140R4021R0004 NIIP PFC Blk 4 Solicitation_final.pdf

PDF 868 KB Posted

Attached to
NIIP Power Factor Corrections, Block 4 Federal contract opportunity
Solicitation number
140R4021R0004
Issued by
Department of the Interior Bureau of Reclamation

About this file

This solicitation requests proposals for power factor correction capacitor installation and related construction work at Block 4 of the Navajo Indian Irrigation Project in Farmington, New Mexico. Key requirements include furnishing and installing capacitors, insulated conductors, and terminal blocks at 11 pumping plant sites, as well as constructing concrete pads and modifying some enclosure walls. Proposals are due by February 19, 2021. Pricing is on a firm-fixed-price basis for line items such as mobilization, drawings, materials, and capacitors. The period of performance is from March 1, 2021 to February 11, 2022. The soliciting agency is the Bureau of Reclamation within the Department of the Interior.

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

POWER FACTOR CORRECTIONS

BLOCK 4

NAVAJO INDIAN IRRIGATION PROJECT

FARMINGTON NM

SOLICITATION NO. 140R4021R0004

UNITED STATES DEPARTMENT OF THE INTERIOR

BUREAU OF RECLAMATION

UPPER COLORADO REGION

FOUR CORNERS CONSTRUCTION OFFICE

FARMINGTON NM

ALL OFFERS MUST BE CLEARLY IDENTIFIED AS

“REQUEST FOR PROPOSAL”

TO PRECLUDE MISHANDLING

Offers must be submitted by mail or electronic transmission (email) to:

psinger@usbr.gov

BUREAU OF RECLAMATION

ATTN: PHILOMA SINGER, FCCO-170

1235 LA PLATA HIGHWAY

FARMINGTON NM 87401

PRIOR TO SOLICITATION CLOSING DATE AND TIME

February 19, 2021 by 12 pm (MST)

Inquiries regarding this solicitation should be made to the office listed below:

Philoma Singer, Contract Specialist Email: psinger@usbr.gov Farmington, New Mexico ............................................................................... 505-324-5033

CONTENTS

SECTION A – SF-1442

SECTION B - CONTINUATION OF SECTION B-SUPPLIES OR SERVICES AND PRICE

SECTION C – STATEMENT/DESCRIPTION/SPECIFICATION OF WORK

SECTION D – PACKAGING AND MARKING

SECTION E – INSPECTION AND ACCEPTANCE

SECTION F – DELIVERIES OR PERFORMANCE

SECTION G – CONTRACT ADMINISTRATION DATA

SECTION H – SPECIAL CONTRACT REQUIREMENTS

SECTION I – CONTRACT CLAUSES

SECTION J – LIST OF ATTACHMENTS AND EXHIBITS

SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS…... 33

SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS OR RESPONDENTS…

SECTION M – EVALUATION FACTORS FOR AWARD

SECTION A – SF-1442

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040392944

Bureau of Reclamation

Upper Colorado Region

Regional Office 125 South State Street, Room 8100

R40

Salt Lake City UT 84138

Philoma Singer 505-324-5033

1x 01/06/2021

140R4021R0004

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

The U.S. Bureau of Reclamation, Upper Colorado Region, Four Corners Construction

Office (FCCO), New Mexico has a need to have fused power factor correction capacitors furnished and installed on 11 pumping plants at Block 4 of the

Navajo Indian Irrigation Project (NIIP). This requires some construction to establish foundations and alterations to enclosure walls.

Principal Components of Work:

Provide and install power factor correction capacitors along with insulated power conductors, terminal connectors, power terminal blocks and other materials required to connect the power factor correction capacitors to the motor controllers at pumping plants. Construct concrete pads for mounting power factor correction capacitors on the outside wall at pumping plants. Some of the pumping plants will require alteration to the enclosure walls.

Per the Reclamation Acquisition Regulation (RAR) - WBR 1436.204 - Disclosure of

Magnitude - the estimated magnitude of construction is: (d) Between $250,000 and

$500,000.

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 347 calendar days and complete it within ________________ ________________ calendar days after receiving

02/19/2021

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Bureau of Reclamation Upper Colorado Region

Regional Office 125 South State Street, Room 8100

R40

Salt Lake City UT 84138

Ashton Jones

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 49

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140R4021R0004

Work is located approximately 10 miles south of

Farmington, New Mexico, in San Juan County.

Please see Attachments 1,2,3,4 and 5 for

Specifications, Drawings, Wage Determination, Past Performance Questionnaire and Subcontracting

Percentage Sheet.

Legacy Doc #: BOR

Period of Performance: 03/01/2021 to 02/11/2022

00010 DESCRIPTION: NIIP Power Factor Corrections, Block 4

Firm-Fixed Price (FFP)

Quantity: 1 AU

Unit of measure: AU (Activity Unit)

Product/Service Code: N059

Product/Service Description: INSTALLATION OF

EQUIPMENT- ELECTRICAL AND ELECTRONIC EQUIPMENT

COMPONENTS

See continuing pages.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation No.:140R4021R0004 Power Factor Corrections – Block 4 P a g e | 4

CONTINUATION OF

SECTION B – SCHEDULE OR SERVICES AND PRICE

B.1 SCHEDULE

(a) Offers will be considered for award on the following schedule, but no offer will be considered for award on only a part of the schedule.

(b)

(1) Offerors shall complete price schedule. Offers are subject to the terms and conditions of this solicitation.

(2) Offers will be evaluated using FAR Part 15.101-2 Lowest Price Technically Acceptable Source Selection Process.

(c) The quantities in the schedule are estimated quantities for comparison of offers only, and except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.

(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.

(e) Definitions:

(1) CLIN – Contract Line Item Number

PRICE SCHEDULE

CLIN Section Supplies or Services Quantity and Unit

Unit Price Amount

1 WBR

1452.232-

Mobilization and preparatory work

For the lump sum of $

2 01 31 30 Contract Document Management System

For the lump sum of $

3 01 33 26 Electrical Drawings and Data For the lump Sum of

4 03 30 00 Cast-In-Place Concrete 7 slabs @ .722 cubic yard (yd3) each

5 26 05 02 Basic Electrical Materials and Methods

For the lump sum of $

P a g e | 5

PRICE SCHEDULE

CLIN Section Supplies or Services Quantity and Unit

Unit Price Amount

6 26 35 33 Power Correction Factor Correction Capacitors

For the lump sum of $

TOTAL FOR PRICE SCHEDULE: $

END OF PRICE SCHEDULE

P a g e | 6

SECTION C – STATEMENT / DESCRIPTION / SPECIFICATION OF WORK

Please see Attachments in Section J.

1. Specifications

2. Drawings

3. Wage Determination

4. Past Performance Questionnaire

5. Subcontracting Percentage Sheet

P a g e | 7

SECTION D – PACKAGING AND MARKING

There are no clauses included in this section

P a g e | 8

SECTION E – INSPECTION AND ACCEPTANCE

E.1 52.246-12 INSPECTION OF CONSTRUCTION AUGUST 1996

(a) Definition - “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not –

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may –

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

P a g e | 9

SECTION F – DELIVERIES OR PERFORMANCE

F.1 52.211-10

ALT I

COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK

APRIL 1984

The Contractor shall be required to

(a) commence work under this contract within 10 calendar days calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use no later than February 11, 2022. The time stated for completion shall include final cleanup of the premises.

Alternate I (April 1984). The completion date is based on the assumption that the successful offeror will receive the notice to proceed November 1, 2021. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

F.2 52.211-18 VARIATION IN ESTIMATED QUANTITY APRIL 1984

If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.

F.3 52.242-14 SUSPENSION OF WORK APRIL 1984

(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer's failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly.

However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or

P a g e | 10 negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.

(c) A claim under this clause shall not be allowed--

(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and

(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.

Solicitation No.: 140R4021R0004 Power Factor Corrections – Block 4

SECTION G – CONTRACT ADMINISTRATION DATA

P a g e | 11

G.1 WBR

1452.201-70

AUTHORITIES AND DELEGATIONS SEPTEMBER 2011

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

G.2 WBR

1452.242-80

POSTAWARD CONFERENCE – BUREAU OF RECLAMATION JULY 1993

(a) Prior to the Contractor starting work, a Postaward conference (as described in FAR Subpart 42.5), will be convened by the contracting activity or contract administration office. The Contractor's Project Manager shall attend the conference. If the contract involves subcontractors, a representative of each major subcontractor is also required to attend.

(b) The conference will be held at a location to be determined in the vicinity of Farmington, New Mexico or by video/ teleconference.

P a g e | 12

(c) The Contracting Officer and the Contractor will agree to the date and time of the conference after award of the contract. In event of a conflict in schedules, the Contracting Officer shall establish the date for the conference.

(d) The Contractor shall include any associated costs for attendance at the conference in its offer.

G.3 DOI- AAAP-0028 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS –

INTERNET PAYMENT PLATFORM (IPP) APRIL 2013

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice

The Contractor shall also submit an electronic copy of their regular vendor invoice and an electronic copy of their IPP invoice to the Contract Specialist, Philoma Singer, at psinger@usbr.gov and the Contracting Officer, Ashton Jones, at ajones@usbr.gov once the IPP invoice has been submitted.

Failure to email the invoice may cause significant delay or possible rejection of your payment request.

The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email:

IPPCustomerSupport@fiscal.treasury.gov or by phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

G.4 WBR

1452.201-80

CONTRACTING OFFICER’S REPRESENTATIVE’S AUTHORITIES

AND LIMITATION – BUREAU OF RECLAMATION MAY 2018

(a) Performance of the work under this contract shall be subject to the technical direction of the Reclamation Contracting Officer's Representative (COR). The term “technical direction” is defined to include, without limitation:

(1) Inspecting and accepting or rejecting work performed under the contract.

(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the Contractor on all technical matters relating to the contract. The COR will supervise or oversee all Government technical and administrative personnel assigned to assist the COR.

(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.

https://www.ipp.gov/ https://www.ipp.gov/ mailto:theirIPPinvoicetotheContractSpecialist%2CPhilomaSinger%2Catpsinger@usbr.govandtheContracting mailto:Officer%2CAshtonJones%2Catajones@usbr.govoncetheIPPinvoicehasbeensubmitted mailto:IPPCustomerSupport@fiscal.treasury.gov

P a g e | 13

(b) The Contractor will receive a copy of the written COR designation from the Contracting Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting Officer.

(c) Technical direction must be within the scope of work stated in the contract. Only the Contracting Officer is authorized to determine if a change is within the scope of the contract; therefore, the COR does not have the authority to, and may not, issue any technical direction that -

(1) Constitutes a direction of additional work outside the Contract requirements;

(2) Constitutes a change as defined in the contract clause entitled “Changes;”

(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;

(4) Changes any of the expressed terms, conditions or specifications of the contract; or

(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.

(d) All technical direction shall be issued in writing by the COR.

(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the COR in the manner prescribed by this clause and within its authority under the provisions of this clause. If, in the opinion of the Contractor, any instruction or direction by the COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the Contractor must not proceed and must notify the Contracting Officer in writing within five

(5) working days after receipt of any such instruction or direction and must request the Contracting Officer to modify the contract accordingly. Upon receiving the notification from the Contractor, the Contracting Officer must -

(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the Changes clause of the contract; or

(2) Advise the Contractor that the Government will issue a written change order.

(f) A failure of the Contractor and Contracting Officer either to agree that the technical direction is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled “Disputes.”

(End of clause)

P a g e | 14

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1 DOI-AAAP-0050 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM

DECEMBER 2015

1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS - pronounced “peepers”) for Government use in evaluating past performance as part of a source selection action.

3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.

4) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at http://www.cpars.csd.disa.mil/ . The CPARS User Manual, registration for Online Training for Contractor Representatives, and a practice application may be found at this site.

5) Within 60 days after the end of a performance period, the CO will complete an interim or final past performance evaluation, and the report will be accessible at http://www.cpars.csd.disa.mil/.

a) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.

b) Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official's narrative and should provide your views on the causes and ramifications of the assessed performance.

c) In addition to the ratings and supporting narratives, blocks 1 - 17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection actions.

d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government.

e) If you do not sign and submit the CPAR within 30 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date).

The contractor neither signed nor offered comment in response to this assessment."

f) Your response is due within 30 calendar days after receipt of the CPAR.

6) The following guidelines apply concerning your use of the past performance evaluation:

a) Protect the evaluation as "source selection information." After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html http://www.cpars.csd.disa.mil/ https://www.cpars.gov/cparsfiles/pdfs/CPARS_User_Manual.pdf https://www.cpars.gov/cparsfiles/pdfs/CPARS_User_Manual.pdf https://www.cpars.csd.disa.mil/webtrain.htm http://www.cpars.csd.disa.mil/

P a g e | 15

b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 30-day review period.

8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

P a g e | 16

SECTION I – CONTRACT CLAUSES

I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at the following addresses:

FAR Clauses - https://www.acquisition.gov/far/

Clause Title Date 52.201-1 Definitions June 2020 52.203-3 Gratuities April 1984 52.203-5 Covenant Against Contingent Fees May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government June 2020 52.203-7 Anti-Kickback Procedures June 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper

Activity May 2014

52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity May 2014 52.203-12 Limitation On Payments To Influence Certain Federal Transactions June 2020 52.203-17 Contractor Employee Whistleblower Rights and Requirements To Inform

Employees of Whistleblower Rights June 2020

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

January 2017

52.204-4 Printed or Copied Double-Sided on Post Consumer Fiber Content Paper May 2011 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards June 2020 52.204-13 System for Award Management Maintenance October 2018 52-204-14 Service Contract Reporting Requirements October 2016 52.204-18 Commercial and Government Entity Code Maintenance August 2020 52.204-19 Incorporation by Reference of Representations and Certifications December 2014 52.204-21 Basic Safeguarding of Covered Contractor Information Systems June 2016

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities

July 2018

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

August 2020

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

June 2020

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations November 2015 52.215-2 Audit and Records--Negotiation June 2020 52.215-8 Order of Precedence--Uniform Contract Format October 1997 52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than

Certified Cost or Pricing Data -Modifications - Alternate IV (October 2010)

June 2020

52.219-8 Utilization of Small Business Concerns October 2018 52.219-28 Post-Award Small Business Program Rerepresentation November 2020 52.222-1 Notice To The Government Of Labor Disputes February 1997 52.222-3 Convict Labor June 2003 52.222-4 Contract Work Hours and Safety Standards Act - Overtime

Compensation March 2018

52.222-6 Construction Wage Rate Requirements August 2018 52.222-7 Withholding of Funds May 2014 52.222-8 Payrolls and Basic Records August 2018 52.222-9 Apprentices and Trainees July 2005 52.222-10 Compliance with Copeland Act Requirements February 1988 52.222-11 Subcontracts (Labor Standards) May 2014 https://www.acquisition.gov/far/

P a g e | 17

52.222-12 Contract Termination-Debarment May 2014 52.222-13 Compliance with Construction Wage Rate Requirements May 2014 52.222-14 Disputes Concerning Labor Standards February 1988 52.222-15 Certification of Eligibility May 2014 52.222-21 Prohibition of Segregated Facilities April 2015 52.222-26 Equal Opportunity September 2016 52.222-27 Affirmative Action Compliance Requirements for Construction April 2015 52.222-35 Equal Opportunity for Veterans June 2020 52.222-36 Affirmative Action For Workers with Disabilities June 2020 52.222-37 Employment Reports on Veterans June 2020 52.222-40 Notification of Employee Rights Under the National Labor Relations Act December 2010 52.222-50 Combating Trafficking in Persons October 2020 52.222-54 Employment Eligibility Verification October 2015 52.222-55 Minimum Wages Under Executive Order 13658 November 2020 52.222-62 Paid Sick Leave Under Executive Order 13706 January 2017 52.223-2 Affirmative Procurement of Biobased Products Under Service and

Construction Contracts September 2013

52.223-3 Alt I Hazardous Material Identification and Material Safety Data – Alternate I (January 1995)

January 1997

52.223-5 Pollution Prevention and Right-to-Know Information May 2011 52.223-6 Drug-Free Workplace May 2001 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and

Construction Contracts August 2018

52.223-18 Encouraging Contractor Policies to Ban text Messaging While Driving June 2020 52.225-9 Buy American Act – Construction Materials May 2014 52.225-13 Restrictions on Certain Foreign Purchases June 2008 52.226-1 Utilization of Indian Organizations and Indian-Owned Economic

Enterprises June 2000

52.227-1 Authorization and Consent June 2020 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement June 2020 52.227-4 Patent Indemnity -- Construction Contracts December 2007 52.228-2 Additional Bond Security October 1997 52.228-5 Insurance – Work on a Government Installation January 1997 52.228-11 Pledges Of Assets August 2018 52.228-12 Prospective Subcontractor Requests for Bonds May 2014 52.228-14 Irrevocable Letter of Credit November 2014 52.228-15 Performance and Payment Bonds--Construction June 2020 52.229-3 Federal, State And Local Taxes February 2013 52.232-5 Payments Under Fixed-Price Construction May 2014 52.232-17 Interest May 2014 52.232-23 Assignment Of Claims May 2014 52.232-27 Prompt Payment for Construction Contracts January 2017 52.232-33 Payment by Electronic Funds Transfer – System for Award Management October 2018 52.232-39 Unenforceability of Unauthorized Obligations June 2013 52.232-40 Providing Accelerated Payment to Small Business Subcontractors December 2013 52.233-1 Alt I Disputes - Alternate I (December 1991) May 2014 52.233-3 Protest After Award August 1996 52.233-4 Applicable Law for Breach of Contract Claim October 2004 52.236-5 Material and Workmanship April 1984 52.236-6 Superintendence by the Contractor April 1984 52.236-7 Permits and Responsibilities November 1991 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements April 1984

52.236-10 Operations and Storage Areas April 1984 52.236-11 Use and Possession Prior to Completion April 1984 52.236-12 Cleaning Up April 1984 52.236-13 Accident Prevention November 1991 52.236-15 Schedules for Construction Contracts April 1984

Solicitation No.: 140R4021R0004 Power Factor Corrections - Block 4 P a g e | 18

52.236-16 Quantity Surveys April 1984 52.236-17 Layout of Work April 1984 52.236-21 Alt I Specifications and Drawings for Construction – Alternate I (April 1984) February 1997 52.236-26 Preconstruction Conference February 1995 52.242-13 Bankruptcy July 1995 52.244-6 Subcontracts for Commercial Items November 2020 52.246-21 Warranty of Construction March 1994 52.248-3 Value Engineering-Construction October 202 52.249-2 Alt 1 Termination for Convenience of the Government (Fixed-Price) -

Alternate I (September 1996) April 2012

52.249-10 Default (Fixed-Price Construction) April 1984 52.253-1 Computer Generated Forms January 1991

I.2 1452.228-70 LIABILITY INSURANCE – DEPARTMENT OF THE INTERIOR JULY 1996

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

Worker’s Compensation and Employer’s Liability: $100,000.00 each person General Liability: $500,000.00 each occurrence Automotive Liability: $200,000.00 each person, $500,000.00 each occurrence, $20,000.00 property damage

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

I.3 1452.203-70 RESTRICTION ON ENDORSEMENTS – DEPARTMENT OF THE

INTERIOR

JULY 1996

The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.

I.4 1452.204-70 RELEASE OF CLAIMS – DEPARTMENT OF THE INTERIOR JULY 1996

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

I.5 1452.215-70 EXAMINATION OF RECORDS BY THE DEPARTMENT OF THE

INTERIOR

For purposes of the Examination of Records by the Comptroller General clause of this contract (FAR 52.215-1), the Secretary of the Interior, the Inspector General, and their duly authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States.

P a g e | 19

I.6 52.236-2 DIFFERING SITE CONDITIONS APRIL 1984

(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of --

(1) Subsurface or latent physical conditions at the site which differ materially from those indicated in this contract; or

(2) Unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

(c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in (a) above for giving written notice may be extended by the Contracting Officer.

(d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.

I.7 52.236-3 SITE INVESTIGATIONS AND CONDITIONS AFFECTING THE

WORK

(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to -

(1) Conditions bearing upon transportation, disposal, handling, and storage of materials;

(2) The availability of labor, water, electric power, and roads;

(3) Uncertainties of weather, river stages, tides, or similar physical conditions at the site;

(4) The conformation and conditions of the ground; and

(5) The character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.

(b) The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding, or representation is expressly stated in this contract.

P a g e | 20

I.8 52.236-8 OTHER CONTRACTS (RECLAMATION DEVIATION) APRIL 1984

The Government may undertake or award other contracts for additional work at or near the site of the work under this contract. The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Government employees.

The following other contract work is anticipated to be performed at or near the site of this contract; there are no other contracts anticipated in the area, but the contractor will be notified of any changes.

I.9 52.243-4 CHANGES JUNE 2007

(a) The Contracting Officer may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract, including changes--

(1) In the specifications (including drawings and designs);

(2) In the method or manner of performance of the work;

(3) In the Government-furnished property or services; or

(4) Directing acceleration in the performance of the work.

(b) Any other written or oral order (which, as used in this paragraph (b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating--

(1) The date, circumstances, and source of the order and

(2) That the Contractor regards the order as a change order.

(c) Except as provided in this clause, no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment.

(d) If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing. However, except for an adjustment based on defective specifications, no adjustment for any change under paragraph (b) of this clause shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required. In the case of defective specifications for which the Government is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with the defective specifications.

(e) The Contractor must assert its right to an adjustment under this clause within 30 days after

(1) Receipt of a written change order under paragraph (a) of this clause or (2) the furnishing of a written notice under paragraph (b) of this clause, by submitting to the Contracting Officer a written statement describing the general nature and amount of the proposal, unless this period is extended by the Government. The statement of proposal for adjustment may be included in the notice under paragraph (b) above.

(f) No proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract.

I.10 52.252-4 ALTERATIONS IN CONTRACT APRIL 1984

As prescribed in 52.107(d), insert the following clause in solicitations and contracts in order to revise or supplement, as necessary, other parts of the contract, or parts of the solicitation that apply after contract award, except for any clause authorized for use with a deviation. Include clear identification of what is being altered.

Portions of this contract are altered as follows:

F. 1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

P a g e | 21

(c) complete the entire work ready for use no later than February 11, 2022. The time stated for completion shall include final cleanup of the premises.

Alternate I (April 1984). The completion date is based on the assumption that the successful offeror will receive the notice to proceed November 1, 2021. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent…