Sol_140P5219R0039_Amd_0002.pdf
PDF 92 KB Posted
- Attached to
- CONSTRUCT CANOE LAUNCH & TRAIL EXTENSION Federal contract opportunity
- Solicitation number
- 140P5219R0039
About this file
This document is an amendment to a federal solicitation for construction services. The National Park Service is seeking proposals to construct a new canoe launch and additional trail surfaces at Mammoth Cave National Park in Kentucky. The project entails building a canoe launch on the Green River, constructing a new trail bridge over the Echo River, and adding concrete surfaces to complete an accessible river trail. The estimated value is between $1 million and $2 million. The period of performance is from April 1, 2020 to December 17, 2020. The solicitation is set aside for small businesses only. A pre-proposal meeting will be announced in the forthcoming solicitation. Interested vendors should monitor the Federal Business Opportunities website for additional details and amendments.
140P5219R0039
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Pre-submittal_Questions_-_Laurie.pdf | ||
| Site_Visit_Docs.pdf | ||
| Directions_To_Training_Center_From_South.pdf | ||
| Directions_To_Training_Center_From_the_North.pdf | ||
| Sol_140P5219R0039_Amd_0001.pdf | ||
| B03_-_DOL_Wage_Determination.pdf | ||
| A06_-_Specifications.pdf | ||
| Sol_140P5219R0039.pdf | ||
| Clauses_-_UCF1.docx | DOCX document | |
| B08_-_Proposal_Submission_Package.pdf | ||
| A06_-_Plans.pdf | ||
| A06_-_Specifications.pdf | ||
| Sol_140P5219R0039.pdf | ||
| B03_-_DOL_Wage_Determination.pdf | ||
| Clauses_-_UCF1.docx | DOCX document | |
| A06_-_Plans.pdf | ||
| B08_-_Proposal_Submission_Package.pdf | ||
| B08_-_Proposal_Submission_Package.pdf | ||
| B03_-_DOL_Wage_Determination.pdf | ||
| Clauses_-_UCF1.docx | DOCX document | |
| A06_-_Specifications.pdf | ||
| Sol_140P5219R0039.pdf | ||
| A06_-_Plans.pdf |
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P5219R0039 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PSW
Tupelo MS 38804 2680 Natchez Trace Parkway DOI, NPS, SER - West MABO
PSW
Tupelo MS 38804 2680 Natchez Trace Parkway NPS, SER - West MABO
240675 & 24059510/18/20190002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
10/18/2019
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to post site visit documents, questions asked and answers provided, change POP start date from 1/15/2020 to 4/1/2020 and POP end date will be 260 days after receiving NTP, include FAR Clause 52.228-1 Bid Guarantee via full text, and add
52.236-14 Availability and Use of Utility Services. All other terms and conditions remain unchanged.
Please note the bridge will be provided by the contractor it will NOT be government furnished. This is answered in the attached questions and answers as well. Any questions remaining unanswered will be answered and posted in a separate amendment by close of business on Tuesday, Nov 12, 2019 and the stamped/revised plans will be posted at that time as well due to our system going down tonight and not being up again until Tuesday morning
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Laurie Sherrod
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 14
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P5219R0039/0002 and the remaining questions needing A/E input.
52.228-1 Bid Guarantee. (Sept 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g.,bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier¿s check, irrevocable letter of credit, or, under
Treasury Department regulations, certain bonds or notes of the United States. The Contracting
Officer will return bid guarantees, other than bid bonds-
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds
(including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $1,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of clause)
52.236-14 Availability and Use of Utility
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 14
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P5219R0039/0002
Services. (Apr 1984)
(a) The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract.
Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates determined by the Contracting
Officer. The Contractor shall carefully conserve any utilities furnished without charge.
(b) The Contractor, at its expense and in a workmanlike manner satisfactory to the
Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the
Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
(1) There is no water source at the construction site. There is water available from the water hydrant at the boneyard near the
Facility Management Office at Mammoth Cave
National Park. It will be the Contractor's responsibility to haul the water from the hydrant to the project site.
(End of clause)
Legacy Doc #: NPS
Delivery: 09/30/2020
Delivery Location Code: 0009060308
NPS, Mammoth Cave NP
P O Box 7
NPS Warehouse, 61 Maintenance Rd
Mammoth Cave KY 42259 US
Period of Performance: 04/01/2020 to 12/17/2020