The document is a Bid Schedule for Bid No. 25-8570 issued by Collier County, Florida, for the Goodland Pump Station Improvements Project. The comprehensive infrastructure upgrade involves a detailed construction project with 19 line items including mobilization, demolition, yard piping, pump assemblies, tank improvements, electrical and mechanical upgrades, and a 500,000-gallon ground storage tank. The project requires substantial completion within 540 consecutive calendar days, with a final completion deadline of 30 consecutive calendar days after the Punch List is delivered. A non-mandatory pre-bid meeting is scheduled for September 17, 2025, at 10:00 a.m., and sealed bids are due by October 17, 2025, at 3:00 p.m. local time.
The project has an anticipated total estimate of $4,201,706.25, with an additional $250,000 Owner's Allowance for unforeseen conditions or directed work. Bidders must submit a 5% bid bond, be enrolled in the E-Verify program, and provide comprehensive insurance coverage including workers' compensation, commercial general liability, automobile liability, and pollution liability. Performance and payment bonds for 100% of the contract award amount are required. The contract will be awarded to the lowest responsive and responsible bidder, with requirements for key personnel documentation, material manufacturer information, and subcontractor details. Successful bidders must comply with Collier County's Vertical Construction Standards and demonstrate appropriate professional licensing and contractor certifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
25-XXXXXX Bid Schedule Construction ITB #25-8570 Goodland Pump Station Improvements
| ITEM NO | DESCRIPTION | QUANTITY | UNITS | TOTAL |
| BASE BID: Includes all items described as the Base Bid in the Summary of Work as shown on the attached Drawings and Exhibits with no substitutions or limitations. | ||||
| 1 | Mobilization/Demobilization | 1 | Lump Sum | |
| 2 | General Requirements | 1 | Lump Sum | |
| 3 | Restoration | 1 | Lump Sum | |
| 4 | Demolition | 1 | Lump Sum | |
| 5 | Asphalt Driveway | 1 | Lump Sum | |
| 6 | Yard Piping | 1 | Lump Sum | |
| 7 | Recirculation Pump Assembly | 1 | Lump Sum | |
| 8 | Tank Drain Assembly | 1 | Lump Sum | |
| 9 | Pump Building Interior Piping Assembly | 1 | Lump Sum | |
| 10 | Vertical Turbine Pumps | 1 | Lump Sum | |
| 11 | Sodium Hypochlorite Pump Skid and Chemical Storage | 1 | Lump Sum | |
| 12 | Caustic Pump Skid and Chemical Storage | 1 | Lump Sum | |
| 13 | Generator | 1 | Lump Sum | |
| 14 | Fuel System Improvements | 1 | Lump Sum | |
| 15 | Mechanical HVAC Improvements | 1 | Lump Sum | |
| 16 | Electrical Improvements | 1 | Lump Sum | |
| 17 | Structural Improvements | 1 | Lump Sum | |
| 18 | 500,000 Gallon Ground Storage Tank | 1 | Lump Sum | |
| 19 | Bypass Operations | 1 | Lump Sum | |
| Total Bid | $0.00 | |||
| *Staff has allocated $250,000 in Owner's Allowance - for Owners Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change |