B09_AM_001_MIMA_Phase_3_PreProposal_Conf_0001.pdf
PDF 2 MB Posted
- Attached to
- MIMA 317529 - Rehab Structures and Landscapes
- Solicitation number
- 140P2023R0127
About this file
This pre-proposal conference document outlines requirements for a rehabilitation project at Minute Man National Historical Park. The National Park Service seeks a firm-fixed price contract to rehabilitate cultural landscapes across several sites, including priority A, B, and C landscape and site work, new septic systems, and completion of a chimney and shelter. Offerors must have experience with projects over $5 million. The period of performance is 455 calendar days from notice to proceed with an estimated completion date of October 2024. Proposals are due by July 24, 2023 and will be evaluated on technical approach, experience, schedule, key personnel, past performance, and price. The project is set aside for small businesses under $19 million and will be awarded without discussions using best value tradeoff.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-proposal Conference/Site Visit June 29th, 2023
Rehabilitate Structures & Landscapes (Phase 3)
MIMA 317529
Solicitation Number 140P2023R0127
Request for Proposals No.1443N5010070901
AGENDA
• Introductions
– Make sure to sign in. Sign-in sheet will be incorporated into an Amendment.
• Today’s Goal
• Project Background/Scope
• Solicitation Review
• Proposal Instructions – Section L
• Proposal Evaluation – Section M
• Site Walk
INTRODUCTIONS
• Tony Jasper, Contracting Officer, NPS Denver Service Center
• Michelle Surber, NPS, Project Specialist
TODAY’S GOAL
• Provide potential Offerors an opportunity for thorough site investigation
(FAR 52.236-3)
• Provide Offerors an opportunity to gain a better understanding, ask questions, interface, and receive clarity from the entire MIMA 317529 team; Park, Technical, and Contracting.
• Encourage questions and clarifications at any time. Questions shall be asked in the open for the entire group to hear. No side-bar conversations.
• You must submit questions in writing for Q and A’s to be incorporated into the contract via a solicitation amendment. It is the Offeror’s responsibility to take notes and submit questions by the deadline.
• Questions are due to the CO/CS by minimum 14 days prior to proposal due date to:
– Tony_Jasper@nps.gov
PROJECT BACKGROUND
• This project will rehabilitate cultural landscapes across several sites at MIMA in Lexington and Concord, MA
• This project is partially funded through the Great American Outdoors Act (aka Legacy Restoration Fund)
• Includes two sets of drawings, one scope of work, and one project manual
• This project is the third phase of work in an ongoing set of projects at MIMA. The first phase (buildings) and the second phase (landscaping) have already been awarded.
PROJECT SCOPE
1. CLIN 1 – Priority A Landscape and Site Work
2. CLIN 2 – Septic
3. CLIN 3 – Option 1 – Priority B Landscape and
Site Work
4. CLIN 4 – Option 2 – Priority C Landscape and
Site Work
5. CLIN 5 – Option 3 – Hartwell Chimney and
Shelter
Completion by
October 2024
LANDSCAPE AND SEPTIC
1. Paving – installation and repair of asphalt, brick, concrete pavements
2. Wall work – repair and reconstruction of brick, stacked stone, and stone retaining wall
3. Site amenity repair and installation – bollards, benches, fences
4. Landscape work – lawn and meadow repair, tree planting
LANDSCAPE AND SEPTIC
1. New Septic Systems at four locations – East Quarter School, George Hall House, Inferrera House, Rego House
2. Connect Stow-Hardy house to existing septic on site
3. Treat well at Rego House, cap and fill existing well in adjacent field
HARTWELL SHELTER AND CHIMNEY
1. Repair, repoint, rebuild and reconstruct exposed 18th-century chimney stack, stone masonry
2. Strip and replace plywood roof sheathing, cedar shingle roofing and associated flashing at shelter, provide new vented chimney cap assembly
3. Renew and replace modern timber framing; provide stainless-steel cable railings around cellar hole
SOLICITATION OVERVIEW
• Estimated price is between $5M and $10M
• Period of Performance is 455 calendar days after NTP
• Total Small Business Set Aside
• One Firm-Fixed-Price Contract will be awarded
• Source selection will be made using FAR 15 - Best
Value/Tradeoffs
• Offer guarantee for 90 days
• NAICS code: 238910, the small business size standard is
$19M
CLIN STRUCTURE
Key Solicitation Clauses
• Special Clause 1: Key Personnel
– Lead Designer, PM, Superintendent, QC Manager and Safety
Manager – no substitutions for 120 days)
• Special Clause 2: Key Trades
- Paving, Masonry, and Carpentry
• Special Clause 6: Options (90 Days after award)
• Liquidated Damages ($1,482/day)
• FAR 52.236-6 – Superintendence by the Contractor
PROPOSAL INSTRUCTIONS
• Please read Section L thoroughly
• Email proposals on or before 17:00 ED, July 24, 2023
– Tony_Jasper@nps.gov, and CS_DSC_Proposal_Submission@nps.gov
• Create two volumes – Technical and Price
• Make sure you verify receipt
• Pay attention to detailed page limitation requirements
PROPOSAL EVALUATION
Basis of Award
• Evaluation process is explained in Section M
• Source Selection using FAR 15.1, Best Value Tradeoff
• Government intends to award without discussions, but reserves the right to conduct discussions if deemed necessary
• The Government may accept other than the lowest priced proposal when the perceived benefits of a higher priced proposal merit the price differential
Factors
• Importance
– Factors 1-5 are in descending order of importance
– Overall: all evaluation Factors other than price, when combined are significantly more importance than price.
– All non-price factors will be assigned adjectival ratings
Volume 1 – Non-Price Proposal
• Factor 1 – Technical Approach
• Factor 2 – Project Experience
• Factor 3 – Schedule
• Factor 4 – Key Personnel
• Factor 5 – Past Performance
Volume 2 – Business and Price Proposal
• SF1442
• Amendment Acknowledgement
• Price Schedule
• SF24 Bid Bond
• Section K: Reps & Certs
• General References
REMINDER
• Questions are currently due to the CO/CS by July 10th,
• Email proposals to CO/CS on or before July 24th, 2023
• Solicitation and project documents are only changed with a formal amendment.
• Direct all inquiries to contracting until contract award. All inquiries will be redirected to contracting.
QUESTIONS?