Feasibility Study Summary
This Feasibility Study document supports the Minneapolis-St. Paul International Airport's (MAC) Private Public Partnership (PPP) Cargo Facility Request for Proposals. The study evaluates the viability of designing, constructing, and operating a cargo facility at MSP International Airport through a public-private partnership model. The feasibility analysis examines market demand, operational requirements, financial projections, and implementation strategies necessary to support cargo operations expansion at the airport. The study provides the technical and market foundation for the RFP, establishing project parameters and identifying site locations, infrastructure needs, and potential facility configurations to accommodate increased cargo handling capacity.
The feasibility study analyzes financial requirements, revenue projections, and funding mechanisms for the proposed cargo facility development. It identifies demand drivers for cargo services at MSP, evaluates competitive positioning within the regional market, and assesses operational considerations including equipment, staffing, and throughput capacity. The document establishes the baseline conditions and economic justification for the partnership structure, providing prospective bidders with critical information regarding facility requirements, anticipated utilization rates, and the business case for private sector participation in the project's design, construction, and long-term ownership and operation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 4-Attachment 2 - Cargo Facility Lease Template.pdf | ||
| 3-Exhibit D- Proforma Operating Statement.docx | DOCX document | |
| 1-RFP Cargo Facility Final.pdf | ||
| 5-Exhibit E - Small Business Goal Worksheet.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHEET
COVER SHEET
AIR CARGO STUDY
Metropolitan Airports Commission
11/14/2025
P010
*AIRCRAFT ARE FOR ILLUSTRATION ONLY - SEE CIVIL
SECTION FOR RECOMMENDED AIRCRAFT LAYOUT
TABLE OF CONTENTS�
00 TABLE OF CONTENTS
01 INTRODUCTION
02 CIVIL NARRATIVE
recommended site plan
03 ARCHITECTURAL NARRATIVE
architectural drawings - phase
| 04 | MECHANICAL, ELECTRICAL, |
| & TECHNOLOGY NARRATIVE |
MAC2511 AIR CARGO STUDY
section title
01/19/2026MAC2511 AIR CARGO STUDY
INTRODUCTION
H W
Y 77
DHL
TAXIWAY L
WEST CARGO
APRON
1.0 Location
The Air Cargo Facility site is located on the western edge of the MAC Campus between Longfellow Avenue and Taxiway L immediately north of the West Cargo Apron. The site is approximately 21.5 acres and is currently used to store contractor vehicles as well as stockpiles of dirt, sand, and other debris.
The site is unpaved and generally undeveloped although most utilities are available on or near the site.
1.1 General Facility Information
The Air Cargo Facility will consist of two buildings that will be leased to tenants who perform Air Cargo transportation services as well as significant site / Civil development.
Phase 1 Development will include the following
a. An addition to the West Cargo Apron to accommodate a wider range of aircraft types for both Air Cargo tenants as well as “Remain Overnight” (RON) uses.
b. An Air Cargo building of approximately 112,350sf to serve two or three tenants.
c. Site development including but not limited to:
i. Allow inbound & outbound tractor-trailer access to the Phase 1 building
ii. Create approximately 152 parking stalls for tenant employees & customers
iii. Create storage & staging space for Phase 1 tenants including
| • | Container storage |
| • | GSE fleet vehicle parking |
| • | Tractor & trailer storage |
| • | Snow storage |
While the line separating Phase 1 and Phase 2 development has not yet been determined Phase 2 Development is anticipated to include the following:
d. An Air Cargo building of approximately 53,400sf to serve an undetermined quantity of tenants
e. Site Development including but not limited to:
i. Utilize inbound & outbound tractor-trailer access created in Phase
ii. Create approximately 145 parking stalls for tenant employees & customers
iii. Install a new snowmelt system on the northern portion of the site
iv. Create storage & staging space for Phase 2 tenants including
| • | Container Storage |
| • | GSE Fleet Vehicle Parking |
| • | Tractor & Trailer Storage |
| • | Snow Storage |
LO
N
G
FELLO
W
AVE
RUNW
AY 17-35
EAST 66th ST
CARGO RD
01/19/2026
1.2 Building Codes and Standards
Building Codes and Standards are based upon those adopted by the State of Minnesota and enforced by the MAC Building Official; applicable codes include but are not limited to the 2020 MN State Building Code and the 2024 MN State Energy Code.
The building will be Type II-B construction with an occupancy classification of B and S1. 1-hour fire ratings between Tenant areas are shown on the drawings.
1.3 Accessibility
Accessibility requirements are based on the Minnesota Building Code and the Americans with Disabilities Act (ADA) and will be fully incorporated into the project.
1.4 Sustainability
Precise sustainability targets and certifications have not be defined by the Owner. However,
a. Tubular Daylighting Devices and Translucent Sandwich Panels as shown on the drawings will enhance daylighting and decrease electrical lighting loads.
b. The roofs of Phase 1 and Phase 2 buildings have been designed to accommodate future installation of photovoltaic (PV) panels.
| i. | Phase 1 could accommodate up to 98,000sf of PV panels. |
| ii. | Phase 2 could accommodate up to 36,000sf of PV panels. |
iii. High Volume, Low Speed (HVLS) destratification fans in the
Warehouse spaces to increase human comfort.
iv. A Solar Air Preheating System (aka Solar Wall) to decrease the
HVAC system’s natural gas usage located on the:
| 1. South Facade of the Phase 1 building, and the |
| 2. East Facade of the Phase 2 building. |
The following items could be considered to further Owner’s sustainability goals:
| 3. | Increased exterior wall insulation by using a “6-4-3” panel |
| 4. | Accommodations for electric vehicle charging |
| 5. | Low carbon concrete mix design |
| a. | Precast panels |
| b. | Building floors, foundations and footings |
| c. | Site concrete |
| 6. | A stormwater retention system to offset graywater usage |
| 8. | A Battery Energy Storage System (BESS) to store electricity from the |
PV panels
1.5 Security Requirements
The Air Cargo Facility will be located at the border of Airside and Landside areas at MSP. Precise delineation of the AOA line will be determined with future development. At this time it can be assumed that the AOA line will be located at the following locations:
| 1. | Northwest and Northwest corner s of the Phase 1 building |
| 2. | Eastern and possibly Northern facades of the Phase 2 building. |
| 3. | New AOA fencing will be required at the following locations: |
a. Between Longfellow Avenue and the Northwest corner of the Phase 1 building.
b. Between the Northeast corner of the Phase 1 building and the existing AOA fence.
c. Between the Northeast corner of the Phase 2 building and the Northern site boundary.
It is currently assumed that overhead and passage doors on the South and East facades of the Phase 1 building and the Eastern and Northern facades of the Phase 2 building will require SIDA controls.
Furthermore, it is anticipated that federal regulations may require on-site screening at outbuildings which abut the AOA line. To accommodate this possibility an area for Screening has been included in the drawings.
INTRODUCTION
01/19/2026
2.1 Scope of Civil Work
The West Cargo site will be developed in two phases. The proposed Phase 1 civil work will extend the existing aircraft parking apron north, construct concrete pavement storage areas for GSE and air cargo containers, construct parking for employees and overflow semi-trailers, and support construction of a new 112,350 square foot Air Cargo building.
The proposed Phase 2 civil work will construct concrete pavement storage areas for GSE and air cargo containers, construct parking for employees and overflow semi-trailers, and support construction of a new 53,400 square foot Air Cargo building.
The study explored several aircraft parking configurations to ensure compliance with FAA Part 77 surfaces, maintain adequate wingtip to wingtip spacing, ensure adequate space for pushing aircraft out of their parking spaces, and consider impacts of jet exhaust velocities at break away taxi power. The aircraft initially considered for Phase 1 of the project were the Boeing 737-8W and Airbus A330-300 based on the aircraft fleet of the assumed primary tenant. With no addition to the parking apron and current aircraft parking on the south end of the apron, four to six aircraft parking spots are possible on the north side of the apron depending on the mix of aircraft.
The study developed the initial Phase 1 building and apron layout with the assumption that Phase 2 of the project would include a new building and construction of additional aircraft parking apron. The study eliminated the aircraft apron from Phase 2 due to:
1. FAA Part 77 surface constraints and site constraints limiting the aircraft size to B737 and B767. Aircraft movement was not practical and there were concerns with B767 exhaust velocities. Input from the MAC was that it was not economically practical to construct additional apron space for only B737s due to air cargo carriers utilizing larger aircraft and B767s phase-out of cargo use.
2. Constructing an aircraft apron would require siting of the Phase 2 building that would result in inefficient tractor-trailer circulation.
Elimination of the aircraft apron allowed the Phase 2 building to be positioned to allow greater flexibility in siting the Phase 1 building. Phase 1 will include an addition of approximately 175’ of apron pavement to the north end of the West Cargo apron to maximize future versatility of the site and maximize GSE and cargo container/cargo handling and storage.
Reconfiguration of the Phase 1 and Phase 2 sites allowed for improved tractor-trailer circulation and centralized employee parking.
The building locations will be located outside the airport Building Restriction Line and building heights will not penetrate Part 77 surfaces.
The site is undeveloped and will require site preparation to excavate and place new base and subbase material to support the new concrete and asphalt pavement. The site is currently used as a contractor storage and staging area.
There are approximately 25,000 cubic yards of concrete/asphalt/soil debris material in mounds that will need to be removed from the site during both phases of the work. This estimate is approximate as of August 2025. Volumes would need to be validated at time of bidding.
Opportunities to incorporate sustainable site elements could include bicycle storage, accommodation for low-emitting and fuel-efficient vehicles, and designating a portion of employee parking for car-share vehicles.
2.2 Scope of Civil Work
Work will include construction of 18-inch concrete pavement for aircraft parking, 12-inch concrete pavement for air cargo buildings apron, GSE and air cargo container storage, asphalt pavement for tenant and customer parking, overflow semi-trailer parking and general circulation.
Work will also include utilities, parking apron and employee/trailer parking lighting, communications, security fencing, and pavement marking. Utilities and communications are available on and adjacent to the site.
2.3 Phase 1 Development will include the following:
1. 17,000 square yards of 18-inch concrete pavement/base/subbase.
Parking apron work will include new lighting and pavement marking.
| 2. | 9,700 square yards of 12-inch concrete pavement/base/subbase. |
| 3. | 31,400 square yards of asphalt pavement/base/subbase. The |
pavement will support Phase 1 traffic and future Phase 2 traffic/ parking.
i. Existing entry to the site from Longfellow Ave. will be widened approximately 20ft to accommodate tractor-trailer entry and exit due to constrained turning radius.
ii. New acceleration lane will be constructed on Longfellow Ave to accommodate tractor-trailer traffic exiting to the north to mitigate limited sight line to vehicle traffic approaching from the south.
4. Underground utilities to support the Phase 1 Air Cargo building and site. Recommend relocating existing eighteen-inch water and six-inch natural gas utilities to avoid disrupting the Phase 1 site during Phase 2 construction. The proposed first phase requires a formal stormwater management review as it exceeds the one (1) acre new impervious surface threshold set by the MAC for new development.
To manage the resulting increased runoff volume and discharge rates, the project is required to include on-site detention to attenuate the peak flows before discharging into the far upstream end of the storm sewer network that feeds MSP Pond No. 1. This is necessary to comply with the Rate Control criteria, which mandates that the proposed activity shall not lead to an increase in existing runoff rates as measured at the discharge point to the Minnesota River.
5. Jet Blast Deflector – There is a concrete retaining wall with varying height (8’-10’) on the west side of the West Cargo apron adjacent to Longfellow Avenue. Current aircraft operations are primarily B737 and B767; exhaust velocities do not appear to have an impact on vehicle movement. If future use is expanded to include larger aircraft, recommend installing a jet blast deflector to mitigate higher exhaust velocity issues. Basis of design: Jet Blast Deflectors Inc, G20NB-4, will accommodate A330, 777F, up to 747-400F.
6. Tie new AOA fencing from Phase 1 building to existing AOA fencing.
2.4 Phase 2 Development will include the following:
| 1. | 8,500 square yards of 12-inch concrete pavement/base/subbase. |
| 2. | 18,600 square yards of asphalt pavement/base/subbase. |
| 3. | Underground utilities to support the Phase 2 Air Cargo building |
and site.
| 4. | Snowmelter – basis of design: Trecan 120-SG |
| 5. | 550 linear feet of AOA fencing and superposts to secure airside |
operations.
2.0 CIVIL NARRATIVE
01/19/2026
757-200PF
757-200PF
F
A300-600F
A300-600F
F
MD 11F
M D 11F
F
F
767-300 Freighter
767-300 Freighter
F
F
A319-100
A319-100
F
Fo
A320-200
A320-200
F
Fo
E170 STD
E170 STD
F
E175 STD
E175 STD
F
737-700W
737-700W
F
737-800W
737-800W
F
A321 NEO
A321 NEO
F
Fo
737-900W
737-900W
F
717-200
717-200
F
A220-100
A220-100
F
F
A220-300
A220-300
F
F
E175 EWT
E175 EWT
F
CRJ-900
CRJ-900
F
CRJ-700CRJ-700
F
A319-100
A319-100
F
Fo
A320-200
A320-200
F
Fo
E170 STD
E170 STD
F
E175 STD
E175 STD
F
737-700W
737-700W
F
737-800W
737-800W
F
A321 NEO
A321 NEO
F
Fo
737-900W
737-900W
F
717-200
717-200
F
A220-100
A220-100
F
F
A220-300
A220-300
F
F
E175 EWT
E175 EWT
F
CRJ-900
CRJ-900
F
CRJ-700CRJ-700
F 767-300 Freighter
767-300 Freighter
F
767-200ER767-200ER
F
737-800W
737-800W
737-900W
737-900W
737-700W
737-700W
767-300ERW
767-300ERW
F
767-300 Freighter
767-300 Freighter
F
F
767-200ER767-200ER
F
F
737-800W
737-800W
F
737-900W
737-900W
F
737-700W
737-700W
F
767-300ERW
767-300ERW
F
F
767-300 Freighter
767-300 Freighter
F
F
767-200ER767-200ER
F
F
737-800W
737-800W
F
737-900W
737-900W
F
737-700W
737-700W
F
767-300ERW
767-300ERW
F
F
Service R oad L
C ed ar A ve nu e / S ta te
H w y
R U
N W
AY 17-35
TAXIW
AY L
TWY L7
TWY L6
TW
Y
K6
TW
Y
Y
706'
180'
50'
80' 150'
A330-800
A330-800
F
A330-900
A330-900
F
747-400 Freighter
747-400 Freighter
F
F
A330-800
A330-800
F
A330-900
A330-900
F
747-400 Freighter
747-400 Freighter
F
F
A330-300
A330-300
F
777 Freighter 777 Freighter
F
F
777 Freighter 777 Freighter
F
F
A330-300
A330-300
F
A330-300
A330-300
F
767-300ERW
767-300ERW
F
F
767-300ERW
767-300ERW
F
F
767-300ERW
767-300ERW
F
F
737-800F-SSW
737-800F-SSW
F
737-800F-SSW
737-800F-SSW
F
737-800F-SSW
737-800F-SSW
F
737-800F-SSW
737-800F-SSW
F
737-800F-SSW
737-800F-SSW
F 737-8W A330-3
737-8W 737-8W
737-8W
777F 747-4F
A330-9 A330-8
737-8W A330-3 777F 747-4F
A330-9 A330-8
A330-3
24'
737-8W HEIGHT: 41.25'
836' + 41.25' ≈ 878'
777F HEIGHT: 62.33'
836' + 62.33' ≈ 899'
A330-3 HEIGHT: 55.08'
836' + 55.08' ≈ 892'
747-400F/800F HEIGHT: 64.17'
836' + 64.08' ≈ 900'
112,350sf
53,400sf
0'
A D
G V
177'
445'
120'
150'
150'
84'
PHASE 1 CARGO BUILDING
PHASE 1:
CONTAINER STORAGE
GSE VEHICLE PARKING
PHASE 2 EMPLOYEE
PARKING - 145 STALLS
(ADJUST # AS NEEDED)
PHASE 2:
CONTAINER STORAGE
GSE VEHICLE PARKING
PHASE 1 EMPLOYEE
PARKING - 152 STALLS
(ADJUST # AS NEEDED)
PHASE 1 ACCELERATION LANE
PHASE 1 AOA FENCE
(CONNECT TO EXISTING)
PHASE 2 CARGO BUILDING
PHASE 1 TRAILER STORAGE
PHASE 2:
TRAILER STORAGE
SNOW STORAGE & SNOWMELTER
PHASE 2 AOA FENCE
(CONNECT TO EXISTING)
JET BLAST DEFLECTOR
PHASE 2:
REMOVE EXISTING AOA FENCE
PHASE 1 AOA FENCE
(CONNECT TO EXISTING
RETAINING WALL)
PHASE 1:
REMOVE EXISTING AOA
FENCE SOUTH OF PH1
APPROXIMATE GROUND ELEV: 836'
WIDEN ENTRANCE
WEST CARGO
APRON
DRAWING NO.
PROJ. NO.
K :\M
A C
\2
\0
4_ P ro du ct io n\
_C A
D \0
3_ C on ce pt s\
_A ir_
C ar go _S tu dy
.d w g D
IR
C U
R R
E N
T:
N ov
6,
- 1 1:
am
AIR CARGO STUDY
EXH1MSP INTERNATIONAL AIRPORT
23097 MSP
GENERAL OFFICES
6040 - 28TH AVENUE SOUTH
MINNEAPOLIS, MINNESOTA 55450
Airports Metropolitan
Commission
NORTHSCALE IN FEET
0 60 120 240
NOVEMBER 6, 2025
LEGEND:
12" CONCRETE
18" CONCRETE
AOA FENCE
STANDARD FENCE
OPTION A: FEATURES
PHASE I
• 112,350sf BUILDING
• 37 TRAILER DOCKS
• UTILIZE EXIST WEST CARGO APRON
- NOMINAL ADDITION TO NORTH SIDE OF EXIST
• AIRCRAFT OPTIONS TBD
PHASE II
• 53,400sf BUILDING
• 29 TRAILER DOCKS
PARKING
• 152 STALLS (PHASE I)
• 145 STALLS (PHASE II)
SITE LAYOUT
2.5 CIVIL DRAWINGS
01/19/2026
MAC2511 AIR CARGO STUDY
MASKED AREAS:
PHASE 2 (NOT IN
CONTRACT)
GREEN HATCHED
AREA: WEST CARGO
APRON EXPANSION
(NOT IN CONTRACT)
GREEN HATCHED AREA:
ROADWAY AND CURB
IMPROVEMTS. (NOT IN
CONTRACT)
PHASE 1 TOTAL SITE
AREA:
APPROX. 472,000
SQUARE FEET
3.0 ARCHITECTRAL NARRATIVE
3.1 Building Exterior
The exterior walls will be 12” insulated precast concrete wall panels in a “6-3-3” configuration. A single concrete mix with three finish textures and decorative reveals is anticipated. Precast will generally begin at an elevation of 95.5’ and extend to an elevation of 125’. A cast-in-place concrete foundation wall with interior insulation from elevation 95.5’ to 100’ will be required at the truck docks on the outbound cargo elevations of Phase 1 and Phase 2 buildings.
Storefront glazing will be utilized at Tenant entry vestibules. Basis of design = Tubelite 400T Thermal Curtainwall, 2-1/2” x 6-1/4” deep framing.
Translucent sandwich panels will be installed above the inbound cargo sides of the Phase 1 (North Elevation) and Phase 2 (East Elevation) buildings as shown on drawings. Basis of design = Kalwall.
Galvanized metal landings and stairs will be installed at Tenant egress doors as shown on drawings.
Sectional overhead doors (OHD) will be used for both inbound and outbound cargo sides of the Phase 1 and Phase 2 buildings. Basis of design = Clopay model 3728 w/ high lift tracks, electrically powered with a manual option in case of a power outage, dimensions as shown on drawings. OHDs on the outbound cargo sides of Phase 1 and Phase 2 buildings shall also include a secondary track system on the interior to support ventilated OHDs. Basis of design = Rasco Industries, Inc.; Expanded Metal Door System Passage doors in exterior walls will be aluminum entry systems with opaque insulated aluminum panels.
The roof system will be a single-ply PVC membrane over rigid insulation and cover board. Roofing will be complemented by pre-finished metal copings and flashings at the top of the precast walls. A lightning protection system will be required. Roof access is provided via painted metal stairs (4’ tread width) with handrails and concrete treads; a landing is also required. The double-leaf roof hatch will include a telescoping post and an integrated guardrail with gate. Fall arrest anchors & cable system will also be provided as shown on the drawings. Tubular daylighting devices will be installed as shown on the drawings. Basis of design = Solatube SkyVault, 29” diameter.
Rooftop walk pads will also be required.
Trash & recycling enclosures sized for two (2), five-cubic-yard dumpsters per Tenant will be located as shown on the drawings. Enclosures will consist of 4” x 4” HSS posts with metal framing & louver panels as infill.
The outbound cargo sides of Phase 1 and Phase 2 buildings will include a nominal metal canopy above the OHDs as shown on the drawings.
Bollards will be required at locations shown on drawings.
3.2 Building Interior – Warehouse Spaces
Warehouse areas will be open to structure above. White paint will be installed on the interior faces of precast walls, exposed vertical and horizontal structure and the underside of the roof deck for lighting efficiency. Floors in warehouse areas will be troweled concrete; 8” thickness is anticipated.
Each OHD on the inbound cargo side will include a sloped area with floor drain as shown on the drawings.
Painted safety striping is anticipated to delineate vehicle and pedestrian areas within Warehouse Spaces.
High Volume, Low Speed (HVLS) fans will be installed as shown on the drawings to increase airflow and reduce stratification. Basis of design = Big Ass Fans.
Each Tenant warehouse will include provisions for a 12’x12’ (minimum) floor scale. Basis of design = Mettler Toledo LIFTMATE.
One Tenant warehouse space per building will include an area for refrigerated storage as shown on the drawings. Basis of design = Thermalrite Cooler, interlocking insulated wall & ceiling panels, insulated floor screed, sliding doors with vision ports and safety latches, self-contained refrigeration system unit, and temperature monitoring system (operating range of 32-40 degrees Fahrenheit).
The interiors of Phase 1 and Phase 2 buildings will require a fire suppression system in all areas.
High bay interior lighting will be required in Warehouse spaces.
Warehouse spaces shall be heated but not cooled.
3.3 Building Interior – Tenant Support Spaces
The interior walls and partitions of the facility will generally be painted CMU.
However, due to the temperature differences between the Warehouse and Support spaces, insulated precast walls may be required at the following interior locations
a. 1Phase 1 Building Option A1: full N/S extents of the walls at Grid G and the wall 8’ east of Grid H.
b. Phase 1 Building Option A2: full N/S extents of the walls at Grids F & G and the Northern half of the wall at Grid L.
Floors will generally be trowel finished concrete (assumed thickness = 6”) with fluid applied flooring (FAF) in Restrooms. Other finishes will focus on durability and the ease of cleaning and maintenance.
Ceilings in Tenant Support Spaces will be a 2’ x 2’ grid with lay-in light fixtures at 8’ or 9’ AFF.
Restrooms are shown on the drawings as the rooms that abut the MAC Plumbing Chase.
Tenant Support Spaces will be heated and cooled.
Other Tenant Support Space rooms are yet to be defined. At a minimum, each Tenant Support Space will include the following:
a. Reception Area adjacent to the Entry Vestibule
i) Built-in desk by project with separating glazing and pass-through countertop
b. Manager’s Office
i) Furniture by tenant
c. Shared Office (for additional staff)
i) Furniture by tenant
d. Breakroom
i) kitchenette-style
ii) sized for up to 60 employees
iii) sink, cabinets, countertops only – no large appliances, refrigerators by Tenant
e. Storage Closet
i) include mop sink
f. Data Closet
i) for Tenant servers only
g. Electrical Closet
i) for distribution panels & gear
3.4 Building Interior – MAC Core
The MAC Core will be accessed from Airside for both Phase 1 and Phase 2 buildings. Rooms shall be sized as shown on the drawings. It is assumed that MAC Core rooms will be constructed from 8” thick CMUs. CMU walls in the MAC Core will be unpainted except for locations where a Tenant space exists on the opposite side of the wall. Ceilings in MAC Core will be open to structure above.
3.5 Interior Openings
Interior doors will be Hollow Metal with painted Hollow Metal frames according to current MAC Standards. Sidelights or 4” wide vision glazing panels are assumed for rooms noted in 3.2.2, 3-6. unless noted otherwise.
3.6 Signage
The full range of interior and exterior signage for MAC projects should be assumed.
Exterior advertising signage shall be by tenants and NIC.
01/19/2026
A1
A2
A3
A4 A5
A7 A8
A9
A12
A12
A11
A15
A16A10
A17
A B C D E F G H I
A13A13
A25
A25
A14
A18
A14
A24
TYP @ ALL PERSON AND
OVERHEAD DOORS THIS FACADE
J ML
A24
K
A13
NOTE:
SEE KEYNOTE LEGEND
ON SHEET P101D
60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 46' - 0"
215' - 0"
43686 SF
Warehouse A
3873 SF
Suite A
2787 SF
Suite C
4949 SF
MAC Core
16003 SF
Warehouse C
30482 SF
Warehouse B
3838 SF
Suite B
4178 SF
REF STOR NIC
261 SF
MAC Core
2253 SF
SCREENING & CBP
A18
A27A28
OPTC Room Legend
MAC Core
REF STOR NIC
SCREENING & CBP
Suite A
Suite B
Suite C
Warehouse A
Warehouse B
Warehouse C
P300
P300
MECH
ROOF
ACCESS
ELEC
FIRETR
SEC. CORRIDOR
PLUMB
PLUMB
BREAK
ROOM
RR
RR RRRR
RR RR RR
WELLNESS
JAN/
STOR
DRIVER
VEST.RR
PLUMB
RR
PLUMB
VEST.
DRIVER
VEST.
OFFICE OFFICE
WELLNESS
DRIVER
VEST.RR
PLUMB
OFFICE
VEST.
LOBBY
RRRRRR
SECURITY
PLUMB
A24
SHEET
FLOOR PLAN LEVEL 1 - OPT A
AIR CARGO STUDY
Metropolitan Airports Commission
11/14/2025
P101A 1" = 50'-0"P101A
1 FLOOR PLAN - OPT A
SHEET
PLAN KEYNOTES
AIR CARGO STUDY
Metropolitan Airports Commission
11/14/2025
P101D
KEYNOTE LEGEND - ALL KEYNOTES
No. KEYNOTES
A1 INSULATED PRECAST WALL PANEL, SINGLE MIX DESIGN
WITH 3 FINISH TYPES, REVEALS TBD. TYP @ EXTERIOR WALLS.
A2 12" X 12" HSS COLUMN, DIMENSIONS TBD, INCLUDE
PROTECTIVE PIER TO 4' AFF AT EACH COLUMN BASE, TYP.
A3 HVLS FAN, TYP.
A4 STOREFRONT STYLE DOOR W/ OPAQUE INSULATED PANEL,
TYP AT EXTERIOR EGRESS DOORS.
A5 BOLLARDS AT AIRSIDE DOORS, TYP THIS ELEVATION, .
A6 10' W X 12' H INSULATED OHD, TYP THIS ELEVATION.
A7 METAL STAIR, TYP.
A8 BOLLARDS AT STAIRS, TYP.
A9 9'6" W X 12' H INSULATED OHD, TYP THIS ELEVATION.
A10 BOLLARDS AT DRIVE UP RAMP WALLS, TYP.
A11 ROOF ACCESS STAIR, TYP.
A12 12' X 12' IN-FLOOR SCALE, TYP.
A13 DOCK PAD / LEVELER AT EACH DOCK DOOR OHD THIS
ELEVATION, TYP.
A14 TRASH & RECYCLING ENCLOSURE: HSS AT CORNERS,
METAL LOUVER PANELS AS WALLS AND DOORS.
A15 INSULATED WALLS AND CEILING OF REFRIGERATED AREA
BY SUPPLIER. ASSUME ADDITIONAL UNDERSLAB
INSULATION BY GC, TYP.
A16 TRACTOR TRAILER BY TENANT, TYP.
A17 FLOOR DRAINS AT EACH OHD THIS ELEVATION, TYP
A18 HM DOORS AT INTERIOR LOCATIONS, TYP
A19 TUBULAR DAYLIGHTING DEVICE, TYP.
A20 SAFETY TIEBACK, TYP.
A21 SAFETY CABLE (BLUE), TYP.
A22 FULL HEIGHT ROOF ACCESS PENTHOUSE WITH INSULATED
WALLS, ROOF, AND PERSON DOOR.
A23 1 HR RATED WALL BETWEEN TENANTS, TYP
A24 SIDA DOOR
A25 AOA LINE
A26 SIDA CONTROLS AT ALL OHDS AND PASSAGE DOORS
(BOTH MAC AND TENANT) WHERE AOA LINE IS SHOWN
A27 8' HIGH X 8' WIDE HIGH SPEED INSULATED FABRIC DOOR
A28 10' WIDE X 24' LONG AREA SLOPED TO TRENCH DRAIN,
TYP
A29 SOLAR AIR HEATING SYSTEM
3.7 ARCHITECTRAL DRAWINGS - PHASE I
01/19/2026
CANOPY ROOF W/ RIGID TIE ROD SUPPORTS, TYP. ASSUME 1' THK X 3'
DEEP CANOPY W/ FORMED METAL PANEL FASCIA AT EXPOSED EDGES.
INCLUDE HEAT TRACED DOWNPOUTS AT ENDS, CENTER, AND EVERY 40-50'
FOR CANOPIES > 100' LONG
FULL HEIGHT ROOF
PENTHOUSE
SOLAR AIR HEATING SYSTEM, TYP
SHEET
EXTERIOR ELEVATIONS - OPT A
AIR CARGO STUDY
Metropolitan Airports Commission
11/14/2025
P200A
1" = 50'-0"P200A
1 NORTH ELEVATION - OPT A
1" = 50'-0"P200A
2 SOUTH ELEVATION - OPT A
1" = 50'-0"P200A
3 EAST ELEVATION - OPT A
1" = 50'-0"P200A
4 WEST ELEVATION - OPT A
3.7 ARCHITECTRAL DRAWINGS - PHASE I
01/19/2026
HATCH INDICATES
GROSS AREA
AVAILABLE FOR PV
ARRAY, +/-83,000sf
A B C D E F G H I J MLK
60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 60' - 0" 46' - 0"
A20A22A19
NOTE:
SEE KEYNOTE LEGEND
ON SHEET P101D
SHEET
ROOF PLAN - OPT A
AIR CARGO STUDY
Metropolitan Airports Commission
11/14/2025
P500A 1" = 50'-0"P500A
1 ROOF PLAN - OPT A
NOTE:
SEE KEYNOTE LEGEND ON PG. 7
3.7 ARCHITECTRAL DRAWINGS - PHASE I
01/19/2026
150' - 0"
WAREHOUSE A
A3
A29
A3
A19
TYP
NOTE:
SEE KEYNOTE LEGEND
ON SHEET P101D
180' - 0"
REF STOR PLUMB RR TENANT B OFFICE DRIVER
VEST.
A29
NOTE:
SEE KEYNOTE LEGEND
ON SHEET P101D
SHEET
BUILDING SECTIONS
AIR CARGO STUDY
Metropolitan Airports Commission
11/14/2025
P300
1/16" = 1'-0"P300 3 Section A
1/16" = 1'-0"P300 4 Section B
NOTE:
SEE KEYNOTE LEGEND ON PG. 7
NOTE:
SEE KEYNOTE LEGEND ON PG. 7
3.7 ARCHITECTRAL DRAWINGS - PHASE I
01/19/2026
DRAIN AT
EACH DOCK
DOOR, TYP
NOTE:
SEE CIVIL FOR
THICKNESS
ROOF ASSEMBLY
R1
ROOF ASSEMBLY NOTES:
REFER ALSO TO OTHER REQUIREMENTS AND INFORMATION CONTAINED ON THE ROOF PLANS & NOTES
ALL ROOF ASSEMBLIES TO BE MINIMUM R-VALUE: 30
R SERIES - ROOF ASSEMBLIES
SELF-ADHERING SHEET
VAPOR BARRIER
6" POLYISOCYANURATE
INSULATION
SINGLE-PLY
MEMBRANE ROOF
5/8" DENS DECK
COVER BOARD
5/8" SUBSTRATE BOARD
LH JOIST
3" METAL DECK
3/16" = 1'-0"P330
1 SECTION AT LANDSIDE DOCK DOORS
SHEET
WALL SECTIONS & DETAILS
AIR CARGO STUDY
Metropolitan Airports Commission
11/14/2025
P330 3" = 1'-0"P330
2 ROOF ASSEMBLY DETAIL
3.7 ARCHITECTRAL DRAWINGS - PHASE I
01/19/2026
4.0 MEP NARRATIVE
4.1 INTRODUCTION
1. Purpose
a. The purpose of this report is to describe the proposed building systems for planning, design, coordination, preliminary pricing, and Owner review.
b. The proposed design assumptions are outlined for Owner review and approval. These assumptions include, but are not limited to, external and internal temperature and humidity criteria, noise limits, occupancy, vibration criteria, future expansion needs, fire resistance, and lighting levels
c. Proposed building systems may evolve during the design phases. Any preliminary pricing must include cost contingencies appropriate to the current phase.
d. Refer to Architectural Design conceptual drawings, project program, and Owner’s design and construction standards for additional information.
2. Project Description
a. The project consists of the construction of two buildings to be utilized for air cargo transportation services that will be constructed in two phases. The first phase is for an approximately 126,000 SF building to house 3 tenants, each with warehouse and office suite spaces, a TSA space, and a MAC core area.
The second phase is for an approximately 52,200 SF building to house an undetermined number of tenants. Both buildings will be of insulated precast concrete panel construction with precast concrete spans covered by single-ply PVC insulation over rigid insulation. Store front glazing will be utilized at the vestibule entry, and the warehouse spaces will have large overhead doors on both sides for inbound and out bound cargo. This report covers Phase 1 proposed mechanical systems.
3. Sustainability and Energy Goals
a. The pursuance of a LEED Silver accreditation is being considered by the owner.
b. Solar Wall panels are to be utilized for the preheating of outdoor ventilation air to the air handling equipment. Refer to the HVAC Systems portion of this report for additional information.
c. A geothermal heating/cooling system was reviewed as a possible energy efficiency strategy. However, after reviewing HVAC systems scope against building space use it was determined that would not be a good application for this project. Refer to the HVAC Systems portion of this report for additional information.
4.2 ADOPTED CODES AND STANDARDS
1. Codes
| a. | Building Code–2020 Minnesota State Building Code |
| b. | Life Safety Code NFPA 101–2021 |
| c. | Electrical Code–National Electrical Code NFPA 70 2023 |
| d. | Mechanical and Fuel Gas Code–2020 Minnesota Mechanical |
Code
| e. | Plumbing Code–2020 Minnesota Plumbing Code |
| f. | Energy Conservation Code–ASHRAE 90.1 2024 Minnesota Energy |
Conservation Code
| g. | Fire Protection Code–2020 Minnesota Fire Code |
| h. | LEED V4.0 |
| i. | State Department of Labor Requirements |
| j. | State Department of Health Requirements |
| k. | State and Federal Safety and Health Laws |
| 2. | Owner Standards |
| a. | Metropolitan Airports Commission (MAC) Construction Standards. |
4.3 GENERAL BUILDING DESIGN CRITERIA AND ASSUMPTIONS
1. Summer Space Environmental Requirements: Warehouse: Ambient;
Suites: 75°F ± 2°F, 50%RH high limit.
2. Cooling Design Outdoor Air Conditions: 89°Fdb/73°Fwb. (Based on ASHRAE [1%] DB/MCWB for Minneapolis, Minnesota)
3. Winter Space Environmental Requirements: Warehouse: 68°F ± 2°F;
Suites: 72°F ± 2°F, no humidity control.
4. Zone Heating Design Outdoor Air Conditions: -15°F based on ASHRAE 99.6% Heating DB.
5. Occupancy: Refer to Architectural Narrative.
6. Typical Hours of Operation: 24 hours/day, 7 days/week.
7. Envelope Assumptions: Refer to Architectural Narrative.
4.4 PROPOSED MECHANICAL SYSTEMS
1. General HVAC System Description
a. Tenant warehouse spaces will be provided with ventilation by rooftop air handling equipment with natural gas fired heat, energy recovery wheels, and MERV 11 air filtration. No space cooling will be provided. Hydronic unit heaters will supplement space heat in addition to addressing infiltration from overhead doors.
Relief air will be provided by the energy recovery component of the air handling unit. A Solar Wall system will be utilized for pre-heating of outdoor air during the heating season and outdoor air ductwork will be extended from the Solar Wall duct collars to the outdoor air intakes at the rooftop air handling units. Large prop fans will be provided for air temperature destratification.
b. Tenant suite spaces and the TSA space will be provided with HVAC by rooftop air handling units with outdoor air ventilation, hydronic heating coils, DX cooling, and MERV 11 air filters.
Ductwork will be extended from the air handling units to variable air volume (VAV) boxes with hydronic heating coils and then to supply air diffusers. Exhaust air fans will service toilet room and janitor closets. Electric cabinet unit heaters will be provided in entry vestibules.
c. The MAC Core space will be served by a rooftop air-handing unit with outdoor air ventilation, hydronic heat and MERV 11 air filtration, but no cooling.
d. The MAC Core space will also contain the building hydronic heating boilers, pumps, and hydronic specialties. The energy used by the tenants will be tracked by dedicated energy (BTU) meters installed on the hydronic lines that extend to the tenant spaces. A building control and energy management system will be provided in accordance with MAC Standards and integrated into the MAC IMACS control system.
e. Solar Wall panels are proposed for installation on this building.
The panels are a propriety product that consists of a custom metal panel assembly with an interior void space and perforations on the exposed front surface that allow for outdoor ventilation air to be drawn in to the panel where it is pre-heated prior to discharging into the outdoor air intake section of air handling units. A means of bypassing the panels is provided for outdoor air provisions outside of the heating season. The panels are marketed as providing for a significant reduction in heating energy use during periods of daytime solar light radiation accessibility in the winter season.
f. The possibility of integrating a geothermal system component into the building HVAC systems was investigated as part of this report study. However, due to the imbalance between the high heating demand and the low cooling demand of the building it was determined that this building was not a good candidate for a geothermal application. This extends behind the concern of the potential for the well field to become irreparably imbalanced, which could be addressed by a Darcy type geothermal well, to include concerns of heat pumps sized for the heating load that will have a cooling fluid flow too low for the resultant compressors.
Utilizing several smaller heat pumps was found to not be either cost or space efficient. Also, due to the increasing demand for Darcy geothermal systems the lead times and costs of the systems have risen dramatically.
01/19/2026
2. Heating, Ventilating, and Air Conditioning (HVAC) System Components (Preliminary)
a. Tenant A Space
i) Warehouse Rooftop Air Handling Unit
• The rooftop air handling unit will include a plenum supply air fan with a VFD, a fully modulating indirect fired natural gas burner, energy recovery wheel with face and bypass dampers, MERV 11 filter section, economizer section with outdoor air intake and exhaust air dampers, a return/exhaust air fan with a VFD, and an outdoor air intake hood. No cooling will be provided. Preliminary HVAC equipment sizing is below.
• Supply Airflow Fan: 14,300 CFM at 4.0 - inches S.P., Outdoor Airflow: 4000 CFM, 15 HP, 480V/ 3 Ph/ 60 Hz.
• Return/Exhaust Fan: 14,300 CFM at 2.5-inches S.P., 7.5 HP, 480V/ 3 Ph/ 60 Hz.
• Heating: 387 MBH
ii) Warehouse Hydronic Unit Heaters
| • | Space Heaters: 3 at 530 MBH Each |
| • | North O.H. Door Heaters: 5 at 135 MBH Each |
| • | South O.H. Door Heaters: 5 at 45 MBH Each |
iii) Suite Rooftop Air Handling Unit
• Rooftop air handling unit will include a plenum supply air fan with a VFD, DX cooling coil and condensing section, a hydronic heating coil, MERV 11 filter section, economizer section with outdoor air intake and exhaust air dampers, and an outdoor air intake hood.
• Supply Air Fan: 4100 CFM at 3.2-inches S.P., 410 CFM OA, 3 HP, 480V/ 3 Ph/ 60 Hz.
| • | Heating: 200 MBH |
| • | Cooling: 10 Tons |
| • | Suite VAV Boxes |
| • | Three boxes for zoning control. |
| • | Suite Exhaust Fan |
| • | Power roof ventilator type. |
| • | Entry Vestibule Cabinet Unit Heater |
| • | Recessed wall mount type, 3 KW. |
b. Tenant B Space
i) Warehouse Rooftop Air Handling Unit
• The rooftop air handling unit will include a plenum supply air fan with a VFD, a fully modulating indirect fired natural gas burner, energy recovery wheel with face and bypass dampers,
4.0 MEP NARRATIVE
MERV 11 filter section, economizer section with outdoor air intake and exhaust air dampers, a return/exhaust air fan with a VFD, and an outdoor air intake hood. No cooling will be provided. Preliminary HVAC equipment sizing is below.
• Supply Airflow Fan: 10,000 CFM at 4.0 - inches S.P., Outdoor Airflow: 2810 CFM, 10 HP, 480V/ 3 Ph/ 60 Hz.
• Return/Exhaust Fan: 10,000 CFM at 2.5-inches S.P., 5 HP, 480V/ 3 Ph/ 60 Hz.
• Heating: 270 MBH
ii) Warehouse Hydronic Unit Heaters
| • | Space Heaters: 3 at 370 MBH Each |
| • | North O.H. Door Heaters: 3 at 135 MBH Each |
| • | South O.H. Door Heaters: 3 at 45 MBH Each |
iii) Suite Rooftop Air Handling Unit
• The rooftop air handling unit will include a plenum supply air fan with a VFD, DX cooling coil and condensing section, a hydronic heating coil, MERV 11 filter section, economizer section with outdoor air intake and exhaust air dampers, and an outdoor air intake hood.
• Supply Air Fan: 4100 CFM at 3.2-inches S.P., 340 CFM OA, 3 HP, 480V/ 3 Ph/ 60 Hz.
| • | Heating: 200 MBH |
| • | Cooling: 10 Tons |
iv) Suite VAV Boxes
• Three boxes for zoning control.
v) Suite Exhaust Fan
• Power roof ventilator type.
vi) Entry Vestibule Cabinet Unit Heater
• Recessed wall mount type, 3 KW.
c. Tenant C Space
i) Warehouse Rooftop Air Handling Unit
• Rooftop air handling unit will include a plenum supply air fan with a VFD, a fully modulating indirect fired natural gas burner, energy recovery wheel with face and bypass dampers, MERV 11 filter section, economizer section with outdoor air intake and exhaust air dampers, a return/exhaust air fan with a VFD, and an outdoor air intake hood. No cooling will be provided.
Preliminary HVAC equipment sizing is below.
• Supply Airflow Fan: 5300 CFM at 4.0 - inches S.P., Outdoor Airflow: 1470 CFM, 7.5 HP, 480V/ 3 Ph/ 60 Hz.
• Return/Exhaust Fan: 5300 CFM at 2.5-inches S.P., 2.5 HP, 480V/ 3 Ph/ 60 Hz.
• Heating: 143 MBH
ii) Warehouse Hydronic Unit Heaters
| • | Space Heaters: 3 at 195 MBH Each |
| • | North O.H. Door Heaters: 2 at 135 MBH Each |
| • | South O.H. Door Heaters: 2 at 45 MBH Each |
iii) Suite Rooftop Air Handling Unit
• The rooftop air handling unit will include a plenum supply air fan with a VFD, DX cooling coil and condensing section, a hydronic heating coil, MERV 11 filter section, economizer section with outdoor air intake and exhaust air dampers, and an outdoor air intake hood.
• Supply Air Fan: 3000 CFM at 3.2-inches S.P., 310 CFM OA, 3 HP, 480V/ 3 Ph/ 60 Hz.
| • | Heating: 142 MBH |
| • | Cooling: 7.5 Tons |
iv) Suite VAV Boxes
• Three boxes for zoning control.
v) Suite Exhaust Fan
• Power roof ventilator type.
vi) Entry Vestibule Cabinet Unit Heater
• Recessed wall mount type, 3 KW.
d. Screening
i) Rooftop Air Handling Unit
• The rooftop air handling unit will include a plenum supply air fan with a VFD, DX cooling coil and condensing section, a hydronic heating coil, MERV 11 filter section, economizer section with outdoor air intake and exhaust air dampers, and an outdoor air intake hood.
• Supply Air Fan: 2400 CFM at 2.5-inches S.P., 1220 CFM OA, 2 HP, 480V/ 3 Ph/ 60 Hz.
| • | Heating: 192 MBH |
| • | Cooling: 6 Tons |
ii) VAV Boxes
• Three boxes for zoning control.
iii) Exhaust Fan
• Power roof ventilator type.
iv) Entry Vestibule Cabinet Unit Heater
• Recessed wall mount type, 5 KW.
01/19/2026
e. MAC Core
i) Rooftop Air Handling Unit
• The rooftop air handling unit will include a plenum supply air fan with a VFD, a hydronic heating coil, MERV 11 filter section, economizer section with outdoor air intake and exhaust air dampers, and an outdoor air intake hood.
• Supply Air Fan: 5200 CFM at 2.7-inches S.P., 400 CFM OA, 3 HP, 480V/ 3 Ph/ 60 Hz.
• Heating: 174 MBH
ii) Building Heating Boilers
• High efficiency type condensing gas fired boilers. Three (3) boilers at 2000 MBH each.
iii) Hydronic Heating Pumps
• Floor mounted close coupled centrifugal pumps, two (2) pumps sized for 435 GPM at 75 FT. HD, 15 HP each.
iv) Hydronic Specialties
• Air separator, diaphragm expansion tank, chemical pot filler, 35% propylene glycol media.
f. Hydronic Piping
i) Hydronic piping will be insulated type L hard copper pipe with soldered wrought copper fittings to size 2 ½” and insulated Schedule 40 black steel pipe with welded or flanged malleable iron fittings for pipe 3” size and above.
3. General Plumbing Description
i) Domestic water service will be 2 ½-inch size and will enter the MAC Core mechanical room from the south. Sanitary will be 6-inch size and will exit the building to the south. Storm will be a 15-inch line exiting the building to the north.
4. Plumbing Systems
a. Domestic Water System
i) Domestic water service will enter the Mechanical Room in MAC Core area. Separate house & individual tenant water meters will be provided in accordance with MAC Standards. Domestic water piping will be insulated Type L hard copper pipe with soldered wrought copper fittings. Valves will be of the standard port ball type.
b. Sanitary System
i) Sanitary piping will be standard weight cast iron hub pipe below grade & cast-iron no-hub pipe with stainless steel band clamps above grade per MAC Standards.
c. Stormwater System
i) Storm piping will be standard weight cast iron hub pipe below grade & cast-iron no-hub pipe with stainless steel band clamps above grade per MAC Standards.
d. Domestic Water Heaters
i) Separate house and individual tenant domestic water heaters will be provided. The water heaters will be of the storage tank electric coil type.
e. Plumbing Fixtures
i) Plumbing fixtures will be of the commercial grade water saving type.
f. Natural Gas Piping System
i) Gas meter and regulator assembly will be located on exterior of building outside the MAC Core area with the gas main extending to the roof to serve the warehouse rooftop air handling units.
Natural gas pipe will be Schedule 40 steel pipe with welded malleable iron fittings and ball type isolation valves.
g. Tenant Supplied Systems
i) Compressed air systems and other tenant utilized process systems will be provided by the tenant.
5. Fire Protection Systems
a. General Fire Suppression Systems Description
i) A fire suppression sprinkler system will be provided for building.
A 6-inch fire sprinkler water service will enter the mechanical space at the MAC Core area. The service valving and riser assembly will be located in a dedicated water/ fire sprinkler service room with the house and each tenant being provided with a separate sprinkler zone. Warehouse Areas will be provided with dry pipe sprinkler systems due to the potential for freezing from the extended time periods that the overhead doors will be open.
Refrigerated storage rooms will also have dry type systems. A means of addressing fire suppression for the proposed roof PV array may need to be considered based on potential future code changes due to pending NFPA Standards recommendations.
b. Design Criteria.
i) Warehouse Areas: Ordinary Hazard Group 2 Occupancy, Miscellaneous low piled storage classification.
ii) Suite Areas and TSA: Light Hazard Occupancy
iii) MAC Core Spaces: Ordinary Hazard Group 2 Occupancy
c. Fire Department Connection
i) Storz Connection, 5-inch size with 4-inch check valve with ball drip.
d. Piping Materials
i) Wet piping 2” and smaller will be Schedule 40 black steel with screwed or flanged joints.
ii) Wet piping 2-1/2” and over will be Schedule 10 black steel with mechanically roll-grooved joints.
iii) Dry piping will be Schedule 40 galvanized steel with screwed or flanged joints 2” and smaller, and screwed, flanged, or mechanically coupled grooved joints 2-1/2” and larger.
e. Sprinkler Types
i) Warehouse Areas: Brass upright type sprinkler heads.
ii) Suite Areas with finish ceilings: Chrome pendent type sprinkler heads.
iii) Suite Areas without Finished Ceilings: Brass upright type sprinkler heads.
iv) MAC Core Areas: Brass upright type sprinkler heads. Higher temperature type in boiler room and similar spaces.
01/19/2026
Project Study MEP Narrative IMEG No.25005382.00 MAC Air Cargo Page 10 of 19
Luminaire Type Description Basis of Design Manufacturer / Series Manufacturer
Recessed Volumetric Luminaire
Direct with high angle illuminance, one-piece steel reflector assembly housing, acrylic prismatic diffuser, single lamp chamber
Cooper Metalux CRUZE Acuity Lithonia BLT
Recessed Down Light
Open downlight, galvanized stamped steel housing, reflector finish, flange finish, damp listed wet shower listed
Signify Lightolier Calculite Acuity Gotham Current Prescolite Liteistry Cooper Halo
Industrial Enclosed frosted lens and gasketed industrial with molded in place gasket, fiberglass housing, stainless steel latches
Cooper Metalux Acuity Lithonia Elite Oracle H.E. Williams Signify Daybrite
Exit Sign Emergency exit sign, white thermoplastic body, red or green letters, universal arrows/mounting.
Acuity Lithonia Cooper Surelites
Site Pole
Site luminaire, aluminum extruded housing, gasketed, distribution type to be determined, listed wet location IP65 rated Pole: Square straight aluminum pole with internal vibration damper, anchor
Beacon Viper Area VP1 Series Concrete base
3. Power System Requirements
a. Utility Service
1) The utility company will provide medium voltage transformers, and primary conductors.
2) Site Utility Raceways: Conduit within the limits of construction will be PVC, Schedule 80, reinforced, concrete encased and will be a minimum 5”. Conduit routing requirements will be based on direction from Civil Engineer. Manholes will be provided for all conduit runs in excess of 500’ and where required by the utility company. 100% spare capacity will be provided for all conduits.
3) Transformer Secondary Service Feeder: Extended from the new pad-mounted transformer to the new utility connection cabinet to the new service-rated distribution equipment. Underground conduit raceway will be installed in a steel rebar reinforced concrete encased duct bank with tracer wire.
4) Utility Metering: Utility metering will be installed in the new utility connection cabinet in accordance with utility company requirements.
b. Service Entrance Distribution The service entrance distribution panel will be rated at 480/277 volt, 1200 amp, 3-phase, 4-wire with a main circuit breaker. The distribution panel will use fixed-mounted power circuit breakers with a microprocessor-based breaker tripping system and electric metering capability. Spare spaces will be provided
Project Study MEP Narrative IMEG No.25005382.00 MAC Air Cargo Page 9 of 19
1) Additional mandatory controls for lighting that includes manual switching/dimming, automatic controls to reduce lighting levels, and daylight responsive controls will be installed.
2) Lighting Control System Basis of Design
a) Custom lighting control relay panel furnished by Division 26 contractor and installed by Division 26 contractor. System shall be monitored by
IMACS
3) The energy code compliant lighting control system will include a combination of standalone controls, room-based control, network-based controls. Refer to the Lighting and Lighting Control System - Space Description Table. The following system components will be included:
a) Wall Mounted: Switches, dimmers, scene selection control stations, manual override stations.
b) PIR, Ultrasonic, and Combination Sensors: Occupancy and vacancy based.
(1) Where allowed, a vacancy sensor that controls lighting with a dimmable driver will come on automatically to 50% and manually to 100%.
c) Time Clock: Astronomical.
d) Photocell.
e) Central Programming and Scheduling: 5/7 day, holiday, special event.
f) Communication / Protocol: Combination of line voltage, low-voltage.
Lighting and Lighting Control System - Space Description Table
Space Description Luminaires Lighting Controls Illuminance Levels
COMMON ADMINISTRATION SPACES
Utility, Janitorial, Storage
Suspended industrial luminaires for non-finished ceiling spaces Occupancy sensor 10 to 15 foot-candles
Mechanical, Electrical
Suspended industrial luminaires for non-finished ceiling spaces Recessed acrylic lens luminaires for spaces with finished ceilings
Wall switch With a minimum of one battery-powered source in electrical rooms and mechanical rooms
30 foot-candles
Restrooms Down lights Occupancy sensor with local wall switch override
10 to 20 foot-candles
Warehouse Areas Suspended high-bay luminaire Manual wall switch 65 to 75 foot-candles
Breakroom/lockers 2’x4’ or 2’x2’ dimmable volumetric type luminaires
Occupancy Vacancy sensors with wall-mounted controller Receptacle control
30 foot-candles
Exterior Lighting Building-mounted luminaires Occupancy Vacancy sensors with wall-mounted multi-level switching 0.5 to 1 foot-candle
4.5 ELECTRICAL DESIGN REQUIREMENTS
1. Overview:
a. The electrical design for this project will include the components of lighting systems and controls, power distribution, fire alarm and automatic detection.
b. Refer to the Technology Design Requirements for a description of the remaining electrical-based low voltage system requirements.
2. Lighting Systems and Controls
a. Lighting System Design Criteria
i) Lighting basis of design per the maintained illumination targets published by the Illumination Engineering Society (IES), applicable local municipal lighting ordinance, and Owner standards. Refer to average maintained illuminance level criteria in the table below.
ii) Correlated Color Temperature (CCT)
| • | Interior Luminaires: 4000 °K |
| • | Exterior Luminaires: 4000 °K |
iii) Color Rendering Index (CRI)
| • | Interior Luminaires: 80 |
| • | Exterior Luminaires: 80 |
iv) Interior Luminaires
• Specification-grade LED source luminaries with switched or dimmable drivers, minimum 50,000 hour rated life.
• Luminaires recessed in the thermal envelope will be IC rated
& airtight.
• Special Application Listings: Listed wet, damp, or ingress protection IP65 rated.
v) Exterior Luminaires
• Specification-grade LED-based light source luminaries with dimmed drivers, minimum 50,000 100,000-hour rated life.
• LED drivers, low temperature, reliable start at -20°F (-29°C) ambient, reliable operation without derating at 122°F (50°C) 140°F (60°C).
• Listed wet, damp, or ingress protection IP65 rated.
vi) Egress and Emergency Egress Lighting Design Basis
• Egress (non-emergency) lighting will be provided for all corridors, stairways, and egress paths defined by the Architect.
• Emergency egress lighting will be served from integral emergency battery or dedicated battery-powered wall/ ceiling-mounted luminaries with self-diagnostics and testing.
• Exterior Entrance / Discharge: Provide with a minimum of two LED sources & drivers for normal and emergency egress code compliance.
01/19/2026
• Exit Signage
Specification grade LED type, edge lit served from integral emergency battery with self-diagnostics and testing.
Ceiling / wall mounted for all applicable egress paths, exterior exits, assembly spaces, and code-required spaces.
b. Lighting Control System Criteria
i) Additional mandatory controls for lighting that includes manual switching/dimming, automatic controls to reduce lighting levels, and daylight responsive controls will be installed.
ii) Lighting Control System Basis of Design
• Custom lighting control relay panel furnished by Division 26…