United States Department of the Interior
NATIONAL PARK SERVICE
Region 1, 2 and 4 – Contracting Office West-PSW 2680 Natchez Trace Parkway
Tupelo MS 38804
NOTICE TO OFFERORS: Solicitation Number: 140P5221Q0016 issued as a Request for Quotation IAW FAR Part 13 - SIMPLIFIED ACQUISITION PROCEDURES.
Description: Asphalt Shingle Roof System Replacement (Naval Live Oaks Area)
Location: Gulf Islands National Seashore, Gulf Breeze, FL (Multiple Sites within Santa Rosa County).
Magnitude of Construction: Roof replacement (approximately 200 to 250 Squares combined) on Six (6) Public Bldg/Structures. The estimated price range is between $100,000 and $250,000.
Synopsis: The National Park Service seeks qualified and properly licensed roofing contractors.
At a minimum, roofing work in Florida requires a competency license under chapter 489, Florida Statutes. In addition to licensure, Florida law requires compliance with workers’ compensation insurance coverage, and general liability insurance is required per contract requirements.
The Florida Building Codes (FBC) are administered by the Florida Building Commission.
According to section 101.4.2, FBC applies to almost every aspect of public and private buildings and structures. The FBC created ‘High Velocity Hurricane Zone’ and set out hurricane provisions specifically for Florida. Areas where wind speeds exceed 120 mph or are greater than 110 mph within close proximity to the coast -1 mile to be exact - requires extra hurricane protection against wind-born debris. Chapter 15 of the FBC deals specifically with roof assemblies and rooftop structures.
The 7th Edition (2020) Florida Building Code includes several key changes to the requirements for roof assemblies. Many changes strengthen the code to improve the resistance wind and water infiltration damage. Several of the changes apply to both new construction and roof replacement.
Refer to the Fact Sheet (attachment) for a summary of the key changes.
Instructions to Offeror:
Submit detailed price quote electronically via email andre_ward@nps.gov on or before 10AM on 15 MAR 2021. At a minimum, a Firm-Fixed Price (per Bldg) quote shall include:
- Labor and materials
- Tear off and dump fees
- General conditions, Building permits, Bond, etc
- Profit & overhead
System for Award Management: Prospective Contractors must maintain an active record in the (www.sam.gov) database, and update annually to ensure accurate and current data.
Site Visit: Wed, March 3, 2021 at 09:00 AM (CST). Participants will meet at Park Headquarters at 1801 Gulf Breeze Pkwy, Gulf Breeze, FL. If you will attend, RSVP andre_ward@nps.gov and scott_mapes@nps.gov. Mask wearing and physical distancing per CDC guidelines apply to federal employees and contractors on federal lands administered by the NPS.
mailto:andre_ward@nps.gov http://www.sam.gov/ mailto:scott_mapes@nps.gov
140P5221Q0016
1. REQUEST NO.
5a. ISSUED BY
NAME
a. NAME
c. STREET ADDRESS
d. CITY
10. PLEASE FURNISH QUOTATIONS TO
THE ISSUING OFFICE IN BLOCK 5a ON
OR BEFORE CLOSE OF BUSINESS (Date)
2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.
UNDER BDSA REG. 2
AND/OR DMS REG.1
RATING
6. DELIVERY BY (Date)
7. DELIVERY
9. DESTINATION
a. NAME OF CONSIGNEE
b. STREET ADDRESS
PAGE OF PAGES
5b. FOR INFORMATION CALL: (No collect calls)
TELEPHONE NUMBER
AREA CODE NUMBER
8. TO:
b. COMPANY
e. STATE f. ZIP CODE
c. CITY
d. STATE e. ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
THIS RFQ
REQUEST FOR QUOTATION
(THIS IS NOT AN ORDER)
IS IS NOT A SMALL BUSINESS SET ASIDEX
02/19/2021 0040520775
1 25
Headquarters, Gulf Islands NS 1801 Gulf Breeze Pkwy Attn: CO Andre Ward 850-232-4630
NPS, SER - West MABO
Gulf Breeze FL 32563
90 Days After Notice to Proceed
NPS, Gulf Islands NS
1801 Gulf Breeze Parkway Headquarters
Gulf Breeze
FL 32563-5008
850 934-2614Evans Ward
03/15/2021 1000 CD
FOB DESTINATION
OTHER
(See Schedule)X
ITEM NO.
(a)
SUPPLIES/SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
R5323210018 Roof Replacement NLO
00010 Roof System Replacement Naval Live Oaks Area
1. Picnic Area Shelter - footprint = 1700 SF
2. Picnic Area Restroom - footprint = 1200 SF
3. Park Headquarters - footprint = 10,970 SF
4. Group Camping Shelter - footprint = 1700 SF
5. Group Camping Restroom - footprint = 1200 SF
6. NLO Compound Fire Cache - footprint = 2960 SF Approximately 200 to 250 squares combined (excluding waste factor) of total roof area of conventional roof pitch from 4:12 to 9:12.
Delivery: 90 Days After Notice to Proceed
12. DISCOUNT FOR PROMPT PAYMENT
a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS
NUMBER PERCENTAGE
NOTE: Additional provisions and representations
13. NAME AND ADDRESS OF QUOTER
b. STREET ADDRESS
c. COUNTY
d. CITY e. STATE f. ZIP CODE
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
16. SIGNER
a. NAME (Type or print)
c. TITLE (Type or print)
a. NAME OF QUOTER
AREA CODE
NUMBER
15. DATE OF QUOTATION
b. TELEPHONE are are not attached
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition not usable
STANDARD FORM 18 (REV. 6-95)
Prescribed by GSA - FAR (48 CFR) 53.215-1(a)
A - Solicitation/Contract Form B - Supplies or Services/Prices C - Description/Specifications D - Packaging and Marking E - Inspection and Acceptance F - Deliveries or Performance G - Contract Administration Data H - Special Contract Requirements I - Contract Clauses J - List of Documents, Exhibits and Other Attachments K - Representations, Certifications, and Other Statements of Bidders L - Instructions,Conditions, and Notices to Bidders M - Evaluation Factors for Award
A - Solicitation/Contract Form
A.1 SF 1442 Solicitation, Offer, and Award
Page 2 Blocks 14 thru 20(c) must be fully completed by offeror.
B - Supplies or Services/Prices
B.1 Construction Price Schedule
Page 2, OPTIONAL FORM 336 (4-86), Offeror to enter into Block 17 Amounts the total price in US Dollars.
In addition to the Lump Sum amount, offer shall include a detailed estimate (itemized by each building) on letterhead stationery. The data must be sufficient enough to demonstrate a clear understanding of the technical requirements, i.e. quantity takeoff of material, labor, product data and warranty being offered for consideration.
C - Description/Specifications
C.1 Description/specifications/statement of work
The requirements document are incorporated by attachment in Section J and made part of this solicitation.
Documents are published online and may be accessed electronically via the Internet address https://beta.sam.gov/.
D - Packaging and Marking
D.1 DELIVERY, STORAGE, AND HANDLING
A. Deliver materials to site in manufacturer¿s unopened bundles with labels intact and legible.
B. Store all products in manufacturer's unopened, labeled packaging until they are ready for installation.
C. Store all products in accordance with Manufacturer's recommendations.
D. Do not install underlayment or shingles on wet surfaces.
E. Store and dispose of solvent-based materials in accordance with all federal, state and local regulations.
F. For rooftop loading, lay shingle bundles flat. Do not bend over the ridge.
E - Inspection and Acceptance https://beta.sam.gov/
52.246-1 Contractor Inspection Requirements. (APR 1984)
52.246-12 Inspection of Construction. (AUG 1996)
F - Deliveries or Performance
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) - Alternate I (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 15 APR 2021. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of clause)
* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
Legal Holidays
"The following legal holidays are observed by this Government agency:
New Year's Day January 01
Martin Luther King's Birthday 3rd Monday in January
Presidents Day 3rd Monday in February
Memorial Day Last Monday in May
Independence Day July 04
Labor Day 1st Monday in September
Columbus Day 2nd Monday in October
Veterans Day November 11
Thanksgiving Day 4th Thursday in November
Christmas Day December 25
When a holiday falls on Saturday or Sunday, it is observed on the adjacent Friday or Monday, respectively.
In addition to the holidays listed above, the contractor agrees to observe leave days or closures designated by Federal Statute, Executive Order, or Presidential Proclamation."
CONTRACT WORK HOURS (NOV 2007)
The performance period established for this contract is based upon all work being conducted during regular working hours. Regular working hours are limited to the time between 7:00 am and 3:30 pm, Monday through Friday, excluding federal holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and Government holidays, a request must be submitted to the Contracting Officer Representative in sufficient time to allow satisfactory arrangements to be made by the Government for access to the work site and inspection.
(End of Clause)
G - Contract Administration Data
Technical Liaison-Technical Direction
(a) The performance required herein shall be subject to the technical direction of the Technical Liaison (TL) as identified below. As used herein, "technical direction" is defined as direction to the contractor that fills in details, suggests possible lines of approach, or otherwise supplements the scope of the work set forth herein and shall not constitute a new assignment, and does not supersede or modify any article or clause of this contract.
(b) The Technical Liaison is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government. Only a warranted Contracting Officer is authorized to obligate funds on this or any other contract action.
(c) The contractor shall immediately notify the Contracting Officer in writing if the Technical Liaison has taken an action (or fails to take action) or issues direction (written or oral) that the contractor considers to exceed the above limitations.
(d) The Technical Liaison assigned for this contract is:
Name: Scott Mapes
Telephone Number: 850-934-2627 (office) 850-393-8036 (cell)
Email: scott_mapes@nps.gov
Address Line 1: Gulf Islands National Seashore
Address Line 2: NLO Compound, 1802 Gulf Breeze Pkwy
Address Line 3: Gulf Breeze, FL
(e) Only the Contracting Officer may designate a different Technical Liaison.
(End of Clause)
Contract Administration Office
(a) This contract will be administered by:
U.S. Department of the Interior/National Park Service Region 2
Insert Name of Acquisition Office: IR2 West Major Acquisition Buying Office (W-MABO)
Attn: Andre Ward, Contracting Officer
Address Line 1: Gulf Islands National Seashore
Address Line 2: Headquarters, 1801 Gulf Breeze Pkwy
Address Line 3: Gulf Breeze, FL 32563
Email: andre_ward@nps.gov
Telephone: 850-934-2614 (office) 850-232-4630 (cell)
(b) Written communications to the Administrative Contracting Officer shall make reference to the contract number and shall be mailed/emailed to the above address.
Unilateral Deobligation of Unexpended Funds
The contractor shall submit all invoices under the award no later than 90 calendar days after the period of performance has expired, unless a request for extension has been submitted to the Contracting Officer.
After 120 days has passed since the expiration of the performance period, the government reserves the right to issue a unilateral modification deobligating any unexpended funds, and to initiate closeout procedures.
H - Special Contract Requirements
52.222-23 Notice of Requirement for Affirmative Action To Ensure Equal Employment Opportunity for Construction. (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
18.3%
Goals for female participation for each trade
6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area.
If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled Affirmative Action Compliance Requirements for Construction, and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the-
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the covered area is FL Escambia; FL Santa Rosa, Pensacola.
(End of provision)
52.246-21 Warranty of Construction. (MAR 1994)
List of subcontractors (Construction)
For purposes of monitoring compliance with the insurance and payroll reporting requirements of this contract, the contractor shall furnish a listing of all subcontractors to the Contracting Officer within 45 calendars days after contract award.
I - Contract Clauses
52.204-12 Unique Entity Identifier Maintenance. (OCT 2016)
52.204-13 System for Award Management Maintenance. (OCT 2018)
52.213-4 Terms and Conditions - Simplified Acquisitions (Other Than Commercial Items). (NOV 2020)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.
113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(ii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (JUL 2018) (Section 1634 of Pub. L. 115-91).
(iii) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (AUG 2020) (Section 889(a)(1)(A) of Pub. L. 115-232).
(iv) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).
(v) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
(vi) 52.222-26, Equal Opportunity (SEP 2016) (E.O. 11246).
(vii) 52.225-13, Restrictions on Certain Foreign Purchases (JUN 2008) (E.O.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
(viii) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(ix) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub.
L. 108-77, 108-78 (19 U.S.C. 3805 note).
(2) Listed below are additional clauses that apply:
(i) 52.232-1, Payments (APR 1984).
(ii) 52.232-8, Discounts for Prompt Payment (FEB 2002).
(iii) 52.232-11, Extras (APR 1984).
(iv) 52.232-25, Prompt Payment (JAN 2017).
(v) 52.232-39, Unenforceability of Unauthorized Obligations (JUN 2013).
(vi) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (DEC 2013).
(vii) 52.233-1, Disputes (MAY 2014).
(viii) 52.244-6, Subcontracts for Commercial Items (NOV 2020)
(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L. 109-282) (31 U.S.C. 6101 note) (Applies to contracts valued at or above the threshold specified in FAR 4.1403(a) on the date of award of this contract).
(ii) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (JAN 2020) (E.O. 13126). (Applies to contracts for supplies exceeding the micro-purchase threshold, as defined in FAR 2.101 on the date of award of this contract).
(iii) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment (JUN 2020) (41 U.S.C. chapter 65) (Applies to supply contracts over the threshold specified in FAR 22.602 on the date of award of this contract, in the United States, Puerto Rico, or the U.S. Virgin Islands).
(iv) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212) (Applies to contracts valued at or above the threshold specified in FAR 22.1303(a) on the date of award of this contract).
(v) 52.222-36, Equal Employment for Workers with Disabilities (JUN 2020) (29 U.S.C. 793) (Applies to contracts over the threshold specified in FAR 22.1408(a) on the date of award of this contract, unless the work is to be performed outside the United States by employees recruited outside the United States). (For purposes of this clause, "United States" includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)
(vi) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212) (Applies to contracts valued at or above the threshold specified in FAR 22.1303(a) on the date of award of this contract).
(vii) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C.
chapter 67) (Applies to service contracts over $2,500 that are subject to the Service Contract Labor Standards statute and will be performed in the United States, District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, Johnston Island, Wake Island, or the outer Continental Shelf).
(viii)(A) 52.222-50, Combating Trafficking in Persons (OCT 2020) (22 U.S.C.
chapter 78 and E.O. 13627) (Applies to all solicitations and contracts).
(B) Alternate I (MAR 2015) (Applies if the Contracting Officer has filled in the following information with regard to applicable directives or notices: Document title(s), source for obtaining document(s), and contract performance location outside the United States to which the document applies).
(ix) 52.222-55, Minimum Wages Under Executive Order 13658 (NOV 2020) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia)).
(x) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017) (E.O.
13706) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia.))
(xi) 52.223-5, Pollution Prevention and Right-to-Know Information (MAY 2011) (E.O. 13423) (Applies to services performed on Federal facilities).
(xii) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016) (E.O. 13693)(applies to contracts for products as prescribed at FAR 23.804(a)(1)).
(xiii) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (JUN 2016) (E.O. 13693) (Applies to maintenance, service, repair, or disposal of refrigeration equipment and air conditioners).
(xiv) 52.223-15, Energy Efficiency in Energy-Consuming Products (MAY 2020) (42 U.S.C. 8259b) (Unless exempt pursuant to 23.204, applies to contracts when energy-consuming products listed in the ENERGY STAR® Program or Federal Energy Management Program (FEMP) will be-
(A) Delivered;
(B) Acquired by the Contractor for use in performing services at a Federally-controlled facility;
(C) Furnished by the Contractor for use by the Government; or
(D) Specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance).
(xv) 52.223-20, Aerosols (JUN 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons as a propellant or as a solvent; or contracts for maintenance or repair of electronic or mechanical devices).
(xvi) 52.223-21, Foams (JUN 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons as a foam blowing agent; or contracts for construction of buildings or facilities.
(xvii) 52.225-1, Buy American-Supplies (MAY 2014) (41 U.S.C. chapter 67) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the micro-purchase threshold, as defined in FAR 2.101 on the date of award of this contract, and the acquisition-
(A) Is set aside for small business concerns; or
(B) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $25,000).
(xviii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (JUN 2020) (42 U.S.C. 1792) (Applies to contracts greater than the threshold specified in FAR 26.404 on the date of award of this contract, that provide for the provision, the service, or the sale of food in the United States).
(xix) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (OCT 2018) (Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses the System for Award Management (SAM) as its source of EFT information).
(xx) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (JUL 2013) (Applies when the payment will be made by EFT and the payment office does not use the SAM database as its source of EFT information.)
(xxi) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C. App. 1241) (Applies to supplies transported by ocean vessels (except for the types of subcontracts listed at 47.504(d).)
(2) Listed below are additional clauses that may apply:
(i) 52.204-21, Basic Safeguarding of Covered Contractor Information Systems (JUN 2016) (Applies to contracts when the contractor or a subcontractor at any tier may have Federal contract information residing in or transiting through its information system.
(ii) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (JUN 2020)
(Applies to contracts over the threshold specified in FAR 9.405-2(b) on the date of award of this contract).
(iii) 52.211-17, Delivery of Excess Quantities (SEP 1989) (Applies to fixed-price supplies).
(iv) 52.247-29, F.o.b. Origin (FEB 2006) (Applies to supplies if delivery is f.o.b.
origin).
(v) 52.247-34, F.o.b. Destination (NOV 1991) (Applies to supplies if delivery is f.o.b. destination).
(c) FAR 52.252-2, Clauses Incorporated by Reference (FEB 1998). This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text.
Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov
(d) Inspection/Acceptance. The Contractor shall tender for acceptance only those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. The Government must exercise its postacceptance rights-
(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(e) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence, such as acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(f) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges that the Contractor can demonstrate to the satisfaction of the Government, using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred that reasonably could have been avoided.
(g) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(h) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(End of clause)
52.219-6 Notice of Total Small Business Set-Aside. (NOV 2020)
52.222-6 Construction Wage Rate Requirements. (AUG 2018)
52.222-7 Withholding of Funds. (MAY 2014)
52.222-8 Payrolls and Basic Records. (AUG 2018)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance With Copeland Act Requirements. (FEB 1988)
52.222-11 Subcontracts (Labor Standards). (MAY 2014)
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (MAY 2014)
52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)
52.225-9 Buy American - Construction Materials. (MAY 2014)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item- (1) Means any item of supply (including construction material) that is-
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph
(1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means-
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if-
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph
(d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description
Unit of measure Quantity
Price (dollars)*
Item 1
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
Item 2
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
(End of clause)
52.228-2 Additional Bond Security. (OCT 1997)
52.228-5 Insurance - Work on a Government Installation. (JAN 1997)
52.228-11 Pledges of Assets. (AUG 2018)
52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)
52.228-13 Alternative Payment Protections. (JUL 2000)
(a) The Contractor shall submit one of the following payment protections: [ ]
(b) The amount of the payment protection shall be 100 percent of the contract price.
(c) The submission of the payment protection is required within [ ] days of contract award.
(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.
(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.
(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.
(End of clause)
52.229-3 Federal, State, and Local Taxes. (FEB 2013)
52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014)
(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.
(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
(1) The Contractor's request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract.
(iii) A listing of the total amount of each subcontract under the contract.
(iv) A listing of the amounts previously paid to each such subcontractor under the contract.
(v) Additional supporting data in a form and detail required by the Contracting Officer.
(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if -
(i) Consideration is specifically authorized by this contract; and
(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that -
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
(Name)
(Title)
(Date)
(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the unearned amount), the Contractor shall -
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until -
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as -
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.
(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) above shall not apply to that portion of progress payments attributable to bond premiums.
(h) Final payment. The Government shall pay the amount due the Contractor under this contract after -
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of 1940 (31 U.S.C. 3727 and 41 U.S.C. 6305).
(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A contract action is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(j) Interest computation on unearned amounts. In accordance with 31 U.S.C. 3903(c)(1), the amount payable under subparagraph (d)(2) of this clause shall be -
(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and
(2) Deducted from the next available payment to the Contractor.
(End of clause)
52.232-23 Assignment of Claims. (MAY 2014)
52.232-27 Prompt Payment for Construction Contracts. (JAN 2017)
52.236-2 Differing Site Conditions. (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
52.236-5 Material and Workmanship. (APR 1984)
52.236-6 Superintendence by the Contractor. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.236-8 Other Contracts. (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.
(APR 1984)
52.236-10 Operations and Storage Areas. (APR 1984)
52.236-11 Use and Possession Prior to Completion. (APR 1984)
52.236-12 Cleaning Up. (APR 1984)
52.236-13 Accident Prevention. (NOV 1991)
52.236-14 Availability and Use of Utility Services. (APR 1984)
52.236-15 Schedules for Construction Contracts. (APR 1984)
52.236-21 Specifications and Drawings for Construction. (FEB 1997)
52.242-14 Suspension of Work. (APR 1984)
52.243-5 Changes and Changed Conditions. (APR 1984)
1452.210-70 Brand Name or Equal (JUL 1996)
(a) The definition for "brand name" includes identification of products by make and model.
(b) The Government has affixed the term "brand name or equal" to one or more requirements in this solicitation. Such description is intended to provide an example of the quality and characteristics the Government deems satisfactory to fulfill this requirement. Unless the bidder/offeror clearly indicates in its bid or proposal that it is offering an "equal" product, the bid/offer will be assumed to offer the brand name product referenced in this solicitation.
(c)(1) Bidders/offerors may offer "equal" products (including products of the brand name manufacturer other than the one described by brand name) if such products are clearly identified in the bids or proposals. The evaluation of bids or proposals and the determination as to equality of the product offered will be based on information furnished or identified by the bidder/offeror in its bid or proposal. The Contracting Officer is not responsible for locating or securing information which is not identified in the bid or proposal. Each bidder and offeror shall furnish as a part of its bid or proposal all descriptive material (such as cuts, illustrations, drawings, or other information) necessary for the Contracting Officer to:
1. establish exactly what the bidder/offeror proposes to furnish.
2. determine whether the product offered meets the salient characteristics required by the solicitation.
(2) If the bidder/offeror proposes to modify a product to make it conform to the requirements of the solicitation, the bid or proposal should contain a clear description of the proposed modification and clearly mark the descriptive material to show the proposed modification.
(3) Modifications proposed after bid opening to make a product conform to a brand name product referenced in the solicitation will not be considered.
(End of provision)
J - List of Documents, Exhibits and Other Attachments
Attachment Number Title Date
01 SECTION J ATTACHMENT 1 - STATEMENT OF
OBJECTIVES (SOO) 11/30/2020
02 SECTION J ATTACHMENT 2 - SPECIFICATIONS 09/30/1988
03 SECTION J ATTACHMENT 3 - DOL WAGE
DETERMINATION 01/01/2021
04 SECTION J ATTACHMENT 4 - FACT SHEET 06/15/2020
K - Representations, Certifications, and Other Statements of Bidders
52.204-8 Annual Representations and Certifications. (MAR 2020)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238160.
(2) The small business size standard is $16.5.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award…