Clarifications asked per company on 6.docx
DOCX document 13 KB Posted
- Attached to
- Replace FCI Rear Gate
- Solicitation number
- 15B41820QV9B30001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 15B41820QV9B30001Modification1.pdf | ||
| INSTRUCTION TO OFFERORS USE THIS.doc | DOC document | |
| 15B41820QV9B30001Revised.pdf | ||
| BEST_VALUE_EVALUATION_FACTORS_FOR_AWARD.docx | DOCX document | |
| REVISEDRFQFENCE.pdf | ||
| INSTRUCTION TO OFFERORS USE THIS.doc | DOC document | |
| INSTRUCTION TO OFFERORS USE THIS.doc | DOC document | |
| BEST_VALUE_EVALUATION_FACTORS_FOR_AWARD.docx | DOCX document | |
| NCIC (BP_660_18).pdf | ||
| Past_performance_Evaluation_Questionnaire_electrical.docx | DOCX document | |
| RFQReplaceFCIrearGate.pdf | ||
| Statement of work.pdf | ||
| 2 Example Instructions to Offerors_revised.doc | DOC document | |
| Wage Determination.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Clarifications asked per company on 6/3/2020 and posted 2020
QUESTION
· Is a bid bond required? A bid bond is not required for 150,000 and under but is required for 150,000 and over per FAR 28.102-1
ANSWER
Our magnitude selected for this project is between 100,000 and 250,000.
QUESTION
· The performance period of 61 days is shorter than the lead time for the materials, can this be extended or the NTP delayed until delivery dates for materials are determined?
ANSWER
This performance period was developed for actual days work crew would be on site. However due to lead times with coronavirus we have modified the RFQ to 180 days total for lead times and total project completion.