Q_A_140P8322Q0079_0001.pdf
PDF 72 KB Posted
- Attached to
- Paint two parking lots Paradise, Mt. Rainier NP
- Solicitation number
- 140P8322Q0079
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P8322Q0079_Amd_0001.pdf | ||
| Site_Visit_Roster_0001.pdf | ||
| Sol_140P8322Q0079.pdf | ||
| paradise_bg.pdf | ||
| Park_Brochure.pdf | ||
| SOW_Paradise_lot_painting.pdf | ||
| KEY_PERSONNEL.docx | DOCX document | |
| PAST_PERFORMANCE.docx | DOCX document | |
| Parking_lot.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P8322Q0079
Questions and Answers
Q.1 WSDOT has oil based paint on the QPL and is what we use on a daily basis for all of our projects, both private and government. Is oil based paint acceptable on this project?
A.1 Water based only
Q.2 Are glass beads required on all painted stripes and markings?
A.2. Yes
Q.3 Are glass beads required on curb painting?
A.3. Not appliable, curbs are not included in this contract.
Q.4 Typical parking lot equipment are fitted with a 5 gallon paint reservoir. 5 gallons of paint will do approx. 500 sf. Will this reservoir be acceptable for use on this job?
A.4. Yes
Q.5 This is a lump sum contract. Do we need to keep track of the linear footage for payment?
A.5. No this is being done as a lump sum.
Q.6 Upper lot boundaries are cut off short of the first turn out on the right going down the one way loop rd. Should we include the striping to the turn out?
A.6. Stay within the marked boundaries of the map provided as an attachment.
Q.7 Upper lot has some double yellow and some fog line on the road way. Are these 2 items included in the work?
A.7. Yes they are included
Q.8 Does this contract include painted curbs?
A.8. No curbs require painting under this contract.
Q.9 Will NPS clean up dirt and debris in the parking lot across from the in where snow has been piled up in the past winter?
A.9. Yes NPS staff will clear dirt and debris
Q.10 Will NPS clear and landscaping back and away from any painted curbs?
A.10 Not applicable, no curbs are being painted
Q.11 Will the NPS accept a phasing plan that includes up to 5 phases?
A.11 Yes
Q.12 Will the NPS be responsible for notifying the INN of the inconvenience of this project during that striping phase?
A.12 Yes
Q.13 Will the NPS post any notices or barricades to show where and when each phase is to be shut down for that particular day?
A.13 No, that is the contractor responsibility
Q.14 What is the plan for “overnighters” that are not aware of the phasing of this project?
A.14 NPS staff will work around this
Q.15 How many attempts are to be made to go back and stripe where cars might have been in the way?
A.15 One day after the initial phases.
Q.16 Will extended work hours be considered if weather allows it?
A.16 Yes, a modification will be provided if weather causes rescheduling.
File details come from the government source that posted it. Updated .