Questions_and_Answers_0001.pdf
PDF 102 KB Posted
- Attached to
- JOTR - BULK ROAD BASE AND COLD MIX ASPHALT
- Solicitation number
- 140P8123Q0007
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P8123Q0007_Amd_0001.pdf | ||
| Specifications_-_Road_Base.pdf | ||
| Delivery_Location_Map.pdf | ||
| Sol_140P8123Q0007.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers Solicitation 140P8123Q0007
Supply and Delivery of Road Base
Q1. Deliveries of all 2,300 tons must be completed during the period of performance, which is April 1, 2023 until August 1, 2023. Are we bringing 2,300 tons in one load or are there production days where we bring in less throughout the duration of the contract?
A2. This does not have to be delivered in one load. In past contracts of the same size we will usually receive approx. 150 – 300 tons a day during the days we are at work which is Monday – Thursday. The material can be delivered in any quantity throughout the period of performance as long as all 2,300 tons are delivered before the end date.