2_Kodiak_Paving_IDIQ_Price Schedule.xlsx

XLSX spreadsheet 33 KB Posted

Attached to
USCG Base Kodiak Paving IDIQ
Solicitation number
70Z08723RKODI8270978
Issued by

View the file

Other files

File Type Posted
Revised__Kodiak_Paving_IDIQ_Price_Schedule.xlsx XLSX spreadsheet
Amend 0001_23KODI8270978_Paving IDIQ.pdf PDF
01_18382348_Specs_Attachment 10 Delegation Signatory.pdf PDF
01_18382348_Specs_Attachment 6 Request for variations_sample.pdf PDF
01_18382348_Specs_Attachment 7 Request for Deviation Form_Sample.pdf PDF
01_18382348_Specs_Attachment 1 Request for Payment Form.xlsx XLSX spreadsheet
01_18382348_Specs_Attachment 2 DHS Contractor Release.pdf PDF
01_18382348_Specs_Attachment 11 Base Kodiak Generic EMP_12032021.pdf PDF
01_18382348_Specs_Attachment 5 Submittal Register.pdf PDF
01_18382348_Specs_Attachment 8 Daily Report.pdf PDF
01_18382348_Specs_Attachment 3 Daily Report_sample.xlsx XLSX spreadsheet
01_18382348_Specs_Attachment 4 Submittal Transmittal Form.pdf PDF
01_18382348_Specs_Attachment 9 Test Report Form_Sample.pdf PDF
4_Past Performance Questionnaire.pdf PDF
5_CertCrnt CostPrice Data_PavingIDIQ.pdf PDF
3_WD_AK20230007_Dated_1-6-2023.pdf PDF
7_TO RFP FY23 Polaris_StElias.pdf PDF
18382348_SPECS.pdf PDF
CGPD Vetting Request.pdf PDF
RFP_Kodiak_Paving_IDIQ_4-5-23.pdf PDF
18382348_Drawings.pdf PDF
Ombudsman Program Notice.pdf PDF
1_SOW Section 01 11 00_PN 8270978.pdf PDF
6_SF24-Bid Bond.pdf PDF
WD_AK20230007_Dated_1-6-2023.pdf PDF
Facility Access Instructions (Base Kodiak).pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IDIQ Price Schedule

INSTRUCTIONS:

1. Enter the unit rate for each work item in Base Year column (D)

2. Enter yearly escalation rate in columns E, G, I and K. Enter as a number 5%=5. Cells formulated as percentages. Option Year unit rates will automatically calculate.

3. Complete Indirect Cost Rate Table (100-102B & C)LEGEND
SYSquare Yard
CYCubic Yard
LFLinear Foot
TNTon
EAEach
ACAcre
SHSheet
HRHour
Work Item Price/Cost
Item No.Work ItemUnitBase Year
Unit Rate (unburdened)Escalation % Rate (enter as number i.e., 2.5, 5)Option Year 1
Unit Rate (unburdened-w/escalation)Escalation % Rate (enter as number i.e., 2.5, 5)Option Year 2
Unit Rate (unburdened-w/escalation)Escalation % Rate (enter as number i.e., 2.5, 5)Option Year 3
Unit Rate (unburdened-w/escalation)Escalation % Rate (enter as number i.e., 2.5, 5)Option Year 4

Unit Rate (unburdened-w/escalation)

1Clearing and Grubbing ≤ 1,000 SYSY$ - 0$ - 0$ - 0$ - 0
2Clearing and Grubbing > 1,000 SYSY$ - 0$ - 0$ - 0$ - 0
3Saw Cut; Bituminous Pavement 4" Thick or less; ≤ 1,000 LFLF$ - 0$ - 0$ - 0$ - 0
4
Saw Cut; Bituminous Pavement 4" Thick or less; > 1,000 LFLF$ - 0$ - 0$ - 0$ - 0
5Saw‐cut; Bituminous Pavement Thicker than 4"; ≤ 1,000 LFLF$ - 0$ - 0$ - 0$ - 0
6Saw‐cut; Bituminous Pavement Thicker than 4"; > 1,000 LFLF$ - 0$ - 0$ - 0$ - 0
7Saw Cut; Rigid Pavement 4" Thick or less, lightly reinforced; ≤
500 LFLF$ - 0$ - 0$ - 0$ - 0
8Saw Cut; Rigid Pavement 4" Thick or less, lightly reinforced; >
500 LFLF$ - 0$ - 0$ - 0$ - 0
9Saw‐cut; Rigid Pavement Thicker than 4", lightly reinforced; ≤
500 LFLF$ - 0$ - 0$ - 0$ - 0
10Saw‐cut; Rigid Pavement Thicker than 4", lightly reinforced; >
500 LFLF$ - 0$ - 0$ - 0$ - 0
11
Remove Bituminous Pavement 4" Thick or less; ≤ 1,000 LFSY$ - 0$ - 0$ - 0$ - 0
12Remove Bituminous Pavement 4" Thick or less; > 1,000 LFSY$ - 0$ - 0$ - 0$ - 0
13Remove Bituminous Pavement; Thicker than 4", price per
each additional 2" lift; ≤ 1,000 LFSY$ - 0$ - 0$ - 0$ - 0
14Remove Bituminous Pavement; Thicker than 4", price per
each additional 2" lift; > 1,000 LFSY$ - 0$ - 0$ - 0$ - 0
15Remove Rigid Pavement: 4" Thick or less; ≤ 1000 SYSY$ - 0$ - 0$ - 0$ - 0
16Remove Rigid Pavement: 4" Thick or less; > 1000 SYSY$ - 0$ - 0$ - 0$ - 0
17Remove Rigid Pavement: Thicker than 4", price per additional
2" lift: ≤ 1,000 SYSY$ - 0$ - 0$ - 0$ - 0
18Remove Rigid Pavement: Thicker than 4", price per additional
2" lift: > 1,000 SYSY
19Mill/Plane Bituminous Pavement; 2" or less; ≤ 2000 SYSY$ - 0$ - 0$ - 0$ - 0
20Mill/Plane Bituminous Pavement; 2" or less; > 2000 SYSY$ - 0$ - 0$ - 0$ - 0
21Mill/Plane Bituminous Pavement; greater than 2", Price per
additional 1" increment; ≤ 2000 SYSY$ - 0$ - 0$ - 0$ - 0
22Mill/Plane Bituminous Pavement; greater than 2", Price per
additional 1" increment; > 2000 SYSY$ - 0$ - 0$ - 0$ - 0
23Bituminous Concrete Patch Repair (includes saw cut the perimeter of the areas to be patched, excavate and remove approximately 4" of bituminous concrete, compaction and placement of up to 2" of base material, furnish and place tack coat along inside edges, furnish and place up to 4" of bituminous concrete in two courses over prepared areas).SY$ - 0$ - 0$ - 0$ - 0
24Remove Unsuitable Base MaterialCY$ - 0$ - 0$ - 0$ - 0
25Bitumen for Prime CoatSY$ - 0$ - 0$ - 0$ - 0
26Bitumen for Tack CoatSY$ - 0$ - 0$ - 0$ - 0
27D1 Base CourseTN$ - 0$ - 0$ - 0$ - 0
28AC Pavement Base CourseTN$ - 0$ - 0$ - 0$ - 0
29AC Pavement Wearing CourseTN$ - 0$ - 0$ - 0$ - 0
30Concrete Paving: 6" or less, reinforced with fiber mesh; ≤ 200
SYSY$ - 0$ - 0$ - 0$ - 0
31Concrete Paving: 6" or less, reinforced with fiber mesh; > 200 SYSY$ - 0$ - 0$ - 0$ - 0
32Concrete Paving: 6" or greater, reinforced with fiber mesh; ≤ 200 SYSY$ - 0$ - 0$ - 0$ - 0
33Concrete Paving: 6" or greater, reinforced with fiber mesh; > 200 SYSY$ - 0$ - 0$ - 0$ - 0
34Seal Cracks Bituminous PavementLF$ - 0$ - 0$ - 0$ - 0
35Seal Cracks (Rigid/Concrete Pavement)LF$ - 0$ - 0$ - 0$ - 0
36Concrete Sidewalks: ≤ 25 SYSY$ - 0$ - 0$ - 0$ - 0
37Concrete Sidewalks: > 25 SYSY$ - 0$ - 0$ - 0$ - 0
38Concrete Handicap SidewalkEA$ - 0$ - 0$ - 0$ - 0
39Bituminous Concrete Sidewalks: ≤ 25 SYSY$ - 0$ - 0$ - 0$ - 0
40Bituminous Concrete Sidewalks: > 25 SYSY$ - 0$ - 0$ - 0$ - 0
41Bituminous Concrete Curb RemovalLF$ - 0$ - 0$ - 0$ - 0
42Bituminous Concrete Curb InstallLF$ - 0$ - 0$ - 0$ - 0
43Cement Concrete Curb RemovalLF$ - 0$ - 0$ - 0$ - 0
44Cement Concrete Curb InstallLF$ - 0$ - 0$ - 0$ - 0
45Fine Grade and Compact SubgradeSY$ - 0$ - 0$ - 0$ - 0
46Site Restoration ‐ Loam and SpreadCY$ - 0$ - 0$ - 0$ - 0
47Site Restoration ‐ SeedingSY$ - 0$ - 0$ - 0$ - 0
48Site Restoration ‐ SoddingSY$ - 0$ - 0$ - 0$ - 0
49Structural Fill for SubbaseTN$ - 0$ - 0$ - 0$ - 0
50Reset Catch Basin/ManholeEA$ - 0$ - 0$ - 0$ - 0
51Rebuild Catch Basin/Manhole (Masonry)EA$ - 0$ - 0$ - 0$ - 0
52Remove and Reset Wheel StopsEA$ - 0$ - 0$ - 0$ - 0
53Wheel Stops ‐ NewEA$ - 0$ - 0$ - 0$ - 0
54Traffic Signs ‐ StopEA$ - 0$ - 0$ - 0$ - 0
55Traffic Signs ‐ No ParkingEA$ - 0$ - 0$ - 0$ - 0
56Traffic Signs ‐ One WayEA$ - 0$ - 0$ - 0$ - 0
57Traffic Signs ‐ Handicap ParkingEA$ - 0$ - 0$ - 0$ - 0
58Remove and Replace Existing SignsEA$ - 0$ - 0$ - 0$ - 0
594" Pavement Marking; Parking StallEA$ - 0$ - 0$ - 0$ - 0
60Methyl Methacrylate Traffic Paint Pavement Marking;
CrosswalkLF$ - 0$ - 0$ - 0$ - 0
61Methyl Methacrylate Traffic Paint Pavement Marking;
CenterlineLF$ - 0$ - 0$ - 0$ - 0
62Methyl Methacrylate Traffic Paint Pavement Marking;
Handicap stall with symbolEA$ - 0$ - 0$ - 0$ - 0
63Methyl Methacrylate Traffic Paint Pavement Marking; Double
Yellow CenterlineLF$ - 0$ - 0$ - 0$ - 0
64
Methyl Methacrylate Traffic Paint Pavement Marking: Misc 4"LF$ - 0$ - 0$ - 0$ - 0
65Removal of Existing Traffic PaintLF$ - 0$ - 0$ - 0$ - 0
66Guardrail RemovalLF$ - 0$ - 0$ - 0$ - 0
67Guardrail Install: Steel Rail/Wood PostLF$ - 0$ - 0$ - 0$ - 0
68Soil/Bituminous Concrete Pavement Density Testing; Nuclear
Density TestLF$ - 0$ - 0$ - 0$ - 0
69Slurry Seal/SealcoatSY$ - 0$ - 0$ - 0$ - 0
70POL‐Contaminated Soil handling, sampling, testing, containerization, barge, disposal at off‐island landfill, disposal
chargesCY$ - 0$ - 0$ - 0$ - 0
71Environmental Management Plan (incl. Contaminated Soil
Disposal Plan)EA$ - 0$ - 0$ - 0$ - 0
72SurveyAC$ - 0$ - 0$ - 0$ - 0
73Stormwater Pollution Prevention Plan (SWPPP)AC$ - 0$ - 0$ - 0$ - 0
74Traffic Control Plan/MOTEA$ - 0$ - 0$ - 0$ - 0
75Environmental Protection PlanEA$ - 0$ - 0$ - 0$ - 0
76Qualified Environmental Professional (QEP)HR$ - 0$ - 0$ - 0$ - 0
77CAD As‐Built DrawingsSH$ - 0$ - 0$ - 0$ - 0
78MobilizationEA$ - 0$ - 0$ - 0$ - 0
79DemobilizationEA$ - 0$ - 0$ - 0$ - 0
Other Indirect Costs% Rate
Overhead
Profit

Sheet2

Sheet3

File details come from the government source that posted it. Updated .