24027PJ_TMP Specs_2026-07-06.pdf

PDF 2 MB Posted

Attached to
Tucson Mountain Park Water Line Replacement
Solicitation number
2600007263, 24027PJ
Issued by
Pima County, Arizona

About this file

Tucson Mountain Park Water Line Replacement Project Summary

This document comprises the Special Provisions for Pima County Project No. 24027PJ, a water infrastructure and roadway repair project managed by Pima County, Arizona, through its Board of Supervisors and Department of Transportation under the direction of Rod Lane, P.E. The project involves replacing approximately 2 miles of 6-inch PVC waterline extending from the intersection of N. Kinney Road and W. McCain Loop to the Ranger House southeast of the Arizona-Sonoran Desert Museum entrance. The work includes furnishing all labor, materials, equipment, and supervision necessary for waterline replacement and associated roadway repair, with N. Kinney Road to be fully closed from McCain Loop to the Desert Museum entrance to facilitate uninterrupted trenching operations. The existing waterline, buried between 3 and 4 feet deep, will be abandoned in place or replaced along the same horizontal alignment while protecting existing 1-inch communications conduits and maintaining Desert Museum service line availability for no more than 24 hours. Substantial project completion is required by November 24, 2026, with work encompassing pavement markings, miscellaneous utility work including removals, erosion control measures, native plant salvage, and related incidental work.

The contractor bears full responsibility for traffic control, permits (including dust control and right-of-way permits), construction surveying and layout, quality control testing, record drawings, and all associated costs and fees. Construction activities must comply with Pima County's Pollution Prevention Plan ("SWPPP Lite"), include installation of rain gauges and erosion control measures, and implement noxious and invasive vegetation treatment prior to construction commencement. The contract documents incorporate Pima Association of Governments Standard Specifications (2015 Edition), Pima County Standard Details and Supplemental Specifications, Tucson Water Standard Specifications (2017), and applicable federal and state standards. All work must proceed in accordance with Section 701 (Maintenance and Protection of Traffic), with contractors required to provide advance-warning signage and ensure trail closures are posted. The specification addresses soil conditions including cobbles, rocky soils, and caliche historically encountered during previous repairs, with all excavation, removal, and disposal costs considered incidental to base contract pricing and included within bid estimates.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROVISIONS

FOR

PIMA COUNTY PROJECT DESIGN & CONSTRCTION

PIMA COUNTY BOARD OF SUPERVISORS

REX SCOTT DISTRICT 1

MATT HEINZ, VICE CHAIR DISTRICT 2

JENNIFER ALLEN, CHAIR DISTRICT 3

STEVE CHRISTY DISTRICT 4

ANDRES CANO DISTRICT 5

ROD LANE, P.E. DIRECTOR

TUCSON MOUNTAIN PARK

Kinney Road, McCain Loop to the Ranger Station southeast of

Arizona-Sonoran Desert Museum

Pima County Project No. 24027PJ

04/07/2026

Special Provisions Pima County Project No. 24027PJ

Tucson Mountain Park, McCain Loop to Ranger Station

SP-1

PROFESSIONAL SEALS

These specifications were prepared under the direction of the following individuals:

(a) Chelsi Remme, PE, Civil Engineer, Psomas

Their seals, affixed below, attest that those portions of these specifications which relate to the drawing sheet numbers appearing next to the seal were prepared under their direction.

Chelsi Remme, PE Civil Design

Drawing Sheets 1-22

CE

RT I F I CATE NO.

R e gi st er ed

Profess ional Engineer (Civ i l)

ASU,ANOZIRA DENGIS

ETA

D

65879

CHELSI

REMME

04/

/2

CE

RT I F I CATE NO.

R e g i st er ed

Prof ess ional Engineer (Ci vi l)

ASU,ANOZIRA DENGIS

ETA

D

65879

CHELSI

REMME

04/

/2

SP-2

INDEX TO THE SPECIAL PROVISIONS:

GENERAL NOTES

SECTION 105 – CONTROL OF WORK

SECTION 106 - CONTROL OF MATERIAL

SECTION 107 - LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC

SECTION 108 - PROSECUTION AND PROGRESS

SECTION 109 - MEASUREMENT AND PAYMENT

SECTION 109 - MEASUREMENT AND PAYMENT

SECTION 110-2 ASPHALTIC CONCRETE

SECTION 201 - CLEARING & GRUBBING

SECTION 404 - BITUMINOUS TREATMENTS

SECTION 406 – ASPHALTIC CONCRETE

ITEM 5150101 - UTILITY IMPACTS ALLOWANCE

SECTION 608 - SIGN PANELS

SECTION 701 - MAINTENANCE AND PROTECTION OF TRAFFIC

SECTION 701 - MAINTENANCE AND PROTECTION OF TRAFFIC

SECTION 704 - THERMOPLASTIC STRIPES AND MARKINGS

SECTION 800, BORING AND CASING NOTES FROM TUCSON WATER SD-800

SECTION 803 - LANDSCAPE BORROW AND PLATING MATERIAL

SECTION 805 - SEEDING

SECTION 809NATIVE PLANT SALVAGE

SECTION 810 - EROSION CONTROL AND POLLUTION PREVENTION

SECTION 908 - CONCRETE CURBS, GUTTERS, SIDEWALKS AND DRIVEWAYS

SECTION 925 - CONSTRUCTION SURVEYING AND LAYOUT

SECTION 1005 - BITUMINOUS MATERIALS FOR SURFACING

SECTION 1007 – RETROREFLECTIVE SHEETING

APPENDIX A : HISTORICAL PHOTOS FROM PROJECT

SP-3

(GENERAL_NOTES, 06/28/22)

GENERAL NOTES

1. Project Location

This project is located within Sections 6, 7 and 8 of Township 14 South, Range 12 East, Gila and

Salt River Meridian, Pima County, Arizona

2. Scope of Work

The project consists of furnishing all labor, materials, equipment and supervision necessary for the 6” PVC waterline replacement and roadway repair described in the project plans.

This project will replace an approximately 2-mile section of the 6” PVC water line from the eastern intersection of N. Kinney Road and W. McCain Loop to the Ranger House located southeast of the entrance to the Arizona-Sonoran Desert Museum.

To facilitate this replacement, N. Kinney Road will be fully closed from the intersection of W.

McCain Loop to the Desert Museum entrance. With the road closed, uninterrupted trenching within the roadway can occur. As-built plans show the existing water line buried between 3’ and

4’ deep, which has been confirmed during emergency repairs. The existing waterline will be abandoned in place or removed and replaced with new 6” PVC along the same horizontal alignment, with care taken to not disturb the existing 1” communications conduit. Service line to

Desert Musuem shall not be offline for more than 24 hours. Existing communication lines shall be protected in place.

The work also includes, but is not limited to, the following: pavement markings, miscellaneous utility work (including removals) and other related incidental work is also included.

3. Contract Time

The project must be substantially complete by November 24, 2026.

4. Maintenance & Protection of Traffic

The contractor shall be responsible for all construction zone traffic control and shall provide a traffic control plan in accordance with Section 701 of the Standard Specifications and these

Special Provisions.

At least 5 (five) calendar days prior to construction; the contractor shall place advance-warning signs at locations designated by Pima County to notify motorists, pedestrians, and bicyclists of construction-related delays due to road closure and detours.

N. Kinney Road will be fully closed immediately northwest of W. McCain Loop to the Desert

SP-4

Museum entrance. Traffic will detour via W. McCain Loop, maintaining access at all times from the east to the Desert Museum, Archery Range and King Canyon Trail. Both the Juan Santa Cruz

Picnic Area and Brown Mountain Picnic Area will be closed during the duration of the road closure. Contractor to furnish and post signs for trail closures (up to four locations).

The cost of traffic control shall be in accordance with Section 701, Maintenance and Protection of Traffic, of the Standard Specifications and these Special Provisions. The cost shall be included under Item No. 7010001, Maintenance and Protection of Traffic.

5. Permits

Before undertaking work at any location covered by this project, the contractor shall obtain all applicable permits, including but not limited to: dust control, dust control and right of way. The approved plan is considered the right-of-way use permit for work within unincorporated Pima

County when administered or funded by Pima County. The contractor is responsible for paying all applicable fees, taxes, and other costs for all work performed on this project, and for obtaining all permits including those in other jurisdictions. Before undertaking work outside the limits of the plans, specifications and project clearances, a separate right-of-way use permit is required.

Necessary environmental studies have been initiated and will be completed and approved prior to construction.

The contractor shall maintain and implement Pima County’s Pollution Prevention Plan (PPP)

“SWPPP Lite” and ensure the following best management practices are followed during construction:

• Commit to items addressed in the “SWPPP Lite”.

• Place stockpiles a minimum of 50 feet away from washes and other stormwater conveyance features.

• Stockpiles will require perimeter protection (i.e., wattles or sediment control berm) if they are unused for 14 days or more.

• Draining the water line is permissible provided that the operator installs stormwater control measures to reduce or eliminate erosion and sediment in the discharge. Please note that the operator will need to collect and retain the water if the water is super-chlorinated (containing chlorine above 4mg/L). This applies to water having chlorine levels above what is deemed acceptable in drinking water systems that does not meet surface water quality standards.

Prior to any ground disturbing activity, the contractor shall obtain a Fugitive Dust Control

Permit. The contractor shall implement the standard specifications for dust suppression.

6. Storm Water/Ground Water Management

SP-5

It is the contractor's responsibility to allow for any subsurface ground water and storm water runoff at the time of project construction. The contractor shall not divert or impound water in such a manner as to flood adjacent homes, facilities, or roadways. No additional compensation shall be provided for dewatering or diversion structures required to construct or protect the work.

The contractor shall post the Arizona Pollutant Discharge Elimination System (AZPDES) project number at the project ingress and egress points before ground disturbance occurs.

The contractor's attention is also directed to Section 810 of these Special Provisions and the

Pollution Prevention Plan (PPP) “SWPPP Lite” for the project regarding the requirements for temporary and permanent erosion control. The original Pollution Prevention Plan shall remain the property of Pima County DOT and will be returned to Pima County DOT at final acceptance

The contractor shall install the required number of rain gauges before ground disturbance occurs, in accordance with Sections 810-2.08 and 810-3.08. Two (2) will be required on this project. At least one rain gauge is required per linear mile of roadway. The rain gauge locations shall be noted in the SWPPP Lite.

7. Construction Survey and Layout

Construction survey and layout will be provided by the contractor. See Section 925 of these

Special Provisions.

8. Existing Vegetation

Existing vegetation, including Native Plants (protected vegetation), on this project shall not be disturbed. The contractor shall notify the Engineer immediately if any vegetation is to be disturbed or has been damaged. Any vegetation unnecessarily damaged shall be repaired or replaced at the contractor's expense.

In some circumstances, vegetation may obstruct construction with branches or other plant parts leaning into the work area. All required pruning shall be performed or directed by a certified arborist.

In situations where roots are damaged from excavation, clean cuts on roots shall be provided.

9. Disadvantaged Business Enterprise Goals and On-the-Job Training Hours

Not Used

10. Specifications and Details

The work embraced herein shall be performed in accordance with the requirements of the following separate documents:

Pima County, (PC), Standard Details for Public Improvements.

SP-6

Pima Association of Governments (PAG), Standard Specifications for Public Improvements, 2015 Edition, Volume 1, and updates http://apps.pagnet.org/standardspecifications

Pima Association of Governments (PAG), Standard Details for Public Improvements, 2015

Edition, Volume 2, http://apps.pagnet.org/standardspecifications

Pima Association of Governments (PAG), Federal Aid Supplement for Public Improvements, 2015 Edition, Volume 3, http://apps.pagnet.org/standardspecifications

Pima County Supplemental Specifications and Details https://www.pima.gov/979/Supplemental-Specifications

Pima County/City of Tucson Signing and Pavement Marking Manual, Latest Edition http://webcms.pima.gov/cms/one.aspx?portalId=169&pageId=63368

Pima County Traffic Signal Design Manual, Latest Edition http://webcms.pima.gov/cms/one.aspx?portalId=169&pageId=63368

Pima County Regional Wastewater Reclamation Department Standard Specifications and Details for Construction for Public Sanitary Sewers, 2012 http://webcms.pima.gov/cms/one.aspx?portalId=169&pageId=56988

Tucson Water Standard Specifications and Details, 2017 https://www.tucsonaz.gov/Departments/Water/Contractors-Developers-and-Engineers/Tucson-

Water-Standard-Specifications-and-Details

U.S. Department of Transportation, Federal Highway Administration, Manual on Uniform

Traffic Control Devices for Streets and Highways, December 2023, and amendments https://mutcd.fhwa.dot.gov/kno_11th_Edition.htm

Arizona Department of Transportation, Highways Division, Part 1 - Construction Standard

Drawings, May 2012 with current updates http://azdot.gov/business/engineering-and-construction/roadway-engineering/roadway-design-standards-and-guidelines/construction-standard-drawings

11. Project Limits

The contractor shall perform all work within the public right-of-way and property owned by Pima County. The contractor shall assume all responsibility and liability for any encroachment upon private property. The use of private property for construction yards will be allowed only if zoning requirements allows its use for this purpose. See Section 106-9 for further details regarding temporary construction yards.

12. Noxious and Invasive Vegetation

SP-7

Prior to the start of construction and before ground disturbing or earthmoving activities occur, the contractor shall treat noxious and invasive vegetation, particularly buffelgrass, in accordance with Section 201-3.04. Invasive species eradication shall continue throughout the entire project from clearing and grubbing through final project acceptance.

13. Disposal of Materials

All construction debris, rubble, and other materials that are not recycled on the project, sent to a recycling facility, or taken by the contractor, shall be disposed of by the contractor at a waste disposal facility. Costs associated with the disposal of these materials shall be incidental to the related items of work. Fees associated with the disposal of these materials shall be paid by the contractor.

14. Contract Administration

Prior to submittal of contract administration documents, examples of which are listed below, the contractor shall review all documentation for accuracy and compliance with the contract. Any variance from the plans and specifications shall be clearly noted and is subject to approval by the Engineer. A contractor’s transmittal letter shall accompany all submittals and shall include certification as to accuracy and compliance with the plans and specifications.

Contract administration submittals shall include, but are not limited to, the following examples: subcontracts; purchase orders; Davis Bacon wage determinations; pay estimates;

requested lien releases; and consent from surety.

Meetings may be scheduled with the contractor, at the discretion of the Engineer, to discuss and resolve any problems associated with contract administration submittals. The monthly meetings shall be held virtually. Meetings shall continue on an accelerated basis after project construction completion until all contract administration issues are resolved.

Submittals that are incomplete, will be returned to the contractor unprocessed for proper resubmittal and may result in payment delays, or partial payment, as deemed appropriate by the

Engineer.

15. Work Hours/Noise Abatement Ordinance

Construction noise abatement and start/stop times shall be in accordance with Pima County

Ordinance No. 1999-61: Regulating the Excessive, Unnecessary and Annoying Noises in Pima

County.

16. Shoring and Bracing

There will be no separate payment for shoring and bracing, unless shown in the bidding schedule.

SP-8

17. Archeological Features

In the event that human remains, including human skeletal remains, cremations, and/or ceremonial objects and funerary objects are found during excavation or construction in any part of the project area, ground disturbing activities must cease in the immediate vicinity of the discovery. Should artifacts or human remains be uncovered, the area will be taped off and further investigation by Pima County will follow. State laws ARS 41-865 and ARS 41-844 require that the Arizona State Museum (520-621-4795) be notified of the discovery by the contractor so that cultural groups who claim cultural or religious affinity to them can make appropriate arrangements for the repatriation and reburial of the remains. The human remains will be removed from the site by a professional archaeologist pending consultation and review by the Arizona State Museum and the concerned cultural groups.

The work is subject to delay in that location pursuant to ARS 41-844 while an examination takes place. Required archeological monitoring will be provided and paid for by Pima County.

18. Hazardous Materials

If suspected hazardous materials are encountered during construction, work shall cease at the location and the Engineer shall be contacted at (520) 724-2814 to arrange for proper assessment, treatment, or disposal of those materials. The area will be taped off, and further investigation and clean up by Pima County will follow. No adjustments will be made due to work shut down. If potentially hazardous or contaminated materials are encountered, the contractor shall stop work and remove all workers within the contaminated area. For life threatening situations, follow the procedures in the Safety Plan, as specified in Subsection 107-7.02.

19. Contractor’s Staging or Storage Yard

No contractor’s staging area or storage yard has been identified for this project. It is the contractor’s responsibility to locate a staging area(s) and obtain approval of said area(s) from the Engineer. Staging areas and vehicle storage yards are not permitted in the washes within the project area. Refer to Section 106-9 of the Standard Specifications for offsite staging outside of the right-of-way. Contractor staging areas, when located outside the project clearing limits, shall be stabilized at the expense of the Contractor and approved by the Engineer.

20. Construction Water/Dust Control

The contractor shall provide potable water for use in construction, compaction and dust control.

Reclaimed water may only be used if there is no discharge of this water to surface waters of the U.S. and the reclaimed water remains on-site. The contractor shall notify the Arizona

Department of Environmental Quality (ADEQ) for all discharges of reclaimed water to surface waters of the U.S. or off-site.

21. Utility Relocation

SP-9

Utility relocation work not anticipated.

Existing Century Link facilities shall be shored and protected in place. Field Contact for Century Link is Joe Parker (520-205-1049).

22. Erosion Control Measures

The contractor’s attention is directed to the requirements of Section 810 of the specifications and the following:

The contractor shall phase or sequence construction activities to minimize the area of disturbance at any one time. Sediment and erosion control measures shall be installed before upgradient land is disturbed. Once an area of the project has been cleared, the contractor is responsible for documenting in the SWPPP book all erosion control measure activities by the contractor or others in the area that has been cleared.

The contractor shall remove, dispose or realign temporary erosion control measures as directed by the Engineer. Subsequent removal, disposal or realignment of temporary erosion control measures will be incidental to the respective work item and no additional payment will be made.

23. Biological Requirements

The contractor shall inspect under and around construction equipment for desert tortoise prior to start up each day. If a desert tortoise is found within the project area, the contractor shall contact the Engineer and follow the guidelines found in the SWPPP Lite.

24. Contractor’s Environmental Requirements and Mitigation Measures

The environmental requirements and mitigation measures will be included in the Environmental

Clearance addendum, to be issued when completed and approved. These mitigation measures are not subject to change without prior written approval from the Federal Highway

Administration.

25. Quality Assurance and Quality Control

The contractor is solely responsible for quality control measures necessary to provide acceptable quality in the production, handling, and placement of all materials. The contractor’s attention is directed to Special Provision 106-4 of the contract documents and the PCDOT Testing Guide for quality control requirements. No payment will be made for such measures the cost being considered as included in contract items.

Quality assurance testing is the responsibility of Pima County.

SP-10

26. Record Drawings

The contractor is responsible for keeping a set of record project plans on site for annotation of changes in detail, location, and depth of all items constructed which vary from the contract documents that are made during the construction. When the project includes utility potholing under either bid item, 5150005 or 5150007 such potholes shall be identified on the record drawings. The record project plans shall include any revised or added plan sheets.

Upon completion of the work, the contractor shall transfer the annotated information to a clean set of the project plans. The dimensions and notations provided on the record project plans shall be complete, clear, and legible.

No later than 60 calendar days after acceptance of the project or as directed by the Engineer, the contractor shall submit the dated record set of project plans along with a transmittal letter to the

Engineer for review and acceptance. Final retention shall not be released until the record project plans are accepted by the Engineer.

The cost of furnishing record drawings shall be considered as included in the contract unit price for one or more of the contract items.

27. Soil Conditions

Contractor shall be advised cobbles, rocky soils and caliche have been historically encountered during previous repairs to existing line, see attached photos in Appendix A. All necessary equipment, labor, and methods to excavate, remove, and dispose of rocky soil shall be provided by the contractor as part of their scope of work. No additional payment will be made for encountering rocky soil or any other unforeseen soil conditions. The contractor is expected to include all potential soil challenges in their bid and contract price. Costs associated with excavation, removal, and disposal of rocky soil are considered incidental to the work and are covered under the base contract.

(101ABREV, 6/5/14)

SECTION 101 - ABBREVIATIONS AND DEFINITIONS

101-3 TERMS of the Standard Specifications are revised as follows:

Contract Time - Change to read “Construction Time”. This change is applicable when the term “Contract Time” is used in all sections throughout the Standard Specifications.

Supplemental Agreement - Add the following: “All supplemental agreements will be issued in compliance with Section 11.16.010 of the Pima County Procurement Code.”

(105REVIEW_OF_WORKSITE, 02-18-16)

SP-11

SECTION 105 – CONTROL OF WORK

105-22 REVIEW OF WORKSITE is added to the Standard Specifications as follows:

(A) Incident. The contractor shall inspect the worksite at least fourteen (14) calendar days prior to the scheduled start of a construction activity for the purpose of identifying any aerial, surface, and underground utility facility or utility activity that will impact (i.e. interfere, alter, or conflict) the work. Each impact hereinafter referred to as an “Incident” whether discovered prior to or during a construction activity shall be addressed in accordance with the procedures and requirements of this Section.

Inspection of the work site shall include, but not be limited to, the collection of field data on the horizontal and vertical location of underground facilities through ground markings (A.R.S. §§

40-360.22), exposing of underground facilities, and evaluating field data against the project plans and construction methods for impacts.

(B) Reporting. The contractor shall fill out an incident report form and assign a sequential incident number. The report form may be obtained from the Agency’s website or Engineer.

The report shall include the name of the utility facility owner (if not known, identify as “unknown”), incident location (station/offset/elevation), date and time discovered, color photographs (preferably date and time stamped), description of incident including the impact on the performance of work and type of facility discovered (type of material, size, quantity, identifying marks).

(C) Notification. The contractor shall notify the Engineer, utility facility owner, and Agency Right-of-way/Utility Section of an Incident no less than fourteen (14) calendar days prior to the scheduled start date of the construction activity unless the Incident was discovered during the construction activity in which case notice shall be given immediately. Notice shall be deemed to have been duly given when the incident report (a) has been delivered in person or (b) upon confirmation of receipt when transmitted by facsimile or email.

If the utility facility owner is not known, the contractor shall contact the state one call notification center (Arizona Blue Stake, Inc.) for assistance in identifying the owner.

(D) Resolution/Mitigation. The Agency, upon receipt of notice, shall take the necessary action to address the incident by removal or relocation of the affected facility, altering the work, or stoppage of the activity.

The Agency shall allow the utility facility owner to resolve the incident within a time frame specified by the Engineer. If the utility facility owner is unable to perform, the Agency may, at its option, authorize the contractor to perform work to resolve or mitigate the incident by force account in accordance with the provisions of subsection 109-5(B).

SP-12

(E) Submission of Additional Compensation. In the event that the contractor perceives that additional compensation has occurred as a result of an incident, the contractor shall immediately bring such matter to the attention of the Engineer for the earliest possible resolution, and the

Engineer shall promptly notify the affect utility provider(s) and Agency Right-of-way/Utility Section of the request for additional compensation.

The contractor may request additional compensation by (a) filing a claim in accordance with the requirements and procedures under Subsection 105-18 or (b) if agreed to by the Engineer, submit for approval by the Engineer an itemization of additional labor, material, and equipment costs.

Itemization of costs shall be documented on the incident report. The amount of payment shall be determined in accordance with the provision of subsection 109-5(B).

At the request of the Engineer, the contractor shall make available all documentation supporting the amount of additional compensation, and the Engineer shall make such documentation available to the utility provider upon request.

When quantifying additional compensation under item (b) above, the contractor shall submit to the Engineer as promptly as possible following completion and acceptance by the Agency the itemization of labor, material, and equipment, but in no event later than fourteen (14) calendar days, the contractor’s incurred costs which shall be considered complete and final compensation for the incident.

Failure on the part of the contractor to adhere to the procedures and requirements of this Section will be cause for dismissal of the additional compensation request.

(F) Incident Log and Progress Meeting. The contractor shall maintain a utility incident log provided by the Agency. The log shall be kept current, reviewed at the weekly progress meeting, and included with the weekly construction progress meeting minutes.

(106QA/QC, 06/20/23)

SECTION 106 - CONTROL OF MATERIAL

106-4 TESTS AND ACCEPTANCE OF MATERIALS of the Standard Specifications is revised to read:

106-4.01 General. All materials will be inspected, tested and approved prior to incorporation in the work. Any work in which materials not previously approved are used shall be performed at the contractor’s risk and may be considered as unauthorized and unacceptable and not subject to the payment provisions of the contract.

Any laboratory performing sampling and testing for the project shall be open to unrestricted access for inspection and review by the Agency. The laboratory shall provide an adequate amount of enclosed space and be supplied with the proper equipment, facilities, and utilities so

SP-13

that the required testing procedures can be performed. It shall have adequate lighting, ventilation, and means of ingress and egress. The laboratory shall be equipped with heating and cooling equipment capable of maintaining an ambient air temperature of 68 to 78 degrees F. The laboratory and all equipment and facilities therein shall be kept clean and maintained in good working order.

Sampling and testing of materials shall be in accordance with the requirements of:

• The PCDOT Testing Guide

• The ADOT Materials Testing Manual

• The ADOT Materials Policy and Procedure Directives Manual.

• Applicable Federal, AASHTO, or ASTM specifications or test designations.

• Applicable specifications or test designations of other nationally recognize organizations.

Whenever a reference is made to an Arizona Test Method or an ADOT Materials Policy and

Procedure Directive, it shall mean the test method or policy and procedure directive in effect on the bid opening date.

Unless otherwise specified, whenever a reference is made to a Federal, AASHTO, or ASTM specification or test designation, or to a specification or test designation of other nationally recognized organizations, it shall mean the specification or test designation in effect on the bid opening date.

106-4.02 Quality Control. The contractor is responsible for quality control measures necessary to provide acceptable quality in the production, handling, and placement of all materials. No payment will be made for such measures; the cost being considered as included in contract items.

(A) General. At the preconstruction conference, the contractor shall designate a qualified employee as Quality Control Manager to be responsible for implementing, monitoring and, as necessary, adjusting the processes to assure acceptable quality. The quality control manager shall be a full time employee of the contractor, and shall be on the project site during all construction activities. Also at the preconstruction conference, the contractor shall be prepared to discuss his understanding of the quality control responsibilities for the specified materials.

(B) Quality Sampling and Testing Supervisor. The contractor shall designate a Quality

Sampling and Testing Supervisor(s) who is responsible to supervise the sampling and testing, and who meets the requirements given in Table 106-1 for the specific material on which sampling and testing is being performed. The Quality Sampling and Testing Supervisor(s) shall be an employee of the contractor or a consultant or a consultant engaged by the contractor, and be responsible for supervising the sampling and testing on more than one project. The Quality

Sampling and Testing Supervisor(s) shall be able to be at the job site within 24 hours from any point in time.

SP-14

(C) Quality Sampling and Testing Technician. Quality Sampling and Testing Technicians who perform the actual sampling and testing shall meet the requirements given in Table 106-2 for the specific material on which sampling and testing is being performed. Quality Sampling and Testing Technicians shall be employees of the Quality Control Laboratory and be supervised by a qualified Quality Sampling and Testing Supervisor for the specific material on which sampling and testing is being performed.

See Table 106-1 on the next page

SP-15

TABLE 106- 1

QUALITY SAMPLING AND TESTING SUPERVISOR REQUIREMENTS

Soils and Aggregate

Field Laboratory

Arizona Technical Testing Institute

(ATTI) “Field” certification plus one of (a) through (g) below.

Arizona Technical Testing

Institute (ATTI) “Laboratory

Soils/ Aggregate” certification plus one of

(a) through (g) below.

Asphaltic Concrete

Field Laboratory

Arizona Technical Testing Institute

(ATTI) “Field” certification plus one of (a) through (g) below.

Arizona Technical Testing Institute (ATTI)

“Asphalt” certification plus one of (a) through (g) below.

Concrete

Field Laboratory

American Concrete Institute (ACI)

“Concrete Field Testing Technician Grade I” certification plus one of (a) through (g) below.

American Concrete Institute (ACI)

“Concrete Strength Testing Technician”

Certification plus one of (a) through (g) below.

(a) Professional Engineer, registered in the State of Arizona, with one year of highway materials sampling and testing experience acceptable to the

Department.

(b) Engineer- In- Training, certified by the State of Arizona, with two years of highway materials sampling and testing experience acceptable to the

Department.

(c) Obtained a Bachelor of Science Degree in Civil Engineering, Civil

Engineering Technology, Construction, or related field acceptable to the

Department; and with three years of highway materials sampling and testing experience acceptable to the Department.

(d) Certified by the National Institute for Certification in Engineering

Technologies (NICET) in the Construction Materials Testing field as an

Engineering Technician (Level III) or higher in the appropriate subfield in which sampling and testing is being performed.

(e) Certified by NICET in the Transportation Engineering Technology field as an Engineering Technician (Level III) or higher in the Highway Materials subfield.

(f) Certified by NICET as an Engineering Technician, or higher, in Civil

Engineering Technology with five years of highway materials sampling and

SP-16

106-4.03 Quality Assurance and Quality Control Laboratory. All field and laboratory sampling and testing shall be performed by a laboratory or laboratories on the ADOT Directory of Approved Materials Testing Laboratories. When field sampling and testing procedures are performed, the appropriate valid Arizona Technical Testing Institute (ATTI) and/or American Concrete Institute (ACI) certification(s) are required.

106-4.04 Quality Assurance Testing. Compliance with specifications is determined by assurance sampling and testing. All materials shall be randomly sampled at prescribed frequencies as given in the Pima County Department of Transportation Sampling Guide

Schedule. On Pima County Capital Improvement Projects, materials shall be sampled and tested by a qualified representative of the Agency, at the expense of the Agency, unless otherwise specified in the contract documents. Testing shall be in accordance with the Pima County

Department of Transportation Sampling Guide Schedule, a copy of which can be found on the Pima County Department of Transportation web-site; Roadway Design Standards and Manuals.

106-4.05 Records. The quality control and the quality assurance laboratory shall maintain all sampling and testing records and supporting documentation used in the preparation of Weekly

Sampling and Testing Reports. Upon request, the contractor shall make sampling and testing records and supporting documentation available to the Engineer for review and copying as desired.

TABLE 106- 2

QUALITY SAMPLING AND TESTING TECHNICIAN

REQUIREMENTS

Soils and Aggregate

Field Laboratory

Arizona Technical Testing Institute

(ATTI) “Field” certification.

Arizona Technical Testing Institute (ATTI) “Laboratory

Soils/ Aggregate” certification.

Asphaltic Concrete

Field Laboratory

Arizona Technical Testing Institute

(ATTI) “Field” certification.

Arizona Technical Testing Institute (ATTI)

“Asphalt” certification.

Concrete

Field Laboratory

American Concrete Institute (ACI) “Concrete Field Testing

Technician Grade I” certification.

American Concrete Institute (ACI)

“Concrete Strength Testing Technician”

Certification.

SP-17

106-4.06 Weekly Reports. Weekly Sampling and Testing Reports are to be submitted to the Engineer. The weekly reports shall state the types of work, such as earthwork, Portland cement concrete, or asphaltic concrete, which have been performed during the report period. The report shall also include the process control measures taken to assure quality. The weekly report shall provide sample identification information for materials tested during the report period, including sample number, date sampled, sample location, person obtaining sample, and original source of material. The report shall also provide the results for all required tests and any retests, corrective actions, and other relevant information. Although hand-written documentation can be included, the report’s narrative, sample identification information, results for tests and any retests, and corrective actions shall be typed to ensure the Agency can make clear reproductions of the documents.

The report period shall end at midnight of each Friday, and the report shall be submitted to the Engineer no later than 5: 00 p.m. of the following Wednesday unless the Engineer and contractor agree upon a different day and time.

(107UTIL, 03/14/17)

SECTION 107 - LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC

107-21 CONTRACTOR’S RESPONSIBILITY FOR UTILITY PROPERTY AND

SERVICES of the Standard Specifications is modified to add:

The following utilities may have facilities in the project area:

Owner Contact Phone Number

Lumen (formerly CenturyLink) Joe Parker (520) 205-1049

Trico Electric Cooperative Roger Patnode (520) 744-2944, Ext.1320

Tucson Electric Power Miranda Jackson

(520) 884-3989, C (520) 449-4309

The existence and locations of underground utilities indicated on the plans are not guaranteed and shall be investigated and verified in the field by the contractor before starting work.

Excavations in the vicinity of existing structures and utilities shall be carefully done. At least two full working days prior to commencing excavation, the contractor shall call Blue Stake

Center, 1-800-STAKE-IT, between the hours of 7:00 a.m. and 4:30 p.m., Monday through Friday, for information relative to the location of buried utilities.

It shall be the responsibility of the contractor to contact the utility companies in order for them to determine if there is a need to brace, shore, support and protect their facilities during the construction of the project.

Utility locations shown on the project plans are approximate, and all utilities are not necessarily

SP-18

shown. The possibility of conflicts with existing utilities exists. If conflicting utilities interfere with the contractor's normal progress towards completion of the project, the Pima County

Department of Transportation may, at its option, authorize the contractor to relocate said conflicting utilities by force account in accordance with the provisions of subsection 109-5.02 of the Standard Specifications and these Special Provisions.

(108PROJ_SCH, 11/20/14)

SECTION 108 - PROSECUTION AND PROGRESS

108-3 PRECONSTRUCTION CONFERENCE

108-3.01 Schedule of the Standard Specifications is modified to add:

The Contractor shall be responsible for planning, scheduling and reporting the progress of the work to ensure timely completion of the contract.

The Contractor shall submit a schedule in two parts, in accordance with the following:

(A) Part I shall be a preliminary schedule and shall be submitted at the Preconstruction Conference for the Engineer's review and concurrence. It shall be a schematic (arrow) diagram or precedence diagram, showing the work stages and operations for all activities required by the contract. The diagram shall be in sufficient detail to allow day-to-day monitoring of the Contractor's operations. Along with the preliminary schedule, the

Contractor shall include its calendar for the contract period which shall show work days, calendar days and dates. The diagram shall include four to 10 milestone events as identified by the Contractor and accepted by the Engineer.

(B) Part II shall be submitted for the Engineer's review and concurrence within 15 calendar days after Part I has been accepted by the Engineer. This second schedule shall include a complete critical path schedule to cover the Contractor's anticipated time schedule. The schedule shall include a detailed network diagram acceptable to the Engineer with the following features:

(1) It shall be time-scaled in calendar days. All activities shall be plotted on their early start and finish dates. Unless approved by the Engineer, activities shall not exceed 15 working days in length. The plot shall have a size and scale acceptable to the Engineer.

(2) It shall show the order and interdependence of activities and the sequence of work as reflected in the Schedule Report specified in Subsection 108.03(B)(7) below. The critical activities shall be prominently distinguished on all reports by the use of color or other means acceptable to the Engineer.

(3) It shall include, in addition to all construction activities, such tasks as mobilization, SP-19 demobilization, submittal and approval of samples of materials and shop drawings, procurement of significant materials and equipment, fabrication of special items, installation and testing and interfacing with other projects.

(4) The activities shall be sufficiently detailed so that a reviewer can follow the sequence.

For example, the activities shall show forming, reinforcing, and placement of concrete on the calendar days they are scheduled to be performed.

(5) The diagram shall show for each activity the preceding and following event numbers or activity numbers, the activity description, the total float, and the duration of the activity in working days.

(6) The activities shall be organized and described so as to conform to the contract bid items.

Activity descriptions shall be unique and specific with respect to the type of work and location.

(7) The diagram shall be accompanied by a Schedule Report of the network with a tabulation of the following data for each activity:

(a) Preceding and following event numbers or activity number

(b) Activity description

(c) Activity duration

(d) Earliest start date

(e) Earliest finish date

(f) Latest start date

(g) Latest finish date

(h) Total float times

(i) Responsibility for activity - e.g., Contractor, subcontractor, supplier, etc.

(j) Resource loading for each activity listing personnel, equipment and anticipated revenue.

(C) The Contractor shall make updated schedules and reports under the following circumstances or as requested:

(1) The Contractor shall submit a monthly report of actual construction progress by the

10th working day of each calendar month by updating its schedule report to reflect all

SP-20

complete and in progress activities on the project. All negative float shall be explained in detail. If, in the opinion of the Engineer, the detailed network diagram requires revision, either wholly or in part, the Engineer shall so direct the Contractor and the Contractor shall submit such revision within 10 calendar days.

(2) The monthly report also shall show the activities or portion of activities completed during the one-month reporting period and the portion completed on the project to date, showing actual start and finish dates plus all future activities.

(3) The monthly report shall state the percentage of revenue actually earned as of the report date.

(4) The monthly report shall be accompanied by a narrative description of job progress, problem areas, current and anticipated delaying factors and their expected effect, and any corrective actions proposed or taken. The narrative description shall also clearly identify any departures from earlier schedules, including, but not limited to, changes in logical sequence or logical ties, constraints, changes in activity durations and changes, additions or deletions in event numbers, activity numbers and activity descriptions. The reasons for each departure shall be included in the narrative description. Any additions or deletions of milestone events must be approved by the

(5) The monthly report shall include a summary of all activities sequenced by the total float from least to greatest float and ordered by early start.

(6) The required schedules and report shall be submitted to the Engineer as follows:

(a) Part I (Preliminary Schedule): seven originals

(b) Part II (Detail Network Diagram): seven originals

(c) Revisions to Part II: seven originals

(d) Monthly Report: three originals plus three copies of the narrative

(7) The monthly report shall include a detailed predecessor/successor analysis showing the predecessors, successors, logic ties, and constraints for each activity scheduled.

These activities shall be ordered by event number or activity number from least to greatest.

(8) All Extra Work shall be shown on an updated Schedule.

The automated system software shall be Primavera or approved equal.

No measurement or direct payment will be made for Contractor costs relating to preparation and

SP-21

submission of schedules and reports and revisions thereto, the cost being considered as included in the prices paid for contract items.

Float time is not for the exclusive use or benefit of either the Department or the Contractor.

Extension of time for performance may be granted to the extent that equitable time adjustment for the activity affected exceeds the total float or where otherwise justified, impact on the contract completion can be shown.

Concurrence of the Contractor's schedules by the Engineer is not to be construed as relieving the

Contractor of its obligation to complete the work within the contract time; or as granting, rejecting, or in any other way acting on the Contractor's requests for adjustments to the date for completing contract work, or claims for additional compensation. Such requests shall be processed in strict compliance with other relevant provisions of the contract.

The Contractor shall participate in a review and evaluation of the proposed Part I, Preliminary

Schedule, and Part II, Schedule, and monthly updated schedule by the Engineer. Any revisions necessary as a result of their review shall be submitted for concurrence to the Engineer within 10 calendar days after the review. The accepted Part II, Schedule, shall then be used by the

Contractor for planning, organizing, executing, and directing the work and for reporting progress of work accomplished. The Contractor shall furnish to the Engineer for project use a copy of the

Part II, Schedule, and a monthly updated schedule on a compatible computer disk of a size and configuration designated by the Engineer.

The Engineer shall complete review of Part I, Preliminary Schedule, and Part II, Schedule, within 15 calendar days of the receipt of each. No monthly progress payment will be made until Part I has been accepted. Within the next 60 calendar days after concurrence with Part I, Part II will be submitted and reviewed. If Part II has not been accepted within these 60 calendar days, progress payment will be withheld until Part II has been concurred with by the Engineer.

Failure of the Contractor to comply with the monthly updated Schedule requirements specified herein will be grounds for the Engineer to withhold an additional 10 percent of the monthly progress payments, in addition to the normal retention, until the Contractor is in compliance.

Additional money withheld will be paid upon compliance to the Contractor in the next scheduled monthly estimate. If the monthly updated schedule is not received by the 10th working day of each month, but received prior to the 25th of the month, five percent will be withheld until the following estimate.

(109ALLOWANCE, 04/11/17)

SECTION 109 - MEASUREMENT AND PAYMENT

109-1 MEASUREMENT OF QUANTITIES of the Standard Specifications is modified to add:

The term “Dollar” or its abbreviation “USD” (US Dollar) when included in the bidding schedule

SP-22

as a unit of measurement, shall mean an allowance for the payment of the work in conformance with the provisions of Subsection 109-5.01.

(109FUEL_ADJUST, 7/08/22)

SECTION 109 - MEASUREMENT AND PAYMENT

109-13 COMPENSATION FOR FUEL ADJUSTMENT is hereby added to the Standard Specifications:

109-13.01 Fuel Cost Adjustment.

(A) General. The Agency will adjust monthly progress payments up or down as appropriate for cost fluctuations in diesel fuel as determined in accordance with these Special Provisions.

A fuel cost adjustment will be made when fluctuations in the price of diesel fuel, in excess of 15 percent, occur throughout this contract. The Agency will not provide such adjustments for fluctuations in the price of diesel fuel of 15 percent or less.

No adjustments will be made for fluctuations in the price of fuels other than diesel.

(B) Determination of Compensation. The base index price of fuel will be determined by the

Agency from the selling prices of diesel fuel published by OPIS (Oil Price Information Service).

The base index price to be used will be the price for Diesel fuel No. 2, Ultra Low Sulfur, PAD 5, City of Tucson. The reported average value for the Tucson area will be used.

The base index price for each month will be the arithmetic average of the selling price for diesel fuel, as specified above, shown in the last four reports received prior to the last Wednesday of the month.

This price will be effective as of the last Wednesday of each month, and will be posted on the

Arizona Department of Transportation (ADOT) website on or shortly after the last Wednesday of the month at: https://azdot.gov/business/contracts-and-specifications/bituminous-and-fuel-price-adjustment

This price may also be obtained from Contracts and Specifications Services at (602) 712 - 7221.

This price will be deemed the "initial cost" for diesel fuel on projects for which bids are opened during the following month.

The current index price for diesel fuel in subsequent months will be the base index price, determined as specified above, for the current month. The amount of adjustment per gallon will be the net difference between the "initial cost," adjusted by 15 percent, and the current index price. The monthly adjustment will be determined by the Engineer and included in the payment

SP-23

estimate as a fuel adjustment. For fluctuations in excess of 15 percent, fuel cost adjustments will only be made for current price index increases greater than 1.15 times the "initial cost" or for decreases less than 0.85 times the "initial cost." No calculation will be made for fluctuations in the current index price of 15 percent or less when compared to the "initial cost."

The number of gallons of diesel fuel used per month will be considered to equal 1.5 percent of the dollar amount of work reported by the contractor for each month. Such dollar amount will not include incentives earned by the contractor for pavement smoothness, thickness, or strength for Portland cement concrete pavements; for pavement smoothness or quality lots for asphaltic concrete pavements; for any other revenue derived from quality incentives; or for revenue accrued in the previous month for bituminous material cost fluctuations or diesel fuel price adjustments.

A monthly adjustment, if applicable, will be made on this quantity, as shown below:

AC)-(CPx

IC

0.015(Q) S =

Where: S = Monetary amount of the adjustment (plus or minus) in dollars CP = Current index price in dollars per gallon

IC = “Initial cost" as determined above, dollars per gallon

AC = Adjusted "initial cost" (1.15 or 0.85 times IC) in dollars per gallon Q = Dollar amount of work completed for the month

If adjustments are made in the contract quantities, the contractor shall accept any fuel adjustment as full compensation for increases or decreases in the price of fuel regardless of the amounts of overrun or underrun.

The value calculated above (plus or minus) will be adjusted to include sales tax and other taxes as applicable.

No additional compensation will be made for any additional charges, costs, expenses, etc.,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .