This document is a set of project specifications for the Replace Mill Creek Campground Water Tank project at Redwood National and State Parks in California. The project involves removing an existing 100,000-gallon redwood water tank and replacing it with a new glass-fused to steel tank. The work will be performed under a single prime contract.
Key details include:
- The project is a joint effort between Redwood National Park and California State Parks, with the National Park Service administering the project.
- The project site is located at the Mill Creek Campground, approximately 4 miles south of Crescent City, California.
- The work includes site preparation, demolition of the existing tank, installation of the new tank and associated piping, valves, and electrical/controls, and final site restoration.
- The project is planned for construction during the off-season when the campground is not in use, typically November through April. However, the NPS is open to considering summer construction if the contractor can maintain temporary water service to the campground.
- The solicitation number is 140P8424R0004, and proposals are due to the Contracting Officer by a date to be determined.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REDWOOD NATIONAL & STATE PARKS
REPLACE MILL CREEK
CAMPGROUND WATER TANK
PMIS NO. 238217
TIC No. 167-192263
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
INTERIOR REGIONS
8, 9, 10, AND 12
REDW 328217 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 31 00a RFI Form 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 33 23a CM16 - Transmittal 01 35 13 Archeological Protection 01 35 25 Safety Requirements 01 40 00 Quality Requirements 01 40 00a Daily Inspection Form 01 42 00 Reference Standards 01 50 00 Temporary Facilities & Controls 01 57 23 Under-an-Acre Pollution Prevention Plan 01 57 23a Under-an-Acre Pollution Prevention Plan Template 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management 01 77 00 Closeout Procedures
DIVISION 02 – EXISTING CONDITIONS
02 05 00 General Site Conditions 02 41 00 Demolition & Removals
DIVISION 03 – CONCRETE
03 30 00 CIP Concrete 03 40 00 Precast Concrete
DIVISION 26 – ELECTRICAL
26 27 00 Basic Electrical Requirements
DIVISION 31 – EARTHWORK
31 05 16 31 05 25 31 12 33
Aggregates for Earthwork Utility Line Marking
Utility Trenching and Backfill
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 16 00 Restoration of Surfaces
DIVISION 33 – UTILITIES
33 11 00 Water Utility Distribution Piping & Fittings 33 12 16 Valves Hydrants & Appurtenances
REDW 328217 TOC-2
33 13 00 Disinfecting Water Utility Distribution 33 16 13 Glass Fused Steel Water Tank 33 19 23 Electromagnetic Flow Meter
REDW 238217 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. The purpose of this project is to remove and replace an existing 100,000 gallon water storage tank. The water tank serves the Mill Creek Campground and several adjacent park structures.
This project is a joint effort between Redwood National Park and California State Parks. The project site is located on State Park land but the project has been designed and will be administered by the National Park Service.
B. Section includes the following:
1. Work Covered by Contract Documents
2. Work Phases
3. Work Under Other Contracts
4. Government-Furnished Materials
5. Contractor Use of Site
6. Public Use of Site
7. Occupancy Requirements for Buildings
8. Conduct of Operations
9. Work Restrictions
10. Special Construction Requirements
C. Project Location: This project is located at the Mill Creek Campground in Redwood State Park, in Del Norte County California. Access to the site is off of U.S. Highway 101, approximately 4 miles south of the City of Crescent City.
D. The Work consists of: Removing a 100,000 gallon redwood water tank and replacing it with a glass-fused to steel tank.
E. Project will be constructed under a single prime contract.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. This project involves the construction of new water tank of proprietary design.
B. Tank and tank foundation design shall be by the tank manufacturer, and shall supersede these plans, specifications, and details upon acceptance of the submittal plans and specifications. Tank and tank foundation plans and specifications shall be stamped by a professional engineer licensed in the state of California.
C. Tank details and specifications are only intended to show the general layout, orientation, and accessories required, as well as provide minimal design requirements necessary to meet the project intent. The design engineer shall determine actual design requirements and shall use more conservative design values if warranted.
REDW 238217 01 11 00 - 2
D. Project plans and specifications are intended to cover all ancillary work that is separate and distinct from the tank and tank foundation.
1.3 WORK PHASES
A. The Work shall be conducted in one phase.
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract.
1.5 GOVERNMENT-FURNISHED MATERIALS
A. In case of Government -furnished materials:
1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.
2. Contractor is responsible for initial inspection, receiving, unloading, and handling Government-furnished items at Project site.
3. Government will inspect delivered items for damage after delivery. Contractor shall be present for and assist in Government's inspection.
4. Government will arrange for replacement if Government-furnished items are damaged, defective, or missing.
5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
7. Contractor shall install and otherwise incorporate Government-furnished items into Work.
B. Government-Furnished Materials:
1. None
1.6 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Storage of Materials: Confine storage of materials to designated staging areas.
C. Parking: Confine parking to designated areas as shown in the plans.
D. Stockpiling: Confine stockpiling to designated staging areas.
E. Preservation of Natural Features:
REDW 238217 01 11 00 - 3
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
G. Construction Camp: Establishment of a camp within park will not be permitted.
H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
I. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
1.7 PUBLIC USE OF SITE
A. This site is not open to the public.
1.8 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 3 business/calendar days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
REDW 238217 01 11 00 - 4
1.9 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 6:00 p.m., Monday through Friday, except when otherwise indicated.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
REDW 238217 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
C. Where unit quantity items are listed, payment shall be up to the contract price amount. Should quantities exceed the contract amount a contract modification shall be required.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 0001: Mobilization and Demobilization
1. This item consists of all preparatory work and operations for all items under the contract, including, but not limited to those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site and all other work or operations which shall be performed, or costs incurred prior to beginning work on the various items on the project site. This item also includes bonding, permits (if any), and demobilization cost.
2. This item may not exceed 20% of the total bid.
3. Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price. No more than 75% of this bid item shall be made until the contractor has demobilized from the site.
B. Contract Line Item Number 0002: Demolition and Removals
1. This item consists of disconnecting and demolishing the existing redwood water tank and all associated piping, valves, and apparatuses as shown in the plans.
2. This item also includes all salvaging of items identified in the plans.
3. Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
C. Contract Line Item Number 0003: Site Preparation & Grading
1. This item consists of all preparatory site work and grading as required to prepare the site as required to construct the water tank per the requirements of the tank manufacturer.
These items include, but are not limited to, grading and excavation to prepare the tank
REDW 238217 01 27 00 - 2
foundation, adjacent temporary site grading, clearing and grubbing, pavement removals, and improvements to access.
2. Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
D. Contract Line Item Number 0004: 4” DIP Water Main
1. This item consists of all constructing 4” DIP Water Main as shown in the plans.
2. This item includes, but is not limited to, pipe trenching, furnishing and installing water main, furnishing and installing pipe bedding, backfill, tracer wire, and marker tape. This item also includes compaction testing.
3. Measurement shall be on an installed Liner Foot Basis.
4. Payment will be made at the contract unit rate.
E. Contract Line Item Number 0005: 4” DIP Fittings
1. This item consists of furnishing and installing 4” DIP Fittings as shown in the plans.
2. For the purposes of this contract the number and type of fittings will not be measured as there are relatively few fittings.
3. Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
F. Contract Line Item Number 0006: 4” Gate Valve & Box
1. This item consists of furnishing and installing 4” Gate Valves and Boxes as shown in the plans.
2. Measurement shall be on a per unit basis.
3. Payment will be made at the contract unit price up to the contract amount.
G. Contract Line Item Number 0007: 1” Service Connection
1. This item consists of furnishing and installing 1” Service Connections as shown in the plans.
2. This item includes excavation, backfilling, service line piping, corp. stops, service and saddle tees, couplings, and adaptors as required to connect to existing service connections as shown in the plans. This item includes up to 10 feet of various sized copper service lines required for stub outs to connect to existing service lines or extending and connecting to new curb stops.
3. Measurement for payment: Measurement shall be on a per unit basis.
4. Payment will be made at the contract unit price up to the contract amount.
H. Contract Line Item Number 0008: 2” Service Connection
1. This item consists of furnishing and installing 2” Service Connections as shown in the plans.
2. This item includes excavation, backfilling, service line piping, corp. stops, service and saddle tees, couplings, and adaptors as required to connect to existing service connections as shown in the plans. This item includes up to 10 feet of various sized copper service lines required for stub outs to connect to existing service lines or extending and connecting to new curb stops.
3. Measurement shall be on a per unit basis.
REDW 238217 01 27 00 - 3
4. Payment will be made at the contract unit price up to the contract amount.
I. Contract Line Item Number 0009: Sampling Tap
1. This item consists of furnishing and installing the sampling tap as shown in the plans.
2. Measurement shall be on a per unit basis.
3. Payment will be made at the contract unit price up to the contract amount.
J. Contract Line Item Number 0010: Flow Meter
1. This item consists of furnishing and installing the Flow Meter as shown in the plans.
2. Measurement shall be on a per unit basis.
3. Payment will be made at the contract unit price up to the contract amount.
K. Contract Line Item Number 0011: Meter Pit
1. This item consists of furnishing and installing the precast Meter Pit and casting as shown in the plans.
2. Measurement shall be on a per unit basis.
3. Payment will be made at the contract unit price up to the contract amount.
L. Contract Line Item Number 0012: Connect to Existing Water Main
1. This item consists of connecting to the existing water mains as required in the plans.
2. This item includes all adaptor fittings as required to complete the connections.
3. Measurement shall be on a per unit basis.
4. Payment will be made at the contract unit price up to the contract amount.
M. Contract Line Item Number 0013: Connect to Catch Basin
1. This item consists of connecting the drain and overflow lines from the water tank to the existing catch basin.
2. This item includes all adaptor and bend fittings as required to complete the connection.
3. Measurement shall be on a per unit basis.
4. Payment will be made at the contract unit price up to the contract amount.
N. Contract Line Item Number 0014: Construct Water Tank Foundation
1. This item consists of constructing the proposed water tank foundation.
2. Under typical construction workflow, the tank foundation is constructed by a contractor that differs from the tank supplier. Therefore, this pay item is broken out separately.
3. Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
O. Contract Line Item Number 0015: Construct New Water Tank
1. This item consists of furnishing and installing the new glass fused to steel water tank and all associated valving, piping, and components, as show in the plans and as specified.
2. Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
REDW 238217 01 27 00 - 4
P. Contract Line Item Number 0016: Reinstall Booster Pump
1. This item consists of fully reinstalling and reconnecting the existing booster pump as shown in the plans.
2. Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
Q. Contract Line Item Number 0017: Misc. Electrical Connections
1. This item consists of making all miscellaneous Electrical (and communication) Connections as shown in the plans. Known connections include the booster pump, existing transducer, and existing float switch.
2. This item also includes recalibrating the existing PLC and control system adjust for the new tank.
3. Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
R. Contract Line Item Number 0018: System Disinfection & Start-Up
1. This item consists of disinfecting the new water tank and new watermain piping as specified.
2. Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
S. Contract Line Item Number 0019: Stormwater & Sediment Control
1. This item consists of implementing limited Stormwater and Sediment Control practices as shown in the plans and as identified by the contractor in the UPPP.
2. This item also consists of removing BMPs.
3. Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
T. Contract Line Item Number 0020: Bollards
1. This item consists of furnishing and installing Bollards as shown in the plans.
2. Measurement shall be on a per unit basis.
3. Payment will be made at the contract unit price.
U. Contract Line Item Number 0021: Aggregate Surfacing
1. This item consists of furnishing and installing aggregate surfacing as shown in the plans.
2. Measurement shall be on a square yard basis.
3. Payment will be made at the contract unit price up to the contract amount.
V. Contract Line Item Number 0022: Site Restoration & Cleanup
1. This item consists of all miscellaneous activities required to fully restore the site to preconstruction conditions upon project completion. Items include but are not limited to, final surface grading, removal of trash and rubbish, removal of installed BMPs, and general site clean-up.
2. Measurement shall be on a lump sum basis.
REDW 238217 01 27 00 - 5
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
REDW 238217 01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. Project Meetings
7. Environmental Coordination
8. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm
REDW 238217 01 31 00 - 2
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and controls.
e. Indicate required installation sequences.
2. Refer to individual Sections for Coordination Drawing requirements for Work in those Section a.
REDW 238217 01 31 00 - 3
B. Division 1 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre- Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. Accident Prevention Plan
4. A List of Subcontractors for this project
5. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
6. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
7. Quality Control Plan
8. Temporary Storm Water Pollution Prevention Plan (UPPP)
9. Schedule of values (as applicable)
10. Copies of applicable permits.
C. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on NPS/DSC management software website.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
REDW 238217 01 31 00 - 4
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete RFI Form as follows:
1. Enter general information at the top of the form.
2. Under the "Action" section at the bottom of the form, select "Question" then select "CMR" in drop-down of "Send to" box.
3. Enter details of question and attach related documents.
4. Select "Submit Form" at bottom of page.
D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
7. Modifications
8. Payments to Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
REDW 238217 01 31 00 - 5
15. Correspondence procedures
16. Acceptance/rejection of work
17. Progress meetings
18. Submittal procedures
19. NPS Final Accessibility Inspection
20. Environmental requirements
21. Permit requirements
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials
25. Value engineering
26. Schedule of Values (if applicable)
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
REDW 238217 01 31 00 - 6
e. Purchases
f. Deliveries
g. Submittals
h. Review of mockups
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
m. Manufacturer's written instructions
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
q. Temporary facilities and controls
r. Space and access limitations
s. Regulations of agency(ies) with jurisdiction
t. Testing and inspecting requirements
u. Installation procedures
v. Coordination with other work
w. Required performance results
x. Protection of adjacent work
y. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Pollution Prevention Plan (UPPP).
c. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
d. Training for Contractor personnel in accordance with position requirements.
e. Monitoring and documentation of environmental procedures.
REDW 238217 01 31 00 - 7
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Storm Water Pollution Prevention Environnemental Management
4. Construction Waste Management
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to building industry.
2. Overview of environmental issues related to Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Storm Water Pollution Prevention
4. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.
1.8 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the Government. Contractor shall comply with appropriate Federal, State and local laws.
B. Government Furnished Permits: During development of the project’s design, permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.
1. None
C. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. Contractor shall obtain all permits required to legally conduct work.
REDW 238217 01 31 00 - 8
D. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
E. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
3. Upload permits to NPS/DSC management software website when permits are obtained.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
Request for Information (RFI) Form, 2-18-20 page 1 of 1
Request for Information (RFI) Form National Park Service (NPS) - Denver Service Center (DSC) | 2-18-20
RFI Number:
Project: Replace Water and Propane Distribution Systems at Drakesbad Guest Ranch
Contract Number:
Date:
To:
Carbon Copy (CC):
From:
Subject:
Please provide the following information or clarification:
Response Required By:
Date:
To:
From:
Subject: Response to RFI Number:
Response:
REDW 238217 01 32 18 - 1
CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of Construction Schedule requirements including:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.
C. Proposed Schedule
The proposed schedule for this project has construction taking place during the winter months when the campground is not in use (typically November – April.) The NPS understands that there may be considerable lead times for ordering manufactured tanks, and this may not align with the desired construction window. In lieu of winter construction, the NPS is willing to consider summer construction provided that temporary water can be maintained to the campground. As part of the proposal the contractor shall submit a proposed schedule and indicate how temporary water will be maintained if required.
1.2 DEFINITIONS
A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
REDW 238217 01 32 18 - 2
D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.
1.3 SUBMITTALS
A. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.
B. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit baseline schedule, large enough to show entire schedule for entire construction period.
Utilize Schedule of Values in preparation of Construction Baseline Schedule.
C. Critical Path Method (CPM) Reports: For each activity, include activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.
D. Construction Schedule Updates: On or before 7th day preceding progress payment request date, submit estimates of percent completion of each schedule activity and necessary supporting data.
Provide two paper copies.
1.4 QUALITY ASSURANCE
A. Contractor shall meet with Contracting Officer on day of the preconstruction conference to go over:
1. Review software limitations, content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Discuss constraints,
4. Review delivery dates for Government-furnished products.
5. Review schedule for work of separate Government contracts.
6. Review time required for review of submittals and re-submittals.
7. Review requirements for tests and inspections by independent testing and inspecting agencies.
8. Review time required for completion and startup procedures.
9. Review time required for obtaining and activating permits.
10. Review and finalize list of construction activities to be included in schedule.
11. Review baseline schedule comments, resolve issues and progress on incorporating them
12. Review procedures for updating schedule.
13. Discuss reporting requirements and establish protocol for naming and transmitting electronic schedules.
B. Contractor's Schedule Representative: Before the preconstruction conference, designate an authorized representative to be responsible for preparing and maintaining the Construction Schedule. Submit resume outlining qualifications of Scheduler to Contracting Officer for acceptance. Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency of using scheduling
REDW 238217 01 32 18 - 3
software. Authorized representative will be responsible for preparing the Baseline Schedule, required updates, revisions, Time Impact Analyses, and reports.
1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.
B. Coordinate Construction Baseline Schedule with Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing Construction Baseline Schedule, ensure Subcontractor’s work at all tiers, and prime Contractor’s work, is included and coordinated.
2. Secure time commitments for performing critical elements of work from parties involved.
3. Coordinate each construction activity in network with other activities and schedule in proper sequence.
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule for which progress payments may be requested. Work activities broken out within schedule of values shall be integrated into and made a logical part of the construction baseline schedule. Total costs for the component work activities shall equal contract price for that lump-sum item. Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. Total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments and the Construction Schedule.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, cost and resource-based, time-scaled Critical Path Method network analysis diagram for the Work.
1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing work within applicable completion dates, regardless of Governments acceptance of schedule.
REDW 238217 01 32 18 - 4
2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using preliminary Critical Path Method network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the Critical Path Method schedule within the limitations of the Contract Time.
4. Show sequence and interdependence of activities required for completion of work. Ensure work sequences are logical and Construction Baseline Schedule shows a coordinated plan of the work.
5. Resource loading of each activity shall include personnel by labor category and equipment type and capacity proposed to complete the activity in duration shown.
6. Consider seasonal weather conditions in planning and scheduling work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of work within contract time.
7. Time Frame: Proposed duration assigned to each activity shall be Contractor's best estimate of time required to complete activity considering the scope and resources planned for activity.
a. An early finish date may be shown but the late finish date shall be same date as last day of contract period.
b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.
c. Contractor shall limit use of lead or lag duration’s between schedule activities.
d. Project Calendars: Develop and incorporate the following calendars:
1) Administrative Calendar: Include calendar based on a 7-day week to be used on activities based on calendar days. Apply this calendar to administrative tasks or other tasks not affected by non-working days (Federal Holidays, weather, etc.).
2) Project Calendar: Include calendar based on planned work week for the project. Include Federal Holidays, weekends, and non-workdays indicated in contract documents. Apply this calendar to activities not anticipated to be affected by weather. Be clear when identifying number of work days in work week.
3) Weather Calendar: Utilize Project Calendar and show anticipated normal downtime related to weather as non-working time. Weather days shall be based on data for local area from a reliable source like the National Oceanic and Atmospheric Administration (NOAA), National Park Service records, or source acceptable to Contracting Officer. Apply this calendar to activities anticipated to be affected by weather.
REDW 238217 01 32 18 - 5
e. Activity Duration: Define so no activity is longer than 14 days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.
f. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 calendar days, as separate activities in the schedule. Procurement cycle activities can include submittals, approvals, purchasing, fabrication, and delivery.
g. Submittal Review Time: Include review and re-submittal times indicated.
Coordinate submittal review times in Construction Baseline Schedule.
h. Substantial Completion: Allow time for Government administrative procedures necessary for certification of Substantial Completion. (For more information, refer to Specification 01 77 00 "Closeout Procedures.")
8. Constraints: Include constraints and work restrictions indicated in Contract Documents and as follows in schedule and show how the sequence of Work is affected.
a. Phasing: Arrange list of activities on schedule by phase.
b. Work under More Than One Contract: Include a separate activity for each contract.
c. Work Restrictions: Show effect of the following on the schedule:
1) Coordination with existing construction
2) Limitations of continued occupancies
3) Uninterruptible services
4) Partial occupancy before Substantial Completion
5) Use of premises restrictions
6) Provisions for future construction
7) Seasonal variations
8) Environmental control
9) Permit provisions
d. Work Stages: Indicate important stages of construction for each major portion of the
Work.
1) Subcontract awards
2) Submittals
3) Purchases
4) Sample testing
5) Deliveries
6) Installation
7) Tests and inspections
8) Curing
C. Joint Review, Revision, and Acceptance:
1. Within seven calendar days of receiving Contractor's proposed Construction Baseline Schedule, Contracting Officer shall review initial Construction Baseline Schedule.
2. Within seven calendar days after review, Contractor shall revise and resubmit Construction Baseline Schedule in accordance with comments presented from review.
3. In the event the Contractor fails to define any element of work, activity, or logic, and the Contracting Officer review does not detect this omission or error, such omission or error, REDW 238217 01 32 18 - 6 when discovered by Contractor or Contracting Officer, shall be corrected by Contractor within seven calendar days and shall not affect contract period.
4. Upon acceptance of the Construction Baseline Schedule, Contracting Officer saves schedule as a baseline and updates on a monthly basis. Construction schedule update will be used to evaluate Contractor's monthly applications for payment based upon information developed at monthly Construction Schedule update meeting.
D. Recovery Schedule: When periodic schedule update indicates Work is 14 or more calendar days behind current accepted schedule, a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule shall also be submitted. Indicate changes to working hours, working days, crew sizes, and equipment required to achieve compliance, and date by which recovery shall be accomplished.
E. Computer Software: Prepare schedules using a program developed specifically to manage construction schedules.
PART 3 - EXECUTION
3.1 CONSTRUCTION SCHEDULE UPDATES
A. Progress Meeting Updates: Provide a 2 week look-ahead…
This is the start of the file's text. The full file is on GovTribe.