2-Contractor Prequalification Form.pdf
PDF 151 KB Posted
- Solicitation number
- 901
- Issued by
- Utah
About this file
This is a Contractor Prequalification Form for the Jordan Basin Improvement District related to Multiple Mountain View Corridor Sewer Projects located in Riverton and Herriman, Utah. The prequalification document establishes minimum qualifications that contractors must meet to bid on four separate sewer projects. Projects include the 13800 South Mountain View Corridor Sewer Project (500 linear feet of 18-inch sewer with 434 linear feet of trenchless guided bore), the 12600 South Mountain View Corridor Sewer Project (2,610 linear feet of 30-inch sewer with 342 linear feet of trenchless guided bore), the 13200 South Mountain View Corridor Sewer Project (1,328 linear feet of 18-inch sewer and 121 linear feet of 10-inch sewer with 534 linear feet of trenchless guided bore), and the 13400 South Mountain View Corridor Sewer Project (1,726 linear feet of 15-inch sewer and 85 linear feet of 8-inch sewer with 519 linear feet of trenchless guided bore). All projects must be completed by June 30, 2027, with construction authorized during the typical winter moratorium period of October 15 through April 15.
To qualify, contractors must demonstrate successful completion of sewer projects with deep pipeline excavation of 25 feet or deeper, trenchless construction guided boring capability (either self-performed or subcontracted), and prior successful completion of a project with Jordan Basin Improvement District within the past 10 years. The prequalification form requires submission of three representative sewer projects with detailed information including project owner contact information, sewer length and diameter, maximum excavation depth, trenchless boring length and casing diameter, and project completion dates. Contractors must also identify a Project Manager and Superintendent, each with minimum five years of experience and comparable project experience meeting the same technical criteria. References will be checked, and contractors must disclose bankruptcy history and any claims related to traffic control.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Contractor Prequalification Package.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MULTIPLE MOUNTAIN VIEW CORRIDOR SEWER PROJECTS
JORDAN BASIN IMPROVEMENT DISTRICT
CONTRACTOR PREQUALIFICATION
09/01/26
Contractor Qualification Form
Jordan Basin Improvement District
Multiple Mountain View Corridor Sewer Crossing Projects Prequalification
Contractor shall have successfully completed sewer projects collectively that meet the minimum following criteria:
o deep sewer pipeline excavation (25 feet and deeper) o trenchless construction guided boring (self-performed or subcontracted work is acceptable) o successfully completed a project with JBID within the past 10 years
Contractor shall provide the project information as requested below. Additional information may be attached as needed to demonstrate the minimum qualifications have been met.
Contractors Name: ______________________________________________________________
Years in operation: ________________Type of Entity__________________________________
Have you or any of your subsidiaries filed bankruptcy? _________________________________
Has your company had any claims related to your traffic control? Y / N
If ‘yes’, please describe on an attached sheet of paper the project and incident.
References will be checked.
Sewer Project 1: ______________________________________Date Completed: ____________ Name and Address of Owner: ______________________________________________________ Contact Person: ________________________________Phone Number: ____________________ Length of Sewer Installed: ______________________LF Diameter: _________Inches Maximum Depth of Sewer Installed ______________ FT Trenchless Guided Boring Installed: ______________ LF Casing Diameter: _________Inches Additional Project Details: ________________________________________________________
Sewer Project 2: ______________________________________Date Completed: ____________ Name and Address of Owner: ______________________________________________________ Contact Person: ________________________________Phone Number: ____________________ Length of Sewer Installed: ______________________LF Diameter: _________Inches Maximum Depth of Sewer Installed ______________ FT Trenchless Guided Boring Installed: ______________ LF Casing Diameter: _________Inches Additional Project Details: ________________________________________________________ Sewer Project 3: ______________________________________Date Completed: ____________ Name and Address of Owner: ______________________________________________________ Contact Person: ________________________________Phone Number: ____________________ Length of Sewer Installed: ______________________LF Diameter: _________Inches Maximum Depth of Sewer Installed ______________ FT Trenchless Guided Boring Installed: ______________ LF Casing Diameter: _________Inches Additional Project Details: ________________________________________________________
Signature Title
Date
Project Manager Qualification Form
Multiple Mountain View Corridor Sewer Crossing Projects Prequalification
Proposed Project Manager must have a minimum of 5 years experience as a project manager and identify what project experience they have with the following criteria:
o deep sewer pipeline excavation (25 feet and deeper) o trenchless construction guided boring (self-performed or subcontracted work is acceptable) o successfully completed a project with JBID within the past 10 years
Project Managers Name: _________________________________________________________
Years as a Project Manager: ______________
References will be checked.
Sewer Project 1: ______________________________________Date Completed: ____________ Name and Address of Owner: ______________________________________________________ Contact Person: ________________________________Phone Number: ____________________ Length of Sewer Installed: ______________________LF Diameter: _________Inches Maximum Depth of Sewer Installed ______________ FT Trenchless Guided Boring Installed: ______________ LF Casing Diameter: _________Inches Additional Project Details: ________________________________________________________
Contact Person: ________________________________Phone Number: ____________________ Length of Sewer Installed: ______________________LF Diameter: _________Inches Maximum Depth of Sewer Installed ______________ FT Trenchless Guided Boring Installed: ______________ LF Casing Diameter: _________Inches Additional Project Details: ________________________________________________________ Sewer Project 3: ______________________________________Date Completed: ____________ Name and Address of Owner: ______________________________________________________ Contact Person: ________________________________Phone Number: ____________________ Length of Sewer Installed: ______________________LF Diameter: _________Inches Maximum Depth of Sewer Installed ______________ FT Trenchless Guided Boring Installed: ______________ LF Casing Diameter: _________Inches Additional Project Details: ________________________________________________________
Signature Title
Project Superintendent Qualification Form
Multiple Mountain View Corridor Sewer Crossing Projects Prequalification
Proposed Superintendent must have a minimum of 5 years experience as a superintendent and identify what project experience they have with the following criteria:
o deep sewer pipeline excavation (25 feet and deeper) o trenchless construction guided boring (self-performed or subcontracted work is acceptable) o successfully completed a project with JBID within the past 10 years
Superintendent Name: _________________________________________________________
Years as a Superintendent: ______________
References will be checked.
Sewer Project 1: ______________________________________Date Completed: ____________ Name and Address of Owner: ______________________________________________________ Contact Person: ________________________________Phone Number: ____________________ Length of Sewer Installed: ______________________LF Diameter: _________Inches Maximum Depth of Sewer Installed ______________ FT Trenchless Guided Boring Installed: ______________ LF Casing Diameter: _________Inches Additional Project Details: ________________________________________________________
Contact Person: ________________________________Phone Number: ____________________ Length of Sewer Installed: ______________________LF Diameter: _________Inches Maximum Depth of Sewer Installed ______________ FT Trenchless Guided Boring Installed: ______________ LF Casing Diameter: _________Inches Additional Project Details: ________________________________________________________
Sewer Project 3: ______________________________________Date Completed: ____________ Name and Address of Owner: ______________________________________________________ Contact Person: ________________________________Phone Number: ____________________ Length of Sewer Installed: ______________________LF Diameter: _________Inches Maximum Depth of Sewer Installed ______________ FT Trenchless Guided Boring Installed: ______________ LF Casing Diameter: _________Inches Additional Project Details: ________________________________________________________
Signature Title
| LOCATION |
| VARIOUS LOCATIONS IN RIVERTON AND HERRIMAN |
| SEPTEMBER 2026 |
File details come from the government source that posted it. Updated .