This is a bid form for Pierce County, Washington's Orangegate Park Phase 1 Site Improvements project, a 40-acre park development in the Summit-Waller community. The project encompasses construction of an ADA-accessible nature playground, parking facilities, bioswales and wetland areas, an off-leash dog park, park shelters, a restroom and maintenance building, soft-surface hiking trails, a safe pedestrian crossing of 84th Street East, and connections to the Pipeline Trail. The bid form requires contractors to submit a base bid for the basic site improvements along with separate pricing for six optional items: a substitutive alternate for a picnic shelter and five additive alternates including an off-leash area loop trail, clearing work, split rail fencing, and trail signage. Contractors must substantially complete all base bid and alternate work within 310 calendar days of receiving the notice to proceed, with an additional 30 calendar days permitted to achieve final completion and acceptance, for a total of 340 calendar days.
Bids will be evaluated based on the lowest base bid subtotal from a responsible, responsive bidder, with Pierce County retaining the right to award the base bid with all, some, or none of the alternates or additives. The bid must include a lump sum amount for apprenticeship utilization requirements, as projects with an engineer's estimate of $1,500,000 or more require fifteen percent of labor hours be performed by apprentices as of July 1, 2026. Bidders must also identify any trench excavation safety provisions costs as a separate line item if applicable. Liquidated damages are set at $3,529 per consecutive calendar day of default. All bidders must submit a bidder responsibility information form, bid bond form, and subcontractors list with their bids and certify compliance with prevailing wage statutes, apprenticeship requirements, and Title VI nondiscrimination provisions. Sales tax will be applied to taxable amounts based on the location of service and is not to be included in bid pricing.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Division 00 - Procurement and Contracting Requirements Bid Form
BID FORM
BIDDER REGISTERED NAME: ________________________________________________
BID DATE: ________________________________________________________________
Having carefully examined all drawings & specifications prepared by Pierce County, as well as the premises and conditions affecting the work, the Undersigned proposes to furnish all labor, equipment, and materials and perform all work for this project in accordance with the drawings, specifications, and addenda (if any), for the consideration of the following amounts. Please note: all items on the bid form need to completed to be considered responsive.
| # |
| Description |
| UOM |
| Extended Price |
BASIC BID ITEMS:
| 1 |
| BASIC BID (Orangegate Park Phase 1 Site Improvements) |
| 1 LS |
| $ |
| *BASIC BID SUBTOTAL |
| $ |
SUBSTITUTIVE ALTERNATES: PER SECTION 01 23 00
| A1 |
| Substitutive Alternate 01: Picnic Shelter 1 |
| 1 LS |
| $ |
ADDITIVE ALTERNATES: PER SECTION 01 23 00
| A2 |
| Additive Alternate 02: OLA (Off Leash Area) Loop Trail |
| 1 LS |
| $ |
| A3 |
| Additive Alternate 03: OLA Clearing |
| 1 LS |
| $ |
| A4 |
| Additive Alternate 04: Split Rail Fence Along 84th St E |
| 1 LS |
| $ |
| A5 |
| Additive Alternate 05: Contractor Furnish, Owner Install Trail Directional Signs |
| 1 LS |
| $ |
| A6 |
| Additive Alternate 06: Contractor Furnish, Owner Install Trail Entry-Large Signage in Greater Orangegate Park Land |
| 1 LS |
| $ |
| *ALTERNATE BID SUBTOTAL (Bid Items A1-A6) |
| $ |
| *TOTAL BID PRICE (Basic Bid Subtotal + Alternate Bid Subtotal) |
| $ |
*Sales tax will be paid on taxable amounts based on the rate of the location of service - NOT TO BE INCLUDED in bid pricing.
EVALUATION OF BIDS: In accordance with the provisions of these Contract Documents, Bids will be evaluated to determine the lowest Base Bid Subtotal offered by a responsible Bidder submitting a responsive bid.
AWARD: For the purposes of awarding the contract and determining responsible, responsive bid, bids are evaluated on the base bid and any combination of alternates and additives that the Owner chooses to exercise. Pierce County reserves the right to award base bid and all or none of the alternates or additives. It is anticipated that any alternate bids for additional or related work will be accepted at the time contract award is made.
LIQUIDATED DAMAGES: The Undersigned acknowledges and agrees to abide by all provisions of the Liquidated Damages of $3,529.00 as it pertains to the Contractor for all work under this Contract. The Undersigned further agrees to pay to the Owner as liquidated damages the sum calculated for each consecutive calendar day that is in default after the time for completion specified herein as per section 007200-10.07 of Pierce County General Conditions.
APPRENTICE UTILIZATION REQUIREMENTS: As of July 1, 2026, all public works contracts with an Engineer's Estimate of $1,500,000.00 or more are required to have an apprenticeship utilization plan submitted by the winning contractor per RCW 39.04.320, where fifteen (15) percent of the labor hours must be performed by apprentices. A monetary incentive and monetary penalty will be applied to the contractor failing to meet the utilization requirement and failing to demonstrate a Good Faith Effort (GFE) per the Apprenticeship Utilization Requirement Section. The contractor's Base Bid shall include a lump sum amount, excluding Washington State Sales Tax for this cost. If contractor is submitting a GFE for this bid, the bidder should enter "not applicable" in the blank below and check the "yes" box indicating they intend on submitting a GFE.
Apprenticeship Utilization Requirement (dollar total in written figures only):
Has the bidder been found out of compliance with the Washington State apprenticeship and training council for working apprentices out of ratio, without appropriated supervision, or outside their approved work processes as outline in their standards of apprenticeship under chapter 49.04 RCW for the one-year period immediately preceding the date of the bid solicitation: ________ (Yes/No)?
TRENCH EXCAVATION SAFETY PROVISIONS: If the contract contains any work which requires trenching exceeding a depth of four feet, all costs for adequate trench safety systems shall be identified as a separate bid item in compliance with Chapter 39.04.180 RCW. The purpose of this provision is to ensure that the bidder agrees to comply with all the relevant trench safety requirements of Chapter 49.17 RCW. This bid amount shall be considered as part of the total base bid set forth above. If trench excavation safety provisions do not pertain to this project, put N.A. for the below.
Trench Excavation Safety Provisions Only (dollar total in written figures only): __________________________ TIME OF COMPLETION: The Contractor shall be required to Substantially Complete all Base Bid and Alternate Bid work within 310 Calendar Days of Notice To Proceed. The Contractor will have an additional 30 CALENDAR DAYS for a total of 340 CALENDAR DAYS to reach Final Completion and Acceptance.
ADDENDA: Bidder acknowledges review of all Addenda through No.
CONTACT INFORMATION:
FIRM: ______________________________________________________________________
ADDRESS: __________________________________________________________________
CITY: STATE: ZIP: ________
NAME OF MAIN CONTACT FOR THIS BID: _______________________________________
PHONE: _________________________________
EMAIL: _________________________________
| SIGNATURE OF AUTHORIZED PERSON*: | _________________ |
| PRINT NAME & TITLE: | _________________ |
DATE: ___________________________
*to determine 'authorized' person reference Division 00 'Instructions to Bidders' Complete the tax status information for one of the following business entity types. Individual or Corporate name must match exactly as registered with either Social Security Administration or Internal Revenue Service.
Identification of Contractor as a sole proprietor, a partnership, a joint venture, a corporation, or another described form of legal entity: __________________________________________________________
Federal Tax ID# (EIN or SSN – as applicable): _____________________________________________
* If a corporation, bid must be executed in the corporate name by the president or vice-president (or any other corporate officer accompanied by evidence of authority to sign). If a co-partnership, bid must be executed by a partner.
THE FOLLOWING DOCUMENTS ARE TO BE SUBMITTED WITH THIS BID FORM:
| • | Bidder Responsibility Information Form |
| • | Bid Bond Form |
| • | Subcontractors List Form |
BIDDER RESPONSIBILITY INFORMATION FORM (TO BE SUBMITTED WITH BID):
State of Washington Contractor's License No:
Unified Business Identifier (UBI) No:
Employment Security Department No:
DEBARMENT: Bidder has not been disqualified from bidding on any public works contract under RCW 39.06.010 or 39.12.065? ☐ YES ☐ NO
| PREVAILING WAGES TRAINING: Bidder has received training on the requirements related to public works and prevailing wage under chapter 39.04 and chapter 39.12 RCW or are exempt from the training per | ||
| RCW 39.04.350: ☐ YES | ☐ NO |
TITLE VI COMPLIANCE
Pierce County, in accordance with Title VI of the Civil Rights Act of 1964, 78 Stat. 252, 42 U.S.C. 2000d to 2000d-4 and Title 49, Code of Federal Regulations, Department of Transportation, subtitle A, Office of the Secretary, Part 21, nondiscrimination in federally assisted programs of the Department of Transportation issued pursuant to such Act, hereby notifies all bidders that it will affirmatively ensure that in any contract entered into pursuant to this advertisement, disadvantaged business enterprises as defined at 49 CFR Part 26 will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.
CERTIFICATION OF COMPLIANCE WITH WAGE PAYMENT STATUTES
The bidder hereby certifies that, within the three-year period immediately preceding the bid due date, the bidder is not a willful violator, as defined in RCW 49.48.082, of any provision of chapters 49.46, 49.48, or 49.52 RCW, as determined by a final and binding citation and notice of assessment issued by the Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction.
I declare under penalty of perjury under the laws of the State of Washington that the statement regarding Certification of Compliance with Wage Payment Statutes is true and correct.
*SIGNATURE OF AUTHORIZED PERSON:
PRINT NAME & TITLE:
DATE:
*to determine ‘authorized’ person reference RCW 39.04.350(1)(g) / RCW 5.50