This is a Statement of Work for the Department of Military Affairs at Camp Lincoln in Springfield, Illinois, detailing the AGO Building Structural Support Project. The project scope requires installation of additional structural support for the AGO building mechanical room penthouse to accommodate two new water tanks necessary for geothermal system upgrades and repairs. The primary deliverable is the construction of a new exterior steel roof frame above the existing penthouse designed to suspend and support the tanks internally, including hanging supports braced to the penthouse floor for seismic restraint as specified in attached design plans. Work must be completed during standard business hours of 0800 to 1600, Monday through Friday, excluding Federal and State holidays. Site visits are mandatory prior to bid submission, and vendors must submit comprehensive Safety Plans along with their bid proposals through the Bid Buy platform.

This procurement is designated as a Small Business Set-Aside Program opportunity. All materials must conform to specified design loads and comply with attached technical plans and industry standards. The Prime Contractor is responsible for coordinating all roof penetrations and patching work with the current warranty holder, Designed Roofing Systems, Inc., to maintain the existing roof warranty. Vendors must provide safety barriers around all equipment, crane placement, materials, and construction areas to prevent unauthorized personnel access to hazardous zones, and maintain a clean work area free of debris at the end of each workday. Pricing and award information are not specified in this Statement of Work document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Camp Lincoln – AGO Building Structural Support Project

1301 North Macarthur Blvd.

Springfield, IL

1. GENERAL OVERVIEW OF WORK.

The scope of this project is to provide all labor, materials, and equipment necessary to install additional structural support for the AGO building mechanical room penthouse. Upgrades and repairs to the building’s Geothermal system require the addition of two (2) water tanks to be installed inside the existing penthouse. Due to the increased size and weight of these tanks, a new exterior steel roof frame must be constructed above the penthouse to suspend and support the tanks internally.

2. MATERIALS.

a. All materials must conform to the design loads and specifications detailed in the attached plans.

3. EXECUTION.

a. See attached plans for specific dimensions, design details, and material requirements.

b. All work shall be completed in a professional, workmanlike manner in accordance with industry standards.

c. The work area shall remain clean and free of debris at the end of each workday.

d. Vendor shall provide safety barriers for all equipment, crane placement, materials, and other construction areas to prevent unauthorized personnel from entering hazardous zones.

e. Provide a new exposed steel roof frame above the existing penthouse to vertically support the new water holding tanks.

f. Hanging supports will be braced to the penthouse floor for seismic restraint, as detailed in the attached plans.

g. Roof penetration of the penthouse is required. To maintain the current roof warranty, the Prime Contractor is responsible for coordinating and subcontracting all roof penetrations and patching to the current warranty holder: Designed Roofing Systems, Inc.

h. ALL WORK TO BE EXECUTED IN ACCORDANCE WITH ATTACHED PLANS.

4. PERIOD OF PERFORMANCE & LOGISTICS

a. Work Hours: All work shall be conducted between the hours of 0800 to 1600, Monday through Friday, excluding Federal/State holidays.

5. PRICING & BID REQUIREMENTS

a. Vendor to submit quote via Bid Buy.

b. Site visits are mandatory prior to bid submission.

c. A comprehensive Safety Plan must be submitted along with the bid proposal.