This document outlines requirements for a federal construction contract. The contractor must commence work within ten calendar days of receiving the notice to proceed, prosecute work diligently, and complete all on-site work by December 22, 2023. The contract is for the Leavenworth National Fish Hatchery Surface Water Intake Fish Screen and Fish Passage Project Phase I being conducted by the Department of the Interior Bureau of Reclamation. The solicitation number is 140R1021R0001 and work includes final cleanup of the premises by the specified completion date.

View the file

Other files

File Type Posted
Sol_140R1021R0001_Amd_0011.pdf PDF
Specificiation_Replacement_Pages_0001_0011.pdf PDF
Final_Contractor_Q_A_6-17-2021_0010.pdf PDF
Sol_140R1021R0001_Amd_0010.pdf PDF
Gate_House_Photographs_0009.pdf PDF
Sol_140R1021R0001_Amd_0009.pdf PDF
J_6h__USACE_Permit_0008.pdf PDF
Sol_140R1021R0001_Amd_0008.pdf PDF
Sol_140R1021R0001_Amd_0007.pdf PDF
J_2__Past_Performance_Questionnaire_0007.pdf PDF
Sol_140R1021R0001_Amd_0006.pdf PDF
SWISP_I_Contractor_Q-A_as_of_6-7-2021_0006.pdf PDF
Sol_140R1021R0001_Amd_0005.pdf PDF
I_73__Amendment_0005.pdf PDF
Site_Visit_Roster_Signed_0005.pdf PDF
Sol_140R1021R0001_Amd_0004.pdf PDF
J_6g__Hydraulic_Project_Approval_0004.pdf PDF
Sol_140R1021R0001_Amd_0003.pdf PDF
Sol_140R1021R0001_Amd_0002.pdf PDF
QandA as of 5-18-2021_0001.pdf PDF
Sol_140R1021R0001_Amd_0001.pdf PDF
J.6e. USFWS Section 7 Combined.pdf PDF
J.3 140R1021R0001 Drawings.pdf PDF
140R1021R0001 LNFH SWISP Phase I fs.pdf PDF
J.6c. NMFS Section 7 combined.pdf PDF
J.6d. SEPA Combined rs.pdf PDF
J.6a. JARPA Application Combined.pdf PDF
Sol_140R1021R0001.pdf PDF
J.6f. FS_7700_40 RUP Application.docx DOCX document
J.6b. NEPA Combined - FEIS and ROD.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F.1. 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to

(a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the Notice to Proceed (NTP).

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 902 calendar days. In water work window concludes on 15 November 2023. All on-site work to be complete by 22 December 2023. The time stated for completion shall include final cleanup of the premises.