This is a Stormwater Report prepared for the City of Eugene, Oregon, for the Cuthbert Amphitheater Site Improvements project located at Tax Lot 300, Lane County Assessor's Map 17 03 29 34 in Alton Baker Park. The project consists of construction improvements including approximately 69 new paved parking spaces, new sidewalk connections, resurfacing of the gravel backstage area, and utility relocation on approximately 6 acres. The improvements will increase impervious surface area by approximately 50,000 square feet. Stormwater management will be accomplished through a Dry Detention Pond (Extended Filtration Facility) designed in accordance with the 2025 City of Eugene Stormwater Management Manual, supplemented by vegetated filtration strips and emergency overflow routing to an existing channel north of the site. The site lies within FEMA Flood Zone AE and Basin WKQF-020 per City of Eugene Storm Drainage Basins. The project requires a City of Eugene Commercial Erosion Prevention Permit and a DEQ 1200-C(A) Erosion and Sediment Control Plan.
The stormwater design was analyzed using HydroCAD modeling software with the Santa Barbara Urban Hydrograph method for the 10-year storm event (4.46 inches in 24 hours) and includes water quality treatment for a 1.4-inch rainfall event. Soils at the site consist primarily of Newberg fine sandy loam (94.1% of site) classified as Hydrologic Soil Group A, with smaller portions of Camas gravelly sandy loam and Cloquato silt loam. Infiltration testing performed in June 2025 established a design infiltration rate of 0.5 inches per hour, which is at the minimum allowable rate for dedicated infiltration facilities. The Dry Detention Pond is sized to treat runoff from approximately 38,000 square feet of impervious area and is designed to fully infiltrate the 10-year storm event with emergency overflow routed to the existing channel. All design analyses confirm compliance with the City of Eugene Stormwater Management Manual for water quality, flow control, and flood control requirements, with post-developed runoff rates reduced to zero cubic feet per second for all design storms through infiltration and treatment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cuthbert Amphitheater Site Improvements – Eugene, Oregon Stormwater Report
June 22, 2026
Contents
1.0 Project Overview and Description
1.1. Executive Summary
1.2. Size and Location of Project Site
1.3. Existing Site Conditions
1.4. Watershed Description
1.5. Permits Required
2.0 Methodology
2.1. Drainage at Existing Site
2.2. Potential Impacts
2.3. Mitigation Techniques
2.4. Depth to Groundwater
2.5. Infiltration Testing
2.6. Proposed Stormwater Management
3.0 Analysis
3.1. Design Assumptions
3.2. Computation Methods and Software Used
3.3. Basin Analysis
3.4. Hydrology Calculations
3.5. Conveyance Requirements and Design
3.6. Flood Control Point of Discharge and Receiving System Capacity
4.0 Conclusions
4.1. Compliance with Stormwater Management Manual
4.2. Requirements Satisfied
Tables Table 3-1: Hydrologic Soil Group Ratings Table 3-2: Rainfall Intensities Table 3-3: Post-Developed Flow Rate Summary Table 3-4: Pre- and Post-Developed Flow Rates
Figures
Figure 1: Pre-Developed Basin Map Figure 2: Post-Developed Basin Map
Appendices Appendix A: HydroCAD Summary Appendix B: Web Soil Survey Appendix C: Geotechnical Report Appendix D: Facility Sizing – Presumptive Approach
STORMWATER REPORT
Cuthbert Amphitheater Site Improvements
Eugene, Oregon
1.0 Project Overview and Description
1.1. Executive Summary
This project consists of improvements to the Cuthbert Amphitheater (Cuthbert) within Alton Baker Park.
Improvements include construction of approximately 69 new paved parking spaces, new sidewalk connections to the pedestrian entry, resurfacing of the gravel backstage area, and utility relocation.
Stormwater from new impervious surfaces will be treated and managed using an Dry Detention Pond (Extended Filtration Facility) designed in accordance with the 2025 City of Eugene Stormwater Management Manual.
The facility provides water quality treatment, supplemental infiltration, and controlled discharge to the existing channel north of the site. The design meets all applicable requirements for water quality, flow control (where required), and flood control.
1.2. Size and Location of Project Site
The project is located in Alton Baker Park along Day Island Road in Eugene, Oregon, Tax Lot 300, Lane County Assessor’s Map 17 03 29 34. The total site area is approximately 6 acres.
1.3. Existing Site Conditions
Currently, the site contains an amphitheater, a gravel area for travel busses, and a grassy area behind the seating bowl of the amphitheater. A gravel path connects Day Island Road to the ticket booth and runs along the chain link fence. Pre’s Trail, a wood chip jogging trail, crosses the site.
1.4. Watershed Description
The site lies within Basin WKQF-020 per the City of Eugene Storm Drainage Basins – HUB. The amphitheater is located within FEMA Flood Zone AE.
1.5. Permits Required
The project requires:
City of Eugene Commercial Erosion Prevention Permit
DEQ 1200-C(A) Erosion and Sediment Control Plan (ESCP)
2.0 Methodology
2.1. Drainage at Existing Site
The southern portion of the site drains toward an existing wetland west of the amphitheater, sloping from approximately elevation 423.5 to 420.0. The northern portion drains toward a channel behind the amphitheater at elevation ~417.0. The site ultimately drains to the Willamette River.
Soils, per the Natural Resources Conservation Service (NRCS) Soil Resource Web Survey (Appendix B), include Camas gravelly sandy loam and Newberg fine sandy loam (HSG A) and Cloquato silt loam (HSG B).
2.2. Potential Impacts
Project improvements increase impervious area by approximately 50,000 square feet, resulting in:
Increased runoff volume and peak flow rates
Potential for increased pollutant loading (sediment, hydrocarbons, nutrients, metals)
Reduced time of concentration
Potential impacts to the downstream channel if unmanaged
These impacts are mitigated through the proposed Dry Detention Pond, vegetated filtration strips, and controlled overflow routing.
2.3. Mitigation Techniques
Mitigation measures include:
Dry Detention Pond providing water quality treatment and extended detention
Filtration strips for areas not tributary to the pond
Emergency overflow routed to the existing channel north of the site
Erosion control BMPs during construction
2.4. Depth to Groundwater
A geotechnical investigation was done by Foundation Engineering, Inc. on June 17, 2025. At the time of drilling, groundwater was not encountered within any of the test hole explorations. Refer to page 3 of the Geotechnical Report (Appendix A) for additional depth to groundwater discussion.
2.5. Infiltration Testing
Infiltration testing was performed by Foundation Engineering, Inc. on June 18, 2025, at three locations.
Testing was performed at depths from ±1 to ±3 feet below existing site grades. The subgrade soil encountered within the test holes consisted of sandy silt and silty sand. The infiltration rate used for this analysis is 0.5 in/hr.
While the infiltration rate used for this analysis is at the minimum allowed rate for a dedicated infiltration facility, a Dry Detention Pond was selected and sized with the understanding that infiltration will continue to occur.
2.6. Proposed Stormwater Management
Stormwater will be managed using:
Dry Detention Pond sized to treat runoff from ~38,000 sq ft of impervious area
Filtration strips for remaining impervious areas
Controlled overflow to the existing channel
The pond is located to allow future expansion if the parking lot is enlarged.
3.0 Analysis
3.1. Design Assumptions
The design of the stormwater system was analyzed for runoff generated by the 10-year storm event per 2025 City of Eugene Stormwater Management Manual. The 10-year storm is 4.46 inches in a 24-hour period for flood control.
The following table outlines the Hydrologic Soil Group rating for the soil types:
Table 3-1: Hydrologic Soil Group Ratings NRCS Map Unit Identification
NRCS Soil Classification (Percentage of Site)
Hydrologic Soil Group Rating
22 Camas Gravelly Sandy Loam (3.7%) A 29 Cloquato Silt Loam (2.3%) B 95 Newberg Fine Sandy Loam (94.1%) A
Runoff curve number (CN) for the developed conditions were obtained from Table C-2 of the City of Eugene Stormwater Management Manual. The following curve number (CN) was used for this analysis:
98 for Paved Parking Lots, roofs, driveways, etc. for Hydrologic Group A/B 76 for Gravel for Hydrologic Group A 72 for Dirt (Pre-Trail) for Hydrologic Group A
A time of concentration of 6 minutes was used for the post-developed runoff rate.
Table 3-2 summarizes the 24-hour rainfall intensities that were used for each design storm.
Table 3-2: Rainfall Intensities Recurrence Interval (Years) Total Precipitation Depth (Inches)
Water Quality 1.40 2-year 3.12 5-year 3.60
10-year 4.46 25-year 5.18
100-year 6.48
3.2. Computation Methods and Software Used
The design storm events were analyzed with HydroCAD (v10.0.22) using the Santa Barbara Urban Hydrograph (SBUH) method to generate the runoff generated from the events. The stormwater pond has been provided to fully infiltrate the 10-year storm event.
3.3. Basin Analysis
The project site was divided into four drainage basins — Basin 2S, Basin 3S, Basin 4S, and Basin 5S see figure 1 — for the purposes of stormwater flow control and water quality treatment analysis. Basin 2S encompasses the proposed sidewalk and parking lot areas, where runoff is collected via catch basins and conveyed to a dry detention pond. The pond is designed to provide both flow control and stormwater treatment. Runoff from concrete paths in Basins 3S and 4S is directed over filtration strips, which provide stormwater treatment through surface filtration. Basin 5S consists primarily of gravel surface areas, where runoff is managed through sheet flow dispersion over adjacent landscaped areas, allowing for natural filtration and passive infiltration into the underlying soils.
3.4. Hydrology Calculations
Table 3-3 below summarizes the post-developed flow rate and basin areas for the proposed site.
Table 3-3: Post-Developed Flow Rate Summary
Basin Area (Acres)
Curve Number
(CN)
Design Storm Event
Time of Concentration
(minutes)
Rainfall Intensity (in/hr)
Runoff Rate (cubic feet per second)
1.0 98 Water Quality 6.0 1.40 0.02 2-year 6.0 3.12 0.04 5-year 6.0 3.60 0.05 10-year 6.0 4.46 0.07
The Dry Detention Pond was sized using:
Impervious area: ~38,000 sq ft
Infiltration rate: 0.5 in/hr with factor of safety = 2
Water quality storm: 1.4 inches
Flood control storm: 10-year, 4.46 inches
3.5. Conveyance Requirements and Design
See Table 3-4 for the comparison between pre- and post-developed flow rates.
Table 3-4: Pre- and Post-Developed Flow Rates Design Storm Pre-Developed Flow Rate (cfs) Post-Developed Flow Rate (cfs)
2-year 0.04 0.00 5-year 0.07 0.00
10-year 0.15 0.00
3.6. Flood Control Point of Discharge and Receiving System Capacity Emergency overflow is directed north of the stormwater pond to the channel and away from the future parking lot. The channel has adequate capacity based on observed conditions and City drainage mapping.
4.0 Conclusions
4.1. Compliance with Stormwater Management Manual
The project complies with the 2025 City of Eugene Stormwater Management Manual through:
Use of an approved Extended Filtration Facility
Proper sizing for water quality treatment
Adequate conveyance and overflow routing
Avoidance of increased peak flows
4.2. Requirements Satisfied
Water Quality: Fully satisfied via Dry Detention Pond
Flow Control: No increase in peak flows
Flood Control: 10-year storm fully infiltrated with overflow routed to existing channel
CHKD:
DRWN:
DATE:
AKS JOB:
DW
G:
BA
SI
N
M
AP
S
FI
G
06/19/2026
12082
ADM
RCW
PRE-DEVELOPED BASIN MAP
FIGURE
1CUTHBERT AMPHITHEATER SITE IMPROVEMENTS
AKS ENGINEERING AND FORESTRY, LLC
3700 RIVER RD N, STE 1
KEIZER, OR 97303
503-400-6028 WWW.AKS-ENG.COM
LEGEND
CHKD:
DRWN:
DATE:
AKS JOB:
DW
G:
BA
SI
N
M
AP
S
FI
G
06/19/2026
12082
ADM
RCW
POST-DEVELOPED BASIN MAP
FIGURE
2CUTHBERT AMPHITHEATER SITE IMPROVEMENTS
AKS ENGINEERING AND FORESTRY, LLC
3700 RIVER RD N, STE 1
KEIZER, OR 97303
503-400-6028 WWW.AKS-ENG.COM
LEGEND
Appendix A: HydroCAD Summary
1S
Pre-Developed Basin
2S
PARKING LOT
1P
DRY DETENTION
POND
Routing Diagram for 12082 SW Calcs Prepared by AKS Engineering & Forestry, Printed 6/19/2026
HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Subcat Reach Pond Link
Type IA 24-hr 2-YR Rainfall=3.12"12082 SW Calcs Printed 6/19/2026Prepared by AKS Engineering & Forestry
Page 3HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 2S: PARKING LOT
Runoff = 0.50 cfs @ 7.94 hrs, Volume= 0.165 af, Depth= 2.01"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Type IA 24-hr 2-YR Rainfall=3.12"
Area (sf) CN Description
* 36,155 98
* 6,700 39
42,855 89 Weighted Average 6,700 15.63% Pervious Area
36,155 84.37% Impervious Area
Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs)
6.0 Direct Entry, Subcatchment 2S: PARKING LOT
Runoff
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F lo w
(c fs
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
Type IA 24-hr
2-YR Rainfall=3.12"
Runoff Area=42,855 sf
Runoff Volume=0.165 af
Runoff Depth=2.01"
Tc=6.0 min
CN=89
0.50 cfs
Page 4HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 1P: DRY DETENTION POND
Inflow Area = 0.984 ac, 84.37% Impervious, Inflow Depth = 2.01" for 2-YR event Inflow = 0.50 cfs @ 7.94 hrs, Volume= 0.165 af Outflow = 0.04 cfs @ 24.06 hrs, Volume= 0.143 af, Atten= 93%, Lag= 967.4 min Discarded = 0.04 cfs @ 24.06 hrs, Volume= 0.143 af Primary = 0.00 cfs @ 0.00 hrs, Volume= 0.000 af
Routing by Dyn-Stor-Ind method, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Peak Elev= 419.52' @ 24.06 hrs Surf.Area= 3,235 sf Storage= 4,891 cf
Plug-Flow detention time= 1,203.2 min calculated for 0.143 af (87% of inflow) Center-of-Mass det. time= 1,118.4 min ( 1,875.8 - 757.4 )
Volume Invert Avail.Storage Storage Description
#1 417.50' 15,390 cf Custom Stage Data (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store (feet) (sq-ft) (cubic-feet) (cubic-feet)
417.50 1,605 0 0
422.00 5,235 15,390 15,390
Device Routing Invert Outlet Devices
#1 Discarded 417.50' 0.500 in/hr Exfiltration over Horizontal area #2 Primary 420.75' 10.0' long Sharp-Crested Rectangular Weir 2 End Contraction(s)
Discarded OutFlow Max=0.04 cfs @ 24.06 hrs HW=419.52' (Free Discharge) 1=Exfiltration (Exfiltration Controls 0.04 cfs)
Primary OutFlow Max=0.00 cfs @ 0.00 hrs HW=417.50' (Free Discharge) 2=Sharp-Crested Rectangular Weir ( Controls 0.00 cfs)
Page 5HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Pond 1P: DRY DETENTION POND
Inflow Outflow Discarded Primary
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
Inflow Area=0.984 ac
Peak Elev=419.52'
Storage=4,891 cf
0.50 cfs
0.04 cfs
0.04 cfs
0.00 cfs
Type IA 24-hr 5-YR Rainfall=3.60"12082 SW Calcs
Page 6HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 1S: Pre-Developed Basin
Runoff = 0.07 cfs @ 22.10 hrs, Volume= 0.056 af, Depth= 0.12"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Type IA 24-hr 5-YR Rainfall=3.60"
Area (ac) CN Description
* 0.100 39
* 0.100 61
* 4.400 39
* 0.900 76
* 0.100 72
5.600 46 Weighted Average
5.600 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs)
41.5 Direct Entry, Subcatchment 1S: Pre-Developed Basin
Runoff
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F
0.08
0.075
0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
Type IA 24-hr
5-YR Rainfall=3.60"
Runoff Area=5.600 ac
Runoff Volume=0.056 af
Runoff Depth=0.12"
Tc=41.5 min
CN=46
0.07 cfs
Page 7HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 2S: PARKING LOT
Runoff = 0.62 cfs @ 7.93 hrs, Volume= 0.201 af, Depth= 2.45"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Type IA 24-hr 5-YR Rainfall=3.60"
Area (sf) CN Description
* 36,155 98
* 6,700 39
42,855 89 Weighted Average 6,700 15.63% Pervious Area
36,155 84.37% Impervious Area
Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs)
6.0 Direct Entry, Subcatchment 2S: PARKING LOT
Runoff
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F
0.65
0.6
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
Type IA 24-hr
5-YR Rainfall=3.60"
Runoff Area=42,855 sf
Runoff Volume=0.201 af
Runoff Depth=2.45"
Tc=6.0 min
0.62 cfs
Page 8HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 1P: DRY DETENTION POND
Inflow Area = 0.984 ac, 84.37% Impervious, Inflow Depth = 2.45" for 5-YR event Inflow = 0.62 cfs @ 7.93 hrs, Volume= 0.201 af Outflow = 0.04 cfs @ 24.07 hrs, Volume= 0.159 af, Atten= 93%, Lag= 968.4 min Discarded = 0.04 cfs @ 24.07 hrs, Volume= 0.159 af Primary = 0.00 cfs @ 0.00 hrs, Volume= 0.000 af
Routing by Dyn-Stor-Ind method, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Peak Elev= 419.92' @ 24.07 hrs Surf.Area= 3,556 sf Storage= 6,243 cf
Plug-Flow detention time= 1,271.3 min calculated for 0.159 af (79% of inflow) Center-of-Mass det. time= 1,141.9 min ( 1,888.4 - 746.5 )
Volume Invert Avail.Storage Storage Description
#1 417.50' 15,390 cf Custom Stage Data (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store (feet) (sq-ft) (cubic-feet) (cubic-feet)
417.50 1,605 0 0
422.00 5,235 15,390 15,390
Device Routing Invert Outlet Devices
#1 Discarded 417.50' 0.500 in/hr Exfiltration over Horizontal area #2 Primary 420.75' 10.0' long Sharp-Crested Rectangular Weir 2 End Contraction(s)
Discarded OutFlow Max=0.04 cfs @ 24.07 hrs HW=419.92' (Free Discharge) 1=Exfiltration (Exfiltration Controls 0.04 cfs)
Page 9HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Pond 1P: DRY DETENTION POND
Inflow Outflow Discarded Primary
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F
0.65
0.6
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
Inflow Area=0.984 ac
Peak Elev=419.92'
Storage=6,243 cf
0.62 cfs
0.04 cfs
0.04 cfs
Type IA 24-hr 10-YR Rainfall=4.46"12082 SW Calcs
Page 10HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 1S: Pre-Developed Basin
Runoff = 0.15 cfs @ 19.94 hrs, Volume= 0.150 af, Depth= 0.32"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Type IA 24-hr 10-YR Rainfall=4.46"
Area (ac) CN Description
* 0.100 39
* 0.100 61
* 4.400 39
* 0.900 76
* 0.100 72
5.600 46 Weighted Average
5.600 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs)
41.5 Direct Entry, Subcatchment 1S: Pre-Developed Basin
Runoff
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
Type IA 24-hr
10-YR Rainfall=4.46"
Runoff Area=5.600 ac
Runoff Volume=0.150 af
Runoff Depth=0.32"
Tc=41.5 min
0.15 cfs
Page 11HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 2S: PARKING LOT
Runoff = 0.84 cfs @ 7.91 hrs, Volume= 0.267 af, Depth= 3.26"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Type IA 24-hr 10-YR Rainfall=4.46"
Area (sf) CN Description
* 36,155 98
* 6,700 39
42,855 89 Weighted Average 6,700 15.63% Pervious Area
36,155 84.37% Impervious Area
Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs)
6.0 Direct Entry, Subcatchment 2S: PARKING LOT
Runoff
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F
0.9
0.85
0.8
0.75
0.7
0.65
0.6
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
Type IA 24-hr
10-YR Rainfall=4.46"
Runoff Area=42,855 sf
Runoff Volume=0.267 af
Runoff Depth=3.26"
Tc=6.0 min
0.84 cfs
Page 12HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 1P: DRY DETENTION POND
Inflow Area = 0.984 ac, 84.37% Impervious, Inflow Depth = 3.26" for 10-YR event Inflow = 0.84 cfs @ 7.91 hrs, Volume= 0.267 af Outflow = 0.05 cfs @ 24.08 hrs, Volume= 0.186 af, Atten= 94%, Lag= 969.7 min Discarded = 0.05 cfs @ 24.08 hrs, Volume= 0.186 af Primary = 0.00 cfs @ 0.00 hrs, Volume= 0.000 af
Routing by Dyn-Stor-Ind method, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Peak Elev= 420.58' @ 24.08 hrs Surf.Area= 4,087 sf Storage= 8,757 cf
Plug-Flow detention time= 1,353.3 min calculated for 0.185 af (69% of inflow) Center-of-Mass det. time= 1,173.0 min ( 1,904.6 - 731.6 )
Volume Invert Avail.Storage Storage Description
#1 417.50' 15,390 cf Custom Stage Data (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store (feet) (sq-ft) (cubic-feet) (cubic-feet)
417.50 1,605 0 0
422.00 5,235 15,390 15,390
Device Routing Invert Outlet Devices
#1 Discarded 417.50' 0.500 in/hr Exfiltration over Horizontal area #2 Primary 420.75' 10.0' long Sharp-Crested Rectangular Weir 2 End Contraction(s)
Discarded OutFlow Max=0.05 cfs @ 24.08 hrs HW=420.58' (Free Discharge) 1=Exfiltration (Exfiltration Controls 0.05 cfs)
Page 13HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Pond 1P: DRY DETENTION POND
Inflow Outflow Discarded Primary
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F
0.9
0.85
0.8
0.75
0.7
0.65
0.6
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
Inflow Area=0.984 ac
Peak Elev=420.58'
Storage=8,757 cf
0.84 cfs
0.05 cfs
0.05 cfs
Type IA 24-hr WQ Rainfall=1.40"12082 SW Calcs
Page 14HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 1S: Pre-Developed Basin
[45] Hint: Runoff=Zero
Runoff = 0.00 cfs @ 0.00 hrs, Volume= 0.000 af, Depth= 0.00"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Type IA 24-hr WQ Rainfall=1.40"
Area (ac) CN Description
* 0.100 39
* 0.100 61
* 4.400 39
* 0.900 76
* 0.100 72
5.600 46 Weighted Average
5.600 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs)
41.5 Direct Entry, Subcatchment 1S: Pre-Developed Basin
Runoff
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F
Type IA 24-hr
WQ Rainfall=1.40"
Runoff Area=5.600 ac
Runoff Volume=0.000 af
Runoff Depth=0.00"
Tc=41.5 min
Page 15HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 2S: PARKING LOT
Runoff = 0.12 cfs @ 7.99 hrs, Volume= 0.046 af, Depth= 0.56"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Type IA 24-hr WQ Rainfall=1.40"
Area (sf) CN Description
* 36,155 98
* 6,700 39
42,855 89 Weighted Average 6,700 15.63% Pervious Area
36,155 84.37% Impervious Area
Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs)
6.0 Direct Entry, Subcatchment 2S: PARKING LOT
Runoff
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F
0.13
0.125 0.12
0.115
0.11
0.105
0.1
0.095
0.09
0.085
0.08
0.075 0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025 0.02
0.015
0.01
0.005
Type IA 24-hr
WQ Rainfall=1.40"
Runoff Area=42,855 sf
Runoff Volume=0.046 af
Runoff Depth=0.56"
Tc=6.0 min
0.12 cfs
Page 16HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 1P: DRY DETENTION POND
Inflow Area = 0.984 ac, 84.37% Impervious, Inflow Depth = 0.56" for WQ event Inflow = 0.12 cfs @ 7.99 hrs, Volume= 0.046 af Outflow = 0.02 cfs @ 21.91 hrs, Volume= 0.046 af, Atten= 81%, Lag= 835.6 min Discarded = 0.02 cfs @ 21.91 hrs, Volume= 0.046 af Primary = 0.00 cfs @ 0.00 hrs, Volume= 0.000 af
Routing by Dyn-Stor-Ind method, Time Span= 0.00-60.00 hrs, dt= 0.05 hrs Peak Elev= 417.87' @ 21.91 hrs Surf.Area= 1,905 sf Storage= 652 cf
Plug-Flow detention time= (not calculated: outflow precedes inflow) Center-of-Mass det. time= 342.8 min ( 1,178.0 - 835.2 )
Volume Invert Avail.Storage Storage Description
#1 417.50' 15,390 cf Custom Stage Data (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store (feet) (sq-ft) (cubic-feet) (cubic-feet)
417.50 1,605 0 0
422.00 5,235 15,390 15,390
Device Routing Invert Outlet Devices
#1 Discarded 417.50' 0.500 in/hr Exfiltration over Horizontal area #2 Primary 420.75' 10.0' long Sharp-Crested Rectangular Weir 2 End Contraction(s)
Discarded OutFlow Max=0.02 cfs @ 21.91 hrs HW=417.87' (Free Discharge) 1=Exfiltration (Exfiltration Controls 0.02 cfs)
Page 17HydroCAD® 10.00-22 s/n 01338 © 2018 HydroCAD Software Solutions LLC
Pond 1P: DRY DETENTION POND
Inflow Outflow Discarded Primary
Hydrograph
Time (hours) 605856545250484644424038363432302826242220181614121086420
F
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
Inflow Area=0.984 ac
Peak Elev=417.87'
Storage=652 cf
0.12 cfs
0.02 cfs
0.02 cfs
Appendix B: Web Soil Survey
Soil Map—Lane County Area, Oregon
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
4/22/2026
493770 493810 493850 493890 493930 493970 494010
493770 493810 493850 493890 493930 493970 494010
44° 3' 26'' N
3°
' 4 0'
' W 44° 3' 26'' N
3°
' 2
8' ' W
44° 3' 14'' N
3°
' 4
0' ' W
44° 3' 14'' N
3°
' 2
8' ' W
N
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 10N WGS84 0 50 100 200 300
Feet 0 25 50 100 150
Meters Map Scale: 1:1,730 if printed on A portrait (8.5" x 11") sheet.
Soil Map may not be valid at this scale.
MAP LEGEND MAP INFORMATION
Area of Interest (AOI) Area of Interest (AOI)
Soils Soil Map Unit Polygons
Soil Map Unit Lines
Soil Map Unit Points
Special Point Features Blowout
Borrow Pit
Clay Spot
Closed Depression
Gravel Pit
Gravelly Spot
Landfill
Lava Flow
Marsh or swamp
Mine or Quarry
Miscellaneous Water
Perennial Water
Rock Outcrop
Saline Spot
Sandy Spot
Severely Eroded Spot
Sinkhole
Slide or Slip
Sodic Spot
Spoil Area
Stony Spot
Very Stony Spot
Wet Spot
Other
Special Line Features
Water Features Streams and Canals
Transportation Rails
Interstate Highways
US Routes
Major Roads
Local Roads
Background Aerial Photography
The soil surveys that comprise your AOI were mapped at 1:20,000.
Warning: Soil Map may not be valid at this scale.
Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale.
Please rely on the bar scale on each map sheet for map measurements.
Source of Map: Natural Resources Conservation Service Web Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as of the version date(s) listed below.
Soil Survey Area: Lane County Area, Oregon Survey Area Data: Version 24, Sep 10, 2025
Soil map units are labeled (as space allows) for map scales 1:50,000 or larger.
Date(s) aerial images were photographed: May 17, 2023—Jun 3, 2023
The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident.
Soil Map—Lane County Area, Oregon
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
4/22/2026
Map Unit Legend
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
22 Camas gravelly sandy loam, occasionally flooded
0.5 6.2%
29 Cloquato silt loam 0.4 4.4%
95 Newberg fine sandy loam 7.8 89.5%
Totals for Area of Interest 8.7 100.0%
Soil Map—Lane County Area, Oregon
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
4/22/2026
Appendix C: Geotechnical Report
Appendix D: Facility Sizing – Presumptive Approach
Stormwater Surface Filtration/Infiltration Facility Sizing Spreadsheet 24 Hour Storm, NRCS Type 1A Rainfall Distribution City of Eugene
Version 2.1 Project Information
Instructions:
Design Requirements:
Choose "Yes" from the dropdown boxes below next to the design standards requirements for this facility.
Pollution Reduction (PR) Yes Flow Control (FC) Yes
Destination (DT) Yes *An infiltration facility must be chosen as the facility type to meet destination requirements
Site Data-Post Development
Total Square Footage Impervious Area= 5144 sqft Total Square Footage Pervious Area= 9153 sqft
Impervious Area CN= 98 Pervious Area CN= 66
Total Square Footage of Drainage Area= 14297 sft Time of Concentration Post Development= 6 min
Weighted Average CN= 78
Site Data-Pre Development (Data in this section is only used if Flow Control is required)
Pre-Development CN= 46 Time of Concentration Pre-Development= 41.5 min
Soil Data
Tested Soil Infiltration Rate= 0.5 in/hr (See Note 4) 0.25 in/hr Design Soil Infiltration Rate= 0.5 in/hr
Design Storms Used For Calculations
Design Storm
1.4 inches Water Quality
3.6 inches Flood Control
3.6 inches Flood Control
Facility Data
Facility Type= Facility Surface Area= 3860 sqft
Surface Width= 20 ft Facility Surface Perimeter= 426 ft
Surface Length= 193 ft Facility Bottom Area= 3860 sqft
Facility Side Slopes= 0 to 1 Facility Bottom Perimeter= 426 ft
2 in Basin Volume= 611.2 cf
18 in Ratio of Facility Area to Impervious Area= 0.270
Permit Number:
Catchment ID:
Destination Design= Soil Infiltration Rate
24-hour Rainfall DepthRequirement
Pollution Reduction
Flow Control
4/27/2026
Depth of Growing Medium (Soil)=
3S & 2P
Date:
1. Complete this form for each drainage catchment in the project site that is to be sized per the Presumptive Approach.
Richard Walker, PE, Principal
AKS Engineering and Forestry
Eugene, OR 97401
Project Address:
Designer:
Company:
Cuthbert Amphitheater Site Improvements
Infiltration Stormwater Planter
Project Name:
200 Day Island Rad
Destination
2. Provide a distinctive Catchment ID for each facility coordinated with the site basin map to correlate the appropriate calculations with the facility.
3. The maximum drainage catchment to be modeled per the Presumptive Approach is 1 acre (43,560 SF)
4.For infiltration facilities in Class A or B soils where no infiltration testing has been perfromed use an infiltration rate of 0.5 in/hr.
For all facilities use a maximum soil infiltration rate of 2.5 in/hr for topsoil/growing medium.
Max. Ponding Depth in Stormwater Facility=
4/24/2026-11:54 AM 1
Pollution Reduction-Calculation Results
Peak Flow Rate to Stormwater Facility = 0.004 cfs Peak Facility Overflow Rate= 0.000 cfs
214 cf Total Overflow Volume= 0 cf
Max. Depth of Stormwater in Facility= 0.0 in
Drawdown Time= 0.2 hours
Yes Facility Sizing Meets Pollution Reduction Standards?
YES Meets Requirement of No Facility Flooding?
YES Meets Requirement for Maximum of 18 Hour Drawdown Time?
Flow Control-Calculation Results
Peak Flow Rate to Stormwater Facility = 0.118 cfs Peak Facility Overflow Rate= 0.000 cfs
1827 cf Total Overflow Volume= 0 cf
Max. Depth of Stormwater in Facility= 0.3 in N\A cfs
Drawdown Time= 0.2 hours
Pre-Development Runoff Data
Peak Flow Rate = 0.005 cfs
Total Runoff Volume = 144 cf
Yes Facility Sizing Meets Flow Control Standards?
YES Meets Requirement for Post Development offsite flow less or equal to Pre-Development Flow?
YES Meets Requirement for Maximum of 18 Hour Drawdown Time?
Destination-Calculation Results
Peak Flow Rate to Stormwater Facility = 0.118 cfs Peak Facility Overflow Rate= 0.000 cfs
1827 cf Total Overflow Volume= 0 cf
Max. Depth of Stormwater in Facility= 1.3 in
Drawdown Time= 4.7 hours
Yes Facility Sizing Meets Destination Standards?
YES Meets Requirement of No Facility Flooding?
YES Meets Requirement for Maximum of 30 hour Drawdown Time?
Total Runoff Volume to Stormwater Facility =
Total Runoff Volume to Stormwater Facility =
Total Runoff Volume to Stormwater Facility =
Peak Off-Site Flow Rate Filtration Facility Underdrain=
4/24/2026-11:54 AM 2
Stormwater Surface Filtration/Infiltration Facility Sizing Spreadsheet 24 Hour Storm, NRCS Type 1A Rainfall Distribution City of Eugene
Version 2.1 Project Information
Instructions:
Design Requirements:
Choose "Yes" from the dropdown boxes below next to the design standards requirements for this facility.
Pollution Reduction (PR) Yes Flow Control (FC) Yes
Destination (DT) Yes *An infiltration facility must be chosen as the facility type to meet destination requirements
Site Data-Post Development
Total Square Footage Impervious Area= 3688 sqft Total Square Footage Pervious Area= 27841 sqft
Impervious Area CN= 98 Pervious Area CN= 62
Total Square Footage of Drainage Area= 31529 sft Time of Concentration Post Development= 6 min
Weighted Average CN= 66
Site Data-Pre Development (Data in this section is only used if Flow Control is required)
Pre-Development CN= 46 Time of Concentration Pre-Development= 41.5 min
Soil Data
Tested Soil Infiltration Rate= 0.5 in/hr (See Note 4) 0.25 in/hr Design Soil Infiltration Rate= 0.5 in/hr
Design Storms Used For Calculations
Design Storm
1.4 inches Water Quality
3.6 inches Flood Control
3.6 inches Flood Control
Facility Data
Facility Type= Facility Surface Area= 4800 sqft
Surface Width= 30 ft Facility Surface Perimeter= 380 ft
Surface Length= 160 ft Facility Bottom Area= 4800 sqft
Facility Side Slopes= 0 to 1 Facility Bottom Perimeter= 380 ft
2 in Basin Volume= 760.0 cf
18 in Ratio of Facility Area to Impervious Area= 0.152
2. Provide a distinctive Catchment ID for each facility coordinated with the site basin map to correlate the appropriate calculations with the facility.
3. The maximum drainage catchment to be modeled per the Presumptive Approach is 1 acre (43,560 SF)
4.For infiltration facilities in Class A or B soils where no infiltration testing has been perfromed use an infiltration rate of 0.5 in/hr.
For all facilities use a maximum soil infiltration rate of 2.5 in/hr for topsoil/growing medium.
Max. Ponding Depth in Stormwater Facility=
Project Address:
Designer:
Company:
Cuthbert Amphitheater Site Improvements
Infiltration Stormwater Planter
Project Name:
200 Day Island Rad
Destination
4/27/2026
Depth of Growing Medium (Soil)=
4S & 3P
Date:
1. Complete this form for each drainage catchment in the project site that is to be sized per the Presumptive Approach.
Richard Walker, PE, Principal
AKS Engineering and Forestry
Eugene, OR 97401
Permit Number:
Catchment ID:
Destination Design= Soil Infiltration Rate
24-hour Rainfall DepthRequirement
Pollution Reduction
Flow Control
5/6/2026-8:26 AM 1
Pollution Reduction-Calculation Results
Peak Flow Rate to Stormwater Facility = 0.003 cfs Peak Facility Overflow Rate= 0.000 cfs
68 cf Total Overflow Volume= 0 cf
Max. Depth of Stormwater in Facility= 0.0 in
Drawdown Time= 0.2 hours
Yes Facility Sizing Meets Pollution Reduction Standards?
YES Meets Requirement of No Facility Flooding?
YES Meets Requirement for Maximum of 18 Hour Drawdown Time?
Flow Control-Calculation Results
Peak Flow Rate to Stormwater Facility = 0.094 cfs Peak Facility Overflow Rate= 0.000 cfs
2263 cf Total Overflow Volume= 0 cf
Max. Depth of Stormwater in Facility= 0.1 in N\A cfs
Drawdown Time= 0.2 hours
Pre-Development Runoff Data
Peak Flow Rate = 0.011 cfs
Total Runoff Volume = 317 cf
Yes Facility Sizing Meets Flow Control Standards?
YES Meets Requirement for Post Development offsite flow less or equal to Pre-Development Flow?
YES Meets Requirement for Maximum of 18 Hour Drawdown Time?
Destination-Calculation Results
Peak Flow Rate to Stormwater Facility = 0.094 cfs Peak Facility Overflow Rate= 0.000 cfs
2263 cf Total Overflow Volume= 0 cf
Max. Depth of Stormwater in Facility= 1.5 in
Drawdown Time= 5.7 hours
Yes Facility Sizing Meets Destination Standards?
YES Meets Requirement of No Facility Flooding?
YES Meets Requirement for Maximum of 30 hour Drawdown Time?
Total Runoff Volume to Stormwater Facility =
Peak Off-Site Flow Rate Filtration Facility Underdrain=
Total Runoff Volume to Stormwater Facility =
Total Runoff Volume to Stormwater Facility =