Notices of Non- Conformance Log, Change Order/Work Directive/Allowance Log, Permit Register Log, Shutdown Log, Pay Application Log, Weather Day Acceptance Log, and any other pertinent information, to PUD staff in writing, two (2) days prior to the meeting.

f. Submittals Reviews

a. EOR shall review, reject with comments, or ultimately approve all the Contractor’s Submittals, including, but not limited to the list shown below for conformance with the Contract Documents.

1. Shop Drawings & Submittals

2. Or-Equal Materials and Substitution Requests

3. Samples

4. Project Schedule - The EOR shall be responsible for the review, reject with comments, or acceptance of the Contractor’s Project Schedule. The EOR shall review the Schedule to ensure that all general work efforts are addressed, that the Schedule follows a logical approach to the job, that it is following sound engineering and construction practices and that it identifies all Critical Path Work. The EOR shall monitor the schedule monthly, and after a review with the Contractor, advise the County Project Manager, in writing, of any areas where the Contractor appears to be falling behind.

5. Schedule of Values

6. Pre-Construction Video - EOR shall review the Pre-Construction Video provided by the

Contractor. The EOR will generate a list of any issues or concerns and submit the list to the County Project Manager, in writing, no later than two (2) business days after receiving the Pre- Construction Video from the Contractor.

7. Material Testing Records - Review and analyze Material Testing Records and provide written comments, in writing, within one (1) week, back to the County Project Manager of all density, sampling, and testing to ascertain acceptability of materials and completed work items.

b. EOR shall meet with County staff to review all the Submittals and incorporate County’s written comments into the EOR’s cover sheet submittal response. Such reviews and approvals or other action will not extend to means, methods, techniques, sequences, or procedures of construction or to safety precautions and programs incident thereto.

c. Review of a specific item shall not indicate the EOR has reviewed the entire assembly of which the item is a component. EOR shall not be required to review partial submissions or those for which submissions of correlated items have not been received. The EOR shall prepare/maintain a complete Submittal Register of all Submittals. The Submittal Register shall contain, but not limited to, Submittal Description, Corresponding Specification Number, the date of first submittal, any subsequent reviews and resubmittals dates, date of County review, and EOR final approval date. A copy of the Submittal Register shall be included in all weekly Meeting/Meeting Minutes and be provided to PUD and the Contractor upon request.

d. Project Pay Applications - The EOR shall review and approve or reject with comments, any Pay Applications submitted by the Contractor before the Pay Application is submitted to the Collier County Clerk’s Office for processing. EOR shall perform this review per § 218.73, Fla. Stat. (2024).

Approval for payment shall constitute a representation by the EOR to PUD, based on the EOR’s on-site observations of the work-in-progress, as an experienced and qualified Construction Professional, and on the EOR’s review of the Pay Application and the accompanying data and Schedules, that the work has progressed to the point indicated; that to the best of the EOR’s knowledge, information and belief, the quality of the work is in accordance with the Contract Documents and that the Contractor is entitled or is not entitled to the payment of the amount requested. All incoming Pay Applications processed by the EOR shall be mechanically stamped with the date received. Once EOR approves Pay Applications, return the Pay Application back to the Contractor and direct the Contractor to submit the approved Pay Application to the Collier County Clerk’s Office via email:

bccapclerk@collierclerk.com. A Pay Application Log shall be included in the Progress Meetings/Meeting Minutes and made available to PUD upon request.

e. Request for Information - EOR shall review and respond, in writing, within three (3) business days to all Requests for Information (RFI’s) that the Contractor submits. EOR shall review all RFIs with County staff and incorporate County’s written comments prior to the EOR’s RFI response. If required, EOR shall revise Construction Plans within thirty (30) days of the RFI response. The EOR shall maintain a complete log of all RFIs, including, but not limited to, RFI Number, Contractor’s RFI, EOR’s final response, RFI Status, date of RFI submittal, and date of EOR’s final response. This RFI Log shall be included in the Construction Progress Meetings/Meeting Minutes and made available to PUD and the Contractor upon request.

f. Change Order & Work Directive Change - EOR shall prepare and distribute, in writing, all Change Order and Work Directive Change during the Project for the County Project Manager’s review and approval. The EOR shall maintain a complete log of all Change Order and Work Directive Change, noting the dates of first submittal and subsequent reviews and resubmittals, approval, etc. This Change Order & Work Directive Change Log shall be included in the Progress Meetings/Meeting Minutes and made available to PUD and the Contractor upon request.

g. Provide cost reasonableness evaluations for all change orders and work directives.

h. Site Visits & Inspections – Make site visits to the construction site at intervals appropriate to the various stages of the construction in order to observe the progress of and quality of the work. These will be scheduled during critical points during the construction of the project and will be determined based upon the Contractor's schedule. These site visits will be to observe the progress and quality of the construction and its general conformance to the Contract Documents. EOR shall notify the County of observed work which does not conform to the Contract Documents, make recommendations for correction.

1. Review the Contractor’s as-built submittals/records monthly for accuracy/adequacy.

2. Monthly Construction Report

3. Report to be submitted to PUD by the 5th day of each month.

4. Sections in the report shall include, but not be limited to, Executive Summary, Contract Status, Safety, Quality and Test Reports, Contract Cost Status, Project Schedule, Critical Issues, Permit Status, Environmental Issues, RFI Status, Submittal Status, Allowance Log, Commissioning and Startup, Shutdowns, Project Payment Application, Long Lead Procurement items, Drawing/Document Register Log, Observation Reports and Project Photos/Videos.

i. Permit Requirements – EOR shall monitor the construction to determine whether construction activities violate the requirements of any permits. Notify the Contractor immediately, in writing, of any violations or potential violations and require immediate resolution of the problem. Violations must be reported to the County Project Manager immediately.

j. Florida Department of Environmental Protection Certifications - The EOR shall prepare and submit certification packages to the Florida Department of Environmental Protection (FDEP) per FDEP’s requirements.

k. Startup & Commissioning - Provide personnel experienced in plant startups and commissioning, approved by the County Project Manager, to oversee the startup & commissioning activities of the facilities. The following reviews and recommendations must be submitted, in writing, to the County Project Manager no later than one (1) month prior to startup and commissioning activities. The responsibilities of the startup & commissioning personnel include, but not limited to:

1. Review of Contractor 's cleaning, testing, and startup & commissioning procedures.

2. Review and approve or reject with comments of Contractor’s component and system tests.

3. Review designed system for operability and maintenance.

4. Coordinate initial operations with PUD staff and the Contractor.

5. Recommend to PUD staff the acceptance of equipment and/or systems.

6. Recommend and establish written operating procedures for all systems and processes.

7. Review, observe and accept or reject with comments startup & commissioning procedures to verify that proposed protocol is in conformance with the intent of the Contract.

8. Assist PUD staff for the duration of startup & commissioning in data collection and trending for process control and completion of monthly operating reports.

l. Equipment and System Operation and Maintenance (O&M) Manuals - EOR will review and approve or reject with comments the O&M manuals submitted by Contractor to ensure they meet Contract Document requirements. EOR shall meet with Plant Staff to determine preference of turnover for each O&M Manual. EOR will assist with the coordination of the Contractor training activities for PUD Staff.

m. O&M Manual Update:

1. EOR shall update the facilities O&M Manual to incorporate changes to the treatment plant.

2. The detailed manual shall be developed in accordance with the unique requirements of the individual wastewater facility and shall provide the operator with adequate information and description regarding the design, operation, and maintenance features of the facility involved.

3. The manual shall include basic hydraulic and engineering design criteria for the facility, as well as information and procedures required for normal control and distribution of wastewater, biosolids, and effluent within the facility. In addition, information concerning process control and performance evaluation for the facility, as well as equipment and procedural descriptions.

4. The manual shall include the PDR.

n. Record Drawings – EOR to prepare and submit to PUD staff upon completion of construction of

Project, five (5) sets of signed and sealed record drawings. EOR shall also provide MSWord format and PDF format copies of the work constructed, as well as electronic copies on AutoCAD disks (current PUD version). All provided copies shall include all changes made during the construction process, using information supplied by the Contractor and other data which can reasonably be verified by the EOR. The Contractor shall provide as-built documents to EOR for use in preparing reproducible and electronic record drawings.

o. Final Construction Certification – Upon issuance of a “Notice of Final Acceptance and Recommendation for Final Payment”, the EOR will provide a signed and sealed certification stating that the Project has been completed by the Contractor in accordance with the Plans and Specifications of the Contract. All tasks related to the Final Construction Certification shall be provided, in writing, and one (1) hard copy, to the County Project Manager.

p. Asset Management Record Information – EOR shall provide all electronic information in the format determined by PUD staff to populate the PUD’s GIS and Asset Management system.

q. Final Project Submittal - EOR shall provide PUD with one (1) complete file, itemized, and indexed, format determined by PUD staff, of all the Project-related records at the conclusion of the Project.

3.2 Warranty Services

The EOR and their team will provide warranty services for one (1) year after the final completion of the project construction. Work under this item is to include, but not be limited to, the following:

a. Post Construction Walk-through - Schedule and attend one (1) year (365 days) Warranty Walk-through with the Contractor and PUD.

b. Generate a list of warranty issues and coordinate with the Contractor until the issues are resolved.

c. Maintain a log of all warranty issues and provide a copy of the Log to PUD at Project Closeout.

d. Review the post-construction video and pictures provided by the Contractor.

TASK 4: Public Involvement

Public Involvement – EOR and their subconsultant(s) shall complete all required public involvement services throughout the project. Work under this item is to include, but not be limited to, the following: