This document is a solicitation for construction services to build a new canoe launch, trail bridge, and additional concrete trail at Mammoth Cave National Park. The National Park Service is seeking proposals on a total small business set-aside basis to construct a new canoe launch at the Green River Ferry Crossing by July-September 2020. Additional work includes building a new trail bridge over the Echo River and constructing more concrete trail surface to complete an accessible Echo River trail between the contract start and end dates of January 15, 2020 to September 30, 2020. The estimated value is between $1,000,000 and $2,000,000. Interested vendors must attend a pre-proposal site visit on November 1, 2019 and submit RSVPs by October 31 to be eligible for the formal site visit. The solicitation will be issued electronically on October 18, 2019.
140P5219R0039
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Pre-submittal_Questions_-_Laurie.pdf | ||
| Sol_140P5219R0039_Amd_0002.pdf | ||
| Site_Visit_Docs.pdf | ||
| Directions_To_Training_Center_From_South.pdf | ||
| Sol_140P5219R0039_Amd_0001.pdf | ||
| Directions_To_Training_Center_From_the_North.pdf | ||
| B03_-_DOL_Wage_Determination.pdf | ||
| Sol_140P5219R0039.pdf | ||
| Clauses_-_UCF1.docx | DOCX document | |
| A06_-_Specifications.pdf | ||
| B08_-_Proposal_Submission_Package.pdf | ||
| A06_-_Plans.pdf | ||
| A06_-_Specifications.pdf | ||
| B03_-_DOL_Wage_Determination.pdf | ||
| Clauses_-_UCF1.docx | DOCX document | |
| A06_-_Plans.pdf | ||
| B08_-_Proposal_Submission_Package.pdf | ||
| B08_-_Proposal_Submission_Package.pdf | ||
| B03_-_DOL_Wage_Determination.pdf | ||
| A06_-_Specifications.pdf | ||
| Clauses_-_UCF1.docx | DOCX document | |
| Sol_140P5219R0039.pdf | ||
| A06_-_Plans.pdf |
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
NPS, SER - West MABO
2680 Natchez Trace Parkway
Tupelo MS 38804
PSW
laurie_sherrod@nps.gov
Laurie Sherrod 404-938-0178
240675 & 240595 x 10/18/2019
140P5219R0039
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Specifications dated August 2019, plans dated 5 August 2019, Davis Bacon Wage
Determination KY20190099 dated 10 May 2019, and terms and conditions
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 260 calendar days and complete it within ________________ ________________ calendar days after receiving
11/18/2019
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
DOI, NPS, SER - West MABO 2680 Natchez Trace Parkway
Tupelo MS 38804
PSW
Laurie Sherrod
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 51
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P5219R0039
The National Park Service (NPS), Mammoth Cave
National Park (MACA), will be contracting the construction of a new canoe launch, construction of a new trail bridge over the Echo River, and construction of an additional concrete trail surface to complete the accessible echo river trail in accordance with the attached specifications, plans, Davis Bacon Wage
Determination KY20190099 and terms and conditions.
This acquisition is a small business set-aside.
The NAICS code is 237990, Other Heavy and Civil
Engineering Construction, and the size standard is $36.5M.
In accordance with FAR subpart 36.204, the magnitude of construction is estimated between
$1,000,000 and $2,000,000.
Type of Contract: Firm-Fixed Price Construction
This solicitation will result in a contract with a period of performance of 260 days. No legal liability on the part of the government for any payment may arise for performance under this contract beyond the amount that has been authorized through the issuance of written contracts.
The contractor shall provide all supervision, labor, materials, equipment, transportation, and incidentals necessary to complete the work with the contract documents, including but not limited to the Contract, Project Specifications, Plans, and other instruments arising under this Contract.
Pre-proposal Conference/Site Visit: All interested contractors are urged and expected to attend the preproposal/site visit on Friday, November 1, 2019 at 10:00 am CST. Interested contractors shall meet at the Mammoth Cave
Maintenance Building, NPS Warehouse, 61
Maintenance Rd., Mammoth Cave, KY 42259.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 51
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P5219R0039
All interested contractors shall RSVP for the site visit NLT 2:00 pm CST on Thursday, October
31, 2019. RSVPs will be received at laurie_sherrod@nps.gov. If no RSVPs are received by 2:00 pm CST on October 31, 2019 a scheduled formal site visit will NOT be conducted.
Prior to any onsite work taking place a Notice to
Proceed (NTP) will be provided. In order for NPS to issue a NTP after contract award, NPS must receive from the Contractor the following items for prior review and approval:
1. Performance and Payment Bonds
2. Certificate of Liability Insurance
3. Contract Specific Safety Plan (reviewed and approved)
4. SF 1413 for each subcontractor
5. Materials Submittals (reviewed and approved)
6. PreCon Completed
It is anticipated construction of the canoe launch ramp will be undertaken in July, August, and September of 2020 in order to correspond with low water conditions in the Green River.
Construction of the new trail bridge and the additional trail work can be accomplished any time between the contract period of performance start and end date.
THIS SOLICITATION WILL RESULT IN A CONTRACT WITH
AN OVERALL PERIOD OF PERFORMANCE FROM JANUARY 15,
2020 THROUGH SEPTEMBER 30, 2020. THE GOVERNMENT
OBLIGATION FOR PERFORMANCE OF THIS CONTRACT
BEYOND THE BASE ITEM IS CONTINGENT UPON THE
AVAILABILITY OF FUNDS.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
5 51
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P5219R0039
Legacy Doc #: NPS
Delivery: 09/30/2020
Delivery Location Code: 0009060308
NPS, Mammoth Cave NP
P O Box 7
NPS Warehouse, 61 Maintenance Rd
Mammoth Cave KY 42259 US
Period of Performance: 01/15/2020 to 09/30/2020
00010 BASE ITEM: Construct New Canoe Launch in accordance with specifications and plans.
Period of Performance: 07/01/2020 to 09/30/2020
00020 OPTION ITEM 1: Construct Additional Accessible
Trail in accordance with the specifications and plans.
(Option Line Item)
01/15/2020
00030 OPTION ITEM 2: Construct Trail Bridge in accordance with the specifications and plans.
(Option Line Item)
01/15/2020