This document outlines requirements for generator air coolers to replace existing equipment for two hydroelectric powerplant generators. The Bureau of Reclamation is soliciting bids under solicitation number 140R2022R0003 to furnish and install six new finned tube air-to-water air coolers for each generator. The air coolers must maintain an air temperature of 40 degrees Celsius or less inside each generator unit when delivering maximum rated output, with specified cooling water supply conditions and estimated heat loads of 640 kW per cooler. The new air coolers must meet ASME and ASTM standards with a maximum operating pressure of 50 psi.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Copy_of_MEP-Rewind-Ops_Data-U1_U2-Historian-06162022_0008.xlsx | XLSX spreadsheet | |
| 140R2022R0003_Amendment_0008_0008.pdf | ||
| Sol_140R2022R0003_Amd_0008.pdf | ||
| Sol_140R2022R0003_Amd_0007.pdf | ||
| 140R2022R0003_Amendment_0006_0006.pdf | ||
| Sol_140R2022R0003_Amd_0006.pdf | ||
| Sol_140R2022R0003_Amd_0005.pdf | ||
| 140R2022R0003_Amendment_0005_0005.pdf | ||
| 140R2022R0003_Amendment_0004_0004.pdf | ||
| Sol_140R2022R0003_Amd_0004.pdf | ||
| 140R2022R0003_Amendment_0003_0003.pdf | ||
| Sol_140R2022R0003_Amd_0003.pdf | ||
| 140R2022R0003_Amendment_0002_0002.pdf | ||
| Sol_140R2022R0003_Amd_0002.pdf | ||
| Amendment_0001_0001.pdf | ||
| Sol_140R2022R0003_Amd_0001.pdf | ||
| Solicitation_140R2022R0003.pdf | ||
| Sol_140R2022R0003.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0007
Att. No. 22
New Melones Powerplant Generator Rewinds
Pre-Proposal Questions and Answers
Question Set 4
1. Question: Section 48 13 17, Pg. 320, It is specified “Furnish 15 sets plus one (1) spare new thrust bearing spring assemblies (springs and caps). Total springs furnished 741”. As there are only 12 nos. of thrust pads / Unit, it seems to be a typo. It should be 12 sets plus (one 1) spare new thrust bearing spring assemblies. This makes it total 741 nos. Kindly review and confirm.
Reclamation Response: The number in the spec. 48 13 17 2.01 A 1) should be 12 not 15. The total springs furnished value of is correct. See amended section.
2. Question: In section I under the Limitation in funds it says
FISCAL YEAR FUNDING AMOUNT
On award of contract: 8%
FY 2023: 24%
FY 2024: 32%
FY2025: 21%
FY 2026: 15%
a. Funding also does not end until 2026. Does this mean the last unit would go in Sep.
‘25- Mar. ‘26?
b. If funding starts in Sep. 2022 and ends in 2026 this means the job would be over 1300 days long. This however would be in conflict with the duration given in Form 1442 page 1 which is 1050 days. What is the USBR intention regarding job duration?
Reclamation Response: See attached amended section I.
3. Question: Section 22 11 85 Paragraph 1.03 C.1e. requires a maximum operating pressure of 100 psi. Paragraph 2.08 A.1 requires to hydrostatic test at 75 psi.
If design pressure is 100 psi, the hydrostatic pressure shall be 150 psi and not 75 psi according to ASME. The hydrostatic test pressure of 75 psi is used when the design pressure is 50 psi.
New Melones Powerplant Generator Rewinds Pre-Proposal Questions and Answers Question Set 4
pg. 2
As a note, the design pressure of 100 psi vs 50 psi has a major impact on price.
Would you confirm the design pressure of the air cooler?
Reclamation Response: The design pressure for the air coolers is 50 psi with a hydrostatic test pressure of 75 psi. See amended section.
4. Question: The cooling water piping inside the air housing is required to be insulated per section 22 10 12, 2.03. Is the cooling water piping covered with insulation per section 22 10 12, 2.03 also required to be coated with coating system of section 09 96 20, Tabulation 2 prior to be insulated?
Reclamation Response: Yes.
SECTION I - CONTRACT CLAUSES
FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEB 1998
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/ (FAR 52.XXX-XX formatted clauses)
FAR Clause Title Date
52.202-1 Definitions JUN 2020
52.203-3 Gratuities APR 1984
52.203-5 Covenant Against Contingent Fees MAY 2014
52.203-6 Restrictions on Subcontractor Sales to the Government JUN 2020
52.203-7 Anti-Kickback Procedures JUN 2020
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
MAY 2014
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity
MAY 2014
52.203-12 Limitation on Payments to Influence Certain Federal
JUN 2020
52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights
JUN 2020
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
JAN 2017
52.204-4 Printing/Copying Double-Sided on Recycled Paper MAY 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
JUN 2020
52.204-13 System for Award Management Maintenance OCT 2018
52.204-14 Service Contract Reporting Requirements OCT 2016
52.204-19 Incorporation by Reference of Representations and Certifications
DEC 2014
https://www.acquisition.gov/
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities
NOV 2021
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment
NOV 2021
52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment
NOV 2021
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
OCT 2018
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations
NOV 2015
52.210-1 Market Research NOV 2021
52.215-2 Audit and Records - Negotiation JUN 2020
52.215-8 Order of Precedence - Uniform Contract Format OCT 1997
52.215-11 Price Reduction for Defective Cost or Pricing Data – Modifications
JUN 2020
52.215-13 Subcontractor Certified Cost or Pricing Data- Modifications
JUN 2020
52.215-15 Pension Adjustments and Asset Reversions OCT 2010
52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions
JUL 2005
52.215-19 Notification of Ownership Changes OCT 1997
52.215-21 Requirements for Certified Cost or Pricing Data and Data Other than Certified Cost or Pricing Data – Modifications
NOV 2021
52.219-8 Utilization of Small Business Concerns OCT 2018
52.219-9 Small Business Sub-Contracting Plan - Alternate I
(NOV 2016)
NOV 2021
52.219-16 Liquidated Damages-Subcontracting Plan SEP 2021
52.219-28 Post-Award Small Business Program Rerepresentation SEP 2021
52.222-3 Convict Labor JUN 2003
52.222-4 Contract Work Hours and Safety Standards-Overtime Compensation
MAR 2018
52.222-6 Construction Wage Rate Requirements AUG 2018
52.222-7 Withholding of Funds MAY 2014
52.222-8 Payrolls and Basic Records JULY 2021
52.222-9 Apprentices and Trainees JUL 2005
52.222-10 Compliance with Copeland Act Requirements FEB 1988
52.222-11 Subcontracts (Labor Standards) MAY 2014
52.222-12 Contract Termination – Debarment MAY 2014
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988
52.222-15 Certification of Eligibility MAY 2014
52.222-21 Prohibition of Segregated Facilities APR 2015
52.222-26 Equal Opportunity SEP 2016
52.222-27 Affirmative Action Compliance Requirements for Construction
APR 2015
52.222-37 Employment Reports on Veterans JUN 2020
52.222-40 Notification of Employee Rights Under the National Labor Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons NOV 2021
52.222-54 Employment Eligibility Verification OCT 2015
52.222-55 Minimum Wages Under Executive Order 13658 NOV 2020
52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022
52.223-3 Alt I Hazardous Material Identification and Material Safety Data (JAN 1997) - Alternate I
FEB 2021
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011
52.223-6 Drug Free Workplace MAY 2001
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contract
AUG 2018
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving
JUN 2020
52.225-13 Restrictions on Certain Foreign Purchases FEB 2021
52.227-1 Authorization and Consent JUN 2020
52.227-2 Notice And Assistance Regarding Patent and Copy Infringement
JUN 2020
52.227-4 Patent Indemnity – Construction Contracts DEC 2007
52.228-2 Additional Bond Security OCT 1997
52.228-5 Insurance - Work on a Government Installation JAN 1997
52.228-11 Pledges of Assets FEB 2021
52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014
52.228-14 Irrevocable Letter of Credit NOV 2014
52.228-15 Performance and Payment Bonds - Construction JUN 2020
52.229-3 Federal, State and Local Taxes FEB 2013
52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014
52.232-17 Interest MAY 2014
52.232-23 Assignment Of Claims MAY 2014
52.232-27 Prompt Payment for Construction Contracts JAN 2017
52.232-33 Payment by Electronic Funds Transfer – System for Award Management
OCT 2018
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013
52.233-1 Alt I Disputes – (MAY 2014) - Alternate I DEC 1991
52.233-3 Protest after Award AUG 1996
52.233-4 Applicable Law For Breach Of Contract Claim OCT 2004
52.236-2 Differing Site Conditions APR 1984
52.236-3 Site Investigation and Conditions Affecting the Work APR 1984
52.236-5 Material and Workmanship APR 1984
52.236-6 Superintendence by the Contractor APR 1984
52.236-7 Permits and Responsibilities NOV 1991
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984
52.236-11 Use and Possession Prior to Completion APR 1984
52.236-12 Cleaning Up APR 1984
52.236-13 Alt I Accident Prevention (NOV 1991) – Alternate I NOV 1991
52.236-14 Availability and Use of Utility Services APR 1984
52.236-17 Layout of Work APR 1984
52.236-21 Alt I Specifications and Drawings for Construction (FEB 1997) – Alternate I
APR 1984
52.236-26 Preconstruction Conference FEB 1995
52.242-5 Payments to Small Business Subcontractors JAN 2017
52.242-13 Bankruptcy JUL 1995
52.243-4 Changes JUN 2007
52.244-6 Subcontracts for Commercial Products and Commercial Services
JAN 2022
52.245-1 Government Property – (SEP 2021) Alternate I APR 2012
52.245-9 Use and Charges APR 2012
52.246-21 Warranty of Construction MAR 1994
52.248-3 Value Engineering – Construction OCT 2020
52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (APR 2012) – Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984
52.253-1 Computer Generated Forms JAN 1991
FAR 52.222-35 EQUAL OPPORTUNITY FOR VETERANS JUN 2020
(a) Definitions. As used in this clause-
“Active duty wartime or campaign badge veteran,” “Armed Forces service medal veteran,” “disabled veteran,” “protected veteran,” “qualified disabled veteran,” and “recently separated veteran” have the meanings given at Federal Acquisition Regulation (FAR) 22.1301.
(b) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-300.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified protected veterans and requires affirmative action by the Contractor to employ and advance in employment qualified protected veterans.
(c) Subcontracts. The Contractor shall insert the terms of this clause in subcontracts valued at or above the threshold specified in FAR 22.1303(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary of Labor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of clause)
FAR 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH JUN 2020
DISABILITIES
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of the threshold specified in Federal Acquisition Regulation (FAR) 22.1408(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
FAR 52.225-11 BUY AMERICAN— CONSTRUCTION MATERIALS NOV 2021
UNDER TRADE AGREEMENTS
(a) Definitions. As used in this clause—
Caribbean Basin country construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C.40102(4), such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Designated country means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);
(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
"Designated country construction material" means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States;
or
(ii) A construction material manufactured in the United States, if—
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States.
Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Free Trade Agreement country construction material means a construction material that-
(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.
Least developed country construction material means a construction material that-
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
United States means the 50 States, the District of Columbia, and outlying areas.
WTO GPA country construction material means a construction material that-
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C.1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction material, excluding COTS fasteners. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.
(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
None
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description
Unit of measure Quantity Price (dollars) *
Item 1 Foreign construction material Domestic construction material Item 1 Foreign construction material Domestic construction material
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[ List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary. ] [ Include other applicable supporting information. ]
(End of clause)
FAR 52.236-8 OTHER CONTRACTS APR 1984
The Government may undertake or award other contracts for additional work at or near the site of the work under this contract. The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Government employees.
(End of Clause)
FAR 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES NOV 2020
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Department of the Interior or Bureau of Reclamation (48 CFR Chapter 5) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
DIAR 1452.203-70 RESTRICTIONS ON ENDORSEMENTS- JUL 1996
DEPARTMENT OF THE INTERIOR
The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.
(End of clause)
DIAR 1452.204-70 RELEASE OF CLAIMS - DEPARTMENT OF JUL 1996
THE INTERIOR
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
DIAR 1452.215-70 EXAMINATION OF RECORDS BY APR 1984
DEPARTMENT OF THE INTERIOR
For purposes of the Examination of Records by the Comptroller General clause of this contract (FAR 52.215-1), the Secretary of the Interior, the Inspector General, and their duly authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States
DIAR 1452.228-70 LIABILITY INSURANCE - DEPARTMENT JUL 1996
OF THE INTERIOR
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
$100,000 each person $500,000 each occurrence
$ 20,000 property damage
(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
WBR 1452.201-80 CONTRACTING OFFICER’S MAY 2018
REPRESENTATIVE’S AUTHORITIES AND
LIMITATIONS – BUREAU OF RECLAMATION
(a) Performance of the work under this contract shall be subject to the technical direction of the Reclamation Contracting Officer's Representative (COR). The term “technical direction” is defined to include, without limitation:
(1) Inspecting and accepting or rejecting work performed under the contract.
(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the Contractor on all technical matters relating to the contract. The COR will supervise or oversee all Government technical and administrative personnel assigned to assist the COR.
(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.
(b) The Contractor will receive a copy of the written COR designation from the Contracting Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting Officer.
(c) Technical direction must be within the scope of work stated in the contract. Only the Contracting Officer is authorized to determine if a change is within the scope of the contract;
therefore, the COR does not have the authority to, and may not, issue any technical direction that
(1) Constitutes a direction of additional work outside the Contract requirements;
(2) Constitutes a change as defined in the contract clause entitled “Changes;”
(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;
(4) Changes any of the expressed terms, conditions or specifications of the contract; or
(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.
(d) All technical direction shall be issued in writing by the COR.
(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the COR in the manner prescribed by this clause and within its authority under the provisions of this clause. If, in the opinion of the Contractor, any instruction or direction by the COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the
Contractor must not proceed and must notify the Contracting Officer in writing within five (5) working days after receipt of any such instruction or direction and must request the Contracting Officer to modify the contract accordingly. Upon receiving the notification from the Contractor, the Contracting Officer must -
(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the Changes clause of the contract; or
(2) Advise the Contractor that the Government will issue a written change order.
(f) A failure of the Contractor and Contracting Officer either to agree that the technical direction is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled “Disputes.”
WBR 1452.209-82 PROHIBITION ON RELEASE OF INFORMATION- MAR 2022
BUREAU OF RECLAMATION
(a) The Contractor shall not disclose information pertaining to the services performed under this contract to anyone other than Government or other personnel authorized by the Contracting Officer. The Contractor agrees that it will protect any information obtained from other companies during the performance of this contract from unauthorized use or disclosure for as long as the information remains proprietary and shall refrain from using such information for any purpose other than that for which it was furnished.
(b) In the event that the Contractor intends to employ individuals other than its own staff or other firms in the performance of the contract, each individual or firm shall be required to furnish the same written certification.
(c) The contractor shall insert, in any subcontract that requires the performance of work similar to that being performed by the Contractor, terms that shall conform substantially to the language of this clause, including this paragraph (c).
WBR 1452.223-80 ASBESTOS-FREE WARRANTY – BUREAU AUG 2021
OF RECLAMATION
(a) The Contractor warrants that all items delivered, or work required by the contract, shall be free of asbestos in any form whatsoever.
(b) The Contractor may request the Contracting Officer to approve an exception to this prohibition when an asbestos-free product is not available. Such requests shall be fully documented and submitted as soon as possible after the contractor determines that an asbestos-free product is not available.
WBR 1452.223-81 SAFETY AND HEALTH – BUREAU OF AUG 2021
RECLAMATION
(a) The Contractor shall not require any person employed in the performance of this contract (including subcontracts) to work under conditions which are unsanitary, hazardous, or dangerous to the employee's health or safety.
(b) Contractor shall comply with the most current version of the Bureau of Reclamation Reclamation Safety and Health Standards (RSHS) and, if applicable, the requirements of the Accident Prevention Clause (FAR 52.236-13).
The RSHS manual shall be obtained at http://www.usbr.gov/ssle/safety/RSHS/rshs.html
(c) Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910 from the Occupational Safety and Health Administration, U.S. Department of Labor, www.osha.gov .
(d) In the event there is a conflict between the requirements contained in paragraphs (b) and (c) referenced herein, the more stringent requirement shall prevail .
(e) The Contractor shall submit a written proposed safety program as prescribed in the RSHS and the written specifications.
(f) The Contractor shall maintain an accurate record of, and shall report to the Contracting Officer (or authorized representative) in the manner prescribed by the Contracting Officer, all cases of death, occupational diseases, or traumatic injury to employees or the public involved, and property damage in accordance with the RSHS and OSHA guidelines.
(g) The rights and remedies of the Government provided in this clause are in addition to any other rights and remedies provided by law or under this contract.
(h) If the RSHS is updated or amended by Reclamation during the course of this contract, the contractor will be notified in writing. The contractor shall comply with the current RSHS immediately upon written notification. Should the contractor feel that the updated version of RSHS constitutes a substantive change to the contract, affecting price or time (or both), the contractor may request an equitable adjustment in the contract price. Any such requests shall include a price proposal submitted in compliance with Contract Clause WBR 1452.243-80, Modification Proposals - Bureau of Reclamation, and in sufficient detail to allow meaningful analysis of labor, equipment and material.
WBR LIMITATION OF FUNDS (FIXED-PRICE CONTRACT) MAR 2022
1452.232-80 BUREAU OF RECLAMATION
(a) Pursuant to Section 12 of the Reclamation Project Act of 1939 (43 U.S.C. 388) incremental funding for this contract will be made available in accordance with this clause. This statute permits the Secretary of the Interior to enter into contracts which will cover such periods as the Secretary may consider necessary but in which liability of the United States shall be contingent upon appropriations being made therefore. For purposes of this clause, the term "appropriations" includes the Bureau of Reclamation’s subsequent allocation of funds for this contract.
(b) Incremental funding in the amount of $400,000 is presently available for payment and allotted under this contract for Disassembly of Power Plant generators, inspection of assembly, replacement of parts, and installation of new generators. This present funding allotment is contemplated to cover the work to be performed until FY 2022. A schedule for anticipated future funding allotments is as follows. This information is for planning purposes only and may not be fully representative of the funds actually allotted under this contract:
FISCAL YEAR FUNDING AMOUNT
On award of contract: 8%
FY 2023: 31%
FY 2024: 40%
FY 2025: 21%
FY 2026: 15%
(c) For work identified in paragraph (b) of this clause, the Contractor agrees to perform up to the point at which the total amount payable by the Government, including reimbursement in the event of termination of specified work for the Government's convenience, approximates the total amount currently allotted to the contract. The Contractor shall not be obligated to continue performance of this work beyond that point. The Government shall not be obligated in any event to reimburse the Contractor in excess of the amount allotted to the contract for this work notwithstanding any contrary provisions of the Termination for Convenience of the Government clause of this contract.
(d) Notwithstanding the date specified in paragraph (b) of this clause, the Contractor shall notify the Contracting Officer in writing at least sixty days prior to the date when, in the Contractor's best judgment, the work will reach the point at which the total amount payable by the Government, including any cost for termination for convenience, will approximate 75 percent of the total amount then allotted to the contract for performance of work identified in paragraph (b) of this clause. The notification shall state (1) the estimated date when that point will be reached and (2) an estimate of additional funding, if any, needed to continue performance of the work up to the next scheduled date for allotment of funds identified in paragraph (b) of this clause, or to a mutually agreed upon substitute date. The notification shall also advise the Contracting Officer of the estimated amount of additional funds that will be required for the timely performance of work funded pursuant to this clause, for a subsequent period as may be specified in the allotment schedule in paragraph (b) of this clause, or otherwise agreed to by the parties. If after such notification additional funds are not allotted by the date identified in the Contractor's notification, or by an agreed substitute date, the Contracting Officer shall terminate any work for which additional funds have not been allotted, pursuant to the Termination for Convenience of the Government clause of this contract.
(e) When additional funds are allotted for continued performance of the work identified in paragraph (b) of this clause, the parties will agree as to the period of contract performance which will be covered by the funds. The provisions of paragraph (c) through (e) of this clause will apply in like manner to the additional allotted funds and agreed substitute date, and the contract will be modified accordingly through revision of paragraph (b) of this clause. The Contracting Officer is the only person authorized to provide notice, communication, or other form of representation to increase or decrease the amount of funds allotted by the Government to this contract. . If agreement cannot be reached, the Contracting Officer will make a final decision as to the period of contract performance that will be covered by the funds. This decision may be appealed by the Contractor under the Disputes clause of the contract.
(f) If, solely by reason of failure of the Government to allot additional funds in amounts sufficient for timely performance of the work identified in paragraph (b) of this clause, the Contractor incurs additional costs or is delayed in the performance of the work under this contract and if additional funds are allotted, an equitable adjustment will be made in the price or prices (including appropriate target, billing, and ceiling prices where applicable) of work, or in the time of delivery, or both. Failure to agree to any such equitable adjustment hereunder shall be a dispute concerning a question of fact within the meaning of the Disputes clause of this contract.
(g) The Government may at any time prior to termination allot additional funds for the performance of the work identified in paragraph (b) of this clause.
(h) The termination provisions of this clause do not limit the rights of the Government under the Default clause of this contract. The provisions of this clause are limited to the work and allotment of funds as set forth in paragraph (b) of this clause. This clause is inapplicable once the contract is fully funded except with regard to the rights or obligations of the parties concerning equitable adjustments negotiated under paragraphs (e) or (f) of this clause.
(i) Change orders shall not be considered authorization to exceed the amount allotted by the Government as specified in paragraph (b) of this clause unless the amount is increased by inclusion of a statement contained in the change order.
(j) Nothing in this clause affects the right of the Government to terminate this contract pursuant to the Termination for Convenience of the Government clause of this contract.
WBR 1452.232-81 PAYMENT FOR MOBILIZATION AND MAR 2022
Alt III PREPARATORY WORK BUREAU OF
RECLAMATION – ALTERNATE III
(a) General. Payment for the Mobilization and Preparatory Work line items of the schedules will be made as reflected herein. To the extent that this line item exceeds the percentages of total schedule pricing as estimated by the Contracting Officer in WBR 1452.236-86, Instruction for Mobilization and Preparatory Work Schedule Line Item, payment will be made as reflected in Section (d)(3), (4) and (5) below. Reclamation will make payment to the Contractor in accordance with this clause for operations including, but not limited to, those necessary for --
(1) Movement of personnel, equipment, supplies, and incidentals to the project site;
(2) The establishment of offices, buildings, plants and other facilities, at the site (excludes temporary buildings (e.g. storage sheds, shops, offices) and utilities listed in the Operations and Storage Areas clause of this contract;
(3) Payment of premiums for project bonds and insurance; and
(4) Other work and operations which must be performed or costs incurred incident to the initiation of meaningful work at the site and for which the contract does not otherwise provide for payment.
(5) Approved detailed logic diagram(s) and the baseline schedule.
(b) Facilities and equipment covered by mobilization work.
(1) All facilities, plant, and equipment which are established at, or brought to, the site shall be deemed to be subject to the provisions of this paragraph unless the Contracting Officer specifically provides other written authorization for a particular item or items.
(2) The Contractor shall be solely responsible for the adequacy, efficiency, use, protection, maintenance, repair, and preservation of all facilities, plant, and equipment on site.
(3) The facilities, plant, and equipment covered by this paragraph shall not be dismantled or removed from the site prior to completion of the work under the contract without the written authorization of the Contracting Officer.
(c) Termination for default. Should the Contractor be terminated for default as provided by the Default clause of this contract --
(1) All facilities, plant, and equipment on the site shall be subject to the Government's right to take possession of and utilize such items for the purpose of completing the work;
(2) The Contractor shall provide evidence of encumbrances, liens, or other security interests, to the Contracting Officer; and
(3) Any encumbrance, lien, or other security interest on such facilities, plant, or equipment shall be subordinated to the Government's rights under the Default clause of this contract to utilize all facilities, plant, and equipment to complete the work under the contract.
(d) Payment. Payment for mobilization and preparatory work under paragraph (a) of this clause shall be made at the contractor lump-sum price for this item as contained in the Schedule.
Progress payments for mobilization and preparatory work shall be made as follows --
(1) In accordance with paragraph (g) of the Payments under Fixed Price Construction Contracts clause of this contract and upon submission of a proper invoice, the Government will reimburse the Contractor for the total amount of premiums paid for performance and payment bonds as required by the Performance and Payment Bond Requirements clause of this contract and for any insurance which is specified as payable by the Government under this contract.
(2) Except as provided in (d)(1) above, progress payments for mobilization and preparatory work shall not be considered a separate division of work for the purposes of progress payments and shall be subject to retainage before payment of the total amount for this contract line item.
(3) When progress payments totaling 5 percent of the total original schedule amount on a schedule have been made by the Government for all other work accomplished under that schedule, the Government shall pay the Contractor 50 percent of the mobilization and preparatory work schedule line item amount or 5 percent of the total original schedule amount (whichever is the lower) exclusive of any payment already made to the Contractor for performance and payment bond premiums and specified insurance under subparagraph (d)(1) of this clause.
(4) When progress payments totaling 10 percent of the total original schedule amount on a schedule have been made by the Government for all other work accomplished under the schedule and upon approval of the detailed logic diagram(s) and baseline schedule, the balance of the amount for the mobilization and preparatory work schedule line item or 10 percent of the total original schedule amount (whichever is the lower) shall be paid to the contractor.
(5) If the schedule amount for mobilization and preparatory work on a schedule exceeds the total of the payments allowed under (3) and (4) above, the balance shall be paid when the schedule work is substantially complete as determined by the Contracting Officer.
WBR 1452.236-84 PRESERVATION OF CULTURAL RESOURCES - MAR 2022
BUREAU OF RECLAMATION
(a) Definitions.
"Cultural items" as defined by Native American Graves Protection and Repatriation Act (NAGPRA) include Native American human remains, funerary objects, sacred objects, and objects of cultural patrimony.
"Cultural resources" is a broad term that includes prehistoric, historic, architectural, and traditional cultural properties; specific items include, but are not limited to, human skeletal remains, archaeological artifacts, records, and material remains related to such properties.
"Funerary objects" means Native American items that, as part of the death rite or ceremony of a culture, are reasonably believed to have been placed intentionally at the time of death or later with or near individual human remains.
"Human remains" means the physical remains of the body of a person.
"Native American" means of, or relating to, a tribe, people, or culture that is indigenous to the United States.
"Sacred objects" means Native American items that are specific ceremonial objects needed by traditional Native American religious leaders for the practice of traditional Native American religions by their present-day adherents. These items are specifically limited to objects that were devoted to a traditional Native American religious ceremony or ritual and which have religious significance or function in the continued observance or renewal of such ceremony.
"Objects of cultural patrimony" means Native American items having ongoing historical, traditional, or cultural importance central to the Native American tribe or Native Hawaiian organization itself, rather than property owned by an individual tribal or organization member.
These objects are of such central importance that they may not be alienated, appropriated, or conveyed by any individual tribal or organization member.
(b) General. Federal legislation provides for the protection and preservation of cultural resources that may be impacted or altered as a result of any Federal project, activity, or program or federally licensed or assisted project, activity, or program.
(c) Discovery of Resources. Should the Contractor, or any of the Contractor's employees, subcontractors, or parties operating or associated with the Contractor, in the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .