01_51_00_Temporary_Utilities_R1_0001.pdf

PDF 121 KB Posted

Attached to
FLORIDA DITCH AND CANAL LINING Federal contract opportunity
Solicitation number
140R4021R0007
Issued by
Department of the Interior Bureau of Reclamation

About this file

This document contains specifications for temporary utilities requirements for the Florida Ditch and Canal Lining Phase 2, Part 1 project. The contractor shall provide temporary electricity, water, and sanitary facilities for construction purposes. For temporary electricity, the contractor must provide generators and distribution equipment in compliance with National Electrical Safety Code clearances. A reservoir will be designated for the contractor to pump water from for construction uses, including concrete, controlled low-strength material and shotcrete, and the contractor must convey the water to points of use. Upon completion of work, the contractor shall remove all temporary equipment and facilities. The related federal contract opportunity is solicitation number 140R4021R0007 from the Department of the Interior Bureau of Reclamation for the Florida Ditch and Canal Lining project.

View the file

Other files for this federal contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Consolidated Ditch Company Florida Ditch and Canal Lining Phase 2, Part 1

Temporary Utilities

01 51 00 - 1

SECTION 01 51 00

TEMPORARY UTILITIES

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Institute of Electrical and Electronics Engineers (IEEE)

1. IEEE C2-12 National Electrical Safety Code (NESC)

1.03 TEMPORARY ELECTRICITY

A. Provide electric power required for construction.

B. Provide generators, transmission lines, distribution circuits, transformers, and other electrical equipment and facilities required for obtaining power and distributing power to points of use.

C. Comply with IEEE C2 clearances and spacing for temporary communications and supply lines.

1.04 TEMPORARY WATER

A. The contractor will be allowed to use water from Pastorius Reservoir for construction purposes. COR will designate the location for pumping at time of construction.

B. Contractor shall provide water which meets specified requirements for water used in concrete, CLSM and shotcrete, C. Provide means of pumping and conveying all water for construction to points of use.

1.05 SANITARY FACILITIES

A. Contractor shall provide sanitary facilities.

PART 2 PRODUCTS

Not Used

Florida Consolidated Ditch Company Florida Ditch and Canal Lining Phase 2, Part 1

Temporary Utilities

01 51 00 - 2

PART 3 EXECUTION

3.01 REMOVAL

A. Remove temporary equipment and facilities upon completion of work under this contract.

END OF SECTION