26-09 Bonded Wearing Course - Addendum 2.pdf
PDF 100 KB Posted
- Attached to
- 26-09 BONDED WEARING COURSE
- Solicitation number
- 26-09
- Issued by
- Middlesex County, Connecticut
About this file
This is Addendum #2 to a bonded wearing course procurement issued by the Town of Wolcott, Connecticut, clarifying specifications and payment terms for asphalt overlay work on town roadways. The addendum addresses contractor questions posed through May 21, 2026, regarding material specifications, pay item scope, and pricing calculations. The Town will accept previously approved ultra-thin asphalt mix designs used on Connecticut Department of Transportation projects, though material testing via MTV is recommended but not mandatory. Work items referenced in Section 6.3—including crack filling, leveling courses, utility structure adjustments, milled keyways, pre-sweeping, and structure covering—are designated as incidental to the per-ton pricing and will not generate separate pay items.
Payment will be calculated based on square yardage but rendered per ton according to weight slips from asphalt plants, ensuring accurate compensation based on actual material delivered. The base price for liquid asphalt adjustment is established at $592.50 per standard ton as of May 2026, with the final Connecticut DOT asphalt price to be determined at bid opening. This adjustment mechanism protects both the Town and contractor from asphalt price fluctuations between the bid date and project execution.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Town of Wolcott 26-09 Bonded Wearing Course
ADDENDUM #2
The following questions have been posed thru 05/21/2026. Our answers are in RED.
Will the town accept previously approved Ultra-thin mix designs used on DOT jobs across the state? YES
Is an MTV required for the Ultra-thin material? Not mandatory but recommended
Section 6.3 references crack filling, a leveling course, adjustment of utility structures, milled keyways, pre-sweeping, and covering of structures. Will pay items be added to the contract to compensate the contractor, or should these operations be incidental to the per ton price? These items will be incidental to the price per ton
Section 8.0 references payment by the square yard (SY) while the Proposal Fee Schedule references pricing by the ton: The tonnage will be calculated based on sq. yds. however payment will be made per ton based on weight slips from the asphalt plants
What is the base price used for liquid asphalt adjustment? The CT DOT Asphalt Price will be established at the Bid Opening. The current Base Price if $592.5 (see below).
Asphalt Prices The pricing information is used to calculate Asphalt Adjustment Cost
Asphalt Prices – May 2026
($/Standard Ton) Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1 2
592.50 592.50
3 4 5 6 7 8 9
592.50 592.50 592.50 592.50 592.50 592.50 592.50
10 11 12 13 14 15 16
592.50 592.50 592.50 592.50 592.50 592.50
17 18 19 20 21 22 23
24 25 26 27 28 29 30