25023 OKV Price Schedule for Bidders 2026.06.17.xlsx

This is a price schedule document for the Northside Site Preparation – Phase 1 project in Virginia. The project consists of site preparation work on the north side of Runway 14-32, including clearing, mass grading, installation of drainage features, fencing, and relocation of electrical utilities. The price schedule is structured to accommodate two bid alternates, allowing bidders to propose pricing for different scope configurations. The document provides the itemized breakdown of work components that bidders must price in their proposals, establishing the baseline for cost evaluation and contract award determination.

The price schedule serves as the standardized pricing template for all bidders participating in this solicitation. By utilizing this uniform format, the contracting authority ensures consistent pricing proposals across all submissions, facilitating equitable evaluation of bids. Bidders are required to complete this schedule with their proposed unit prices and extended costs for each line item associated with the site preparation work, including any costs related to the two designated bid alternates. This standardized approach enables transparent comparison of pricing among competing bidders and supports fair contract award decisions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Schedule - Alternate 1

BID ALTERNATE ONE (1)
(Completed Form Shall Be Submitted with the Bid)
BIDDER NAME: ______________________________________________

All costs for the Project shall be provided in full detail to satisfy the scope of work as requested.

The Vendor is required to have established processes, procedures, staff resources and relevant tools in place for the project.

The formal bid, once accepted by the Winchester Regional Airport Authority (the “WRAA”), will constitute a firm, fixed price for completion of the job. The charges for the accepted bid may not increase or decrease by the awarded Vendor unless, (a) quantities increase or decrease as authorized by the WRAA in writing, (b) modification to the design of the installation as authorized by the WRAA could reasonably increase or decrease the costs of the installation work. In either case, the increased or decreased charges will be approved by the WRAA prior to the Vendor performing the work.

UNIT PRICESEXTENDED
ITEMAPPROX.ITEM WITH UNIT PRICEIN FIGURESTOTAL
NO.QUANTITYWRITTEN IN WORDS------------------------------------------
DOLLARSDOLLARS
CENTSCENTS
TEMPORARY SLOPE DRAINS
1
C-10260LF
PER LINEAR FOOT
INSTALLATION AND REMOVAL OF SILT FENCE
2
C-1021,000LF
PER LINEAR FOOT
TEMPORARY STONE CONSTRUCTION ENTRANCE
3
C-1021EA
PER EACH
TEMPORARY SEDIMENT BASIN
4
C-1021EA
PER EACH
INLET PROTECTION
5
C-1021EA
PER EACH
CULVERT INLET PROTECTION
6
C-1021EA
PER EACH
TEMPORARY DIVERSION DIKE
7
C-102200LF
PER LINEAR FOOT
COMPOST FILTER SOCK
8
C-1021,800LF
PER LINEAR FOOT
FILTER BAGS
9
C-1022EA
PER EACH
TEMPORARY STREAM BYPASS
10
C-1021LS
PER LUMP SUM
MOBILIZATION
11
C-1051LS
PER LUMP SUM
MUCK EXCAVATION
12
P-1525,000CY
PER CUBIC YARD
EMBANKMENT IN PLACE (ON-SITE)
13
P-15260,000CY
PER CUBIC YARD
CHAIN-LINK FENCE (SALVAGED FABRIC)
14
F-1621,300LF
PER LINEAR FOOT
CHAIN-LINK FENCE (NEW FABRIC)
15
F-162400LF
PER LINEAR FOOT
DOUBLE SWING GATE
16
F-1621EA
PER EACH
NON-ENCASED ELECTRICAL CONDUIT, 2 WAY - 6" PVC
17
L-1102,600LF
PER LINEAR FOOT
REMOVE CONDUIT AND CABLE
18
M-1502,000LF
PER LINEAR FOOT
REMOVE ABANDONED GAS LINE
19
M-1501,250LF
PER LINEAR FOOT
REMOVE ELECTRICAL JUNCTION STRUCTURE
20
M-1502EA
PER EACH
REMOVE FENCE (INCLUDING GATE)
21
M-1501,400LF
PER LINEAR FOOT
MISCELLANEOUS DEMOLITION
22
M-1501LS
PER LUMP SUM
SEPARATION GEOTEXTILE
23
R-2456,000SY
PER SQUARE YARD
CLEARING AND GRUBBING
24
R-3019AC
PER ACRE
30" RCP, CLASS V
25
R-302200LF
PER LINEAR FOOT
42" RCP, CLASS V
26
R-302128LF
PER LINEAR FOOT
48" RCP, CLASS III
27
R-30260LF
PER LINEAR FOOT
48" ENDWALL, VDOT STD. EW-2
28
R-3021EA
PER EACH
30" END SECTION, VDOT STD. ES-1
29
R-3021EA
PER EACH
42" END SECTION, VDOT STD. ES-1
30
R-3021EA
PER EACH
DROP INLET, VDOT STD. DI-7
31
R-3021EA
PER EACH
BASIN OUTLET STRUCTURE
32
R-3021EA
PER EACH
AGGREGATE SUBBASE COURSE
33
R-3084,000TN
PER TON
RIPRAP, CLASS AI
34
R-4141,100SY
PER SQUARE YARD
RIPRAP, CLASS II
35
R-414200SY
PER SQUARE YARD
MAINTAINING TRAFFIC
36
R-5121LS
PER LUMP SUM
SEEDING AND MULCHING
37
R-60326AC
PER ACRE
SOIL STABILIZATION MAT (TREATMENT 1)
38
R-6068,000SY
PER SQUARE YARD
SOIL STABILIZATION MAT (TREATMENT 2)
39
R-6064,000SY
PER SQUARE YARD
SUBGRADE REPAIR UNDERCUT
40
28.SP2,000CY
PER CUBIC YARD
UTILITY EXCAVATION AND COORDINATION
41
37.SP1LS
PER LUMP SUM
TEMPORARY FENCING
42
38.SP1LS

PER LUMP SUM

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

Total Bid Amount $

SP-1 Non-AIP Insurance Allowance $

Bidder’s Stated Completion Time: _______________ Calendar Days

Print Name: ____________________________________________ Title: _____________________________________________
Signature: ____________________________________________ Date: _____________________________________________
(This form must be signed. All signatures must be original and not photocopies.)

&"Times New Roman,Bold"&14ATTACHMENT D: PRICE SCHEDULE &12Bid Alternate One (1)

&"Times New Roman,Regular"Price Schedule - Bid Alternate One (1) &8Northside Site Preparation - Phase 1 | 25023 - OKV &"Times New Roman,Regular"D-&P&8

&K00+000BLANK

Price Schedule - Alternate 2

BID ALTERNATE TWO (2)
(Completed Form Shall Be Submitted with the Bid)
BIDDER NAME: ______________________________________________

All costs for the Project shall be provided in full detail to satisfy the scope of work as requested.

The Vendor is required to have established processes, procedures, staff resources and relevant tools in place for the project.

The formal bid, once accepted by the Winchester Regional Airport Authority (the “WRAA”), will constitute a firm, fixed price for completion of the job. The charges for the accepted bid may not increase or decrease by the awarded Vendor unless, (a) quantities increase or decrease as authorized by the WRAA in writing, (b) modification to the design of the installation as authorized by the WRAA could reasonably increase or decrease the costs of the installation work. In either case, the increased or decreased charges will be approved by the WRAA prior to the Vendor performing the work.

UNIT PRICESEXTENDED
ITEMAPPROX.ITEM WITH UNIT PRICEIN FIGURESTOTAL
NO.QUANTITYWRITTEN IN WORDS------------------------------------------
DOLLARSDOLLARS
CENTSCENTS
TEMPORARY SLOPE DRAINS
1
C-10260LF
PER LINEAR FOOT
INSTALLATION AND REMOVAL OF SILT FENCE
2
C-1021,000LF
PER LINEAR FOOT
TEMPORARY STONE CONSTRUCTION ENTRANCE
3
C-1021EA
PER EACH
TEMPORARY SEDIMENT BASIN
4
C-1021EA
PER EACH
INLET PROTECTION
5
C-1021EA
PER EACH
CULVERT INLET PROTECTION
6
C-1021EA
PER EACH
COMPOST FILTER SOCK
7
C-102900LF
PER LINEAR FOOT
FILTER BAGS
8
C-1022EA
PER EACH
TEMPORARY STREAM BYPASS
9
C-1021LS
PER LUMP SUM
MOBILIZATION
10
C-1051LS
PER LUMP SUM
MUCK EXCAVATION
11
P-1524,000CY
PER CUBIC YARD
EMBANKMENT IN PLACE (ON-SITE)
12
P-15240,000CY
PER CUBIC YARD
CHAIN-LINK FENCE (SALVAGED FABRIC)
13
F-1621,300LF
PER LINEAR FOOT
CHAIN-LINK FENCE (NEW FABRIC)
14
F-162400LF
PER LINEAR FOOT
DOUBLE SWING GATE
15
F-1621EA
PER EACH
NON-ENCASED ELECTRICAL CONDUIT, 2 WAY - 6" PVC
16
L-1101,200LF
PER LINEAR FOOT
REMOVE CONDUIT AND CABLE
17
M-1502,600LF
PER LINEAR FOOT
REMOVE ABANDONED GAS LINE
18
M-1501,250LF
PER LINEAR FOOT
REMOVE ELECTRICAL JUNCTION STRUCTURE
19
M-1502EA
PER EACH
REMOVE FENCE (INCLUDING GATE)
20
M-1501,400LF
PER LINEAR FOOT
MISCELLANEOUS DEMOLITION
21
M-1501LS
PER LUMP SUM
SEPARATION GEOTEXTILE
22
R-2454,000SY
PER SQUARE YARD
CLEARING AND GRUBBING
23
R-3019AC
PER ACRE
30" RCP, CLASS V
24
R-302100LF
PER LINEAR FOOT
42" RCP, CLASS V
25
R-302128LF
PER LINEAR FOOT
48" RCP, CLASS III
26
R-30260LF
PER LINEAR FOOT
48" ENDWALL, VDOT STD. EW-2
27
R-3021EA
PER EACH
30" END SECTION, VDOT STD. ES-1
28
R-3021EA
PER EACH
42" END SECTION, VDOT STD. ES-1
29
R-3021EA
PER EACH
DROP INLET, VDOT STD DI-7
30
R-3021EA
PER EACH
BASIN OUTLET STRUCTURE
31
R-3021EA
PER EACH
AGGREGATE SUBBASE COURSE
32
R-3083,000TN
PER TON
RIPRAP, CLASS AI
33
R-4141,100SY
PER SQUARE YARD
RIPRAP, CLASS II
34
R-414200SY
PER SQUARE YARD
MAINTAINING TRAFFIC
35
R-5121LS
PER LUMP SUM
SEEDING AND MULCHING
36
R-60324AC
PER ACRE
SOIL STABILIZATION MAT (TREATMENT 1)
37
R-6066,000SY
PER SQUARE YARD
SOIL STABILIZATION MAT (TREATMENT 2)
38
R-6062,500SY
PER SQUARE YARD
SUBGRADE REPAIR UNDERCUT
39
28.SP1,500CY
PER CUBIC YARD
UTILITY EXCAVATION AND COORDINATION
40
37.SP1LS
PER LUMP SUM
TEMPORARY FENCING
41
38.SP1LS

PER LUMP SUM

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

ERROR:#N/A

Total Bid Amount $

SP-1 Non-AIP Insurance Allowance $

Bidder’s Stated Completion Time: _______________ Calendar Days

Print Name: ____________________________________________ Title: _____________________________________________
Signature: ____________________________________________ Date: _____________________________________________
(This form must be signed. All signatures must be original and not photocopies.)

&"Times New Roman,Bold"&14ATTACHMENT D: PRICE SCHEDULE &12Bid Alternate Two (2)

&"Times New Roman,Regular"Price Schedule - Bid Alternate Two (2) &8Northside Site Preparation - Phase 1 | 25023 - OKV &"Times New Roman,Regular"D-&P&8

&K00+000BLANK

File details come from the government source that posted it. Updated .